Closeout checklist: Construct New Maintenance Building, Albany Readiness Center (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 78 items across Division 01, 11 trade divisions and the contract conditions, including 25 warranties, 24 tests and certificates and 11 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project T2327-01
- Location
- Albany, MO
- Bid date
- 2025-07-22
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 433 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 78 items, by trade
Division 01 General requirements 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 95Spec wording“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...” | 01 32 00 3.1.A | 95 | – |
| Warranty | WarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 103Spec wording“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.” | 01 33 00 1.8.A | 103 | – |
| Warranty | WarrantyContractor shall submit the following information for materials and equipment ...Submittals01 33 00 3.1.A · PDF p. 103-105Spec wording“A. Contractor shall submit the following information for materials and equipment to be provided under this contract. SPEC SECTION TITLE CATEGORY 013200 Schedules Construction Schedule 013200 Schedules Schedule of Values 013200 Schedules List of Subcontractors 013200 Schedules Major Material Suppliers 033000 Cast-In-Place Concrete Product Data 033000 Cast-In-Place Concrete Shop Drawings 033000 Cast-In-Place Concrete ...” | 01 33 00 3.1.A | 103-105 | – |
Division 03 Concrete 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyDesign MixturesCast-In-Place Concrete03 30 00 1.3.B · PDF p. 126Spec wording“B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.” | 03 30 00 1.3.B | 126 | – |
| Test / cert. | Test / cert.Material Test ReportsCast-In-Place Concrete03 30 00 1.4.C · PDF p. 127Spec wording“C. Material Test Reports: For the following, from a qualified testing agency, indicating compliance with requirements: 1. Aggregates.” | 03 30 00 1.4.C | 127 | – |
| Test / cert. | Test / cert.Field quality-control reportsCast-In-Place Concrete03 30 00 1.4.D · PDF p. 127Spec wording“D. Field quality-control reports.” | 03 30 00 1.4.D | 127 | – |
| Test / cert. | Test / cert.Testing and InspectingCast-In-Place Concrete03 30 00 3.13.A · PDF p. 141Spec wording“A. Testing and Inspecting: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.” | 03 30 00 3.13.A | 141 | – |
Division 07 Roofing, insulation and waterproofing 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Field quality-control reportsWater Repellents07 19 00 1.5.D · PDF p. 151Spec wording“D. Field quality-control reports.” | 07 19 00 1.5.D | 151 | – |
| Warranty | WarrantyWarrantyWater Repellents07 19 00 1.5.E · PDF p. 151Spec wording“E. Warranty: Special warranty specified in this Section.” | 07 19 00 1.5.E | 151 | – |
| Warranty | WarrantySpecial WarrantyWater Repellents07 19 00 1.8.A · PDF p. 151Spec wording“A. Special Warranty: Manufacturer's standard form in which manufacturer and Applicator agree(s) to repair or replace materials that fail to maintain water repellency specified in "Performance Requirements" Article within specified warranty period. 1. Warranty Period: Five years from date of Substantial Completion.” | 07 19 00 1.8.A | 151 | – |
| Test / cert. | Test / cert.Product Test ReportsThermal Insulation07 21 00 1.4.A · PDF p. 155Spec wording“A. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for each product.” | 07 21 00 1.4.A | 155 | – |
| Test / cert. | Test / cert.Product Test ReportsJoint Sealants07 92 00 1.3.B · PDF p. 166Spec wording“B. Product Test Reports: For each kind of joint sealant, for tests performed by manufacturer and witnessed by a qualified testing agency.” | 07 92 00 1.3.B | 166 | – |
| Warranty | WarrantySpecial Installer's WarrantyJoint Sealants07 92 00 1.6.A · PDF p. 167Spec wording“A. Special Installer's Warranty: Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period. 1. Warranty Period: Two years from date of Substantial Completion.” | 07 92 00 1.6.A | 167 | – |
| Warranty | WarrantySpecial Manufacturer's WarrantyJoint Sealants07 92 00 1.6.B · PDF p. 167Spec wording“B. Special Manufacturer's Warranty: Manufacturer agrees to furnish joint sealants to repair or replace those joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period. 1. Warranty Period: Five years from date of Substantial Completion.” | 07 92 00 1.6.B | 167 | – |
| Warranty | WarrantySpecial warranties specified in this article exclude deterioration or failure ...Joint Sealants07 92 00 1.6.C · PDF p. 167Spec wording“C. Special warranties specified in this article exclude deterioration or failure of joint sealants from the following: 1. Movement of the structure caused by stresses on the sealant exceeding sealant manufacturer's written specifications for sealant elongation and compression. 2. Disintegration of joint substrates from causes exceeding design specifications. 3. Mechanical damage caused by individuals, tools, or ...” | 07 92 00 1.6.C | 167 | – |
Division 08 Doors, windows and hardware 5 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Product Test ReportsHollow Metal Doors And Frames08 11 13 1.5.A · PDF p. 174Spec wording“A. Product Test Reports: For each type of hollow-metal door and frame assembly, for tests performed by a qualified testing agency.” | 08 11 13 1.5.A | 174 | – |
| O&M | O&MMaintenance DataSectional Doors08 36 13 1.5.A · PDF p. 182Spec wording“A. Maintenance Data: For sectional doors to include in maintenance manuals.” | 08 36 13 1.5.A | 182 | – |
| Warranty | WarrantySpecial WarrantySectional Doors08 36 13 1.7.A · PDF p. 182Spec wording“A. Special Warranty: Manufacturer agrees to repair or replace components of sectional doors that fail in materials or workmanship within specified warranty period. Failures include, but are not limited to, the following: a. Structural failures including, but not limited to, excessive deflection. b. Failure of components or operators before reaching required number of operation cycles. c. Faulty operation of ...” | 08 36 13 1.7.A | 182 | – |
| Test / cert. | Test / cert.Engage a factory-authorized service representative to perform startup service ...Sectional Doors08 36 13 3.3.A · PDF p. 190Spec wording“A. Engage a factory-authorized service representative to perform startup service. 1. Complete installation and startup checks according to manufacturer's written instructions. 2. Test and adjust controls and safety devices. Replace damaged and malfunctioning controls and equipment.” | 08 36 13 3.3.A | 190 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Sectional Doors08 36 13 3.5.A · PDF p. 190Spec wording“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain sectional doors.” | 08 36 13 3.5.A | 190 | – |
Division 09 Finishes 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsFurnish extra materials, that match products installed and that are ...High-Performance Coatings09 96 00 1.5.A · PDF p. 195Spec wording“A. Furnish extra materials, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Coatings: 5 percent, but not less than 1 gal. (3.8 L) of each material and color applied.” | 09 96 00 1.5.A | 195 | – |
| Warranty | WarrantySpecial WarrantyHigh-Performance Coatings09 96 00 1.9.A · PDF p. 195Spec wording“A. Special Warranty: The manufacturer shall warrant the work of this Section to be in accordance with the Contract Documents and free from faults and defects in materials for a period of five years from date of Substantial Completion. This special warranty shall extend the one year period of limitations contained in the General Conditions.” | 09 96 00 1.9.A | 195 | – |
Division 13 Special construction 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Material Test ReportsMetal Building Systems13 34 19 1.5.G · PDF p. 204Spec wording“G. Material Test Reports: For each of the following products: 1. Structural steel including chemical and physical properties. 2. Bolts, nuts, and washers including mechanical properties and chemical analysis. 3. Tension-control, high-strength, bolt-nut-washer assemblies. 4. Shop primers. 5. Nonshrink grout.” | 13 34 19 1.5.G | 204 | – |
| Test / cert. | Test / cert.Product Test ReportsMetal Building Systems13 34 19 1.5.H · PDF p. 204Spec wording“H. Product Test Reports: Based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified testing agency, for insulation and vapor-retarder facings. Include reports for thermal resistance, fire-test-response characteristics, water-vapor transmission, and water absorption.” | 13 34 19 1.5.H | 204 | – |
| Test / cert. | Test / cert.Field quality-control reportsMetal Building Systems13 34 19 1.5.J · PDF p. 204Spec wording“J. Field quality-control reports.” | 13 34 19 1.5.J | 204 | – |
| Warranty | WarrantyWarrantiesMetal Building Systems13 34 19 1.5.K · PDF p. 205Spec wording“K. Warranties: Sample of special warranties.” | 13 34 19 1.5.K | 205 | – |
| O&M | O&MMaintenance DataMetal Building Systems13 34 19 1.6.A · PDF p. 205Spec wording“A. Maintenance Data: For metal panel finishes and door hardware to include in maintenance manuals.” | 13 34 19 1.6.A | 205 | – |
| Warranty | WarrantySpecial Warranty on Metal Panel FinishesMetal Building Systems13 34 19 1.11.A · PDF p. 207Spec wording“A. Special Warranty on Metal Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal panels that show evidence of deterioration of factory-applied finishes within specified warranty period. 1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following: a. Color fading more than 5 Hunter units when tested according to ASTM D 2244. b. ...” | 13 34 19 1.11.A | 207 | – |
| Warranty | WarrantySpecial Weathertightness Warranty for Standing-Seam Metal Roof PanelsMetal Building Systems13 34 19 1.11.B · PDF p. 207Spec wording“B. Special Weathertightness Warranty for Standing-Seam Metal Roof Panels: Manufacturer's standard form in which manufacturer agrees to repair or replace standing-seam metal roof panel assemblies that leak or otherwise fail to remain weathertight within specified warranty period. 1. Warranty Period: 25 years from date of Substantial Completion.” | 13 34 19 1.11.B | 207 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsMetal Building Systems13 34 19 3.10.E · PDF p. 225Spec wording“E. Prepare test and inspection reports.” | 13 34 19 3.10.E | 225 | – |
Division 22 Plumbing 10 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyProvide separate shop drawing submittals for the following items:Basic Plumbing Requirements22 05 00 1.9.C · PDF p. 228-230Spec wording“C. Provide separate shop drawing submittals for the following items: 1. Section 22 05 00: Submittal Requirement: Date Submitted: Plumbing permits Plumbing licenses Welding certificates Warranties As-built documents Pipe pressure test logs Operation and maintenance manuals Close-out / walk-through documentation Training seminar documentation 2. Section 22 05 19: Submittal Requirement: Date Submitted: Pressure gauges ...” | 22 05 00 1.9.C | 228-230 | – |
| Warranty | WarrantyRefer to the General Conditions section of this Specification for ...Basic Plumbing Requirements22 05 00 1.11.A · PDF p. 231Spec wording“A. Refer to the General Conditions section of this Specification for general warranty requirements and information. Additional warranty requirements are specified in subsequent Mechanical Sections.” | 22 05 00 1.11.A | 231 | – |
| Record docs | Record docsPrepare as-built documents in accordance with the requirements in Division ...Basic Plumbing Requirements22 05 00 1.13.A · PDF p. 231-232Spec wording“A. Prepare as-built documents in accordance with the requirements in Division 1 Section "PROJECT CLOSEOUT." In addition to the requirements specified in above, indicate the following installed conditions: 1. The Plumbing Contractor shall provide the Owner with as-built drawings for piping mains and branches, size and location, for both exterior and interior; and indicate all devices requiring periodic maintenance ...” | 22 05 00 1.13.A | 231-232 | – |
| O&M | O&MPrepare maintenance manuals in accordance with Division 1 Section "PROJECT ...Basic Plumbing Requirements22 05 00 1.14.A · PDF p. 232Spec wording“A. Prepare maintenance manuals in accordance with Division 1 Section "PROJECT CLOSEOUT." In addition to the requirements specified in Division 1, include the following information for equipment items: 1. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests, and complete nomenclature and commercial numbers of replacement parts. 2. Manufacturer's ...” | 22 05 00 1.14.A | 232 | – |
| Record docs | Record docsRecord actual locations of tagged valvesPlumbing Identification22 05 53 1.3.A · PDF p. 252Spec wording“A. Record actual locations of tagged valves. 2. PRODUCTS” | 22 05 53 1.3.A | 252 | – |
| Test / cert. | Test / cert.Field quality-control test reportsFacility Water Distribution Piping22 11 13 1.2.B · PDF p. 264Spec wording“B. Field quality-control test reports.” | 22 11 13 1.2.B | 264 | – |
| O&M | O&MOperation and maintenance dataFacility Water Distribution Piping22 11 13 1.2.C · PDF p. 264Spec wording“C. Operation and maintenance data.” | 22 11 13 1.2.C | 264 | – |
| Test / cert. | Test / cert.Prepare reports of testing activitiesFacility Water Distribution Piping22 11 13 3.10.C · PDF p. 271Spec wording“C. Prepare reports of testing activities.” | 22 11 13 3.10.C | 271 | – |
| Test / cert. | Test / cert.Test and certify all backflow preventers for proper operation. Testing ...Plumbing Specialties22 11 19 2.3.A · PDF p. 274Spec wording“A. Test and certify all backflow preventers for proper operation. Testing agent shall be Grade VI Water Operator. 1. Test shall be completed within 30 days of installation or Substantial Completion, whichever is later.” | 22 11 19 2.3.A | 274 | – |
| Test / cert. | Test / cert.Field quality-control reportsFacility Sanitary Sewers22 13 13 1.3.C · PDF p. 275Spec wording“C. Field quality-control reports.” | 22 13 13 1.3.C | 275 | – |
Division 23 HVAC 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyProvide separate shop drawing submittals for all items listed in ...Basic Hvac Requirements23 05 00 1.9.C · PDF p. 287-289Spec wording“C. Provide separate shop drawing submittals for all items listed in Shop Drawing and Submittal Log in Division 1. 1. Section 23 05 00: Submittal Requirement: Date Submitted: Mechanical permits Welding certificates Warranties As-built documents Pipe pressure test logs Operation and maintenance manuals Close-out / walk-through documentation Training seminar documentation 2. Section 23 05 29: Submittal Requirement: ...” | 23 05 00 1.9.C | 287-289 | – |
| Warranty | WarrantyRefer to the General Conditions section of this Specification for ...Basic Hvac Requirements23 05 00 1.11.A · PDF p. 290Spec wording“A. Refer to the General Conditions section of this Specification for general warranty requirements and information. Additional warranty requirements are specified in subsequent Mechanical Sections.” | 23 05 00 1.11.A | 290 | – |
| Record docs | Record docsPrepare as-built documents in accordance with the requirements in Division ...Basic Hvac Requirements23 05 00 1.13.A · PDF p. 291Spec wording“A. Prepare as-built documents in accordance with the requirements in Division 1 Section "PROJECT CLOSEOUT." In addition to the requirements specified in above, indicate the following installed conditions: 1. The Mechanical Contractor shall provide the Owner with as-built drawings for ductwork mains and branches, size and location, for both exterior and interior; locations of dampers and other control devices; ...” | 23 05 00 1.13.A | 291 | – |
| O&M | O&MPrepare maintenance manuals in accordance with Division 1 Section "PROJECT ...Basic Hvac Requirements23 05 00 1.14.A · PDF p. 291Spec wording“A. Prepare maintenance manuals in accordance with Division 1 Section "PROJECT CLOSEOUT." In addition to the requirements specified in Division 1, include the following information for equipment items: 1. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests, and complete nomenclature and commercial numbers of replacement parts. 2. Manufacturer's ...” | 23 05 00 1.14.A | 291 | – |
| Test / cert. | Test / cert.Perform the following field tests and inspections according to SMACNA's ...Ductwork23 31 13 3.7.A · PDF p. 322Spec wording“A. Perform the following field tests and inspections according to SMACNA's "HVAC Air Duct Leakage Test Manual" and prepare test reports: 1. Disassemble, reassemble, and seal segments of systems to accommodate leakage testing and for compliance with test requirements. 2. Conduct tests at static pressures equal to maximum design pressure of system or section being tested. If pressure classes are not indicated, test ...” | 23 31 13 3.7.A | 322 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsPower Ventilators23 34 23 2.4.C · PDF p. 325Spec wording“C. Prepare test and inspection reports.” | 23 34 23 2.4.C | 325 | – |
| Record docs | Record docsSee Section 23 05 00Air Outlets And Inlets23 37 00 1.4.A · PDF p. 326Spec wording“A. See Section 23 05 00.” | 23 37 00 1.4.A | 326 | – |
| Warranty | WarrantyWarrantyLow Intensity Gas-Fired Radiant Heaters23 55 23 1.3.D · PDF p. 331Spec wording“D. Warranty: Special warranty specified in Section 1.5.” | 23 55 23 1.3.D | 331 | – |
| O&M | O&MSee Section 23 05 00Low Intensity Gas-Fired Radiant Heaters23 55 23 1.4.A · PDF p. 331Spec wording“A. See Section 23 05 00.” | 23 55 23 1.4.A | 331 | – |
| Warranty | WarrantyWarranty PeriodLow Intensity Gas-Fired Radiant Heaters23 55 23 1.8.A · PDF p. 332Spec wording“A. Warranty Period: One year on all internal components, five years on tube exchangers, and ten years on burner from date of substantial completion. 2. PRODUCTS” | 23 55 23 1.8.A | 332 | – |
| Training | TrainingTrain Owner's maintenance personnel to adjust, operate, and maintain gas-fired ...Low Intensity Gas-Fired Radiant Heaters23 55 23 3.5.A · PDF p. 334Spec wording“A. Train Owner's maintenance personnel to adjust, operate, and maintain gas-fired radiant heaters. Refer to Division 01 Section "Demonstration and Training."” | 23 55 23 3.5.A | 334 | – |
Division 26 Electrical 5 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test ReportsElectrical General Provisions26 05 00 3.2.A · PDF p. 336-337Spec wording“A. Test Reports: Provide the tests as outlined in this specification and all other tests necessary to establish the adequacy, quality, safety, completed status, and suitable operation of each electrical system. Provide the Engineer with a complete schedule of all tests. 1. Ground Rod Test: Immediately after installation, test driven grounds and counterpoises with a ground resistance direct-reading single-test ...” | 26 05 00 3.2.A | 336-337 | – |
| Warranty | WarrantyOperation and Maintenance ManualsElectrical General Provisions26 05 00 3.2.B · PDF p. 337Spec wording“B. Operation and Maintenance Manuals: Operation and Maintenance Manuals shall be provided according to Division 1 requirements. In general, during the time of the contract, and before substantial completion of the electrical installation, submit to the Engineer the number of copies described in the Division 1 specifications and the General and Supplemental Conditions copies of descriptive literature, maintenance ...” | 26 05 00 3.2.B | 337 | – |
| Record docs | Record docsA low voltage Arc Flash Hazard Analysis shall be provided ...Electrical General Provisions26 05 00 3.2.E · PDF p. 339Spec wording“E. A low voltage Arc Flash Hazard Analysis shall be provided by the contractor for this project The analysis shall be based on the specific equipment installed, and shall be updated to include project "as built" documentation. Where the arc flash hazard/risk category is equal to or greater than level 3, the overcurrent protective device coordination study shall be reviewed and recommendations shall be provided to ...” | 26 05 00 3.2.E | 339 | hard copy |
| Warranty | WarrantyRefer to the General Conditions section of this Specification for ...Electrical General Provisions26 05 00 3.17.A · PDF p. 342Spec wording“A. Refer to the General Conditions section of this Specification for warranty requirements and information.” | 26 05 00 3.17.A | 342 | – |
| Record docs | Record docsContractor shall provide the Owner with as-built drawings for all ...Electrical General Provisions26 05 00 3.19.A · PDF p. 343Spec wording“A. Contractor shall provide the Owner with as-built drawings for all electrical systems as described in these specifications and/or shown on the Drawings.” | 26 05 00 3.19.A | 343 | – |
Division 31 Earthwork 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Material Test ReportsEarth Moving31 20 00 1.5.B · PDF p. 392Spec wording“B. Material Test Reports: For each soil material proposed for fill and backfill as follows: 1. Classification according to ASTM D 2487. 2. Laboratory compaction curve according to ASTM D 698. 3. Top Soil Analysis according to ASTM D 442” | 31 20 00 1.5.B | 392 | – |
| Test / cert. | Test / cert.When testing agency reports that subgrades, fills, or backfills have ...Earth Moving31 20 00 3.19.F · PDF p. 401Spec wording“F. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.” | 31 20 00 3.19.F | 401 | – |
Division 32 Paving and site improvements 7 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Product Test ReportsChain Link Fences And Gates32 31 13 1.3.D · PDF p. 411Spec wording“D. Product Test Reports: For framing strength according to ASTM F 1043” | 32 31 13 1.3.D | 411 | – |
| O&M | O&MOperation and Maintenance DataChain Link Fences And Gates32 31 13 1.3.E · PDF p. 411Spec wording“E. Operation and Maintenance Data: For the following to include in emergency, operations, and maintenance manuals: 1. Polymer finish 2. Gate hardware 3. Gate operator” | 32 31 13 1.3.E | 411 | – |
| Warranty | WarrantyWarrantyChain Link Fences And Gates32 31 13 1.3.F · PDF p. 411Spec wording“F. Warranty: Sample of special warranty.” | 32 31 13 1.3.F | 411 | – |
| Warranty | WarrantySpecial WarrantyChain Link Fences And Gates32 31 13 1.6.A · PDF p. 412Spec wording“A. Special Warranty: Manufacturer's standard form in which installer agrees to repair or replace components of chain-link fences and gates that fail in materials or workmanship within specified warranty period. 1. Failures include, but are not limited to, the following: a. Faulty operation of gate operators and controls b. Deterioration of metals, metal finishes, and other materials beyond normal weathering. 2. ...” | 32 31 13 1.6.A | 412 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's personnel to ...Chain Link Fences And Gates32 31 13 3.5.A · PDF p. 417Spec wording“A. Engage a factory-authorized service representative to train Owner's personnel to adjust, operate, and maintain chain-link fences and gates.” | 32 31 13 3.5.A | 417 | – |
| Test / cert. | Test / cert.Material Test ReportsTurf And Grasses32 92 00 1.3.E · PDF p. 419Spec wording“E. Material Test Reports: For existing native surface topsoil, existing in-place surface soil and imported or manufactured topsoil.” | 32 92 00 1.3.E | 419 | – |
| Closeout step | Closeout stepThe Owner will provide full maintenance (mowing, watering and weeding) ...Turf And Grasses32 92 00 1.8.A · PDF p. 420Spec wording“A. The Owner will provide full maintenance (mowing, watering and weeding) post acceptance of established turf as defined by paragraph 3.7 Satisfactory Turf. 2. PRODUCTS” | 32 92 00 1.8.A | 420 | – |
Division 33 Utilities 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsProvide site drainage record drawings:Storm Drain Systems33 41 00 1.4.B · PDF p. 428-429Spec wording“B. Provide site drainage record drawings: 1. Legibly mark drawings to record actual construction. 2. Indicate horizontal and vertical locations, referenced to permanent surface improvements. 3. Identify field changes of dimension, detail and changes made by Change Order.” | 33 41 00 1.4.B | 428-429 | – |
Front end Contract conditions (final payment, releases, retainage) 12 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 23Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 23 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 34Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 34 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 35Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 35 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 41Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 41 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 42Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 42 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 54Spec wording“The Contractor agrees to maintain all books, records and reports required under this contract for a period of not less than three years after final payment is made and all pending matters are closed.” | Conditions Of The Contract (Find Heading On The Cited Page) | 54 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 34Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 34 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 34Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 34 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 34-35Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 34-35 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 35Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 35 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 39-40Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 39-40 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 40Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 40 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.