Closeout checklist: Renovate Building 9, Bath VA Medical Center (U.S. Department of Veterans Affairs, NY)
Every closeout item we found in the public spec book for this job: 558 items across Division 01, 17 trade divisions, including 272 tests and certificates, 77 warranties and 68 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- U.S. Department of Veterans Affairs, Network Contracting Office 2
- Number
- Solicitation 36C24225B0006, VA project 528A6-20-633
- Location
- Bath, NY
- Contract signed
- 2025-02-14
- Spec book size
- 1,665 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 558 items, by trade
Division 01 General requirements 105 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsThe contractor shall maintain two full size sets of as-built ...General Requirements01 00 00 1.11.A · PDF p. 23Spec wording“A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.” | 01 00 00 1.11.A | 23 | two full size sets |
| Record docs | Record docsAll variations shall be shown in the same general detail ...General Requirements01 00 00 1.11.B · PDF p. 23Spec wording“B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.” | 01 00 00 1.11.B | 23 | – |
| Record docs | Record docsContractor shall deliver two approved completed sets of as-built drawings ...General Requirements01 00 00 1.11.C · PDF p. 23Spec wording“C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.” | 01 00 00 1.11.C | 23 | electronic version; PDF |
| Record docs | Record docsParagraphs A, B, & C shall also apply to all shop drawingsGeneral Requirements01 00 00 1.11.D · PDF p. 23Spec wording“D. Paragraphs A, B, & C shall also apply to all shop drawings.” | 01 00 00 1.11.D | 23 | – |
| Warranty | WarrantyWarranty Management PlanGeneral Requirements01 00 00 1.12.A · PDF p. 23-25Spec wording“A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The ...” | 01 00 00 1.12.A | 23-25 | one set; binder |
| Warranty | WarrantyPerformance & Payment BondsGeneral Requirements01 00 00 1.12.B · PDF p. 25-26Spec wording“B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period. 1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the ...” | 01 00 00 1.12.B | 25-26 | – |
| Warranty | WarrantyPre-Warranty ConferenceGeneral Requirements01 00 00 1.12.C · PDF p. 26Spec wording“C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for ...” | 01 00 00 1.12.C | 26 | – |
| Warranty | WarrantyContractor's Response to Construction Warranty Service Requirements:General Requirements01 00 00 1.12.D · PDF p. 26Spec wording“D. Contractor's Response to Construction Warranty Service Requirements:” | 01 00 00 1.12.D | 26 | – |
| Warranty | WarrantyFollowing oral or written notification by the Contracting Officer, the ...General Requirements01 00 00 1.12.E · PDF p. 26-29Spec wording“E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date ...” | 01 00 00 1.12.E | 26-29 | – |
| Warranty | WarrantyWarranty TagsGeneral Requirements01 00 00 1.12.F · PDF p. 29-30Spec wording“F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for ...” | 01 00 00 1.12.F | 29-30 | – |
| O&M | O&MContractor shall furnish Maintenance and Operating manuals (hard copies and ...General Requirements01 00 00 1.19.A · PDF p. 35Spec wording“A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.” | 01 00 00 1.19.A | 35 | – |
| O&M | O&MManualsGeneral Requirements01 00 00 1.19.B · PDF p. 35-36Spec wording“B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, ...” | 01 00 00 1.19.B | 35-36 | four hard copies; one electronic copy |
| Training | TrainingInstructionsGeneral Requirements01 00 00 1.19.C · PDF p. 36-37Spec wording“C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of ...” | 01 00 00 1.19.C | 36-37 | – |
| O&M | O&MSubmit data specified for a given item within 30 calendar ...Shop Drawings, Product Data, And Samples01 33 23 1.8.A · PDF p. 60Spec wording“A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.” | 01 33 23 1.8.A | 60 | – |
| O&M | O&MIn the event the Contractor fails to deliver O&M Data ...Shop Drawings, Product Data, And Samples01 33 23 1.8.B · PDF p. 60Spec wording“B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.” | 01 33 23 1.8.B | 60 | – |
| Training | TrainingThe designated Prime Contractor SSHO must meet the requirements of ...Safety Requirements01 35 26 1.8.A · PDF p. 75Spec wording“A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project. As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety class and have five (5) years of ...” | 01 35 26 1.8.A | 75 | – |
| Training | TrainingAll designated CPs shall have completed the OSHA 30-hour Construction ...Safety Requirements01 35 26 1.8.B · PDF p. 75Spec wording“B. All designated CPs shall have completed the OSHA 30-hour Construction Safety course within the past 5 years.” | 01 35 26 1.8.B | 75 | – |
| Training | TrainingIn addition to the OSHA 30 Hour Construction Safety Course, ...Safety Requirements01 35 26 1.8.C · PDF p. 75-76Spec wording“C. In addition to the OSHA 30 Hour Construction Safety Course, all CPs with high hazard work operations such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations shall have a specialized formal course in the hazard recognition & control associated with those high hazard work operations. ...” | 01 35 26 1.8.C | 75-76 | – |
| Training | TrainingAll other construction workers shall have the OSHA 10-hour Construction ...Safety Requirements01 35 26 1.8.D · PDF p. 76Spec wording“D. All other construction workers shall have the OSHA 10-hour Construction Safety Outreach course and any necessary safety training to be able to identify hazards within their work environment.” | 01 35 26 1.8.D | 76 | – |
| Training | TrainingSubmit training records associated with the above training requirements to ...Safety Requirements01 35 26 1.8.E · PDF p. 76Spec wording“E. Submit training records associated with the above training requirements to the Contracting Officer Representative for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance.” | 01 35 26 1.8.E | 76 | – |
| Training | TrainingPrior to any worker for the contractor or subcontractors beginning ...Safety Requirements01 35 26 1.8.F · PDF p. 76Spec wording“F. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, this briefing shall include information on the site-specific hazards, construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, emergency procedures, ...” | 01 35 26 1.8.F | 76 | – |
| Training | TrainingOngoing safety training will be accomplished in the form of ...Safety Requirements01 35 26 1.8.G · PDF p. 76Spec wording“G. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.” | 01 35 26 1.8.G | 76 | – |
| Test / cert. | Test / cert.Government approval is required for all submittals. CQC inspection reports ...Quality Control01 45 00 1.3 · PDF p. 107Spec wording“Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Initial, or Follow-Up)]: [Applicable Specification section] naming convention. 1. Preconstruction Submittals a. Interim CQC Plan b. CQC Plan c. Additional Requirements for Design Quality Control (DQC) Plan 2. Design Data a. ...” | 01 45 00 1.3 | 107 | – |
| Test / cert. | Test / cert.Personnel RequirementsQuality Control01 45 00 3.4.A · PDF p. 112Spec wording“A. Personnel Requirements: The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager (if applicable), and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager shall satisfy the requirements of Specification 01 35 26 Safety Requirements and reports directly to a senior project (or ...” | 01 45 00 3.4.A | 112 | – |
| Test / cert. | Test / cert.CQC PersonnelQuality Control01 45 00 3.4.C · PDF p. 113-114Spec wording“C. CQC Personnel: In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist in the CQC System Manager for the following areas, as applicable: electrical, mechanical, civil, structural, environmental, architectural, materials technician submittals clerk, Commissioning Agent/LEED specialist, and low voltage systems. These individuals or ...” | 01 45 00 3.4.C | 113-114 | – |
| Test / cert. | Test / cert.Submittals have to comply with the requirements in Section 01 ...Quality Control01 45 00 3.5 · PDF p. 114Spec wording“Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Product Data, and Samples. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When Section 01 91 00 General Commissioning Requirements is included in the contract, the submittals required by the section have to be coordinated with the Section 01 33 ...” | 01 45 00 3.5 | 114 | – |
| Test / cert. | Test / cert.Establish and maintain quality control for the environmental protection of ...Temporary Environmental Controls01 57 19 1.2 · PDF p. 149Spec wording“Establish and maintain quality control for the environmental protection of all items set forth herein. Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.” | 01 57 19 1.2 | 149 | – |
| Training | TrainingIn accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT ...Temporary Environmental Controls01 57 19 1.4 · PDF p. 149Spec wording“In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following: 1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the Contracting Officer's Representative (COR) to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental ...” | 01 57 19 1.4 | 149 | – |
| Closeout step | Closeout stepCloseout SubmittalsSustainable Construction Requirements01 81 13 1.5.G · PDF p. 167Spec wording“G. Closeout Submittals: Within 14 days after Substantial Completion provide the following: 1. Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet. 2. Manufacturer's cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction if permanently installed air handling units are used during construction. ...” | 01 81 13 1.5.G | 167 | – |
| Test / cert. | Test / cert.This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form ...General Commissioning Requirements01 91 00 1.1.A · PDF p. 177Spec wording“A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form the basis of the construction phase commissioning process and procedures. The Commissioning Agent shall add, modify, and refine the commissioning procedures, as approved by the Department of Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed ...” | 01 91 00 1.1.A | 177 | – |
| Test / cert. | Test / cert.Various sections of the project specifications require equipment startup, testing, ...General Commissioning Requirements01 91 00 1.1.B · PDF p. 177Spec wording“B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the Division 7, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not ...” | 01 91 00 1.1.B | 177 | – |
| Test / cert. | Test / cert.Where individual testing, adjusting, or related services are required in ...General Commissioning Requirements01 91 00 1.1.C · PDF p. 177Spec wording“C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services shall be provided and copies of documentation, as required by those specifications shall be submitted to the VA and the Commissioning Agent to be indexed for future reference.” | 01 91 00 1.1.C | 177 | – |
| Test / cert. | Test / cert.Where training or educational services for VA are required and ...General Commissioning Requirements01 91 00 1.1.D · PDF p. 177Spec wording“D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 7, Division 8, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.” | 01 91 00 1.1.D | 177 | – |
| Test / cert. | Test / cert.Commissioning is a systematic process of verifying that the building ...General Commissioning Requirements01 91 00 1.1.E · PDF p. 177-178Spec wording“E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA's operational needs. The commissioning process shall encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy ...” | 01 91 00 1.1.E | 177-178 | – |
| Test / cert. | Test / cert.The commissioning process does not take away from or reduce ...General Commissioning Requirements01 91 00 1.1.F · PDF p. 178Spec wording“F. The commissioning process does not take away from or reduce the responsibility of the Contractor to provide a finished and fully functioning product.” | 01 91 00 1.1.F | 178 | – |
| Test / cert. | Test / cert.The commissioning team shall consist of, but not be limited ...General Commissioning Requirements01 91 00 1.8.A · PDF p. 193Spec wording“A. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning Agent.” | 01 91 00 1.8.A | 193 | – |
| Test / cert. | Test / cert.Members Appointed by Contractor:General Commissioning Requirements01 91 00 1.8.B · PDF p. 193Spec wording“B. Members Appointed by Contractor: 1. Contractor' Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team. 2. Contractor's Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through ...” | 01 91 00 1.8.B | 193 | – |
| Test / cert. | Test / cert.Members Appointed by VA:General Commissioning Requirements01 91 00 1.8.C · PDF p. 193-194Spec wording“C. Members Appointed by VA: 1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA will engage the CxA under a separate contract. 2. User: Representatives of the facility user and operation and maintenance personnel. 3. A/E: Representative of the Architect and engineering design professionals.” | 01 91 00 1.8.C | 193-194 | – |
| Test / cert. | Test / cert.Appoint an individual, company or firm to act as the ...General Commissioning Requirements01 91 00 1.9.A · PDF p. 194Spec wording“A. Appoint an individual, company or firm to act as the Commissioning Agent.” | 01 91 00 1.9.A | 194 | – |
| Test / cert. | Test / cert.Assign operation and maintenance personnel and schedule them to participate ...General Commissioning Requirements01 91 00 1.9.B · PDF p. 194Spec wording“B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following: 1. Coordination meetings. 2. Training in operation and maintenance of systems, subsystems, and equipment. 3. Testing meetings. 4. Witness and assist in Systems Functional Performance Testing. 5. Demonstration of operation of systems, subsystems, and equipment.” | 01 91 00 1.9.B | 194 | – |
| Test / cert. | Test / cert.Provide the Construction Documents, prepared by Architect and approved by ...General Commissioning Requirements01 91 00 1.9.C · PDF p. 194Spec wording“C. Provide the Construction Documents, prepared by Architect and approved by VA, to the Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.” | 01 91 00 1.9.C | 194 | – |
| Test / cert. | Test / cert.The Contractor shall assign a Commissioning Manager to manage commissioning ...General Commissioning Requirements01 91 00 1.10.A · PDF p. 194Spec wording“A. The Contractor shall assign a Commissioning Manager to manage commissioning activities of the Contractor, and subcontractors.” | 01 91 00 1.10.A | 194 | – |
| Test / cert. | Test / cert.The Contractor shall ensure that the commissioning responsibilities outlined in ...General Commissioning Requirements01 91 00 1.10.B · PDF p. 194Spec wording“B. The Contractor shall ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.” | 01 91 00 1.10.B | 194 | – |
| Test / cert. | Test / cert.The Contractor shall ensure that each installing subcontractor shall assign ...General Commissioning Requirements01 91 00 1.10.C · PDF p. 194-195Spec wording“C. The Contractor shall ensure that each installing subcontractor shall assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the following: 1. Participate in commissioning coordination meetings. 2. Conduct operation and maintenance training sessions in accordance with ...” | 01 91 00 1.10.C | 194-195 | – |
| Test / cert. | Test / cert.Organize and lead the commissioning teamGeneral Commissioning Requirements01 91 00 1.11.A · PDF p. 195Spec wording“A. Organize and lead the commissioning team.” | 01 91 00 1.11.A | 195 | – |
| Test / cert. | Test / cert.Prepare the commissioning plan. See Paragraph 1.11-A of this specification ...General Commissioning Requirements01 91 00 1.11.B · PDF p. 195Spec wording“B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.” | 01 91 00 1.11.B | 195 | – |
| Test / cert. | Test / cert.Review and comment on selected submittals from the Contractor for ...General Commissioning Requirements01 91 00 1.11.C · PDF p. 195Spec wording“C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems ...” | 01 91 00 1.11.C | 195 | – |
| Test / cert. | Test / cert.At the beginning of the construction phase, conduct an initial ...General Commissioning Requirements01 91 00 1.11.D · PDF p. 195Spec wording“D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre-Functional Checklists, Systems Functional Performance Testing; and project completion.” | 01 91 00 1.11.D | 195 | – |
| Test / cert. | Test / cert.Convene commissioning team meetings for the purpose of coordination, communication, ...General Commissioning Requirements01 91 00 1.11.E · PDF p. 195-196Spec wording“E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The Commissioning Agent shall prepare and distribute minutes to commissioning team members and attendees within five workdays of the ...” | 01 91 00 1.11.E | 195-196 | – |
| Test / cert. | Test / cert.Observe construction and report progress, observations and issues. Observe systems ...General Commissioning Requirements01 91 00 1.11.F · PDF p. 196Spec wording“F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.” | 01 91 00 1.11.F | 196 | – |
| Test / cert. | Test / cert.Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test ...General Commissioning Requirements01 91 00 1.11.G · PDF p. 196Spec wording“G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.” | 01 91 00 1.11.G | 196 | – |
| Test / cert. | Test / cert.Coordinate Systems Functional Performance Testing schedule with the Contractor ...General Commissioning Requirements01 91 00 1.11.H · PDF p. 196Spec wording“H. Coordinate Systems Functional Performance Testing schedule with the Contractor.” | 01 91 00 1.11.H | 196 | – |
| Test / cert. | Test / cert.Witness selected systems startupsGeneral Commissioning Requirements01 91 00 1.11.I · PDF p. 196Spec wording“I. Witness selected systems startups.” | 01 91 00 1.11.I | 196 | – |
| Test / cert. | Test / cert.Verify selected Pre-Functional Checklists completed and submitted by the Contractor ...General Commissioning Requirements01 91 00 1.11.J · PDF p. 196Spec wording“J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.” | 01 91 00 1.11.J | 196 | – |
| Test / cert. | Test / cert.Witness and document Systems Functional Performance TestingGeneral Commissioning Requirements01 91 00 1.11.K · PDF p. 196Spec wording“K. Witness and document Systems Functional Performance Testing.” | 01 91 00 1.11.K | 196 | – |
| Test / cert. | Test / cert.Compile test data, inspection reports, and certificates and include them ...General Commissioning Requirements01 91 00 1.11.L · PDF p. 196Spec wording“L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.” | 01 91 00 1.11.L | 196 | – |
| Test / cert. | Test / cert.Review and comment on operation and maintenance (O&M) documentation and ...General Commissioning Requirements01 91 00 1.11.M · PDF p. 196Spec wording“M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.” | 01 91 00 1.11.M | 196 | – |
| Test / cert. | Test / cert.Review operation and maintenance training program developed by the Contractor. ...General Commissioning Requirements01 91 00 1.11.N · PDF p. 196Spec wording“N. Review operation and maintenance training program developed by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.” | 01 91 00 1.11.N | 196 | – |
| Test / cert. | Test / cert.Prepare commissioning Field Observation ReportsGeneral Commissioning Requirements01 91 00 1.11.O · PDF p. 196Spec wording“O. Prepare commissioning Field Observation Reports.” | 01 91 00 1.11.O | 196 | – |
| Test / cert. | Test / cert.Prepare the Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.11.P · PDF p. 196Spec wording“P. Prepare the Final Commissioning Report.” | 01 91 00 1.11.P | 196 | – |
| Test / cert. | Test / cert.Return to the site at 10 months into the 12 ...General Commissioning Requirements01 91 00 1.11.Q · PDF p. 196Spec wording“Q. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Systems Functional Performance Testing. Also interview facility staff and identify problems or concerns they have operating the building as originally intended. Make suggestions for improvements and for ...” | 01 91 00 1.11.Q | 196 | – |
| Test / cert. | Test / cert.Assemble the final commissioning documentation, including the Final Commissioning Report ...General Commissioning Requirements01 91 00 1.11.R · PDF p. 196Spec wording“R. Assemble the final commissioning documentation, including the Final Commissioning Report and Addendum to the Final Commissioning Report.” | 01 91 00 1.11.R | 196 | – |
| Test / cert. | Test / cert.Commissioning PlanGeneral Commissioning Requirements01 91 00 1.12.A · PDF p. 197Spec wording“A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited, to the following: 1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a ...” | 01 91 00 1.12.A | 197 | – |
| Test / cert. | Test / cert.Systems Functional Performance Test ProceduresGeneral Commissioning Requirements01 91 00 1.12.B · PDF p. 197-198Spec wording“B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested. Preliminary Systems Functional ...” | 01 91 00 1.12.B | 197-198 | – |
| Test / cert. | Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.12.C · PDF p. 198Spec wording“C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre-Functional Checklists. Pre-Functional Checklists shall be completed and signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing. Inaccurate or incomplete Pre-Functional ...” | 01 91 00 1.12.C | 198 | – |
| Test / cert. | Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.12.D · PDF p. 198Spec wording“D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application shall be included with data. Commissioning Agent Will compile test and inspection reports and test and ...” | 01 91 00 1.12.D | 198 | – |
| Test / cert. | Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.12.E · PDF p. 198Spec wording“E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results.” | 01 91 00 1.12.E | 198 | – |
| Test / cert. | Test / cert.Commissioning Issues LogGeneral Commissioning Requirements01 91 00 1.12.F · PDF p. 199Spec wording“F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues Log will identify and track issues as they are ...” | 01 91 00 1.12.F | 199 | – |
| Test / cert. | Test / cert.Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.G · PDF p. 200Spec wording“G. Final Commissioning Report: The Commissioning Agent will document results of the commissioning process, including unresolved issues, and performance of systems, subsystems, and equipment. The Commissioning Report will indicate whether systems, subsystems, and equipment have been properly installed and are performing according to the Contract Documents. This report will be used by the Department of Veterans ...” | 01 91 00 1.12.G | 200 | – |
| Test / cert. | Test / cert.Addendum to Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.H · PDF p. 200-201Spec wording“H. Addendum to Final Commissioning Report: The Commissioning Agent will prepare an Addendum to the Final Commissioning Report near the end of the Warranty Period. The Addendum will indicate whether systems, subsystems, and equipment are complete and continue to perform according to the Contract Documents. The Addendum to the Final Commissioning Report shall include, but is not limited to, the following: 1. ...” | 01 91 00 1.12.H | 200-201 | – |
| Test / cert. | Test / cert.Systems ManualGeneral Commissioning Requirements01 91 00 1.12.I · PDF p. 201Spec wording“I. Systems Manual: The Commissioning Agent will gather required information and compile the Systems Manual. The Systems Manual will include, but is not limited to, the following: 1. Design Narrative, including system narratives, schematics, single-line diagrams, flow diagrams, equipment schedules, and changes made throughout the Project. 2. Reference to Final Commissioning Plan. 3. Reference to Final Commissioning ...” | 01 91 00 1.12.I | 201 | – |
| Test / cert. | Test / cert.Preliminary Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.A · PDF p. 201-202Spec wording“A. Preliminary Commissioning Plan Submittal: The Commissioning Agent has prepared a Preliminary Commissioning Plan based on the final Construction Documents. The Preliminary Commissioning Plan is included as an Appendix to this specification section. The Preliminary Commissioning Plan is provided for information only. It contains preliminary information about the following commissioning activities: 1. The ...” | 01 91 00 1.13.A | 201-202 | – |
| Test / cert. | Test / cert.Final Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.B · PDF p. 202Spec wording“B. Final Commissioning Plan Submittal: Based on the Final Construction Documents and the Contractor's project team, the Commissioning Agent will prepare the Final Commissioning Plan as described in this section. The Commissioning Agent will submit three hard copies and three sets of electronic files of Final Commissioning Plan. The Contractor shall review the Commissioning Plan and provide any comments to the VA. ...” | 01 91 00 1.13.B | 202 | three hard copies; three sets; electronic files |
| Test / cert. | Test / cert.Systems Functional Performance Test ProcedureGeneral Commissioning Requirements01 91 00 1.13.C · PDF p. 202Spec wording“C. Systems Functional Performance Test Procedure: The Commissioning Agent will submit preliminary Systems Functional Performance Test Procedures to the Contractor, and the VA for review and comment. The Contractor shall return review comments to the VA and the Commissioning Agent. The VA will also return review comments to the Commissioning Agent. The Commissioning Agent will incorporate review comments into the ...” | 01 91 00 1.13.C | 202 | – |
| Test / cert. | Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.13.D · PDF p. 202Spec wording“D. Pre-Functional Checklists: The Commissioning Agent will submit Pre-Functional Checklists to be completed by the Contractor.” | 01 91 00 1.13.D | 202 | – |
| Test / cert. | Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.13.E · PDF p. 202Spec wording“E. Test and Inspection Reports: The Commissioning Agent will submit test and inspection reports to the VA with copies to the Contractor and the Architect/Engineer.” | 01 91 00 1.13.E | 202 | – |
| Test / cert. | Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.13.F · PDF p. 202Spec wording“F. Corrective Action Documents: The Commissioning Agent will submit corrective action documents to the VA COR with copies to the Contractor and Architect.” | 01 91 00 1.13.F | 202 | – |
| Test / cert. | Test / cert.Preliminary Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.G · PDF p. 202-203Spec wording“G. Preliminary Commissioning Report Submittal: The Commissioning Agent will submit three electronic copies of the preliminary commissioning report. One electronic copy, with review comments, will be returned to the Commissioning Agent for preparation of the final submittal.” | 01 91 00 1.13.G | 202-203 | three electronic copies; One electronic copy |
| Test / cert. | Test / cert.Final Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.H · PDF p. 203Spec wording“H. Final Commissioning Report Submittal: The Commissioning Agent will submit four sets of electronically formatted information of the final commissioning report to the VA. The final submittal will incorporate comments as directed by the VA.” | 01 91 00 1.13.H | 203 | four sets; electronically |
| Test / cert. | Test / cert.Data for Commissioning:General Commissioning Requirements01 91 00 1.13.I · PDF p. 203Spec wording“I. Data for Commissioning: 1. The Commissioning Agent will request in writing from the Contractor specific information needed about each piece of commissioned equipment or system to fulfill requirements of the Commissioning Plan. 2. The Commissioning Agent may request further documentation as is necessary for the commissioning process or to support other VA data collection requirements, including Construction ...” | 01 91 00 1.13.I | 203 | – |
| Test / cert. | Test / cert.The Commissioning Agent will be responsible for the overall management ...General Commissioning Requirements01 91 00 1.14.A · PDF p. 203Spec wording“A. The Commissioning Agent will be responsible for the overall management of the commissioning process as well as coordinating scheduling of commissioning tasks with the VA and the Contractor. As directed by the VA, the Contractor shall incorporate Commissioning tasks, including, but not limited to, Systems Functional Performance Testing (including predecessors) with the Master Construction Schedule.” | 01 91 00 1.14.A | 203 | – |
| Test / cert. | Test / cert.Within 30 days of contract award, the Contractor shall designate ...General Commissioning Requirements01 91 00 1.14.B · PDF p. 203Spec wording“B. Within 30 days of contract award, the Contractor shall designate a specific individual as the Commissioning Manager (CxM) to manage and lead the commissioning effort on behalf of the Contractor. The Commissioning Manager shall be the single point of contact and communications for all commissioning related services by the Contractor.” | 01 91 00 1.14.B | 203 | – |
| Test / cert. | Test / cert.Within 30 days of contract award, the Contractor shall ensure ...General Commissioning Requirements01 91 00 1.14.C · PDF p. 203-204Spec wording“C. Within 30 days of contract award, the Contractor shall ensure that each subcontractor designates specific individuals as Commissioning Representatives (CXR) to be responsible for commissioning related tasks. The Contractor shall ensure the designated Commissioning Representatives participate in the commissioning process as team members providing commissioning testing services, equipment operation, adjustments, ...” | 01 91 00 1.14.C | 203-204 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.A · PDF p. 206-208Spec wording“A. The following table outlines the roles and responsibilities for the Commissioning Team members during the Construction Phase: Construction Phase CxA = Commissioning Agent L = Lead COR = Contracting Officer's P = Participate Representative A = Approve Commissioning Roles & Responsibilities A/E = Design Arch/Engineer R = Review PC = Prime Contractor O = Optional O&M = Gov't Facility O&M Category Task Description ...” | 01 91 00 3.1.A | 206-208 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.B · PDF p. 208-210Spec wording“B. The following table outlines the roles and responsibilities for the Commissioning Team members during the Acceptance Phase: Acceptance Phase CxA = Commissioning Agent L = Lead COR = Contracting Officer's P = Participate Representative A = Approve A/E = Design Arch/Engineer Commissioning Roles & Responsibilities R = Review PC = Prime Contractor O = Optional O&M = Gov't Facility O&M Category Task Description CxA ...” | 01 91 00 3.1.B | 208-210 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.C · PDF p. 210-211Spec wording“C. The following table outlines the roles and responsibilities for the Commissioning Team members during the Warranty Phase: Warranty Phase CxA = Commissioning Agent L = Lead Commissioning Roles & Responsibilities Category Task Description Meetings Post-Occupancy User Review Meeting Site Periodic Site Visits Observations Functional Deferred and/or seasonal Testing Test Protocols Technical Issues Resolution Meetings ...” | 01 91 00 3.1.C | 210-211 | – |
| Test / cert. | Test / cert.The following procedures shall apply to all equipment and systems ...General Commissioning Requirements01 91 00 3.2.A · PDF p. 212-213Spec wording“A. The following procedures shall apply to all equipment and systems to be commissioned, according to Part 1, Systems to Be Commissioned. 1. Pre-Functional Checklists are important to ensure that the equipment and systems are hooked up and operational. These ensure that Systems Functional Performance Testing may proceed without unnecessary delays. Each system to be commissioned shall have a full Pre-Functional ...” | 01 91 00 3.2.A | 212-213 | – |
| Test / cert. | Test / cert.The Contractor shall clearly list any outstanding items of the ...General Commissioning Requirements01 91 00 3.3.A · PDF p. 213Spec wording“A. The Contractor shall clearly list any outstanding items of the initial startup and Pre-Functional Checklist procedures that were not completed successfully, at the bottom of the procedures form or on an attached sheet. The procedures form and any outstanding deficiencies shall be provided to the VA and the Commissioning Agent within two days of completion.” | 01 91 00 3.3.A | 213 | – |
| Test / cert. | Test / cert.The Commissioning Agent will review the report and submit comments ...General Commissioning Requirements01 91 00 3.3.B · PDF p. 213-214Spec wording“B. The Commissioning Agent will review the report and submit comments to the VA. The Commissioning Agent will work with the Contractor to correct and verify deficiencies or uncompleted items. The Commissioning Agent will involve the VA and others as necessary. The Contractor shall correct all areas that are noncompliant or incomplete in the checklists in a timely manner, and shall notify the VA and Commissioning ...” | 01 91 00 3.3.B | 213-214 | – |
| Test / cert. | Test / cert.The Contractor shall be responsible for resolution of deficiencies as ...General Commissioning Requirements01 91 00 3.3.C · PDF p. 214Spec wording“C. The Contractor shall be responsible for resolution of deficiencies as directed the VA.” | 01 91 00 3.3.C | 214 | – |
| Test / cert. | Test / cert.The project may require startup and initial checkout to be ...General Commissioning Requirements01 91 00 3.4.A · PDF p. 214Spec wording“A. The project may require startup and initial checkout to be executed in phases. This phasing shall be planned and scheduled in a coordination meeting of the VA, Commissioning Agent, and the Contractor. Results will be added to the master construction schedule and the commissioning schedule.” | 01 91 00 3.4.A | 214 | – |
| Test / cert. | Test / cert.Trending is a method of testing as a standalone method ...General Commissioning Requirements01 91 00 3.5.A · PDF p. 214Spec wording“A. Trending is a method of testing as a standalone method or to augment manual testing. The Contractor shall trend any and all points of the system or systems at intervals specified below.” | 01 91 00 3.5.A | 214 | – |
| Test / cert. | Test / cert.Alarms are a means to notify the system operator that ...General Commissioning Requirements01 91 00 3.5.B · PDF p. 214-215Spec wording“B. Alarms are a means to notify the system operator that abnormal conditions are present in the system. Alarms shall be structured into three tiers – Critical, Priority, and Maintenance. 1. Critical alarms are intended to be alarms that require the immediate attention of and action by the Operator. These alarms shall be displayed on the Operator Workstation in a popup style window that is graphically linked to the ...” | 01 91 00 3.5.B | 214-215 | – |
| Test / cert. | Test / cert.The Contractor shall provide a wireless internet network in the ...General Commissioning Requirements01 91 00 3.5.C · PDF p. 215Spec wording“C. The Contractor shall provide a wireless internet network in the building for use during controls programming, checkout, and commissioning. This network will allow project team members to more effectively program, view, manipulate and test control devices while being in the same room as the controlled device.” | 01 91 00 3.5.C | 215 | – |
| Test / cert. | Test / cert.The Contractor shall provide graphical trending through the DDC control ...General Commissioning Requirements01 91 00 3.5.D · PDF p. 215-227Spec wording“D. The Contractor shall provide graphical trending through the DDC control system of systems being commissioned. Trending requirements are indicated below and included with the Systems Functional Performance Test Procedures. Trending shall occur before, during and after Systems Functional Performance Testing. The Contractor shall be responsible for producing graphical representations of the trended DDC points that ...” | 01 91 00 3.5.D | 215-227 | – |
| Test / cert. | Test / cert.The Contractor shall provide the following information prior to Systems ...General Commissioning Requirements01 91 00 3.5.E · PDF p. 227-228Spec wording“E. The Contractor shall provide the following information prior to Systems Functional Performance Testing. Any documentation that is modified after submission shall be recorded and resubmitted to the COR and Commissioning Agent. 1. Point-to-Point checkout documentation; 2. Sensor field calibration documentation including system name, sensor/point name, measured value, DDC value, and Correction Factor. 3. A sensor ...” | 01 91 00 3.5.E | 227-228 | – |
| O&M | O&MTraining Preparation ConferenceGeneral Commissioning Requirements01 91 00 3.9.A · PDF p. 236Spec wording“A. Training Preparation Conference: Before operation and maintenance training, the Commissioning Agent will convene a training preparation conference to include VA's COR, VA's Operations and Maintenance personnel, and the Contractor. The purpose of this conference will be to discuss and plan for Training and Demonstration of VA Operations and Maintenance personnel.” | 01 91 00 3.9.A | 236 | – |
| O&M | O&MThe Contractor shall provide training and demonstration as required by ...General Commissioning Requirements01 91 00 3.9.B · PDF p. 236Spec wording“B. The Contractor shall provide training and demonstration as required by other Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 sections. The Training and Demonstration shall include, but is not limited to, the following: 1. Review the Contract Documents. 2. Review installed systems, subsystems, and equipment. 3. Review instructor qualifications. 4. Review instructional ...” | 01 91 00 3.9.B | 236 | – |
| O&M | O&MTraining Module SubmittalsGeneral Commissioning Requirements01 91 00 3.9.C · PDF p. 236-237Spec wording“C. Training Module Submittals: The Contractor shall submit the following information to the VA and the Commissioning Agent: 1. Instruction Program: Submit two copies of outline of instructional program for demonstration and training, including a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training ...” | 01 91 00 3.9.C | 236-237 | two copies; DVD; 3-ring; binders; binder |
| O&M | O&MQuality Assurance:General Commissioning Requirements01 91 00 3.9.D · PDF p. 237Spec wording“D. Quality Assurance: 1. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. 2. Instructor Qualifications: A factory authorized service representative, complying with ...” | 01 91 00 3.9.D | 237 | – |
| O&M | O&MTraining Coordination:General Commissioning Requirements01 91 00 3.9.E · PDF p. 238Spec wording“E. Training Coordination: 1. Coordinate instruction schedule with VA's operations. Adjust schedule as required to minimize disrupting VA's operations. 2. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. 3. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction ...” | 01 91 00 3.9.E | 238 | – |
| O&M | O&MInstruction Program:General Commissioning Requirements01 91 00 3.9.F · PDF p. 238Spec wording“F. Instruction Program: 1. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections, and as follows: a. Fire protection systems, including fire alarm, fire pumps, and fire suppression systems. b. Intrusion detection systems. c. Conveying systems, including elevators, wheelchair ...” | 01 91 00 3.9.F | 238 | – |
| O&M | O&MTraining ModulesGeneral Commissioning Requirements01 91 00 3.9.G · PDF p. 239-240Spec wording“G. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participants are expected to master. For each module, include instruction for the following: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment descriptions. b. Performance and design criteria if ...” | 01 91 00 3.9.G | 239-240 | – |
| O&M | O&MTraining Execution:General Commissioning Requirements01 91 00 3.9.H · PDF p. 240-241Spec wording“H. Training Execution: 1. Preparation: Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a combined training manual. Set up instructional equipment at instruction location. 2. Instruction: a. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate ...” | 01 91 00 3.9.H | 240-241 | – |
| O&M | O&MDemonstration and Training Recording:General Commissioning Requirements01 91 00 3.9.I · PDF p. 241-242Spec wording“I. Demonstration and Training Recording: 1. General: Engage a qualified commercial photographer to record demonstration and training. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. At beginning of each training module, record each chart containing learning objective and lesson outline. 2. Video Format: ...” | 01 91 00 3.9.I | 241-242 | DVD |
Division 02 Existing conditions 14 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Monitoring, Inspection and Testing by Contractor CPIH/CIHTraditional Asbestos Abatement02 82 11 2.2.C · PDF p. 285-286Spec wording“C. Monitoring, Inspection and Testing by Contractor CPIH/CIH: The Contractor's CPIH/CIH is responsible for managing all monitoring, inspections, and testing required by these specifications, as well as any and all regulatory requirements adopted by these specifications. The CPIH/CIH is responsible for the continuous monitoring of all subsystems and procedures which could affect the health and safety of the ...” | 02 82 11 2.2.C | 285-286 | |
| Training | TrainingPre-Start Meeting Submittals:Traditional Asbestos Abatement02 82 11 2.4.A · PDF p. 287Spec wording“A. Pre-Start Meeting Submittals: 1. Submit to the VA a minimum of 14 days prior to the pre-start meeting the following for review and approval. Meeting this requirement is a prerequisite for the pre-start meeting for this project: a. Submit a detailed work schedule for the entire project reflecting contract documents and the phasing/schedule requirements from the CPM chart. b. Submit a staff organization chart ...” | 02 82 11 2.4.A | 287 | – |
| Test / cert. | Test / cert.Submittals at Completion of AbatementTraditional Asbestos Abatement02 82 11 2.4.C · PDF p. 291Spec wording“C. Submittals at Completion of Abatement: The CPIH/CIH shall submit a project report consisting of the daily log book requirements and documentation of events during the abatement project including Waste Shipment Records signed by the landfill's agent. It will also include information on the containment and transportation of waste from the containment with applicable Chain of Custody forms. The report shall include ...” | 02 82 11 2.4.C | 291 | – |
| Test / cert. | Test / cert.Laboratory Testing of PCM Clearance SamplesTraditional Asbestos Abatement02 82 11 3.6.G · PDF p. 313Spec wording“G. Laboratory Testing of PCM Clearance Samples: The services of an AIHA accredited laboratory will be employed by the VA to perform analysis for the PCM air samples. The accredited laboratory shall be successfully participating in the AIHA Proficiency Analytical Testing (PAT) program. Samples will be sent daily by the VPIH/CIH so that verbal/faxed reports can be received within 24-36 hours. A complete record, ...” | 02 82 11 3.6.G | 313 | – |
| Test / cert. | Test / cert.Laboratory Testing of Tem SamplesTraditional Asbestos Abatement02 82 11 3.6.H · PDF p. 314Spec wording“H. Laboratory Testing of Tem Samples: Samples shall be sent by the VPIH/CIH to a NIST NVLAP accredited laboratory for analysis by TEM. The laboratory shall be successfully participating in the NIST Airborne Asbestos Analysis (TEM) program. Verbal/faxed results from the laboratory shall be available within 24-36 hours after receipt of the samples. A complete record, certified by the laboratory, of all TEM results ...” | 02 82 11 3.6.H | 314 | – |
| Test / cert. | Test / cert.Laboratory Testing of Bulk SamplesTraditional Asbestos Abatement02 82 11 3.6.I · PDF p. 314Spec wording“I. Laboratory Testing of Bulk Samples: Samples shall be sent by the VPIH/CIH or CPIH/CIH to a NIST NVLAP accredited laboratory for analysis by PLM. The laboratory shall successfully participate in the NIST NVLAP Bulk Asbestos Analysis (PLM) program. Verbal/faxed results from the laboratory shall be available within 24-36 hours after receipt of the samples. A complete record, certified by the laboratory, of all PLM ...” | 02 82 11 3.6.I | 314 | – |
| Test / cert. | Test / cert.Completion of Abatement Work:Traditional Asbestos Abatement02 82 11 3.7.A · PDF p. 314Spec wording“A. Completion of Abatement Work: 1. After thorough decontamination, seal negative air machines with 2 layers of 6-mil poly and duct tape to form a tight seal at the intake/outlet ends before removal from the regulated area. Complete asbestos abatement work upon meeting the regulated area visual and air clearance criteria and fulfilling the following: a. Remove all equipment and materials from the project area. b. ...” | 02 82 11 3.7.A | 314 | – |
| Test / cert. | Test / cert.Certificate of Completion By ContractorTraditional Asbestos Abatement02 82 11 3.7.B · PDF p. 314Spec wording“B. Certificate of Completion By Contractor: The CPIH/CIH shall complete and sign the "Certificate of Completion" in accordance with Attachment 1 at the completion of the abatement and decontamination of the regulated area.” | 02 82 11 3.7.B | 314 | – |
| Test / cert. | Test / cert.Work ShiftsTraditional Asbestos Abatement02 82 11 3.7.C · PDF p. 314Spec wording“C. Work Shifts: All work shall generally be done during administrative hours (8:00 AM to 4:30 PM) Monday - Friday excluding Federal Holidays. Any change in the work schedule must be approved in writing by the VA Representative.” | 02 82 11 3.7.C | 314 | – |
| Test / cert. | Test / cert.Re-InsulationTraditional Asbestos Abatement02 82 11 3.7.D · PDF p. 315-319Spec wording“D. Re-Insulation: If required as part of the contract, replace all asbestos containing insulation/fire-proofing with suitable non-asbestos material. Provide SDS's for all replacement materials in advance of installation for VA approval. Refer to Section 23 07 11, HVAC, PLUMBING, AND BOILER PLANT INSULATION. ATTACHMENT #1 CERTIFICATE OF COMPLETION DATE: VA Project #: PROJECT NAME: Abatement Contractor: VAMC/ADDRESS: ...” | 02 82 11 3.7.D | 315-319 | – |
| Test / cert. | Test / cert.Test ReportsLead-Based Paint Removal And Disposal02 83 33.13 1.6.C · PDF p. 323Spec wording“C. Test Reports: Submit testing laboratory reports. 1. Submit air monitoring results within three working days, signed by testing laboratory employee performing air monitoring, employee analyzing sample, and CIH.” | 02 83 33.13 1.6.C | 323 | – |
| Training | TrainingCertificatesLead-Based Paint Removal And Disposal02 83 33.13 1.6.D · PDF p. 323Spec wording“D. Certificates: Certify completed lead training. 1. Submit certificate for each employee signed and dated by CIH and employee stating employee was trained.” | 02 83 33.13 1.6.D | 323 | – |
| Record docs | Record docsRecord Documents:Lead-Based Paint Removal And Disposal02 83 33.13 1.6.F · PDF p. 324Spec wording“F. Record Documents: 1. Completed and signed hazardous waste manifest from waste transporter. 2. Hazardous waste transporter permit. 3. Disposal facility hazardous waste permit. 4. Toxicity Characteristic Leaching Procedure (TCLP) test results to determine if waste is hazardous. 5. Paint disposal facility receipts and disposition reports. 6. Certification of medical examinations. 7. Medical Opinion that employee is ...” | 02 83 33.13 1.6.F | 324 | – |
| Warranty | WarrantyConstruction WarrantyLead-Based Paint Removal And Disposal02 83 33.13 1.8.A · PDF p. 326Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 02 83 33.13 1.8.A | 326 | – |
Division 03 Concrete 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Testing agency maintaining active participation in Program of Cement and ...Cast-In-Place Concrete03 30 00 1.3.B · PDF p. 356Spec wording“B. Testing agency maintaining active participation in Program of Cement and Concrete Reference Laboratory (CCRL) of National Institute of Standards and Technology. Accompany request for approval of testing agency with a copy of Report of Latest Inspection of Laboratory Facilities by CCRL.” | 03 30 00 1.3.B | 356 | – |
| Test / cert. | Test / cert.Mill Test Reports:Cast-In-Place Concrete03 30 00 1.6.C · PDF p. 357Spec wording“C. Mill Test Reports: 1. Reinforcing Steel. 2. Cement.” | 03 30 00 1.6.C | 357 | – |
| Training | TrainingManufacturer's Certificates:Cast-In-Place Concrete03 30 00 1.6.D · PDF p. 357Spec wording“D. Manufacturer's Certificates: 1. Abrasive aggregate. 2. Lightweight aggregate for structural concrete. 3. Air-entraining admixture. 4. Chemical admixtures, including chloride ion content. 5. Waterproof paper for curing concrete. 6. Liquid membrane-forming compounds for curing concrete. 7. Non-shrinking grout. 8. Liquid hardener. 9. Waterstops. 10. Expansion joint filler. 11. Adhesive binder.” | 03 30 00 1.6.D | 357 | binder |
| Test / cert. | Test / cert.Test Report for Concrete Mix DesignsCast-In-Place Concrete03 30 00 1.6.F · PDF p. 358Spec wording“F. Test Report for Concrete Mix Designs: Trial mixes including water-cement ratio or water-fly ash ratio curves, concrete mix ingredients, and admixtures.” | 03 30 00 1.6.F | 358 | – |
Division 04 Masonry 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test reports:Maintenance Of Masonry04 01 00 1.4.D · PDF p. 389Spec wording“D. Test reports: 1. Preconstruction test results of existing masonry mortar and units. 2. Recommended mortar mix and mortar materials sources.” | 04 01 00 1.4.D | 389 | – |
| Warranty | WarrantyConstruction WarrantyMaintenance Of Masonry04 01 00 1.9.A · PDF p. 390Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 04 01 00 1.9.A | 390 | – |
| Test / cert. | Test / cert.Test ReportsMasonry Mortaring04 05 13 1.4.C · PDF p. 393Spec wording“C. Test Reports: Certify each product complies with specifications. 1. Mortar. 2. Admixtures.” | 04 05 13 1.4.C | 393 | – |
| Warranty | WarrantyConstruction WarrantyMasonry Mortaring04 05 13 1.8.A · PDF p. 395Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 04 05 13 1.8.A | 395 | – |
| Test / cert. | Test / cert.Test ReportsMasonry Grouting04 05 16 1.4.C · PDF p. 398Spec wording“C. Test Reports: Certify each product complies with specifications. 1. Grout, each type. 2. Cement. 3. Aggregate.” | 04 05 16 1.4.C | 398 | – |
| Warranty | WarrantyConstruction WarrantyMasonry Grouting04 05 16 1.8.A · PDF p. 399Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 04 05 16 1.8.A | 399 | – |
| Test / cert. | Test / cert.Test reportsUnit Masonry04 20 00 1.4.E · PDF p. 403Spec wording“E. Test reports: Certify products comply with specifications.” | 04 20 00 1.4.E | 403 | – |
| Warranty | WarrantyConstruction WarrantyUnit Masonry04 20 00 1.9.A · PDF p. 404Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 04 20 00 1.9.A | 404 | – |
Division 06 Wood and plastics 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantyFinish Carpentry06 20 00 1.9.A · PDF p. 470Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 06 20 00 1.9.A | 470 | – |
Division 07 Roofing, insulation and waterproofing 19 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyManufacturer's Literature and Data:Preparation For Re-Roofing07 01 50.19 1.5.C · PDF p. 478-479Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Description of temporary roof system and components. 3. List of patching materials. 4. Recover board fastening requirements. 5. Temporary roofing installation instructions and removal instructions. Preparation instructions to receive new roofing. 6. Existing roofing warrantor's instructions.” | 07 01 50.19 1.5.C | 478-479 | – |
| Warranty | WarrantyField Inspection Reports:Preparation For Re-Roofing07 01 50.19 1.5.E · PDF p. 479Spec wording“E. Field Inspection Reports: 1. Certify warrantor inspected completed roofing and existing warranty remains in effect.” | 07 01 50.19 1.5.E | 479 | – |
| Warranty | WarrantyConstruction WarrantyPreparation For Re-Roofing07 01 50.19 1.8.A · PDF p. 480Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 01 50.19 1.8.A | 480 | – |
| Warranty | WarrantyExisting WarrantiesPreparation For Re-Roofing07 01 50.19 1.8.B · PDF p. 480Spec wording“B. Existing Warranties: Perform work to maintain existing roofing warranty in effect. 1. Notify warrantor before beginning, and upon completion of reroofing. 2. Obtain warrantor's instructions for maintaining existing warranty.” | 07 01 50.19 1.8.B | 480 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Modified Bituminous Sheet Waterproofing07 13 52 1.4.C · PDF p. 483Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.” | 07 13 52 1.4.C | 483 | – |
| Test / cert. | Test / cert.Test reportsModified Bituminous Sheet Waterproofing07 13 52 1.4.E · PDF p. 483Spec wording“E. Test reports: Certify products comply with specifications.” | 07 13 52 1.4.E | 483 | – |
| Warranty | WarrantyConstruction WarrantyModified Bituminous Sheet Waterproofing07 13 52 1.9.A · PDF p. 484Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 13 52 1.9.A | 484 | – |
| Warranty | WarrantyManufacturer's WarrantyModified Bituminous Sheet Waterproofing07 13 52 1.9.B · PDF p. 484Spec wording“B. Manufacturer's Warranty: Warrant waterproofing system against material and manufacturing defects and agree to repair any leak caused by a defect in the waterproofing system materials or workmanship of the installer. 1. Warranty Period: 10 years.” | 07 13 52 1.9.B | 484 | – |
| Warranty | WarrantyConstruction WarrantyThermal Insulation07 21 13 1.7.A · PDF p. 489Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 21 13 1.7.A | 489 | – |
| Test / cert. | Test / cert.Test reports:Fluid-Applied Membrane Air Barriers, Vapor Retarding07 27 27 1.4.D · PDF p. 497Spec wording“D. Test reports: 1. Submit field inspection and test reports.” | 07 27 27 1.4.D | 497 | – |
| Warranty | WarrantyConstruction WarrantyFluid-Applied Membrane Air Barriers, Vapor Retarding07 27 27 1.9.A · PDF p. 499Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 27 27 1.9.A | 499 | – |
| Test / cert. | Test / cert.Submit inspection and test reports to Contracting Officer's Representative within ...Fluid-Applied Membrane Air Barriers, Vapor Retarding07 27 27 3.3.E · PDF p. 502Spec wording“E. Submit inspection and test reports to Contracting Officer's Representative within seven calendar days of completing inspection and test.” | 07 27 27 3.3.E | 502 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Asphalt Shingles07 31 13 1.4.B · PDF p. 504Spec wording“B. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.” | 07 31 13 1.4.B | 504 | – |
| Warranty | WarrantyConstruction WarrantyAsphalt Shingles07 31 13 1.7.A · PDF p. 505Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 31 13 1.7.A | 505 | – |
| Warranty | WarrantyManufacturer's WarrantyAsphalt Shingles07 31 13 1.7.B · PDF p. 505Spec wording“B. Manufacturer's Warranty: Warrant asphalt shingles against material and manufacturing defects. 1. Material Warranty Period: 35 years. 2. Wind-Speed Warranty Period: Resist wind speeds up to 160 km/h (100 mph) for 15 years. 3. Algae-Resistance Warranty Period: No discoloration for 15 years.” | 07 31 13 1.7.B | 505 | – |
| Test / cert. | Test / cert.Furnish service of approved inspector to inspect firestopping in accordance ...Firestopping07 84 00 3.5.B · PDF p. 542Spec wording“B. Furnish service of approved inspector to inspect firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results. Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers.” | 07 84 00 3.5.B | 542 | – |
| Warranty | WarrantyConstruction WarrantyJoint Sealants07 92 00 1.9.A · PDF p. 545Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".” | 07 92 00 1.9.A | 545 | – |
| Warranty | WarrantyManufacturer WarrantyJoint Sealants07 92 00 1.9.B · PDF p. 545Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their sealant for a minimum of five (5) years from the date of installation and final acceptance by the Government. Submit manufacturer warranty.” | 07 92 00 1.9.B | 545 | – |
| Test / cert. | Test / cert.Inspect tested joints and report on following:Joint Sealants07 92 00 3.6.C · PDF p. 553Spec wording“C. Inspect tested joints and report on following: 1. Whether sealants in joints connected to pulled-out portion failed to adhere to joint substrates or tore cohesively. Include data on pull distance used to test each type of product and joint substrate. 2. Compare these results to determine if adhesion passes sealant manufacturer's field-adhesion hand-pull test criteria. 3. Whether sealants filled joint cavities ...” | 07 92 00 3.6.C | 553 | – |
Division 08 Doors, windows and hardware 35 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test reportsHollow Metal Doors And Frames08 11 13 1.4.E · PDF p. 556-557Spec wording“E. Test reports: Certify each product complies products comply with specifications. 1. Sound rated door.” | 08 11 13 1.4.E | 556-557 | – |
| Warranty | WarrantyConstruction WarrantyHollow Metal Doors And Frames08 11 13 1.8.A · PDF p. 558Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 11 13 1.8.A | 558 | – |
| Test / cert. | Test / cert.Test ReportsInterior Wood Doors08 14 00 1.4.F · PDF p. 566Spec wording“F. Test Reports: Indicate each product complies with specifications. 1. Screw Holding Capacity Test. 2. Cycle-Slam Test. 3. Hinge-Loading Test.” | 08 14 00 1.4.F | 566 | – |
| O&M | O&MOperation and Maintenance Data:Interior Wood Doors08 14 00 1.4.G · PDF p. 566Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 08 14 00 1.4.G | 566 | – |
| Warranty | WarrantyConstruction WarrantyInterior Wood Doors08 14 00 1.9.A · PDF p. 567Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 14 00 1.9.A | 567 | – |
| Warranty | WarrantyManufacturer's WarrantyInterior Wood Doors08 14 00 1.9.B · PDF p. 567Spec wording“B. Manufacturer's Warranty: Warrant interior factory finished flush wood doors against material and manufacturing defects. 1. Warranty Period: Lifetime of original installation.” | 08 14 00 1.9.B | 567 | – |
| Warranty | WarrantyConstruction WarrantyAccess Doors And Frames08 31 13 1.8.A · PDF p. 571Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 31 13 1.8.A | 571 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Aluminum Windows08 51 13 1.5.C · PDF p. 587-588Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.” | 08 51 13 1.5.C | 587-588 | – |
| Test / cert. | Test / cert.Test reportsAluminum Windows08 51 13 1.5.E · PDF p. 588Spec wording“E. Test reports: Indicate each product complies with specifications. 1. Windows. 2. Operating hardware.” | 08 51 13 1.5.E | 588 | – |
| Warranty | WarrantyConstruction WarrantyAluminum Windows08 51 13 1.8 · PDF p. 588-589Spec wording“Construction Warranty: FAR clause 52.246-21, "Warranty of Construction." Manufacturer's Warranty: Warrant windows against material and manufacturing defects. 1. Warranty Period: 10 years.” | 08 51 13 1.8 | 588-589 | – |
| Test / cert. | Test / cert.Manufacturer's Certificates:Transaction Window08 56 53 1.5.B · PDF p. 595Spec wording“B. Manufacturer's Certificates: 1. Certificate stating that fire-protection and fire-resistive glazing units meet code requirements for fire-resistance-rated assembly and applicable safety glazing requirements. 2. Certificate on solar heat gain coefficient when value is specified. 3. Certificate on "R" value when value is specified. 4. Certificate test reports confirming compliance with specified bullet resistive ...” | 08 56 53 1.5.B | 595 | – |
| Warranty | WarrantyManufacturer WarrantyTransaction Window08 56 53 1.5.C · PDF p. 596Spec wording“C. Manufacturer Warranty.” | 08 56 53 1.5.C | 596 | – |
| Spare parts | Spare partsManufacturer's Literature and Data:Transaction Window08 56 53 1.5.D · PDF p. 596Spec wording“D. Manufacturer's Literature and Data: 1. Glass, each kind required. 2. Insulating glass units. 3. Transparent (one-way vision glass) mirrors. 4. Elastic compound for metal sash glazing. 5. Putty, for wood sash glazing. 6. Glazing cushion. 7. Sealing compound. 8. Bullet resistive material. 9. Plastic glazing material, each type required.” | 08 56 53 1.5.D | 596 | – |
| Test / cert. | Test / cert.Preconstruction Adhesion and Compatibility Test ReportTransaction Window08 56 53 1.5.F · PDF p. 596Spec wording“F. Preconstruction Adhesion and Compatibility Test Report: Submit glazing sealant manufacturer's test report indicating glazing sealants were tested for adhesion to glass and glazing channel substrates and for compatibility with glass and other glazing materials.” | 08 56 53 1.5.F | 596 | – |
| Warranty | WarrantyConstruction WarrantyTransaction Window08 56 53 1.8.A · PDF p. 597Spec wording“A. Construction Warranty: Comply with the FAR clause 52.246-21 "Warranty of Construction".” | 08 56 53 1.8.A | 597 | – |
| Warranty | WarrantyManufacturer WarrantyTransaction Window08 56 53 1.8.B · PDF p. 597Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their glazing from the date of installation and final acceptance by the Government as follows. Submit manufacturer warranty. 1. Bullet resistive plastic material to remain visibly clear without discoloration for 10 years. 2. Workmanship Warranty: All materials shall be warranted against defects for a period of one (1) year for the date of receipt at the project ...” | 08 56 53 1.8.B | 597 | – |
| Warranty | WarrantyConstruction WarrantyDetention Window Screens08 56 66 1.6.A · PDF p. 604Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 56 66 1.6.A | 604 | – |
| Warranty | WarrantyAutomatic door operators shall be subject to the terms of ...Door Hardware08 71 00 1.4.1 · PDF p. 609Spec wording“1. Automatic door operators shall be subject to the terms of FAR Clause 52.246-21, except that the Warranty period shall be two years in lieu of one year for all items except as noted below:” | 08 71 00 1.4.1 | 609 | – |
| Warranty | WarrantyLocks, latchsets, and panic hardwareDoor Hardware08 71 00 1.4.2 · PDF p. 609Spec wording“2. Locks, latchsets, and panic hardware: 5 years.” | 08 71 00 1.4.2 | 609 | – |
| Warranty | WarrantyDoor closers and continuous hingesDoor Hardware08 71 00 1.4.3 · PDF p. 609Spec wording“3. Door closers and continuous hinges: 10 years.” | 08 71 00 1.4.3 | 609 | – |
| O&M | O&MIn accordance with Section 01 00 00, GENERAL REQUIREMENTS Article ...Door Hardware08 71 00 1.5.1 · PDF p. 609Spec wording“1. In accordance with Section 01 00 00, GENERAL REQUIREMENTS Article titled "INSTRUCTIONS", furnish maintenance manuals and instructions on all door hardware. Provide installation instructions with the submittal documentation.” | 08 71 00 1.5.1 | 609 | – |
| O&M | O&MLigature Resistant Door Alarm Riser DiagramDoor Hardware08 71 00 1.6.3 · PDF p. 609Spec wording“3. Ligature Resistant Door Alarm Riser Diagram: Prepare and submit 6 copies of shop drawings of electric riser diagram complete with all required equipment components. Submission shall be in accordance with requirements per Section 01 33 23 for review and approval by project CO. Along with shop drawing submittal provide installation data. At completion of project provide CO with operation and maintenance manuals” | 08 71 00 1.6.3 | 609 | 6 copies |
| Test / cert. | Test / cert.Certificate of Compliance and Test ReportsDoor Hardware08 71 00 1.6.7 · PDF p. 610Spec wording“7. Certificate of Compliance and Test Reports: Submit certificates that hardware conforms to the requirements specified herein. Certificates shall be accompanied by copies of reports as referenced. The testing shall have been conducted either in the manufacturer's plant and certified by an independent testing laboratory or conducted in an independent laboratory, within four years of submittal of reports for approval.” | 08 71 00 1.6.7 | 610 | – |
| Closeout step | Closeout stepHardware Set Symbols on DrawingsDoor Hardware08 71 00 1.9.1 · PDF p. 611Spec wording“1. Hardware Set Symbols on Drawings: Except for protective plates, door stops, mutes, thresholds and the like specified herein, hardware requirements for each door are indicated on drawings by symbols. Symbols for hardware sets consist of letters (e.g., "HW") followed by a number. Each number designates a set of hardware items applicable to a door type.” | 08 71 00 1.9.1 | 611 | – |
| Closeout step | Closeout stepKeyingDoor Hardware08 71 00 1.9.2 · PDF p. 611Spec wording“2. Keying: All cylinders shall be keyed into existing Grand Master Key System. Provide removable core cylinders that are removable only with a special key or tool without disassembly of knob or lockset. Cylinders shall be 6 or 7 pin type. Keying information shall be furnished at a later date by the COR.” | 08 71 00 1.9.2 | 611 | – |
| Spare parts | Spare partsKeyingDoor Hardware08 71 00 1.9.3 · PDF p. 611Spec wording“3. Keying: A new Great Grandmaster key shall be established for this project. The key system shall be small format (Best size and profile) removable core type as previously described. The key blanks shall be protected by a utility patent with a minimum seven years remaining on the patent from the start of construction, and protected by contract-controlled distribution. The manufacturer shall furnish code pattern ...” | 08 71 00 1.9.3 | 611 | electronic format |
| Closeout step | Closeout stepKeying information will be furnished to the Contractor by the CORDoor Hardware08 71 00 1.9.4 · PDF p. 611Spec wording“4. Keying information will be furnished to the Contractor by the COR.” | 08 71 00 1.9.4 | 611 | – |
| Spare parts | Spare partsSupply information regarding key control of cylinder locks to manufacturers ...Door Hardware08 71 00 1.9.5 · PDF p. 611Spec wording“5. Supply information regarding key control of cylinder locks to manufacturers of equipment having cylinder type locks. Notify COR immediately when and to whom keys or keying information is supplied. Return all such keys to the COR.” | 08 71 00 1.9.5 | 611 | – |
| Training | TrainingDemonstrate efficacy of mechanical hardware and electrical, and electronic hardware ...Door Hardware08 71 00 3.4.1 · PDF p. 630Spec wording“1. Demonstrate efficacy of mechanical hardware and electrical, and electronic hardware systems, including adjustment and maintenance procedures, to satisfaction of Resident/Project Engineer and VA Locksmith.” | 08 71 00 3.4.1 | 630 | – |
| Test / cert. | Test / cert.Manufacturer's Certificates:Glazing08 80 00 1.5.B · PDF p. 635-636Spec wording“B. Manufacturer's Certificates: 1. Certificate stating that fire-protection and fire-resistive glazing units meet code requirements for fire-resistance-rated assembly and applicable safety glazing requirements. 2. Certificate on solar heat gain coefficient when value is specified. 3. Certificate on "R" value when value is specified. 4. Certificate test reports confirming compliance with specified bullet resistive ...” | 08 80 00 1.5.B | 635-636 | – |
| Warranty | WarrantyManufacturer WarrantyGlazing08 80 00 1.5.C · PDF p. 636Spec wording“C. Manufacturer Warranty.” | 08 80 00 1.5.C | 636 | – |
| Spare parts | Spare partsManufacturer's Literature and Data:Glazing08 80 00 1.5.D · PDF p. 636Spec wording“D. Manufacturer's Literature and Data: 1. Glass, each kind required. 2. Insulating glass units. 3. Transparent (one-way vision glass) mirrors. 4. Elastic compound for metal sash glazing. 5. Putty, for wood sash glazing. 6. Glazing cushion. 7. Sealing compound. 8. Bullet resistive material. 9. Plastic glazing material, each type required.” | 08 80 00 1.5.D | 636 | – |
| Test / cert. | Test / cert.Preconstruction Adhesion and Compatibility Test ReportGlazing08 80 00 1.5.F · PDF p. 637Spec wording“F. Preconstruction Adhesion and Compatibility Test Report: Submit glazing sealant manufacturer's test report indicating glazing sealants were tested for adhesion to glass and glazing channel substrates and for compatibility with glass and other glazing materials.” | 08 80 00 1.5.F | 637 | – |
| Warranty | WarrantyConstruction WarrantyGlazing08 80 00 1.8.A · PDF p. 638Spec wording“A. Construction Warranty: Comply with the FAR clause 52.246-21 "Warranty of Construction".” | 08 80 00 1.8.A | 638 | – |
| Warranty | WarrantyManufacturer WarrantyGlazing08 80 00 1.8.B · PDF p. 638Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their glazing from the date of installation and final acceptance by the Government as follows. Submit manufacturer warranty. 1. Bullet resistive plastic material to remain visibly clear without discoloration for 10 years. 2. Insulating glass units to remain sealed for ten (10) years. 3. Laminated glass units to remain laminated for five (5) years. 4. ...” | 08 80 00 1.8.B | 638 | – |
Division 09 Finishes 13 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantyCeramic/Porcelain Tiling09 30 13 1.6.A · PDF p. 679Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 09 30 13 1.6.A | 679 | – |
| Test / cert. | Test / cert.Product Test ReportsAcoustical Metal Pan Ceilings09 51 33 1.4.D · PDF p. 698Spec wording“D. Product Test Reports: For each acoustical metal pan ceiling, for tests performed by manufacturer and witnessed by a qualified testing agency.” | 09 51 33 1.4.D | 698 | – |
| Test / cert. | Test / cert.Field quality-control reportsAcoustical Metal Pan Ceilings09 51 33 1.4.F · PDF p. 698Spec wording“F. Field quality-control reports.” | 09 51 33 1.4.F | 698 | – |
| O&M | O&MMaintenance DataAcoustical Metal Pan Ceilings09 51 33 1.5.A · PDF p. 698Spec wording“A. Maintenance Data: For finishes to include in maintenance manuals.” | 09 51 33 1.5.A | 698 | – |
| Spare parts | Spare partsFurnish extra materials that match products installed and that are ...Acoustical Metal Pan Ceilings09 51 33 1.6.A · PDF p. 698Spec wording“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Acoustical Metal Pans: Full-size units with sound absorber equal to (5) percent of quantity installed. 2. Suspension-System Components: Quantity of each grid, exposed molding, and trim equal to Five (5) percent of quantity installed. 3. Hold-Down ...” | 09 51 33 1.6.A | 698 | Full-size |
| O&M | O&MOperation and Maintenance Data:Resilient Base And Accessories09 65 13 1.4.E · PDF p. 710Spec wording“E. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 09 65 13 1.4.E | 710 | – |
| Warranty | WarrantyConstruction WarrantyResilient Base And Accessories09 65 13 1.8.A · PDF p. 710Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 09 65 13 1.8.A | 710 | – |
| Test / cert. | Test / cert.Test Reports:Resilient Tile Flooring09 65 19 1.3.F · PDF p. 713Spec wording“F. Test Reports: 1. Abrasion resistance: Depth of wear for each tile type and color and volume loss of tile, certified by independent laboratory. Tested per ASTM F510/F510M. 2. Moisture and pH test results as per Section 09 05 16, SUBSURFACE PREPARATION FOR FLOOR FINISHES.” | 09 65 19 1.3.F | 713 | – |
| Warranty | WarrantyConstruction WarrantyResilient Tile Flooring09 65 19 1.7.A · PDF p. 715Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 09 65 19 1.7.A | 715 | – |
| O&M | O&MMaintenance DataCarpeting09 68 00 1.4.E · PDF p. 721Spec wording“E. Maintenance Data: Carpet manufacturer's maintenance instructions describing recommended type of cleaning equipment and material, spotting and cleaning methods and cleaning cycles.” | 09 68 00 1.4.E | 721 | – |
| Warranty | WarrantyManufacturer's warrantyCarpeting09 68 00 1.4.G · PDF p. 721Spec wording“G. Manufacturer's warranty.” | 09 68 00 1.4.G | 721 | – |
| Warranty | WarrantyConstruction WarrantyCarpeting09 68 00 1.7.A · PDF p. 722Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 09 68 00 1.7.A | 722 | – |
| Warranty | WarrantyManufacturer WarrantyCarpeting09 68 00 1.7.B · PDF p. 722Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their carpet for a minimum of ten (10) years from date of installation and final acceptance by the Government. Submit manufacturer warranty.” | 09 68 00 1.7.B | 722 | – |
Division 10 Specialties 5 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantySignage10 14 00 1.6.A · PDF p. 754Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 10 14 00 1.6.A | 754 | – |
| O&M | O&MOperation and Maintenance Data:Toilet, Bath, And Laundry Accessories10 28 00 1.4.G · PDF p. 766Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 10 28 00 1.4.G | 766 | – |
| Warranty | WarrantyConstruction WarrantyToilet, Bath, And Laundry Accessories10 28 00 1.8.A · PDF p. 766Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 10 28 00 1.8.A | 766 | – |
| O&M | O&MMaintenance dataMetal Lockers10 51 13 1.4.D · PDF p. 776Spec wording“D. Maintenance data: For Adjusting, repairing, and replacement of the doors, drawers, and mechanisms which shall include a maintenance manual with product specifications.” | 10 51 13 1.4.D | 776 | – |
| Warranty | WarrantySpecial WarrantyMetal Lockers10 51 13 1.9.A · PDF p. 777Spec wording“A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of metal lockers that fail in materials or workmanship, excluding finish, within specified warranty period. 1. Failures include, but are not limited to, the following: a. Structural failures. b. Faulty operation of latches and other door hardware. 2. Damage from deliberate destruction and vandalism is ...” | 10 51 13 1.9.A | 777 | – |
Division 12 Furnishings 5 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantyManufactured Wood Casework12 32 00 1.5.A · PDF p. 785Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".” | 12 32 00 1.5.A | 785 | – |
| Warranty | WarrantyManufacturer WarrantyManufactured Wood Casework12 32 00 1.5.B · PDF p. 785Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their wood casework for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer warranty.” | 12 32 00 1.5.B | 785 | – |
| Closeout step | Closeout stepProvide operational and cleaning manuals and verbal instructions in accordance ...Manufactured Wood Casework12 32 00 3.7.A · PDF p. 792Spec wording“A. Provide operational and cleaning manuals and verbal instructions in accordance with Article INSTRUCTIONS, SECTION 01 00 00, GENERAL REQUIREMENTS.” | 12 32 00 3.7.A | 792 | – |
| Training | TrainingProvide in service training both prior to and after facility ...Manufactured Wood Casework12 32 00 3.7.B · PDF p. 792Spec wording“B. Provide in service training both prior to and after facility opening. Coordinate in service activities with COR.” | 12 32 00 3.7.B | 792 | – |
| Closeout step | Closeout stepCommencing at least seven (7) days prior to opening of ...Manufactured Wood Casework12 32 00 3.7.C · PDF p. 792Spec wording“C. Commencing at least seven (7) days prior to opening of facility, provide one (1) four (4) hour day of on-site orientation and technical instruction on use and cleaning procedures application to products and systems specified herein.” | 12 32 00 3.7.C | 792 | – |
Division 21 Fire suppression (sprinklers) 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MSubmit as one package in accordance with Section 01 33 ...Wet-Pipe Sprinkler Systems21 13 13 1.4.A · PDF p. 802-804Spec wording“A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting ...” | 21 13 13 1.4.A | 802-804 | binders; electronically; pdf; full size; One complete set; AutoCAD |
| O&M | O&MFurnish the services of a competent instructor for not less ...Wet-Pipe Sprinkler Systems21 13 13 3.3 · PDF p. 811Spec wording“Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.” | 21 13 13 3.3 | 811 | – |
Division 22 Plumbing 60 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MPlumbing Maintenance Data and Operating Instructions:Common Work Results For Plumbing22 05 11 1.4.J · PDF p. 821Spec wording“J. Plumbing Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all ...” | 22 05 11 1.4.J | 821 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.A · PDF p. 826Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 05 11 1.7.A | 826 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.B · PDF p. 826Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions will be in electronic version on CD or DVD. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation will be included in ...” | 22 05 11 1.7.B | 826 | electronic version; CD; DVD |
| Record docs | Record docsThe installing Contractor will maintain as-built drawings of each completed ...Common Work Results For Plumbing22 05 11 1.7.C · PDF p. 826Spec wording“C. The installing Contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 22 05 11 1.7.C | 826 | AutoCAD; CD; DVD; CAD |
| Record docs | Record docsThe as-built drawings will indicate the location and type of ...Common Work Results For Plumbing22 05 11 1.7.D · PDF p. 826Spec wording“D. The as-built drawings will indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 22 05 11 1.7.D | 826 | – |
| Record docs | Record docsCertification documentation will be provided to COR 21 working days ...Common Work Results For Plumbing22 05 11 1.7.E · PDF p. 826-827Spec wording“E. Certification documentation will be provided to COR 21 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results will ...” | 22 05 11 1.7.E | 826-827 | – |
| Test / cert. | Test / cert.Startup of equipment will be performed as described in the ...Common Work Results For Plumbing22 05 11 3.7.A · PDF p. 840Spec wording“A. Startup of equipment will be performed as described in the equipment specifications. Vibration within specified tolerance will be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.” | 22 05 11 3.7.A | 840 | – |
| O&M | O&MAll new and temporary equipment and all elements of each ...Common Work Results For Plumbing22 05 11 3.9.A · PDF p. 840Spec wording“A. All new and temporary equipment and all elements of each assembly will be included.” | 22 05 11 3.9.A | 840 | – |
| O&M | O&MData sheet on each device listing model, size, capacity, pressure, ...Common Work Results For Plumbing22 05 11 3.9.B · PDF p. 840Spec wording“B. Data sheet on each device listing model, size, capacity, pressure, speed, horsepower, impeller size, and other information will be included.” | 22 05 11 3.9.B | 840 | – |
| O&M | O&MManufacturer's installation, maintenance, repair, and operation instructions for each device ...Common Work Results For Plumbing22 05 11 3.9.C · PDF p. 840Spec wording“C. Manufacturer's installation, maintenance, repair, and operation instructions for each device will be included. Assembly drawings and parts lists will also be included. A summary of operating precautions and reasons for precautions will be included in the Operations and Maintenance Manual.” | 22 05 11 3.9.C | 840 | – |
| O&M | O&MLubrication instructions, type and quantity of lubricant will be included ...Common Work Results For Plumbing22 05 11 3.9.D · PDF p. 841Spec wording“D. Lubrication instructions, type and quantity of lubricant will be included.” | 22 05 11 3.9.D | 841 | – |
| O&M | O&MSchematic diagrams and wiring diagrams of all control systems corrected ...Common Work Results For Plumbing22 05 11 3.9.E · PDF p. 841Spec wording“E. Schematic diagrams and wiring diagrams of all control systems corrected to include all field modifications will be included.” | 22 05 11 3.9.E | 841 | – |
| O&M | O&MSet points of all interlock devices will be listedCommon Work Results For Plumbing22 05 11 3.9.F · PDF p. 841Spec wording“F. Set points of all interlock devices will be listed.” | 22 05 11 3.9.F | 841 | – |
| O&M | O&MTrouble-shooting guide for the control system troubleshooting will be inserted ...Common Work Results For Plumbing22 05 11 3.9.G · PDF p. 841Spec wording“G. Trouble-shooting guide for the control system troubleshooting will be inserted into the Operations and Maintenance Manual.” | 22 05 11 3.9.G | 841 | – |
| O&M | O&MThe control system sequence of operation corrected with submittal review ...Common Work Results For Plumbing22 05 11 3.9.H · PDF p. 841Spec wording“H. The control system sequence of operation corrected with submittal review comments will be inserted into the Operations and Maintenance Manual.” | 22 05 11 3.9.H | 841 | – |
| O&M | O&MEmergency procedures for shutdown and startup of equipment and systemsCommon Work Results For Plumbing22 05 11 3.9.I · PDF p. 841Spec wording“I. Emergency procedures for shutdown and startup of equipment and systems.” | 22 05 11 3.9.I | 841 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Common Work Results For Plumbing22 05 11 3.10.A · PDF p. 841Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 05 11 3.10.A | 841 | – |
| O&M | O&MComplete operating and maintenance manual shall including wiring diagrams, technical ...Meters And Gauges For Plumbing Piping22 05 19 1.4.D · PDF p. 843Spec wording“D. Complete operating and maintenance manual shall including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the system. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and ...” | 22 05 19 1.4.D | 843 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Meters And Gauges For Plumbing Piping22 05 19 1.5.A · PDF p. 843Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 05 19 1.5.A | 843 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Meters And Gauges For Plumbing Piping22 05 19 3.3.A · PDF p. 846Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 05 19 3.3.A | 846 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Meters And Gauges For Plumbing Piping22 05 19 3.3.B · PDF p. 846Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 05 19 3.3.B | 846 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Meters And Gauges For Plumbing Piping22 05 19 3.4.A · PDF p. 846Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 05 19 3.4.A | 846 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General-Duty Valves For Plumbing Piping22 05 23 1.4.E · PDF p. 849-850Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance. 4. Piping ...” | 22 05 23 1.4.E | 849-850 | – |
| Test / cert. | Test / cert.Testing and adjusting of balancing valves shall be performed by ...General-Duty Valves For Plumbing Piping22 05 23 3.4.D · PDF p. 856Spec wording“D. Testing and adjusting of balancing valves shall be performed by an independent NEBB Accredited Test and Balance Contractor. A final settings and flow report shall be submitted to the VA Contracting Officer's Representative (COR).” | 22 05 23 3.4.D | 856 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General-Duty Valves For Plumbing Piping22 05 23 3.5.A · PDF p. 856Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 05 23 3.5.A | 856 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...General-Duty Valves For Plumbing Piping22 05 23 3.5.B · PDF p. 856Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 05 23 3.5.B | 856 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...General-Duty Valves For Plumbing Piping22 05 23 3.6.A · PDF p. 856Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 05 23 3.6.A | 856 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.A · PDF p. 863Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 07 11 1.6.A | 863 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.B · PDF p. 863Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included in the ...” | 22 07 11 1.6.B | 863 | electronic version; DVD |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Plumbing Insulation22 07 11 1.6.C · PDF p. 863Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 07 11 1.6.C | 863 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided prior to submitting the request ...Plumbing Insulation22 07 11 1.6.D · PDF p. 863Spec wording“D. Certification documentation shall be provided prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 07 11 1.6.D | 863 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Water Distribution22 11 00 1.4.D · PDF p. 878Spec wording“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets and information for ordering replacement parts: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 11 00 1.4.D | 878 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Facility Water Distribution22 11 00 1.7.A · PDF p. 878Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 11 00 1.7.A | 878 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Facility Water Distribution22 11 00 1.7.B · PDF p. 878-879Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included in the ...” | 22 11 00 1.7.B | 878-879 | electronic version; DVD |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Facility Water Distribution22 11 00 1.7.C · PDF p. 879Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 11 00 1.7.C | 879 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided to COR 10 working days ...Facility Water Distribution22 11 00 1.7.D · PDF p. 879Spec wording“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certificate if applicable that all results of tests were within limits specified. If a certificate is not ...” | 22 11 00 1.7.D | 879 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Facility Water Distribution22 11 00 3.5.A · PDF p. 885Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 11 00 3.5.A | 885 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Domestic Water Pumps22 11 23 1.4.F · PDF p. 888Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 11 23 1.4.F | 888 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Domestic Water Pumps22 11 23 1.6.A · PDF p. 889Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 11 23 1.6.A | 889 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Domestic Water Pumps22 11 23 1.6.B · PDF p. 890Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included in the ...” | 22 11 23 1.6.B | 890 | electronic version; DVD |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Domestic Water Pumps22 11 23 1.6.C · PDF p. 890Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 11 23 1.6.C | 890 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided to COR 10 working days ...Domestic Water Pumps22 11 23 1.6.D · PDF p. 890Spec wording“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 11 23 1.6.D | 890 | – |
| Test / cert. | Test / cert.Make tests as recommended by product manufacturer and listed standards ...Domestic Water Pumps22 11 23 3.1.A · PDF p. 892Spec wording“A. Make tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 11 23 3.1.A | 892 | – |
| Test / cert. | Test / cert.System TestDomestic Water Pumps22 11 23 3.1.B · PDF p. 892Spec wording“B. System Test: After installation is completed provide an operational test of the completed system including flow rates, pressure compliance, alarms and all control functions.” | 22 11 23 3.1.B | 892 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Domestic Water Pumps22 11 23 3.1.C · PDF p. 892Spec wording“C. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 11 23 3.1.C | 892 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Domestic Water Pumps22 11 23 3.1.D · PDF p. 892Spec wording“D. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Contractor shall provide a minimum of 10 working days prior to startup and testing.” | 22 11 23 3.1.D | 892 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Domestic Water Pumps22 11 23 3.3.A · PDF p. 892Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 11 23 3.3.A | 892 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Sanitary And Vent Piping22 13 00 1.4.E · PDF p. 897Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 13 00 1.4.E | 897 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Facility Sanitary And Vent Piping22 13 00 1.6.A · PDF p. 897Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 13 00 1.6.A | 897 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Facility Sanitary And Vent Piping22 13 00 3.6.A · PDF p. 904Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 13 00 3.6.A | 904 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Electric Domestic Water Heaters22 33 00 1.4.G · PDF p. 907Spec wording“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 33 00 1.4.G | 907 | – |
| Record docs | Record docsComply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 ...Electric Domestic Water Heaters22 33 00 1.6.A · PDF p. 908Spec wording“A. Comply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 33 00 1.6.A | 908 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Electric Domestic Water Heaters22 33 00 3.4.A · PDF p. 911Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 33 00 3.4.A | 911 | – |
| Test / cert. | Test / cert.The tests shall include system capacity, control function, and alarm ...Electric Domestic Water Heaters22 33 00 3.4.B · PDF p. 911Spec wording“B. The tests shall include system capacity, control function, and alarm functions.” | 22 33 00 3.4.B | 911 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Electric Domestic Water Heaters22 33 00 3.4.C · PDF p. 911Spec wording“C. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 33 00 3.4.C | 911 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.A · PDF p. 914Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 40 00 1.6.A | 914 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.B · PDF p. 914Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions will be in electronic version on compact disc or DVD. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation will be included in the operation ...” | 22 40 00 1.6.B | 914 | electronic version; DVD |
| Record docs | Record docsThe installing contractor will maintain as-built drawings of each completed ...Plumbing Fixtures22 40 00 1.6.C · PDF p. 914Spec wording“C. The installing contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in AutoCAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a ...” | 22 40 00 1.6.C | 914 | AutoCAD; DVD |
| Record docs | Record docsCertification documentation will be provided to COR 10 working days ...Plumbing Fixtures22 40 00 1.6.D · PDF p. 914Spec wording“D. Certification documentation will be provided to COR 10 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 40 00 1.6.D | 914 | – |
| Training | TrainingProvide 0.5 hour demonstration and plumbing systems review for VA ...Plumbing Fixtures22 40 00 3.5.A · PDF p. 921Spec wording“A. Provide 0.5 hour demonstration and plumbing systems review for VA staff.” | 22 40 00 3.5.A | 921 | – |
Division 23 HVAC 177 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MHVAC Maintenance Data and Operating Instructions:Common Work Results For Hvac23 05 11 1.4.M · PDF p. 930-931Spec wording“M. HVAC Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, paragraph INSTRUCTIONS for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all components ...” | 23 05 11 1.4.M | 930-931 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Common Work Results For Hvac23 05 11 1.4.O · PDF p. 931Spec wording“O. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 1.4.O | 931 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Common Work Results For Hvac23 05 11 1.4.P · PDF p. 931Spec wording“P. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 1.4.P | 931 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.A · PDF p. 935Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 23 05 11 1.7.A | 935 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.B · PDF p. 935-936Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...” | 23 05 11 1.7.B | 935-936 | electronic version; CD; DVD; three-ring; binder |
| Record docs | Record docsThe installing Contractor shall maintain as-built drawings of each completed ...Common Work Results For Hvac23 05 11 1.7.C · PDF p. 936Spec wording“C. The installing Contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 23 05 11 1.7.C | 936 | AutoCAD; CD; DVD; CAD |
| Record docs | Record docsThe as-built drawings shall indicate the location and type of ...Common Work Results For Hvac23 05 11 1.7.D · PDF p. 936Spec wording“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 23 05 11 1.7.D | 936 | – |
| Record docs | Record docsCertification documentation shall be provided to COR 21 working days ...Common Work Results For Hvac23 05 11 1.7.E · PDF p. 936-937Spec wording“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...” | 23 05 11 1.7.E | 936-937 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Common Work Results For Hvac23 05 11 3.11.A · PDF p. 955Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 05 11 3.11.A | 955 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Common Work Results For Hvac23 05 11 3.11.B · PDF p. 955Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 05 11 3.11.B | 955 | – |
| Test / cert. | Test / cert.The CxA will observe startup and Contractor testing of selected ...Common Work Results For Hvac23 05 11 3.11.C · PDF p. 955Spec wording“C. The CxA will observe startup and Contractor testing of selected equipment. Coordinate the startup and Contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 05 11 3.11.C | 955 | – |
| Test / cert. | Test / cert.Startup of equipment shall be performed as described in equipment ...Common Work Results For Hvac23 05 11 3.11.D · PDF p. 955Spec wording“D. Startup of equipment shall be performed as described in equipment specifications. Vibration within specified tolerance shall be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, paragraph TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.” | 23 05 11 3.11.D | 955 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Hvac23 05 11 3.13.A · PDF p. 956Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 3.13.A | 956 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Common Work Results For Hvac23 05 11 3.13.B · PDF p. 956Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 05 11 3.13.B | 956 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4hours to instruct ...Common Work Results For Hvac23 05 11 3.14.A · PDF p. 956Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 05 11 3.14.A | 956 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Hvac23 05 11 3.14.B · PDF p. 956Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 3.14.B | 956 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.F · PDF p. 958-959Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 05 12 1.4.F | 958-959 | – |
| Test / cert. | Test / cert.CertificationGeneral Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.G · PDF p. 959Spec wording“G. Certification: Two weeks prior to final inspection, unless otherwise noted, certification shall be submitted to the COR stating that the motors have been properly applied, installed, adjusted, lubricated, and tested.” | 23 05 12 1.4.G | 959 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.H · PDF p. 959Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 1.4.H | 959 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.I · PDF p. 959Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 1.4.I | 959 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.5.A · PDF p. 959Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 05 12 1.5.A | 959 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.A · PDF p. 965Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 05 12 3.3.A | 965 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.B · PDF p. 965Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 05 12 3.3.B | 965 | – |
| Test / cert. | Test / cert.The CxA shall observe startup and contractor testing of selected ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.C · PDF p. 965Spec wording“C. The CxA shall observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 05 12 3.3.C | 965 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.4.A · PDF p. 965Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 3.4.A | 965 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification shall be ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.4.B · PDF p. 965Spec wording“B. Components provided under this section of the specification shall be tested as part of a greater system.” | 23 05 12 3.4.B | 965 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 1 hour to ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.5.A · PDF p. 965Spec wording“A. Provide services of manufacturer's technical representative for 1 hour to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 05 12 3.5.A | 965 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.5.B · PDF p. 965Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 3.5.B | 965 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Noise And Vibration Control For Hvac Piping And Equipment23 05 41 1.6.A · PDF p. 968Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC. 23 05 41 3” | 23 05 41 1.6.A | 968 | – |
| Test / cert. | Test / cert.Submit the following for review and approval:Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.E · PDF p. 975Spec wording“E. Submit the following for review and approval: 1. Design Review Report within 90 days for conventional design projects after the system layout on air and water side is completed by the Contractor. 2. Systems inspection report on equipment and installation for conformance with design. 3. Duct Air Leakage Test Report. 4. Systems Readiness Report. 5. Intermediate and Final TAB reports covering flow balance and ...” | 23 05 93 1.4.E | 975 | – |
| Test / cert. | Test / cert.Prior to request for Final or Partial Final inspection, submit ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.F · PDF p. 975Spec wording“F. Prior to request for Final or Partial Final inspection, submit completed Test and Balance report for the area with noted critical paths.” | 23 05 93 1.4.F | 975 | – |
| Test / cert. | Test / cert.Record initial measurements for each unit of equipment on test ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.8.B · PDF p. 981-982Spec wording“B. Record initial measurements for each unit of equipment on test forms and submit a report to the COR. Where vibration readings exceed the allowable tolerance Contractor shall be directed to correct the problem. The TAB agency shall verify that the corrections are done and submit a final report to the COR.” | 23 05 93 3.8.B | 981-982 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.14.A · PDF p. 984Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 93 3.14.A | 984 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.14.B · PDF p. 984Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 05 93 3.14.B | 984 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of section ...Hvac And Boiler Plant Insulation23 07 11 3.7.A · PDF p. 1005Spec wording“A. Provide commissioning documentation in accordance with the requirements of section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.” | 23 07 11 3.7.A | 1005 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hvac And Boiler Plant Insulation23 07 11 3.7.B · PDF p. 1005Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.” | 23 07 11 3.7.B | 1005 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Hvac Systems23 08 00 1.6.A · PDF p. 1009Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 23 08 00 1.6.A | 1009 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Hvac Systems23 08 00 1.6.B · PDF p. 1009Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 23 08 00 1.6.B | 1009 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Hvac Systems23 08 00 3.4.A · PDF p. 1011Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. ...” | 23 08 00 3.4.A | 1011 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Hvac Systems23 08 00 3.5.A · PDF p. 1011-1012Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the ...” | 23 08 00 3.5.A | 1011-1012 | – |
| Warranty | WarrantyLabor and materials for control systems shall be warranted for ...Direct-Digital Control System For Hvac23 09 23 1.6 · PDF p. 1026Spec wording“Labor and materials for control systems shall be warranted for a period as specified under Warranty in FAR clause 52.246-21. Control system failures during the warranty period shall be adjusted, repaired, or replaced at no cost or reduction in service to the owner. The system includes all computer equipment, transmission equipment, and all sensors and control devices. Deleted Controls subcontractor shall be ...” | 23 09 23 1.6 | 1026 | – |
| Warranty | WarrantySubmit shop drawings in accordance with Section 01 33 23, ...Direct-Digital Control System For Hvac23 09 23 1.7 · PDF p. 1026-1028Spec wording“Submit shop drawings in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Information and material submitted under this section shall be marked "SUBMITTED UNDER SECTION 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC", with applicable paragraph identification. Manufacturer's Literature and Data Including: 1. A wiring diagram for each type of input device and output device including DDC ...” | 23 09 23 1.7 | 1026-1028 | three (3) copies; one (1) set; CD-ROM; CAD; One copy |
| Training | TrainingInstructions to VA operations personnelDirect-Digital Control System For Hvac23 09 23 1.8 · PDF p. 1029-1030Spec wording“Instructions to VA operations personnel: Perform in accordance with Article, INSTRUCTIONS, in Specification Section 01 00 00, GENERAL REQUIREMENTS, and as noted below. 1. First Phase: Formal instructions to the VA facilities personnel for a total of 8 hours, given in multiple training sessions (each no longer than four hours in length), conducted sometime between the completed installation and prior to the ...” | 23 09 23 1.8 | 1029-1030 | – |
| Training | TrainingAs part of final system acceptance, a system demonstration is ...Direct-Digital Control System For Hvac23 09 23 3.2 · PDF p. 1050-1052Spec wording“As part of final system acceptance, a system demonstration is required (see below). Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the controls and instrumentation system. When formal commissioning is included in the project the system validation/test shall be part of the commissioning and shall be witnessed by the CxA. Validation 1. Prepare and submit for ...” | 23 09 23 3.2 | 1050-1052 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Direct-Digital Control System For Hvac23 09 23 3.3 · PDF p. 1052Spec wording“Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part. When any defects are detected, correct defects and repeat test at no additional cost or time to ...” | 23 09 23 3.3 | 1052 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Direct-Digital Control System For Hvac23 09 23 3.4 · PDF p. 1053Spec wording“Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS. Components provided under this section of the specification will be tested as part of a larger system.” | 23 09 23 3.4 | 1053 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 8 hourss to ...Direct-Digital Control System For Hvac23 09 23 3.5 · PDF p. 1053Spec wording“Provide services of manufacturer's technical representative for 8 hourss to instruct each VA personnel responsible in the operation and maintenance of the system. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 09 23 3.5 | 1053 | – |
| Record docs | Record docsAs-Built Piping DiagramsHydronic Piping23 21 13 1.4.G · PDF p. 1058Spec wording“G. As-Built Piping Diagrams: Provide drawings as follows for heating hot water system and other piping systems and equipment. 1. 1wall-mounted stick file with complete set of prints. 2. 1 complete set of reproducible drawings. 3. 1 complete set of drawings in electronic AutoCAD and pdf format.” | 23 21 13 1.4.G | 1058 | 1 complete set; AutoCAD; pdf |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hydronic Piping23 21 13 1.4.H · PDF p. 1058Spec wording“H. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 21 13 1.4.H | 1058 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hydronic Piping23 21 13 1.4.I · PDF p. 1058Spec wording“I. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 1.4.I | 1058 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Hydronic Piping23 21 13 1.4.J · PDF p. 1058Spec wording“J. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 1.4.J | 1058 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hydronic Piping23 21 13 1.6.A · PDF p. 1059Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 21 13 1.6.A | 1059 | – |
| Spare parts | Spare partsFor mechanical pressed sealed fittings provide tools required for each ...Hydronic Piping23 21 13 1.7.A · PDF p. 1059Spec wording“A. For mechanical pressed sealed fittings provide tools required for each pipe size used at the facility.” | 23 21 13 1.7.A | 1059 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hydronic Piping23 21 13 3.8.A · PDF p. 1070Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 21 13 3.8.A | 1070 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hydronic Piping23 21 13 3.8.B · PDF p. 1070Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 21 13 3.8.B | 1070 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hydronic Piping23 21 13 3.8.C · PDF p. 1070Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 21 13 3.8.C | 1070 | – |
| Test / cert. | Test / cert.Adjust red set hand on pressure gauges to normal working pressureHydronic Piping23 21 13 3.8.D · PDF p. 1070Spec wording“D. Adjust red set hand on pressure gauges to normal working pressure.” | 23 21 13 3.8.D | 1070 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hydronic Piping23 21 13 3.9.A · PDF p. 1070Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 3.9.A | 1070 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hydronic Piping23 21 13 3.9.B · PDF p. 1070Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 21 13 3.9.B | 1070 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Hydronic Piping23 21 13 3.10.A · PDF p. 1070Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 21 13 3.10.A | 1070 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hydronic Piping23 21 13 3.10.B · PDF p. 1070Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 3.10.B | 1070 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hydronic Pumps23 21 23 1.4.E · PDF p. 1072Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 21 23 1.4.E | 1072 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hydronic Pumps23 21 23 1.4.F · PDF p. 1072Spec wording“F. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 23 1.4.F | 1072 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Hydronic Pumps23 21 23 1.4.G · PDF p. 1073Spec wording“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 23 1.4.G | 1073 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hydronic Pumps23 21 23 1.6.A · PDF p. 1074Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 21 23 1.6.A | 1074 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hydronic Pumps23 21 23 3.2.A · PDF p. 1076Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 21 23 3.2.A | 1076 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hydronic Pumps23 21 23 3.2.B · PDF p. 1076Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 21 23 3.2.B | 1076 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hydronic Pumps23 21 23 3.2.C · PDF p. 1076Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 21 23 3.2.C | 1076 | – |
| Test / cert. | Test / cert.Verify that the piping system has been flushed, cleaned and filledHydronic Pumps23 21 23 3.2.D · PDF p. 1076Spec wording“D. Verify that the piping system has been flushed, cleaned and filled.” | 23 21 23 3.2.D | 1076 | – |
| Test / cert. | Test / cert.Lubricate pumps before startupHydronic Pumps23 21 23 3.2.E · PDF p. 1076Spec wording“E. Lubricate pumps before startup.” | 23 21 23 3.2.E | 1076 | – |
| Test / cert. | Test / cert.Prime the pump, vent all air from the casing and ...Hydronic Pumps23 21 23 3.2.F · PDF p. 1076Spec wording“F. Prime the pump, vent all air from the casing and verify that the rotation is correct. To avoid damage to mechanical seals, never start or run the pump in dry condition.” | 23 21 23 3.2.F | 1076 | – |
| Test / cert. | Test / cert.Verify that correct size heaters-motor over-load devices are installed for ...Hydronic Pumps23 21 23 3.2.G · PDF p. 1077Spec wording“G. Verify that correct size heaters-motor over-load devices are installed for each pump controller unit.” | 23 21 23 3.2.G | 1077 | – |
| Test / cert. | Test / cert.Field modifications to the bearings and or impeller (including trimming) ...Hydronic Pumps23 21 23 3.2.H · PDF p. 1077Spec wording“H. Field modifications to the bearings and or impeller (including trimming) are prohibited. If the pump does not meet the specified vibration tolerance, send the pump back to the manufacturer for a replacement pump. All modifications to the pump shall be performed at the factory.” | 23 21 23 3.2.H | 1077 | – |
| Test / cert. | Test / cert.Ensure the disposable strainer is free of debris prior to ...Hydronic Pumps23 21 23 3.2.I · PDF p. 1077Spec wording“I. Ensure the disposable strainer is free of debris prior to testing and balancing of the hydronic system.” | 23 21 23 3.2.I | 1077 | – |
| Test / cert. | Test / cert.After several days of operation, replace the disposable startup strainer ...Hydronic Pumps23 21 23 3.2.J · PDF p. 1077Spec wording“J. After several days of operation, replace the disposable startup strainer with a regular strainer in the suction diffuser.” | 23 21 23 3.2.J | 1077 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hydronic Pumps23 21 23 3.3.A · PDF p. 1077Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 23 3.3.A | 1077 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hydronic Pumps23 21 23 3.3.B · PDF p. 1077Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 21 23 3.3.B | 1077 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4hours to instruct ...Hydronic Pumps23 21 23 3.4.A · PDF p. 1077Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 21 23 3.4.A | 1077 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hydronic Pumps23 21 23 3.4.B · PDF p. 1077Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 23 3.4.B | 1077 | – |
| Record docs | Record docsAs-Built Piping DiagramsSteam And Condensate Heating Piping23 22 13 1.4.F · PDF p. 1081Spec wording“F. As-Built Piping Diagrams: Provide drawing as follows for steam and steam condensate piping and other central plant equipment. 1. One wall-mounted stick file for prints. Mount stick file in the chiller plant or adjacent control room along with control diagram stick file. 2. One set of reproducible drawings.” | 23 22 13 1.4.F | 1081 | One set |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Steam And Condensate Heating Piping23 22 13 1.4.G · PDF p. 1081Spec wording“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams will have their terminals identified to facilitate installation, operation and maintenance.” | 23 22 13 1.4.G | 1081 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the Commissioning Agent and ...Steam And Condensate Heating Piping23 22 13 1.4.H · PDF p. 1081Spec wording“H. Completed System Readiness Checklist provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 1.4.H | 1081 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 1.4.I · PDF p. 1081Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 1.4.I | 1081 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.A · PDF p. 1082Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 23 22 13 1.6.A | 1082 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.B · PDF p. 1082Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions will be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence ...” | 23 22 13 1.6.B | 1082 | electronic version; CD; DVD; three-ring; binder |
| Record docs | Record docsThe installing contractor will maintain as-built drawings of each completed ...Steam And Condensate Heating Piping23 22 13 1.6.C · PDF p. 1082-1083Spec wording“C. The installing contractor will maintain as-built drawings of each completed phase for verification; and will provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 23 22 13 1.6.C | 1082-1083 | AutoCAD; CD; DVD; CAD |
| Record docs | Record docsThe as-built drawings will indicate the location and type of ...Steam And Condensate Heating Piping23 22 13 1.6.D · PDF p. 1083Spec wording“D. The as-built drawings will indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 23 22 13 1.6.D | 1083 | – |
| Record docs | Record docsCertification documentation will be provided to COR 21 working days ...Steam And Condensate Heating Piping23 22 13 1.6.E · PDF p. 1083Spec wording“E. Certification documentation will be provided to COR 21 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results will ...” | 23 22 13 1.6.E | 1083 | – |
| Test / cert. | Test / cert.Prepare and submit test and inspection reports to the COR ...Steam And Condensate Heating Piping23 22 13 3.7.D · PDF p. 1095Spec wording“D. Prepare and submit test and inspection reports to the COR within 5 working days of test completion and prior to covering the pipe.” | 23 22 13 3.7.D | 1095 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Steam And Condensate Heating Piping23 22 13 3.10.A · PDF p. 1096Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment will be performed simultaneously with the system of which each item is an integral part.” | 23 22 13 3.10.A | 1096 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Steam And Condensate Heating Piping23 22 13 3.10.B · PDF p. 1096Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 22 13 3.10.B | 1096 | – |
| Test / cert. | Test / cert.The Commissioning Agent will observe startup and contractor testing of ...Steam And Condensate Heating Piping23 22 13 3.10.C · PDF p. 1096Spec wording“C. The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and Commissioning Agent. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 22 13 3.10.C | 1096 | – |
| Test / cert. | Test / cert.Adjust red set hand on pressure gauges to normal working pressureSteam And Condensate Heating Piping23 22 13 3.10.D · PDF p. 1096Spec wording“D. Adjust red set hand on pressure gauges to normal working pressure.” | 23 22 13 3.10.D | 1096 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Steam And Condensate Heating Piping23 22 13 3.11.A · PDF p. 1096Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 3.11.A | 1096 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Steam And Condensate Heating Piping23 22 13 3.11.B · PDF p. 1096Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 22 13 3.11.B | 1096 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4hours to instruct ...Steam And Condensate Heating Piping23 22 13 3.12.A · PDF p. 1096Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 22 13 3.12.A | 1096 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 3.12.B · PDF p. 1096Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 3.12.B | 1096 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 ...Refrigerant Piping23 23 00 1.6.A · PDF p. 1100Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 23 00 1.6.A | 1100 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Refrigerant Piping23 23 00 3.6.A · PDF p. 1107Spec wording“A. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum of 7 days prior notice.” | 23 23 00 3.6.A | 1107 | – |
| Test / cert. | Test / cert.DeletedRefrigerant Piping23 23 00 3.6.B · PDF p. 1107Spec wording“B. Deleted” | 23 23 00 3.6.B | 1107 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Refrigerant Piping23 23 00 3.7.A · PDF p. 1107Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the CxA.” | 23 23 00 3.7.A | 1107 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Refrigerant Piping23 23 00 3.7.B · PDF p. 1107Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning. /” | 23 23 00 3.7.B | 1107 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Refrigerant Piping23 23 00 3.8.A · PDF p. 1107Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct VA personnel in operation and maintenance of units.” | 23 23 00 3.8.A | 1107 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Refrigerant Piping23 23 00 3.8.B · PDF p. 1107Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 23 00 3.8.B | 1107 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Water Treatment23 25 00 1.4.F · PDF p. 1109Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 25 00 1.4.F | 1109 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hvac Water Treatment23 25 00 1.4.G · PDF p. 1109Spec wording“G. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 25 00 1.4.G | 1109 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Hvac Water Treatment23 25 00 1.4.H · PDF p. 1110Spec wording“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING of HVAC SYSTEMS.” | 23 25 00 1.4.H | 1110 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Water Treatment23 25 00 1.6.A · PDF p. 1110Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 25 00 1.6.A | 1110 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Water Treatment23 25 00 3.2.A · PDF p. 1113Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 25 00 3.2.A | 1113 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Water Treatment23 25 00 3.2.B · PDF p. 1113Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 25 00 3.2.B | 1113 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hvac Water Treatment23 25 00 3.2.C · PDF p. 1113Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 25 00 3.2.C | 1113 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hvac Water Treatment23 25 00 3.3.A · PDF p. 1113Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 25 00 3.3.A | 1113 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hvac Water Treatment23 25 00 3.3.B · PDF p. 1113Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 25 00 3.3.B | 1113 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Hvac Water Treatment23 25 00 3.4.A · PDF p. 1113Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 25 00 3.4.A | 1113 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hvac Water Treatment23 25 00 3.4.B · PDF p. 1113Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 25 00 3.4.B | 1113 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Ducts And Casings23 31 00 1.4.E · PDF p. 1117Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 31 00 1.4.E | 1117 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Ducts And Casings23 31 00 1.6.A · PDF p. 1118Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 31 00 1.6.A | 1118 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Fans23 34 00 1.4.G · PDF p. 1129Spec wording“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 34 00 1.4.G | 1129 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hvac Fans23 34 00 1.4.H · PDF p. 1129Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance wiI. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 1.4.H | 1129 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Fans23 34 00 1.6.A · PDF p. 1130Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 34 00 1.6.A | 1130 | – |
| Spare parts | Spare partsProvide one additional set of belts for all belt-driven fansHvac Fans23 34 00 1.7.A · PDF p. 1130Spec wording“A. Provide one additional set of belts for all belt-driven fans.” | 23 34 00 1.7.A | 1130 | one additional set |
| Test / cert. | Test / cert.Verify operation of motor, drive system and fan wheel according ...Hvac Fans23 34 00 3.3.A · PDF p. 1132Spec wording“A. Verify operation of motor, drive system and fan wheel according to the contract documents.” | 23 34 00 3.3.A | 1132 | – |
| Test / cert. | Test / cert.Check vibration and correct as necessary for air balance workHvac Fans23 34 00 3.3.B · PDF p. 1132Spec wording“B. Check vibration and correct as necessary for air balance work.” | 23 34 00 3.3.B | 1132 | – |
| Test / cert. | Test / cert.After air balancing is complete and permanent sheaves are in ...Hvac Fans23 34 00 3.3.C · PDF p. 1133Spec wording“C. After air balancing is complete and permanent sheaves are in place perform necessary field mechanical balancing to meet vibration tolerance in Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and EQUIPMENT.” | 23 34 00 3.3.C | 1133 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Fans23 34 00 3.3.D · PDF p. 1133Spec wording“D. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 34 00 3.3.D | 1133 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Fans23 34 00 3.3.E · PDF p. 1133Spec wording“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 34 00 3.3.E | 1133 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hvac Fans23 34 00 3.3.F · PDF p. 1133Spec wording“F. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 34 00 3.3.F | 1133 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hvac Fans23 34 00 3.3.A · PDF p. 1133Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 3.3.A | 1133 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hvac Fans23 34 00 3.3.B · PDF p. 1133Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 34 00 3.3.B | 1133 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Hvac Fans23 34 00 3.4.A · PDF p. 1133Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 34 00 3.4.A | 1133 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hvac Fans23 34 00 3.4.B · PDF p. 1133Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 3.4.B | 1133 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Terminal Units23 36 00 1.4.E · PDF p. 1135Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 36 00 1.4.E | 1135 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Air Terminal Units23 36 00 1.4.F · PDF p. 1135Spec wording“F. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 1.4.F | 1135 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Air Terminal Units23 36 00 1.4.G · PDF p. 1135Spec wording“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 1.4.G | 1135 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Terminal Units23 36 00 1.6.A · PDF p. 1136Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 36 00 1.6.A | 1136 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Terminal Units23 36 00 3.2.A · PDF p. 1138Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 36 00 3.2.A | 1138 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Air Terminal Units23 36 00 3.2.B · PDF p. 1138Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 36 00 3.2.B | 1138 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Air Terminal Units23 36 00 3.2.C · PDF p. 1138-1139Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 36 00 3.2.C | 1138-1139 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Air Terminal Units23 36 00 3.3.A · PDF p. 1139Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 3.3.A | 1139 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Air Terminal Units23 36 00 3.3.B · PDF p. 1139Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 36 00 3.3.B | 1139 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4hours to instruct ...Air Terminal Units23 36 00 3.4.A · PDF p. 1139Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 36 00 3.4.A | 1139 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Air Terminal Units23 36 00 3.4.B · PDF p. 1139Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 3.4.B | 1139 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Outlets And Inlets23 37 00 1.4.D · PDF p. 1141Spec wording“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 37 00 1.4.D | 1141 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Outlets And Inlets23 37 00 1.6.A · PDF p. 1141Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 37 00 1.6.A | 1141 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Outlets And Inlets23 37 00 3.4.A · PDF p. 1145Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 37 00 3.4.A | 1145 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Air Outlets And Inlets23 37 00 3.4.B · PDF p. 1145Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 37 00 3.4.B | 1145 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Indoor Central-Station Air-Handling Units23 73 00 1.4.F · PDF p. 1150Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include instructions for lubrication, filter replacement, motor and drive replacement, and spare parts list. 3. Include complete diagrams of the internal wiring for each item of ...” | 23 73 00 1.4.F | 1150 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Indoor Central-Station Air-Handling Units23 73 00 1.4.G · PDF p. 1150Spec wording“G. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 1.4.G | 1150 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Indoor Central-Station Air-Handling Units23 73 00 1.4.H · PDF p. 1150Spec wording“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 1.4.H | 1150 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Indoor Central-Station Air-Handling Units23 73 00 1.6.A · PDF p. 1151Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 73 00 1.6.A | 1151 | – |
| Test / cert. | Test / cert.The air handling unit shall not be operated for any ...Indoor Central-Station Air-Handling Units23 73 00 3.2.A · PDF p. 1159Spec wording“A. The air handling unit shall not be operated for any purpose, temporary or permanent, until ductwork is clean, filters are in place, bearings are lubricated, and the fan has been test run under observation.” | 23 73 00 3.2.A | 1159 | – |
| Test / cert. | Test / cert.After the air handling unit is installed and tested, provide ...Indoor Central-Station Air-Handling Units23 73 00 3.2.B · PDF p. 1159Spec wording“B. After the air handling unit is installed and tested, provide startup and operating instructions to VA personnel.” | 23 73 00 3.2.B | 1159 | – |
| Test / cert. | Test / cert.An authorized factory representative should startup, test, and certify the ...Indoor Central-Station Air-Handling Units23 73 00 3.2.C · PDF p. 1159Spec wording“C. An authorized factory representative should startup, test, and certify the final installation and application specific calibration of control components. Items to be verified include fan performance over entire operating range, noise and vibration testing, verification of proper alignment, overall inspection of the installation, Owner/Operator training, etc.” | 23 73 00 3.2.C | 1159 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Indoor Central-Station Air-Handling Units23 73 00 3.2.D · PDF p. 1159-1160Spec wording“D. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 73 00 3.2.D | 1159-1160 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Indoor Central-Station Air-Handling Units23 73 00 3.2.E · PDF p. 1160Spec wording“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 73 00 3.2.E | 1160 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Indoor Central-Station Air-Handling Units23 73 00 3.2.F · PDF p. 1160Spec wording“F. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 73 00 3.2.F | 1160 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Indoor Central-Station Air-Handling Units23 73 00 3.3.A · PDF p. 1160Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 3.3.A | 1160 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Indoor Central-Station Air-Handling Units23 73 00 3.3.B · PDF p. 1160Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 73 00 3.3.B | 1160 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Indoor Central-Station Air-Handling Units23 73 00 3.4.A · PDF p. 1160Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 73 00 3.4.A | 1160 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Indoor Central-Station Air-Handling Units23 73 00 3.4.B · PDF p. 1160Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 3.4.B | 1160 | – |
| Test / cert. | Test / cert.Perform tests and inspections and prepare test reportsDecentralized Unitary Hvac Equipment23 81 00 3.3.A · PDF p. 1167Spec wording“A. Perform tests and inspections and prepare test reports.” | 23 81 00 3.3.A | 1167 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Decentralized Unitary Hvac Equipment23 81 00 3.4.A · PDF p. 1167Spec wording“A. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum of 7 days prior notice.” | 23 81 00 3.4.A | 1167 | – |
| Test / cert. | Test / cert.Provide services of manufacturer's technical representative for four hours to ...Decentralized Unitary Hvac Equipment23 81 00 3.4.B · PDF p. 1167Spec wording“B. Provide services of manufacturer's technical representative for four hours to instruct VA personnel in operation and maintenance of units.” | 23 81 00 3.4.B | 1167 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Decentralized Unitary Hvac Equipment23 81 00 3.5.A · PDF p. 1167Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the CxA.” | 23 81 00 3.5.A | 1167 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Decentralized Unitary Hvac Equipment23 81 00 3.5.B · PDF p. 1167-1168Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning. DEMONSTRATION AND TRAINING” | 23 81 00 3.5.B | 1167-1168 | – |
| Test / cert. | Test / cert.Provide services of manufacturer's technical representative for 4hours to instruct ...Decentralized Unitary Hvac Equipment23 81 00 3.5.A · PDF p. 1168Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct VA personnel in operation and maintenance of units.” | 23 81 00 3.5.A | 1168 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Decentralized Unitary Hvac Equipment23 81 00 3.5.B · PDF p. 1168Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS. ---END---” | 23 81 00 3.5.B | 1168 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Convection Heating And Cooling Units23 82 00 1.4.E · PDF p. 1170Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 82 00 1.4.E | 1170 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the CxA and completed ...Convection Heating And Cooling Units23 82 00 1.4.F · PDF p. 1170Spec wording“F. Completed System Readiness Checklists provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 82 00 1.4.F | 1170 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Convection Heating And Cooling Units23 82 00 1.6.A · PDF p. 1171Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 82 00 1.6.A | 1171 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Convection Heating And Cooling Units23 82 00 3.2.A · PDF p. 1173Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 82 00 3.2.A | 1173 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Convection Heating And Cooling Units23 82 00 3.2.B · PDF p. 1173Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 82 00 3.2.B | 1173 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Convection Heating And Cooling Units23 82 00 3.2.C · PDF p. 1173Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior o startup and testing.” | 23 82 00 3.2.C | 1173 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Convection Heating And Cooling Units23 82 00 3.3.A · PDF p. 1173Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 82 00 3.3.A | 1173 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Convection Heating And Cooling Units23 82 00 3.3.B · PDF p. 1173Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 82 00 3.3.B | 1173 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Convection Heating And Cooling Units23 82 00 3.4.A · PDF p. 1173Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 82 00 3.4.A | 1173 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Convection Heating And Cooling Units23 82 00 3.4.B · PDF p. 1173Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 82 00 3.4.B | 1173 | – |
Division 26 Electrical 25 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.All submittals shall include six copies of adequate descriptive literature, ...Requirements For Electrical Installations26 05 11 1.12.C · PDF p. 1181Spec wording“C. All submittals shall include six copies of adequate descriptive literature, catalog cuts, shop drawings, test reports, certifications, samples, and other data necessary for the Government to ascertain that the proposed materials and equipment comply with drawing and specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify specific materials and equipment being ...” | 26 05 11 1.12.C | 1181 | six copies |
| O&M | O&MThe submittals shall include the following:Requirements For Electrical Installations26 05 11 1.12.E · PDF p. 1181Spec wording“E. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, manuals, pictures, nameplate data, and test reports as required. 2. Elementary and interconnection wiring diagrams for communication and signal systems, control systems, and equipment ...” | 26 05 11 1.12.E | 1181 | – |
| O&M | O&MMaintenance and Operation Manuals:Requirements For Electrical Installations26 05 11 1.12.F · PDF p. 1181-1182Spec wording“F. Maintenance and Operation Manuals: 1. Submit as required for systems and equipment specified in the technical sections. Furnish in hardcover binders or an approved equivalent. 2. Inscribe the following identification on the cover: the words "MAINTENANCE AND OPERATION MANUAL," the name and location of the system, material, equipment, building, name of Contractor, and contract name and number. Include in the ...” | 26 05 11 1.12.F | 1181-1182 | binders |
| Test / cert. | Test / cert.Approvals will be based on complete submission of shop drawings, ...Requirements For Electrical Installations26 05 11 1.12.G · PDF p. 1182Spec wording“G. Approvals will be based on complete submission of shop drawings, manuals, test reports, certifications, and samples as applicable.” | 26 05 11 1.12.G | 1182 | – |
| Warranty | WarrantyAll work performed and all equipment and material furnished under ...Requirements For Electrical Installations26 05 11 1.15.A · PDF p. 1183Spec wording“A. All work performed and all equipment and material furnished under this Division shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer for the Government.” | 26 05 11 1.15.A | 1183 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Low-Voltage Electrical Power Conductors And Cables26 05 19 1.4.A · PDF p. 1184Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings and insulation type for each conductor and cable. 2) Splicing materials and pulling lubricant. ...” | 26 05 19 1.4.A | 1184 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Grounding And Bonding For Electrical Systems26 05 26 1.4.A · PDF p. 1191-1192Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit plans showing the location of system grounding electrodes and connections, and the routing of aboveground and underground grounding electrode ...” | 26 05 26 1.4.A | 1191-1192 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Raceway And Boxes For Electrical Systems26 05 33 1.4.A · PDF p. 1199Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Size and location of main feeders. b. Size and location of panels and pull-boxes. c. Layout of required conduit penetrations through structural elements. d. Submit the following data for approval: 1) Raceway types and sizes. 2) Conduit bodies, ...” | 26 05 33 1.4.A | 1199 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Overcurrent Protective Device Coordination Study26 05 73 1.4.A · PDF p. 1211Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Product data on the software program to be used for the study. Software shall be in mainstream use in the industry, shall provide device settings and ratings, and shall show selective coordination by time-current drawings. 2. Complete study as described in paragraph ...” | 26 05 73 1.4.A | 1211 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Electrical Systems26 08 00 1.6.A · PDF p. 1216Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 26 08 00 1.6.A | 1216 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Electrical Systems26 08 00 1.6.B · PDF p. 1216Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 26 08 00 1.6.B | 1216 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Electrical Systems26 08 00 3.4.A · PDF p. 1217Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. ...” | 26 08 00 3.4.A | 1217 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Electrical Systems26 08 00 3.5.A · PDF p. 1217-1218Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the ...” | 26 08 00 3.5.A | 1217-1218 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Lighting Controls26 09 23 1.4.A · PDF p. 1219-1220Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting controls. b. Material and construction details. c. Physical dimensions and description. d. Wiring schematic and connection diagram. e. Installation details. 2. Manuals: a. Submit, ...” | 26 09 23 1.4.A | 1219-1220 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Panelboards26 24 16 1.4.A · PDF p. 1228-1229Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, circuit breakers, wiring and connection ...” | 26 24 16 1.4.A | 1228-1229 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Wiring Devices26 27 26 1.4.A · PDF p. 1234-1235Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, construction materials, grade, and termination information. 2. Manuals: a. Submit, simultaneously ...” | 26 27 26 1.4.A | 1234-1235 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Enclosed Switches And Circuit Breakers26 29 21 1.4.A · PDF p. 1240-1241Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, ...” | 26 29 21 1.4.A | 1240-1241 | – |
| Spare parts | Spare partsTwo weeks prior to the final inspection, furnish one complete ...Enclosed Switches And Circuit Breakers26 29 21 3.3.A · PDF p. 1243Spec wording“A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the COR. ---END---” | 26 29 21 3.3.A | 1243 | one complete set |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Engine Generators26 32 13 1.5.A · PDF p. 1245-1246Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Scaled drawings, showing plan views, side views, elevations, and cross-sections. 2. Diagrams: a. Control system diagrams, control sequence diagrams or ...” | 26 32 13 1.5.A | 1245-1246 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Automatic Transfer Switches26 36 23 1.5.A · PDF p. 1255-1256Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include voltage rating, continuous current rating, number of phases, withstand and closing rating, dimensions, weights, mounting details, conduit entry ...” | 26 36 23 1.5.A | 1255-1256 | – |
| Test / cert. | Test / cert.An authorized representative of the automatic transfer switch manufacturer shall ...Automatic Transfer Switches26 36 23 3.2.A · PDF p. 1264Spec wording“A. An authorized representative of the automatic transfer switch manufacturer shall technically supervise and participate during all of the field adjustments and tests. Major adjustments and field tests shall be witnessed by the COR. The manufacturer's representative shall certify in writing that the equipment has been installed, adjusted and tested in accordance with the manufacturer's recommendations.” | 26 36 23 3.2.A | 1264 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Facility Lightning Protection26 41 00 1.4.A · PDF p. 1267Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Show locations of air terminals, connections to required metal surfaces, down conductors, and grounding means. c. Show the mounting hardware and materials ...” | 26 41 00 1.4.A | 1267 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Surge Protective Devices26 43 13 1.4.A · PDF p. 1272Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings and device nameplate data. 2. Manuals: a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance ...” | 26 43 13 1.4.A | 1272 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Interior Lighting26 51 00 1.4.A · PDF p. 1276-1277Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...” | 26 51 00 1.4.A | 1276-1277 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Exterior Lighting26 56 00 1.4.A · PDF p. 1285-1286Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...” | 26 56 00 1.4.A | 1285-1286 | – |
Division 27 Communications 18 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MProvide parts list including quantity of spare partsRequirements For Communications Installations27 05 11 1.7.B · PDF p. 1316Spec wording“B. Provide parts list including quantity of spare parts.” | 27 05 11 1.7.B | 1316 | – |
| Test / cert. | Test / cert.Furnish electronic certified test reports to COR prior to final ...Requirements For Communications Installations27 05 11 1.7.K · PDF p. 1318Spec wording“K. Furnish electronic certified test reports to COR prior to final inspection and not more than 90 days after completion of tests.” | 27 05 11 1.7.K | 1318 | – |
| Warranty | WarrantyProvide following closeout submittals prior to project closeout date:Requirements For Communications Installations27 05 11 1.8.A · PDF p. 1318-1319Spec wording“A. Provide following closeout submittals prior to project closeout date: 1. Warranty certificate. 2. Evidence of compliance with requirements such as low voltage certificate of inspection. 3. Project record documents. 4. Instruction manuals and software that are a part of system.” | 27 05 11 1.8.A | 1318-1319 | – |
| Warranty | WarrantyMaintenance and Operation ManualsRequirements For Communications Installations27 05 11 1.8.B · PDF p. 1319Spec wording“B. Maintenance and Operation Manuals: Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS. 1. Prepare a manual for each system and equipment specified. 2. Furnish on portable storage drive in PDF format or equivalent accepted by COR. 3. Furnish complete manual as specified in specification section, fifteen days prior to performance of systems or equipment test. 4. Furnish remaining manuals prior to ...” | 27 05 11 1.8.B | 1319 | |
| Test / cert. | Test / cert.Record Wiring Diagrams:Requirements For Communications Installations27 05 11 1.8.C · PDF p. 1319-1320Spec wording“C. Record Wiring Diagrams: 1. Red Line Drawings: Keep one E size 91.44 cm x 121.92 cm (36 inches x 48 inches) set of floor plans, on site during work hours, showing installation progress marked and backbone cable labels noted. Make these drawings available for examination during construction meetings or field inspections. 2. General Drawing Specifications: Detail and elevation drawings to be D size 61 cm x 91.44 cm ...” | 27 05 11 1.8.C | 1319-1320 | CAD; four complete sets |
| Closeout step | Closeout stepService QualificationsRequirements For Communications Installations27 05 11 1.8.D · PDF p. 1320Spec wording“D. Service Qualifications: Submit name and contact information of service organizations providing service to this installation within eight hours of receipt of notification service is needed.” | 27 05 11 1.8.D | 1320 | – |
| Spare parts | Spare partsAfter approval and prior to installation, furnish COR with the ...Requirements For Communications Installations27 05 11 1.9.A · PDF p. 1320-1321Spec wording“A. After approval and prior to installation, furnish COR with the following: 1. A 300 mm (12 inch) length of each type and size of wire and cable along with tag from coils of reels from which samples were taken. 2. One coupling, bushing and termination fitting for each type of conduit. 3. Samples of each hanger, clamp and supports for conduit and pathways. 4. Duct sealing compound.” | 27 05 11 1.9.A | 1320-1321 | – |
| Warranty | WarrantyComply with FAR clause 52.246-21Requirements For Communications Installations27 05 11 1.13.A · PDF p. 1323Spec wording“A. Comply with FAR clause 52.246-21” | 27 05 11 1.13.A | 1323 | – |
| Test / cert. | Test / cert.Proof of Performance Certification:Requirements For Communications Installations27 05 11 3.6.M · PDF p. 1332Spec wording“M. Proof of Performance Certification: 1. If system is declared acceptable, AHJ provides COR notice stating system processes to required operating standards and functions and is Government accepted for use by facility. 2. Validate items with COR needing to be provided to complete project contract (i.e. charts & diagrams, manuals, spare parts, system warranty documents executed, etc.). Once items have been provided, ...” | 27 05 11 3.6.M | 1332 | – |
| Training | TrainingProvide training in accordance with subsection, INSTRUCTIONS, of Section 01 ...Requirements For Communications Installations27 05 11 3.8.A · PDF p. 1333Spec wording“A. Provide training in accordance with subsection, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.” | 27 05 11 3.8.A | 1333 | – |
| Training | TrainingProvide training for equipment or system as required in each ...Requirements For Communications Installations27 05 11 3.8.B · PDF p. 1333Spec wording“B. Provide training for equipment or system as required in each associated specification.” | 27 05 11 3.8.B | 1333 | – |
| Training | TrainingDevelop and submit training schedule for approval by COR, at ...Requirements For Communications Installations27 05 11 3.8.C · PDF p. 1333Spec wording“C. Develop and submit training schedule for approval by COR, at least 30 days prior to planned training.” | 27 05 11 3.8.C | 1333 | – |
| Test / cert. | Test / cert.Closeout SubmittalsGrounding And Bonding For Communications Systems27 05 26 1.3.C · PDF p. 1335Spec wording“C. Closeout Submittals: In addition to Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS provide the following: 1. Certified test reports of ground resistance. 2. Certifications: Two weeks prior to final inspection, submit following to COR: a. Certification materials and installation is in accordance with construction documents. b. Certification complete installation has been installed and tested.” | 27 05 26 1.3.C | 1335 | – |
| Test / cert. | Test / cert.CertificationRaceways And Boxes For Communications Systems27 05 33 1.3.B · PDF p. 1343Spec wording“B. Certification: Provide letter prior to final inspection, certifying material is in accordance with construction documents and properly installed.” | 27 05 33 1.3.B | 1343 | – |
| Warranty | WarrantyCloseout Submittals:Control, Communication And Signal Wiring27 10 00 1.3.F · PDF p. 1355Spec wording“F. Closeout Submittals: 1. Provide contact information for maintenance personnel to contact contractor for emergency maintenance and logistic assistance, and assistance in resolving technical problems at any time during warranty period. 2. Provide certified OEM sweep test tags from each cable reel to COR. 3. Furnish spare or unused wire and cable with appropriate connectors (female types) for installation in ...” | 27 10 00 1.3.F | 1355 | – |
| Warranty | WarrantyCertifications:Communications Structured Cabling27 15 00 1.3.B · PDF p. 1374-1375Spec wording“B. Certifications: 1. Submit written certification from OEM indicating that proposed supervisor of installation and proposed provider of contract maintenance are authorized representatives of OEM. Include individual's legal name and address and OEM warranty credentials in the certification. 2. Pre-acceptance Certification: Submit in accordance with test procedures. 3. Test system cables and certify to COR before ...” | 27 15 00 1.3.B | 1374-1375 | – |
| Test / cert. | Test / cert.Closeout SubmittalCommunications Structured Cabling27 15 00 1.3.C · PDF p. 1375Spec wording“C. Closeout Submittal: Provide document from OEM certifying that each item of equipment installed conforms to OEM published specifications.” | 27 15 00 1.3.C | 1375 | – |
| Warranty | WarrantyWork subject to terms of Article "Warranty of Construction," FAR ...Communications Structured Cabling27 15 00 1.4.A · PDF p. 1375Spec wording“A. Work subject to terms of Article "Warranty of Construction," FAR clause 52.246-21.” | 27 15 00 1.4.A | 1375 | – |
Division 28 Fire alarm and security 59 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe submittals shall include the following:Common Work Results For Electronic Safety And Security28 05 00 1.6.D · PDF p. 1399-1400Spec wording“D. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required. 3. Parts list which shall include those replacement parts recommended by the equipment manufacturer, quantity of parts, current ...” | 28 05 00 1.6.D | 1399-1400 | – |
| Warranty | WarrantySubmittals shall be in full compliance of the Contract Documents. ...Common Work Results For Electronic Safety And Security28 05 00 1.6.E · PDF p. 1400-1405Spec wording“E. Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. All submittals ...” | 28 05 00 1.6.E | 1400-1405 | AutoCAD; CAD; Binders; binder; four copies |
| Record docs | Record docsGroup IV Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.I · PDF p. 1410-1412Spec wording“I. Group IV Technical Data Package 1. Performance Verification Test a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to the ...” | 28 05 00 1.6.I | 1410-1412 | CAD; hard copy |
| O&M | O&MGroup V Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.J · PDF p. 1412-1416Spec wording“J. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or ...” | 28 05 00 1.6.J | 1412-1416 | CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Common Work Results For Electronic Safety And Security28 05 00 1.6.N · PDF p. 1418Spec wording“N. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 05 00 1.6.N | 1418 | – |
| Warranty | WarrantyThe Contractor shall, as a condition precedent to the final ...Common Work Results For Electronic Safety And Security28 05 00 1.20.A · PDF p. 1436-1437Spec wording“A. The Contractor shall, as a condition precedent to the final payment, execute a written guarantee (warranty) to the COR certifying all contract requirements have been completed according to the final specifications. Contract drawings and the warranty of all materials and equipment furnished under this contract are to remain in satisfactory operating condition (ordinary wear and tear, abuse and causes beyond his ...” | 28 05 00 1.20.A | 1436-1437 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Electronic Safety And Security28 05 00 3.3.A · PDF p. 1451Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.” | 28 05 00 3.3.A | 1451 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Common Work Results For Electronic Safety And Security28 05 00 3.3.B · PDF p. 1451Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS and related sections for contractor responsibilities for system commissioning.” | 28 05 00 3.3.B | 1451 | – |
| Training | TrainingTraining shall be provided in accordance with Article, INSTRUCTIONS, of ...Common Work Results For Electronic Safety And Security28 05 00 3.4.A · PDF p. 1451Spec wording“A. Training shall be provided in accordance with Article, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.” | 28 05 00 3.4.A | 1451 | – |
| Training | TrainingTraining shall be provided for the particular equipment or system ...Common Work Results For Electronic Safety And Security28 05 00 3.4.B · PDF p. 1451Spec wording“B. Training shall be provided for the particular equipment or system as required in each associated specification.” | 28 05 00 3.4.B | 1451 | – |
| Training | TrainingA training schedule shall be developed and submitted by the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.C · PDF p. 1451Spec wording“C. A training schedule shall be developed and submitted by the contractor and approved by the COR at least 30 days prior to the planned training.” | 28 05 00 3.4.C | 1451 | – |
| Training | TrainingProvide services of manufacturer's technical representative for <insert hours> hours ...Common Work Results For Electronic Safety And Security28 05 00 3.4.D · PDF p. 1452Spec wording“D. Provide services of manufacturer's technical representative for <insert hours> hours to instruct VA personnel in operation and maintenance of units.” | 28 05 00 3.4.D | 1452 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.E · PDF p. 1452Spec wording“E. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 05 00 3.4.E | 1452 | – |
| Test / cert. | Test / cert.The inspection and test will be conducted by a factory-certified ...Common Work Results For Electronic Safety And Security28 05 00 3.7.D · PDF p. 1459Spec wording“D. The inspection and test will be conducted by a factory-certified contractor representative and witnessed by a Government Representative. The results of the inspection will be officially recorded by a designated Government Representative and maintained on file by the COR, until completion of the entire project. The results will be compared to the Acceptance Test results.” | 28 05 00 3.7.D | 1459 | – |
| O&M | O&MIn accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT ...Conductors And Cables For Electronic Safety And Security28 05 13 1.5.A · PDF p. 1465Spec wording“A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following: 1. Manufacturer's Literature and Data: Showing each cable type and rating. 2. Certificates: Two weeks prior to final inspection, deliver to the COR four copies of the certification that the material is in accordance with the drawings and specifications and diagrams for cable management system. 3. Shop Drawings: ...” | 28 05 13 1.5.A | 1465 | four copies; electronic copy |
| Test / cert. | Test / cert.Document data for each measurement. Print data for submittals in ...Conductors And Cables For Electronic Safety And Security28 05 13 3.8.D · PDF p. 1478Spec wording“D. Document data for each measurement. Print data for submittals in a summary report that is formatted using Table 10.1 in BICSI TDMM as a guide, or transfer the data from the instrument to the computer, save as text files, print, and submit.” | 28 05 13 3.8.D | 1478 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsConductors And Cables For Electronic Safety And Security28 05 13 3.8.F · PDF p. 1478Spec wording“F. Prepare test and inspection reports.” | 28 05 13 3.8.F | 1478 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Electronic Safety And Security Systems28 08 00 1.6.A · PDF p. 1480Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 28 08 00 1.6.A | 1480 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Electronic Safety And Security Systems28 08 00 1.6.B · PDF p. 1480Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 28 08 00 1.6.B | 1480 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Electronic Safety And Security Systems28 08 00 3.4.A · PDF p. 1481Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. ...” | 28 08 00 3.4.A | 1481 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Electronic Safety And Security Systems28 08 00 3.5.A · PDF p. 1481-1482Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the ...” | 28 08 00 3.5.A | 1481-1482 | – |
| Record docs | Record docsProvide a pre-installation and as-built design package in both electronic ...Physical Access Control System And Database Management28 13 16 1.4.C · PDF p. 1485Spec wording“C. Provide a pre-installation and as-built design package in both electronic format and on paper, minimum size 34 x 44 inches (864mm x 1118mm); drawing submittals shall be per the established project schedule.” | 28 13 16 1.4.C | 1485 | electronic format |
| Record docs | Record docsPre-installation design and as-built packages shall include, but not be ...Physical Access Control System And Database Management28 13 16 1.4.D · PDF p. 1485-1486Spec wording“D. Pre-installation design and as-built packages shall include, but not be limited to: 1. Index Sheet that shall: a. Define each page of the design package to include facility name, building name, floor, and sheet number. b. Provide a list of all security abbreviations and symbols. c. Reference all general notes that are utilized within the design package. d. Specification and scope of work pages for all security ...” | 28 13 16 1.4.D | 1485-1486 | – |
| Warranty | WarrantyWarrant PACMS work subject to the Article "Warranty of Construction" ...Physical Access Control System And Database Management28 13 16 1.6.A · PDF p. 1490Spec wording“A. Warrant PACMS work subject to the Article "Warranty of Construction" of FAR clause 52.246-21 and Section 280500.” | 28 13 16 1.6.A | 1490 | – |
| Warranty | WarrantyDemonstration and training shall be performed prior to system acceptance ...Physical Access Control System And Database Management28 13 16 1.6.B · PDF p. 1490Spec wording“B. Demonstration and training shall be performed prior to system acceptance.” | 28 13 16 1.6.B | 1490 | – |
| Test / cert. | Test / cert.All testing and training shall be compliant with the VA ...Physical Access Control System And Database Management28 13 16 3.2.A · PDF p. 1499Spec wording“A. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS.” | 28 13 16 3.2.A | 1499 | – |
| Test / cert. | Test / cert.Perform testing and system certification as outlined in section 28 ...Physical Access Control System And Database Management28 13 16 3.2.B · PDF p. 1499Spec wording“B. Perform testing and system certification as outlined in section 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY.” | 28 13 16 3.2.B | 1499 | – |
| Test / cert. | Test / cert.The software shall be entered into the SMS computer systems ...Physical Access Control System And Database Management28 13 16 3.2.C · PDF p. 1499Spec wording“C. The software shall be entered into the SMS computer systems and debugged. The Contractor shall be responsible for documenting and entering the initial database into the system. The Contractor shall provide the necessary blank forms with instructions to fill in all the required data information that will make up the database. The database shall then be reviewed by the Contractor and entered into the system. Prior ...” | 28 13 16 3.2.C | 1499 | – |
| Test / cert. | Test / cert.Upon satisfactory on line operation of the system software, the ...Physical Access Control System And Database Management28 13 16 3.2.D · PDF p. 1499Spec wording“D. Upon satisfactory on line operation of the system software, the entire installation including all subsystems shall be inspected. The Contractor shall perform all tests, furnish all test equipment and consumable supplies necessary and perform any work as required to establish performance levels for the system in accordance with the specifications. Each device shall be tested as a working component of the ...” | 28 13 16 3.2.D | 1499 | – |
| Test / cert. | Test / cert.Tests shall demonstrate the response time and display format of ...Physical Access Control System And Database Management28 13 16 3.2.E · PDF p. 1499-1500Spec wording“E. Tests shall demonstrate the response time and display format of each different type of input sensor and output control device. Response time shall be measured with the system functioning at full capacity. Computer operation shall be tested with the complete data file.” | 28 13 16 3.2.E | 1499-1500 | – |
| Test / cert. | Test / cert.The Contractor shall provide a competent trainer who has extensive ...Physical Access Control System And Database Management28 13 16 3.2.F · PDF p. 1500Spec wording“F. The Contractor shall provide a competent trainer who has extensive experience on the installed systems and in delivering training to provide the instruction. As an alternative, the Contractor may propose the use of factory training personnel and coordinate the number of personnel to be trained.” | 28 13 16 3.2.F | 1500 | – |
| Record docs | Record docsProvide a shop drawing and as-built design package in both ...Intrusion Detection System28 16 00 1.5.C · PDF p. 1503Spec wording“C. Provide a shop drawing and as-built design package in both electronic format and on paper, minimum size 1220 x 1220 millimeters (48 x 48 inches); drawing submittals shall be per the established project schedule.” | 28 16 00 1.5.C | 1503 | electronic format |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Intrusion Detection System28 16 00 1.5.H · PDF p. 1505Spec wording“H. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 16 00 1.5.H | 1505 | – |
| Warranty | WarrantyWarrant IDS work subject to the Article "Warranty of Construction" ...Intrusion Detection System28 16 00 1.9.A · PDF p. 1507Spec wording“A. Warrant IDS work subject to the Article "Warranty of Construction" of FAR 52.246-21.” | 28 16 00 1.9.A | 1507 | – |
| Warranty | WarrantyDemonstration and training shall be performed prior to system acceptance ...Intrusion Detection System28 16 00 1.9.B · PDF p. 1507Spec wording“B. Demonstration and training shall be performed prior to system acceptance.” | 28 16 00 1.9.B | 1507 | – |
| Test / cert. | Test / cert.The Commissioning Agent will observe startup and contractor testing of ...Intrusion Detection System28 16 00 3.4.A · PDF p. 1523Spec wording“A. The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and Commissioning Agent. Provide a minimum of 7 days prior notice.” | 28 16 00 3.4.A | 1523 | – |
| Training | TrainingAll testing and training shall be compliant with the VA ...Intrusion Detection System28 16 00 3.6.A · PDF p. 1523Spec wording“A. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS.” | 28 16 00 3.6.A | 1523 | – |
| Training | TrainingProvide services of manufacturer's technical representative for [insert number] hours ...Intrusion Detection System28 16 00 3.6.B · PDF p. 1524Spec wording“B. Provide services of manufacturer's technical representative for [insert number] hours to instruct VA personnel in operation and maintenance of units.” | 28 16 00 3.6.B | 1524 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Intrusion Detection System28 16 00 3.6.C · PDF p. 1524Spec wording“C. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS. -----END----” | 28 16 00 3.6.C | 1524 | – |
| Record docs | Record docsProvide a pre-installation and as-built design package in both electronic ...Video Surveillance28 23 00 1.5.C · PDF p. 1528Spec wording“C. Provide a pre-installation and as-built design package in both electronic format and on paper, minimum size 1220 x 1220 millimeters (48 x 48 inches); drawing submittals shall be per the established project schedule.” | 28 23 00 1.5.C | 1528 | electronic format |
| Record docs | Record docsPre-installation design and as-built packages shall include, but not be ...Video Surveillance28 23 00 1.5.D · PDF p. 1528-1530Spec wording“D. Pre-installation design and as-built packages shall include, but not be limited to: 1. Index Sheet that shall: a. Define each page of the design package to include facility name, building name, floor, and sheet number. b. Provide a list of all security abbreviations and symbols. c. Reference all general notes that are utilized within the design package. d. Specification and scope of work pages for all security ...” | 28 23 00 1.5.D | 1528-1530 | – |
| Test / cert. | Test / cert.Submit completed System Readiness Checklists provided by the Commissioning Agent ...Video Surveillance28 23 00 1.5.H · PDF p. 1531Spec wording“H. Submit completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 23 00 1.5.H | 1531 | – |
| Warranty | WarrantyWarrant VASS System work subject to the Article "Warranty of ...Video Surveillance28 23 00 1.8.A · PDF p. 1532Spec wording“A. Warrant VASS System work subject to the Article "Warranty of Construction" of FAR clause 52.246-21.” | 28 23 00 1.8.A | 1532 | – |
| Warranty | WarrantyDemonstration and training shall be performed prior to system acceptance ...Video Surveillance28 23 00 1.8.B · PDF p. 1532Spec wording“B. Demonstration and training shall be performed prior to system acceptance.” | 28 23 00 1.8.B | 1532 | – |
| Test / cert. | Test / cert.The Contractor shall not apply power to the VASS System ...Video Surveillance28 23 00 3.3.A · PDF p. 1573Spec wording“A. The Contractor shall not apply power to the VASS System until the following items have been completed: 1. VASS System equipment items and have been set up in accordance with manufacturer's instructions. 2. A visual inspection of the VASS System has been conducted to ensure that defective equipment items have not been installed and that there are no loose connections. 3. System wiring has been tested and verified ...” | 28 23 00 3.3.A | 1573 | – |
| Test / cert. | Test / cert.The Commissioning Agent will observe startup and contractor testing of ...Video Surveillance28 23 00 3.3.B · PDF p. 1573Spec wording“B. The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and Commissioning Agent. Provide a minimum of 7 days prior notice.” | 28 23 00 3.3.B | 1573 | – |
| Test / cert. | Test / cert.Satisfaction of the above requirements shall not relieve the Contractor ...Video Surveillance28 23 00 3.3.C · PDF p. 1573Spec wording“C. Satisfaction of the above requirements shall not relieve the Contractor of responsibility for incorrect installation, defective equipment items, or collateral damage as a result of Contractor work efforts.” | 28 23 00 3.3.C | 1573 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Video Surveillance28 23 00 3.5.A · PDF p. 1574Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.” | 28 23 00 3.5.A | 1574 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Video Surveillance28 23 00 3.5.B · PDF p. 1574Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 28 08 00 – "COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS" and related sections for contractor responsibilities for system commissioning.” | 28 23 00 3.5.B | 1574 | – |
| Training | TrainingAll testing and training shall be compliant with the VA ...Video Surveillance28 23 00 3.6.A · PDF p. 1574Spec wording“A. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, "GENERAL REQUIREMENTS".” | 28 23 00 3.6.A | 1574 | – |
| Training | TrainingProvide services of manufacturer's technical representative for [four] <insert hours> ...Video Surveillance28 23 00 3.6.B · PDF p. 1574Spec wording“B. Provide services of manufacturer's technical representative for [four] <insert hours> hours to instruct VA personnel in operation and maintenance of units.” | 28 23 00 3.6.B | 1574 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Video Surveillance28 23 00 3.6.C · PDF p. 1574Spec wording“C. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – "COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS". -----END----” | 28 23 00 3.6.C | 1574 | – |
| Warranty | WarrantyWarrant EPPS System work subject to the Article "Warranty of ...Electronic Personal Protection System28 26 00 1.8.A · PDF p. 1584Spec wording“A. Warrant EPPS System work subject to the Article "Warranty of Construction" of FAR clause 52.246-21.” | 28 26 00 1.8.A | 1584 | – |
| Warranty | WarrantyDemonstration and training shall be performed prior to system acceptance ...Electronic Personal Protection System28 26 00 1.8.B · PDF p. 1584Spec wording“B. Demonstration and training shall be performed prior to system acceptance.” | 28 26 00 1.8.B | 1584 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Electronic Personal Protection System28 26 00 3.7.A · PDF p. 1593Spec wording“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain electronic personal protection system (EPSS) equipment. 1. Train Owner's maintenance personnel on procedures and schedules for troubleshooting, servicing, and maintaining equipment. 2. Demonstrate methods of determining optimum alignment and adjustment of components and settings for system ...” | 28 26 00 3.7.A | 1593 | – |
| Training | TrainingAll testing and training shall be compliant with the VA ...Electronic Personal Protection System28 26 00 3.9.A · PDF p. 1594Spec wording“A. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS and Section 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY. -----END----” | 28 26 00 3.9.A | 1594 | – |
| Record docs | Record docsDrawings:Fire Detection And Alarm28 31 00 1.4.B · PDF p. 1597-1598Spec wording“B. Drawings: 1. Deleted. 2. Floor plans: Provide locations of all devices (with device number at each addressable device corresponding to control unit programming), appliances, panels, equipment, junction/terminal cabinets/boxes, risers, electrical power connections, individual circuits and raceway routing, system zoning; number, size, and type of raceways and conductors in each raceway; conduit fill calculations ...” | 28 31 00 1.4.B | 1597-1598 | 3 sets; one set; AutoCAD |
| O&M | O&MManuals:Fire Detection And Alarm28 31 00 1.4.C · PDF p. 1598-1599Spec wording“C. Manuals: 1. Submit simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets for all items used in the system, power requirements, device wiring diagrams, dimensions, and information for ordering replacement parts. a. Wiring diagrams shall have their terminals identified to facilitate installation, operation, expansion and maintenance. ...” | 28 31 00 1.4.C | 1598-1599 | binder; 4 copies |
| Warranty | WarrantyAll work performed and all material and equipment furnished under ...Fire Detection And Alarm28 31 00 1.5 · PDF p. 1600Spec wording“All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer.” | 28 31 00 1.5 | 1600 | – |
Division 31 Earthwork 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Furnish to COR:Earthwork31 20 00 1.7.C · PDF p. 1618-1619Spec wording“C. Furnish to COR: 1. Contactor shall furnish resumes with all personnel involved in the project including Project Manager, Superintendent, and on-site Engineer. Project Manager and Superintendent should have at least 3 years of experience on projects of similar size. 2. Soil samples. a. Classification in accordance with ASTM D2487 for each on-site or borrow soil material proposed for fill, backfill, engineered ...” | 31 20 00 1.7.C | 1618-1619 | – |
Division 32 Paving and site improvements 7 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test reportsCement And Concrete For Exterior Improvements32 05 23 1.5.E · PDF p. 1639Spec wording“E. Test reports: Certify products comply with specifications. 1. Concrete materials. 2. Select subbase materials. 3. Field test reports.” | 32 05 23 1.5.E | 1639 | – |
| Warranty | WarrantyConstruction WarrantyCement And Concrete For Exterior Improvements32 05 23 1.10.A · PDF p. 1641Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 32 05 23 1.10.A | 1641 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Planting32 90 00 1.6.B · PDF p. 1653-1654Spec wording“B. Manufacturer's Literature and Data: 1. Description of each product. 2. Photographs: Color photographs of each plant species showing actual size and condition of plants to be provided with measuring device included for scale. Where more than 20 plants are required of any species, submit minimum three photographs of average, best, and worst quality plant to be provided. Include on each photograph, plant full ...” | 32 90 00 1.6.B | 1653-1654 | – |
| Test / cert. | Test / cert.Test reportsPlanting32 90 00 1.6.E · PDF p. 1654Spec wording“E. Test reports: Certify products comply with specifications.” | 32 90 00 1.6.E | 1654 | – |
| O&M | O&MOperation and Maintenance Data:Planting32 90 00 1.6.H · PDF p. 1654Spec wording“H. Operation and Maintenance Data: 1. Care instructions for each plant material.” | 32 90 00 1.6.H | 1654 | – |
| Warranty | WarrantyConstruction WarrantyPlanting32 90 00 1.11.A · PDF p. 1658Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 32 90 00 1.11.A | 1658 | – |
| Warranty | WarrantyManufacturer's WarrantyPlanting32 90 00 1.11.B · PDF p. 1658Spec wording“B. Manufacturer's Warranty: Warrant plantings and against material defects. 1. Warranty Period: Two years. 2. Plant and Turf Warranty Periods will begin from date of Government acceptance of project or phase for beneficial use and occupancy. 3. Contracting Officer's Representative will reinspect plants and turf at end of Warranty Period. Replace any dead, missing, or defective plant material and turf immediately. ...” | 32 90 00 1.11.B | 1658 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.