Free closeout checklist · State job · Missouri

Closeout checklist: Replace Fire Alarm System and Electrical Renovation, Bellefontaine Habilitation Center (Missouri FMDC, MO)

Every closeout item we found in the public spec book for this job: 136 items across Division 01, 7 trade divisions and the contract conditions, including 29 O&M manual items, 26 tests and certificates and 26 training items. Each one is tied to its spec section and the PDF page it sits on.

Owner
State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
Number
FMDC project M2006-01
Location
St. Louis, MO
Bid date
2025-05-20
Public spec book
Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing
Spec book size
376 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

15Warranties
29O&M manuals
26Tests and certificates
26Training
15Record documents
20Spare parts
5Payment release

All 136 items, by trade

Division 01 General requirements 42 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantySubstitution RequestsSubstitution Procedures01 25 00 1.4.A · PDF p. 63-64
Spec wording
“A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. 1. Substitution Request Form: Use Owner provided form in Section 006325 – Product Substitution Request. 2. Documentation: Show compliance with requirements for substitutions and the ...”
01 25 00 1.4.A63-64three copies
O&MO&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 79
Spec wording
“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...”
01 32 00 3.1.A79–
WarrantyWarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 87
Spec wording
“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with Division 00, Section 007213 "General Conditions", Article 3.5 "Operation and Maintenance Manuals", and Division 00, Section 007300 "Supplementary Conditions" along with this and other Sections of the Contract Documents.”
01 33 00 1.8.A87–
WarrantyWarrantyWarranties specified in other Sections shall be in addition to, ...Product Requirements01 60 00 1.7.A · PDF p. 110
Spec wording
“A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. 1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and ...”
01 60 00 1.7.A110–
WarrantyWarrantySpecial WarrantiesProduct Requirements01 60 00 1.7.B · PDF p. 110
Spec wording
“B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. 1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed. 2. Specified Form: When specified forms are included with the Specifications, prepare a written document using indicated form properly executed. 3. See Divisions 02 through 26 Sections for ...”
01 60 00 1.7.B110–
WarrantyWarrantySubmittal TimeProduct Requirements01 60 00 1.7.C · PDF p. 110
Spec wording
“C. Submittal Time: Comply with requirements in Division 00, Section 007213 "General Conditions."”
01 60 00 1.7.C110–
O&MO&MOperation and maintenance manual contentOperation And Maintenance Data01 78 23 1.4.A · PDF p. 116
Spec wording
“A. Operation and maintenance manual content: See Division 00, Section 007213 "General Conditions", Article 3.5 "Operation and Maintenance Manuals" and Division 00 through 26 Specification Sections. Submit manual content formatted and organized as required by this Section. 1. Designer will comment on whether content of operations and maintenance submittals are acceptable. 2. Where applicable, clarify and update ...”
01 78 23 1.4.A116–
O&MO&MFormatOperation And Maintenance Data01 78 23 1.4.B · PDF p. 116
Spec wording
“B. Format: Submit operation and maintenance manuals in the following format: 1. For Review and Comments: PDF electronic file. Assemble each manual into a composite electronically indexed file. Submit electronic file for review on eBuilder. 2. For Final Submission: a. PDF Electronic File on USB thumb drive. b. Printed Hard Copies: See Division 00, Section 007213 "General Conditions", Article 3.5 "Operation and ...”
01 78 23 1.4.B116PDF; electronic file; electronically; USB; thumb drive; hard copy
O&MO&MManual Submittal:Operation And Maintenance Data01 78 23 1.4.C · PDF p. 117
Spec wording
“C. Manual Submittal: 1. Submit manuals for review in a sufficient time before final submission is required as per Division 00, Section 007213 "General Conditions", Article 3.5 "Operation and Maintenance Manuals". Designer shall review submission and return copy with comments. 2. Correct or revise manual to comply with Designer's comments. Submit revised copy of manual for review. 3. Final Submission: See Division ...”
01 78 23 1.4.C117–
O&MO&MOrganizationOperation And Maintenance Data01 78 23 2.1.A · PDF p. 117
Spec wording
“A. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the following materials, in the order listed: 1. Title page 2. Table of contents 3. Manual contents”
01 78 23 2.1.A117–
O&MO&MTitle PageOperation And Maintenance Data01 78 23 2.1.B · PDF p. 117
Spec wording
“B. Title Page: Include the following information: 1. Subject matter included in manual 2. Name and address of Project 3. Name and address of Owner 4. Date of submittal 5. Name and contact information for Contractor 6. Name and contact information for Designer 7. Names and contact information for major consultants to the Designer that designed the systems contained in the manuals 8. Cross-reference to related ...”
01 78 23 2.1.B117–
O&MO&MTable of ContentsOperation And Maintenance Data01 78 23 2.1.C · PDF p. 117
Spec wording
“C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual. 1. If operation or maintenance documentation requires more than one volume to accommodate data, include comprehensive table of contents for all volumes in each volume of the set.”
01 78 23 2.1.C117–
O&MO&MManual ContentsOperation And Maintenance Data01 78 23 2.1.D · PDF p. 118
Spec wording
“D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.”
01 78 23 2.1.D118binder
O&MO&MManuals, Electronic FilesOperation And Maintenance Data01 78 23 2.1.E · PDF p. 118
Spec wording
“E. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required. 1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size.”
01 78 23 2.1.E118Electronic Files; PDF
O&MO&MContentOperation And Maintenance Data01 78 23 2.2.A · PDF p. 118
Spec wording
“A. Content: In addition to requirements in this Section, include operation data required in Division 00 through 26 Specification Sections and the following information: 1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents. 2. Performance and design criteria 3. Operating standards 4. Operating procedures 5. Operating logs 6. Wiring diagrams 7. ...”
01 78 23 2.2.A118–
O&MO&MDescriptionsOperation And Maintenance Data01 78 23 2.2.B · PDF p. 118
Spec wording
“B. Descriptions: Include the following: 1. Product name and model number. Use designations for products indicated on Contract Documents. 2. Manufacturer's name 3. Equipment identification with serial number of each component 4. Equipment function 5. Operating characteristics 6. Limiting conditions 7. Performance curves 8. Engineering data and tests 9. Complete nomenclature and number of replacement parts”
01 78 23 2.2.B118–
O&MO&MOperating ProceduresOperation And Maintenance Data01 78 23 2.2.C · PDF p. 118-119
Spec wording
“C. Operating Procedures: Include the following, as applicable: 1. Startup procedures 2. Equipment or system break-in procedures 3. Routine and normal operating instructions 4. Regulation and control procedures 5. Instructions on stopping 6. Normal shutdown instructions 7. Seasonal and weekend operating instructions 8. Required sequences for electric or electronic systems 9. Special operating instructions and ...”
01 78 23 2.2.C118-119–
O&MO&MContentOperation And Maintenance Data01 78 23 2.3.A · PDF p. 119
Spec wording
“A. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranty and bond information, as described below.”
01 78 23 2.3.A119–
O&MO&MMaintenance ProceduresOperation And Maintenance Data01 78 23 2.3.D · PDF p. 119
Spec wording
“D. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures: 1. Test and inspection instructions 2. Troubleshooting guide 3. Precautions against improper maintenance 4. Disassembly; component removal, repair, and replacement; and reassembly instructions 5. Aligning, adjusting, and checking instructions 6. Demonstration and training video recording, if available”
01 78 23 2.3.D119–
O&MO&MMaintenance and Service SchedulesOperation And Maintenance Data01 78 23 2.3.E · PDF p. 119-120
Spec wording
“E. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment. 1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly, semiannual, and annual frequencies. 2. Maintenance and Service Record: Include manufacturers' ...”
01 78 23 2.3.E119-120–
O&MO&MSpare Parts List and Source InformationOperation And Maintenance Data01 78 23 2.3.F · PDF p. 120
Spec wording
“F. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services.”
01 78 23 2.3.F120–
O&MO&MWarranties and BondsOperation And Maintenance Data01 78 23 2.3.G · PDF p. 120
Spec wording
“G. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. 1. Include procedures to follow and required notifications for warranty claims.”
01 78 23 2.3.G120–
O&MO&MOperation and Maintenance ManualsOperation And Maintenance Data01 78 23 3.1.A · PDF p. 120
Spec wording
“A. Operation and Maintenance Manuals: Assemble a complete set of operation and maintenance data indicating operation and maintenance of each system, subsystem, and piece of equipment not part of a system.”
01 78 23 3.1.A120–
O&MO&MManufacturers' DataOperation And Maintenance Data01 78 23 3.1.B · PDF p. 120
Spec wording
“B. Manufacturers' Data: Where manuals contain manufacturers' standard printed data, include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Documents. Identify data applicable to the Work and delete ...”
01 78 23 3.1.B120–
O&MO&MDrawingsOperation And Maintenance Data01 78 23 3.1.C · PDF p. 120
Spec wording
“C. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information noted on As-Built Drawings to ensure correct illustration of completed installation. 1. Do not use original project As-Built Drawings as part of operation and maintenance ...”
01 78 23 3.1.C120–
TrainingTrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 121
Spec wording
“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.”
01 79 00 1.3.A121–
TrainingTrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 121
Spec wording
“B. Attendance Record: For each training module, submit list of participants and length of instruction time.”
01 79 00 1.3.B121–
TrainingTrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 121
Spec wording
“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.”
01 79 00 1.3.C121–
TrainingTrainingDemonstration and Training Video RecordingsDemonstration And Training01 79 00 1.4.A · PDF p. 121
Spec wording
“A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Designer. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. Transcript: Prepared in PDF electronic format. ...”
01 79 00 1.4.A121two copies; PDF; electronic format; electronic file
TrainingTrainingFacilitator QualificationsDemonstration And Training01 79 00 1.5.A · PDF p. 122
Spec wording
“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.”
01 79 00 1.5.A122–
TrainingTrainingPreinstruction ConferenceDemonstration And Training01 79 00 1.5.C · PDF p. 122
Spec wording
“C. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Coordination". Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, ...”
01 79 00 1.5.C122–
O&MO&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.6.C · PDF p. 122
Spec wording
“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Designer.”
01 79 00 1.6.C122–
WarrantyWarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 122-124
Spec wording
“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...”
01 79 00 2.1.B122-124–
TrainingTrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 124
Spec wording
“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".”
01 79 00 3.1.A124–
TrainingTrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 124
Spec wording
“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Designer will furnish an instructor to describe basis of system design, operational requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names ...”
01 79 00 3.2.A124–
TrainingTrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 124
Spec wording
“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.”
01 79 00 3.2.B124–
TrainingTrainingGeneralDemonstration And Training01 79 00 3.3.A · PDF p. 125
Spec wording
“A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. 1. At beginning of each training module, record each chart containing learning objective and lesson outline.”
01 79 00 3.3.A125–
TrainingTrainingVideoDemonstration And Training01 79 00 3.3.B · PDF p. 125
Spec wording
“B. Video: Provide minimum 640 x 480 video resolution converted to format file type acceptable to Owner, on electronic media. 1. Electronic Media: Read-only format compact disc acceptable to Owner, with commercial-grade graphic label. 2. File Hierarchy: Organize folder structure and file locations according to project manual table of contents. Provide complete screen-based menu. 3. File Names: Utilize file names ...”
01 79 00 3.3.B125electronic media; DVD
TrainingTrainingLight LevelsDemonstration And Training01 79 00 3.3.D · PDF p. 125
Spec wording
“D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. 1. Furnish additional portable lighting as required.”
01 79 00 3.3.D125–
TrainingTrainingNarrationDemonstration And Training01 79 00 3.3.E · PDF p. 125
Spec wording
“E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.”
01 79 00 3.3.E125–
TrainingTrainingTranscriptDemonstration And Training01 79 00 3.3.F · PDF p. 125
Spec wording
“F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.”
01 79 00 3.3.F125–
TrainingTrainingPreproduced Video RecordingsDemonstration And Training01 79 00 3.3.G · PDF p. 125
Spec wording
“G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.”
01 79 00 3.3.G125–

Division 02 Existing conditions 1 item

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyExisting WarrantiesSelective Demolition02 41 19 1.7.A · PDF p. 128
Spec wording
“A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.”
02 41 19 1.7.A128–

Division 03 Concrete 4 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Certified copies of mill test reports of reinforcement material analysis ...Concrete Reinforcing03 20 00 1.5.C · PDF p. 142
Spec wording
“C. Certified copies of mill test reports of reinforcement material analysis.”
03 20 00 1.5.C142–
Record docsRecord docsProject Record Documents:Cast-In-Place Concrete03 30 00 1.5.F · PDF p. 147
Spec wording
“F. Project Record Documents: 1. Accurately record actual locations of embedded utilities and components that are concealed from view. 2. Submit upon request for record copies of all concrete delivery tickets. 3. Submit upon request for record copy of plan with locations and dates for concrete placements shown on drawing.”
03 30 00 1.5.F147–
Test / cert.Test / cert.Construction Field Test ResultsCast-In-Place Concrete03 30 00 1.5.I · PDF p. 147
Spec wording
“I. Construction Field Test Results: Fresh concrete properties, including slump, air content, temperature, and unit weight, and hardened concrete properties, such as strength, shall be measured and submitted for record.”
03 30 00 1.5.I147–
Test / cert.Test / cert.Field inspection and testing will be performed in accordance with ...Cast-In-Place Concrete03 30 00 3.11.A · PDF p. 154
Spec wording
“A. Field inspection and testing will be performed in accordance with ACI 301 by ACI certified technicians.”
03 30 00 3.11.A154–

Division 26 Electrical 29 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Preventative Maintenance test reportsPreventative Maintenance For 15Kv Metal-Clad26 01 15 1.5.F · PDF p. 158
Spec wording
“F. Preventative Maintenance test reports”
26 01 15 1.5.F158–
Test / cert.Test / cert.Procure and Review:Preventative Maintenance For 15Kv Metal-Clad26 01 15 3.1.A · PDF p. 161-162
Spec wording
“A. Procure and Review: 1. Equipment drawings, schematics and wiring diagrams associated with equipment/device being tested (Owner has on file) 2. Instruction bulletins/books (Owner has on file) 3. Revised power system study provided under Section 260573 – Protective Device Coordination Study and Arc Flash Risk Assessment 4. Test data and field service forms 5. Safe working procedures and MSDS forms that apply to ...”
26 01 15 3.1.A161-162–
Test / cert.Test / cert.Preparation and Safety (NOTEPreventative Maintenance For 15Kv Metal-Clad26 01 15 3.1.B · PDF p. 162
Spec wording
“B. Preparation and Safety (NOTE: The following recommendations are not intended to take precedence over the Contractor's safety procedures or industry standards. The Contractor shall be responsible for the safety of all personnel on-site and for any damage to Owner's equipment caused by Contractor's action, inaction, willful act and/or negligence.) 1. Perform switching of existing S&C pad-mounted switchgear as ...”
26 01 15 3.1.B162–
Test / cert.Test / cert.Verify:Preventative Maintenance For 15Kv Metal-Clad26 01 15 3.1.C · PDF p. 162
Spec wording
“C. Verify: 1. The equipment nameplate ratings are consistent with the equipment drawings provided. 2. Suitability of tools and test equipment for use on the equipment to be tested. 3. Test data and field service forms are available with the following data to be recorded prior to the start of testing: a. Customer and project information b. Equipment designation from site one-line diagram and equipment schedules c. ...”
26 01 15 3.1.C162–
O&MO&MProvide operating instructions and maintenance manuals in accordance with Section ...Common Work Results For Electrical26 05 00 1.6.H · PDF p. 172
Spec wording
“H. Provide operating instructions and maintenance manuals in accordance with Section 013300 – Submittals, Section 007213 – General Conditions and 007300 – Supplementary Conditions.”
26 05 00 1.6.H172–
Record docsRecord docsThe Contractor shall update a complete set of the construction ...Common Work Results For Electrical26 05 00 1.7.A · PDF p. 172
Spec wording
“A. The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work daily by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative in accordance with Section 007213 – General Conditions. The updates shall show all addenda, all field changes that ...”
26 05 00 1.7.A172electronic file
Record docsRecord docsNo deviations from the Contract Drawings or approved shop drawings ...Common Work Results For Electrical26 05 00 1.7.B · PDF p. 172
Spec wording
“B. No deviations from the Contract Drawings or approved shop drawings shall be made without prior approval from the Designer or Construction Representative.”
26 05 00 1.7.B172–
WarrantyWarrantyExisting WarrantiesSelective Demolition For Electrical26 05 05 1.9.A · PDF p. 184
Spec wording
“A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.”
26 05 05 1.9.A184–
Test / cert.Test / cert.Submit test report indicating results for copper wire and cable ...Low-Voltage Electrical Power Conductors And26 05 19 1.4.B · PDF p. 191
Spec wording
“B. Submit test report indicating results for copper wire and cable continuity and resistance testing.”
26 05 19 1.4.B191–
Test / cert.Test / cert.Perform and record results of megger tests for each phase ...Low-Voltage Electrical Power Conductors And26 05 19 3.4.F · PDF p. 197
Spec wording
“F. Perform and record results of megger tests for each phase and neutral conductor for each feeder. Include actual recorded megaohm value for each conductor of each feeder in the feeder conductor insulation test report.”
26 05 19 3.4.F197–
Test / cert.Test / cert.Grounding rod resistance test reportGrounding And Bonding For Electrical Systems26 05 26 1.4.B · PDF p. 198
Spec wording
“B. Grounding rod resistance test report.”
26 05 26 1.4.B198–
Test / cert.Test / cert.Provide written report of test results including date and time ...Grounding And Bonding For Electrical Systems26 05 26 3.5.C · PDF p. 202
Spec wording
“C. Provide written report of test results including date and time of testing, test equipment used, test equipment calibration date, and names of individuals performing the testing,”
26 05 26 3.5.C202–
TrainingTrainingStudy documentationProtective Device Coordination Study And Arc26 05 73 1.4.A · PDF p. 234
Spec wording
“A. Study documentation 1. Product Certificates: For coordination study and fault-current study computer software programs, certifying compliance with IEEE 399 2. Qualification Data: For fault-current study and arc flash risk assessment specialist who shall be a professional engineer registered in the State of the Missouri 3. Demonstrate experience with Arc Flash Risk Assessment by submitting names of at least three ...”
26 05 73 1.4.A234–
TrainingTrainingThe arc flash study provider shall train the Owner's personnel ...Protective Device Coordination Study And Arc26 05 73 1.16.A · PDF p. 243
Spec wording
“A. The arc flash study provider shall train the Owner's personnel on the potential arc flash hazards associated with working on energized electrical equipment. The audience will include employees who work on or near energized electrical equipment, who must be made aware of the associated electrical hazards. The training shall be conducted at the Owner's facility and shall be a minimum of 1 hour and a maximum of 2 ...”
26 05 73 1.16.A243–
TrainingTrainingThe intent of this training is not to "certify" or ...Protective Device Coordination Study And Arc26 05 73 1.16.B · PDF p. 243
Spec wording
“B. The intent of this training is not to "certify" or "qualify" the Owner's maintenance personnel to work on energized electrical equipment or provide an adequate level of training for them to meet the NFPA 70E definition of a "qualified person" but rather to give them a broad understanding of the purpose of arc flash hazard warning labeling and an awareness of the dangers of working on or near energized electrical ...”
26 05 73 1.16.B243–
TrainingTrainingA key purpose of the training is to help the ...Protective Device Coordination Study And Arc26 05 73 1.16.C · PDF p. 243
Spec wording
“C. A key purpose of the training is to help the attendees become aware of potential shock and arc flash hazards associated with energized electrical equipment and ways to mitigate the risk of injury associated with these hazards.”
26 05 73 1.16.C243–
TrainingTrainingIt is not the intent of this training to provide ...Protective Device Coordination Study And Arc26 05 73 1.16.D · PDF p. 243
Spec wording
“D. It is not the intent of this training to provide electrical equipment preventative maintenance training.”
26 05 73 1.16.D243–
O&MO&MManufacturer's product data sheets and shop drawings shall be submitted ...Dry-Type, Medium-Voltage Transformers26 12 16 1.5.A · PDF p. 249-250
Spec wording
“A. Manufacturer's product data sheets and shop drawings shall be submitted for each transformer: 1. Master drawing index 2. Front view elevation and weight 3. Plan view 4. Schematic diagrams 5. Nameplate diagram 6. Component list 7. Conduit entry/exit locations 8. Ratings including: a. kVA b. Primary and secondary voltage c. Taps d. Primary and secondary continuous current e. Basic Impulse Level f. Impedance g. ...”
26 12 16 1.5.A249-250–
WarrantyWarrantyThe manufacturer's factory warranty shall be a minimum of twelve ...Dry-Type, Medium-Voltage Transformers26 12 16 1.8.A · PDF p. 250
Spec wording
“A. The manufacturer's factory warranty shall be a minimum of twelve (12) months after energization or eighteen (18) months after delivery, whichever comes first.”
26 12 16 1.8.A250–
Test / cert.Test / cert.Submit signed and dated field test report indicating results of ...Dry-Type, Medium-Voltage Transformers26 12 16 3.2.C · PDF p. 254
Spec wording
“C. Submit signed and dated field test report indicating results of all field testing and make, model and calibration date of all test equipment used.”
26 12 16 3.2.C254–
Test / cert.Test / cert.Provide certified test reports indicating compliance with specified performance requirements ...Pad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.5.A · PDF p. 256
Spec wording
“A. Provide certified test reports indicating compliance with specified performance requirements.”
26 12 19 1.5.A256–
Test / cert.Test / cert.Coordination and Site Service DataPad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.5.F · PDF p. 257
Spec wording
“F. Coordination and Site Service Data: Provide with shop drawings erection drawings and complete installation instructions for shipment, unpacking, installation, erection, adjustment, commissioning, and operation of equipment.”
26 12 19 1.5.F257–
O&MO&MSubmit Operation and Maintenance ManualsPad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.5.I · PDF p. 257
Spec wording
“I. Submit Operation and Maintenance Manuals 1. Submit operating instructions including instructions for fuse replacement and switch adjustment. 2. Manuals shall include items listed below and other information recommended by manufacturer: a. Catalog information of unit installed b. Capacity and installation details c. Wiring diagrams of electrical components d. Complete list of parts with reordering numbers e. ...”
26 12 19 1.5.I257–
Spare partsSpare partsProvide three (3) spare bayonet expulsion fusesPad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.6.A · PDF p. 257
Spec wording
“A. Provide three (3) spare bayonet expulsion fuses.”
26 12 19 1.6.A257–
Spare partsSpare partsProvide one (1) 12-ounce to 16-ounce minimum, aerosol can each ...Pad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.6.B · PDF p. 257
Spec wording
“B. Provide one (1) 12-ounce to 16-ounce minimum, aerosol can each of red-oxide primer and Munsell 7.0GY3.29/1.5 paint for touching up scratches in the transformer enclosure paint finish.”
26 12 19 1.6.B257–
Spare partsSpare partsProvide three (3) spare elbow type surge arrestersPad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.6.C · PDF p. 257
Spec wording
“C. Provide three (3) spare elbow type surge arresters.”
26 12 19 1.6.C257–
WarrantyWarrantyManufacturer of pad-mounted, liquid-filled, medium-voltage transformers shall warrant that equipment ...Pad-Mounted, Liquid-Filled, Medium-Voltage26 12 19 1.7.A · PDF p. 258
Spec wording
“A. Manufacturer of pad-mounted, liquid-filled, medium-voltage transformers shall warrant that equipment will be free from defects in material and workmanship for a period of twelve (12) months from energization and acceptance or eighteen (18) months from date of shipment, whichever comes first.”
26 12 19 1.7.A258–
WarrantyWarrantyThe following submittals shall be provided for each panelboard surge ...Panelboards26 24 16 1.4.D · PDF p. 267-268
Spec wording
“D. The following submittals shall be provided for each panelboard surge protective device (SPD) (Alternate Bid No. 1): 1. Provide verification that the SPD unit complies with the required UL 1449, Fourth Edition and UL 1283 surge voltage rating (SVR). 2. Provide actual let through voltage test data in the form of oscillograph results for both the ANSI/IEEE C62.41 Category C3 (combination wave) and B3 (ringwave) ...”
26 24 16 1.4.D267-268–
Spare partsSpare partsThe Contractor shall provide and turn over to the Owner's ...Fuses26 28 13 1.5.A · PDF p. 276
Spec wording
“A. The Contractor shall provide and turn over to the Owner's Representative, 10% spare fuses (minimum of 3) for each size and type of fuse, including control fuses, used on this project.”
26 28 13 1.5.A276–

Division 28 Fire alarm and security 26 items

TypeItemSpec sectionPDF pageCopies / format
Spare partsSpare partsPrior to release of equipment for shipment or installation, submit ...Addressable Fire Alarm System28 31 11 1.8.E · PDF p. 292-293
Spec wording
“E. Prior to release of equipment for shipment or installation, submit to the Engineer the following: 1. Shop Drawings. The specific quantity to be submitted shall be confirmed with the General Contractor and Owner. Electronic submittals are acceptable. Submittal must be comprehensive of the entire project, complete in all detail, and include, but not be limited to, the following: a. Floor plans showing equipment ...”
28 31 11 1.8.E292-293Electronic submittals; AutoCAD
Record docsRecord docsThe Contractor shall provide and maintain on site an up-to-date ...Addressable Fire Alarm System28 31 11 1.9.A · PDF p. 294
Spec wording
“A. The Contractor shall provide and maintain on site an up-to-date record set of satisfactory shop drawings which shall be marked to show each and every change made to the fire alarm system from the original approved shop drawings. This shall not be construed as authorization to deviate from or make changes to the shop drawings reviewed by the Engineer without written instructions from the Engineer in each case. ...”
28 31 11 1.9.A294–
Record docsRecord docsThe preparation of a record of completion shall be the ...Addressable Fire Alarm System28 31 11 1.9.B · PDF p. 294
Spec wording
“B. The preparation of a record of completion shall be the responsibility or the qualified and experienced installation personnel, as indicated in NFPA 72.”
28 31 11 1.9.B294–
Record docsRecord docsThe preparation of a record of completion shall be in ...Addressable Fire Alarm System28 31 11 1.9.C · PDF p. 294
Spec wording
“C. The preparation of a record of completion shall be in accordance with NFPA 72. Record of completion shall include, but not be limited to, the following: 1. A final copy of the record of completion shall be provided after completion of the operational acceptance tests. 2. One copy of the record of completion shall be stored at the fire alarm control panel or other approved location. 3. This copy shall be updated ...”
28 31 11 1.9.C294One copy
Record docsRecord docsThe Contractor shall continually document software and programming changes. This ...Addressable Fire Alarm System28 31 11 1.9.D · PDF p. 294
Spec wording
“D. The Contractor shall continually document software and programming changes. This documentation shall include: 1. A complete printout of the system prior to the change. 2. A complete printout of the system program subsequent to the change, with all modifications highlighted. 3. A letter prepared and signed by the individual who made the changes, describing each change made and the reason for the change. This ...”
28 31 11 1.9.D294–
Record docsRecord docsAll fire alarm system modifications made after the initial installation ...Addressable Fire Alarm System28 31 11 1.9.E · PDF p. 295
Spec wording
“E. All fire alarm system modifications made after the initial installation shall be recorded on a revised version of the original record of completion, as indicated in NFPA 72.”
28 31 11 1.9.E295–
Record docsRecord docsOnce the fire alarm system is put into service, in ...Addressable Fire Alarm System28 31 11 1.9.F · PDF p. 295
Spec wording
“F. Once the fire alarm system is put into service, in whole or in part, and the associated building(s) are partially or wholly occupied, no software changes shall be performed without prior written permission of the Owner, or Owner's Representative.”
28 31 11 1.9.F295–
Record docsRecord docsOnly a certified manufacturer's representative trained in the specific programming ...Addressable Fire Alarm System28 31 11 1.9.G · PDF p. 295
Spec wording
“G. Only a certified manufacturer's representative trained in the specific programming software shall make changes to the fire alarm system software once the system is in service.”
28 31 11 1.9.G295–
Record docsRecord docsEach revision to the software shall be identified by a ...Addressable Fire Alarm System28 31 11 1.9.H · PDF p. 295
Spec wording
“H. Each revision to the software shall be identified by a unique version number and date.”
28 31 11 1.9.H295–
Record docsRecord docsPrior to final payment for the fire alarm system and ...Addressable Fire Alarm System28 31 11 1.9.I · PDF p. 295
Spec wording
“I. Prior to final payment for the fire alarm system and the beginning of the warranty period, submit a CD ROM and two (2) sets (or as directed by the Owner's Representative) of the following completed project record documents to the Owner's Representative: 1. Copies of all test and inspection reports as required by the AHJ and NFPA 72: a. The Record of Completion form shall be in the format as outlined in NFPA 72. ...”
28 31 11 1.9.I295CD; two (2) sets; AutoCAD
Record docsRecord docsUpon completion of construction, submit two (2) sets and a ...Addressable Fire Alarm System28 31 11 1.9.J · PDF p. 295-296
Spec wording
“J. Upon completion of construction, submit two (2) sets and a CD ROM of equipment warranties and two (2) sets and a CD ROM of installation, operations and maintenance instructions to the Owner's Representative. This manual shall reflect the completed installation and include, but not be limited to the following information: 1. A detailed narrative description of the systems architecture, inputs, evacuation ...”
28 31 11 1.9.J295-296two (2) sets; CD
Record docsRecord docsA copy of all software documentation required by this section ...Addressable Fire Alarm System28 31 11 1.9.K · PDF p. 296
Spec wording
“K. A copy of all software documentation required by this section shall be maintained on-site by the Contractor, in a binder, arranged in chronological order. This binder shall be provided to the Owner's Representative at the completion of the project.”
28 31 11 1.9.K296binder
WarrantyWarrantyRepair all defective workmanship or replace all defective materials for ...Addressable Fire Alarm System28 31 11 1.15.A · PDF p. 297
Spec wording
“A. Repair all defective workmanship or replace all defective materials for a period of one (1) year from the date of acceptance by the Owner's Representative. Workmanship or equipment found to be defective during that period shall be replaced at no additional cost to the Owner.”
28 31 11 1.15.A297–
WarrantyWarrantyThe warranty or any part of the warranty shall not ...Addressable Fire Alarm System28 31 11 1.15.B · PDF p. 298
Spec wording
“B. The warranty or any part of the warranty shall not be made void by any required operation or inspection of the system after acceptance during the warranty period. The Owner may select qualified firms other than Warrantor to provide required tests and inspections. System testing and inspections will be conducted only by a duly licensed company under contract with the Owner to perform scheduled testing and ...”
28 31 11 1.15.B298–
Spare partsSpare partsInitiating DevicesAddressable Fire Alarm System28 31 11 2.13.A · PDF p. 308
Spec wording
“A. Initiating Devices: Provide a quantity equal to ten (10) percent of the number of each type of device installed, but not less than one of each type.”
28 31 11 2.13.A308–
Spare partsSpare partsNotification AppliancesAddressable Fire Alarm System28 31 11 2.13.B · PDF p. 308
Spec wording
“B. Notification Appliances: Provide a quantity equal to ten (10) percent of the number of each type (e.g. candela rating) of appliance installed, but not less than one of each type.”
28 31 11 2.13.B308–
Spare partsSpare partsDetector BasesAddressable Fire Alarm System28 31 11 2.13.C · PDF p. 308
Spec wording
“C. Detector Bases: Provide a quantity equal to two (2) percent of the number of each type installed, but not less than one (1) of each type.”
28 31 11 2.13.C308–
Spare partsSpare partsKeysAddressable Fire Alarm System28 31 11 2.13.D · PDF p. 308
Spec wording
“D. Keys: Provide a minimum of five (5) keys of each type required. Keys and locks for all equipment shall be identical.”
28 31 11 2.13.D308–
Spare partsSpare partsLamps for Remote Indicating Lamp UnitsAddressable Fire Alarm System28 31 11 2.13.E · PDF p. 308
Spec wording
“E. Lamps for Remote Indicating Lamp Units: Quantity equal to ten (10) percent of amount installed, but no less than 1 unit.”
28 31 11 2.13.E308–
Spare partsSpare partsLamps for Strobe UnitsAddressable Fire Alarm System28 31 11 2.13.F · PDF p. 308
Spec wording
“F. Lamps for Strobe Units: Quantity equal to ten (10) percent of amount installed, but no less than 1 unit.”
28 31 11 2.13.F308–
Spare partsSpare partsSmoke Detectors, Heat Detectors, Projected Beam DetectorsAddressable Fire Alarm System28 31 11 2.13.G · PDF p. 308
Spec wording
“G. Smoke Detectors, Heat Detectors, Projected Beam Detectors: Quantity equal to ten (10) percent of amount of each type installed, but no less than 1 unit of each type.”
28 31 11 2.13.G308–
Spare partsSpare partsDetector BasesAddressable Fire Alarm System28 31 11 2.13.H · PDF p. 308
Spec wording
“H. Detector Bases: Quantity equal to two (2) percent of amount of each type installed, but no less than 1 unit of each type.”
28 31 11 2.13.H308–
Spare partsSpare partsAudible and Visual Notification AppliancesAddressable Fire Alarm System28 31 11 2.13.I · PDF p. 308
Spec wording
“I. Audible and Visual Notification Appliances: Quantity equal to ten (10) percent of amount of each type installed, but no less than one (1) unit of each type.”
28 31 11 2.13.I308–
Spare partsSpare partsKeys and ToolsAddressable Fire Alarm System28 31 11 2.13.J · PDF p. 308
Spec wording
“J. Keys and Tools: One (1) extra set for access to locked and tamper proofed components.”
28 31 11 2.13.J308–
Spare partsSpare partsFusesAddressable Fire Alarm System28 31 11 2.13.K · PDF p. 309
Spec wording
“K. Fuses: Two (2) of each type installed in the system.”
28 31 11 2.13.K309–
TrainingTrainingTrain Owner's maintenance personnel to adjust, operate, and maintain fire ...Addressable Fire Alarm System28 31 11 3.9.A · PDF p. 318
Spec wording
“A. Train Owner's maintenance personnel to adjust, operate, and maintain fire alarm system.”
28 31 11 3.9.A318–

Division 31 Earthwork 3 items

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsRecord DrawingsSite Clearing31 10 00 1.5.A · PDF p. 319
Spec wording
“A. Record Drawings: Identifying and accurately showing locations of capped utilities and other subsurface structural, electrical, and mechanical conditions.”
31 10 00 1.5.A319–
Test / cert.Test / cert.Material Test ReportsEarth Moving31 20 00 1.4.C · PDF p. 323
Spec wording
“C. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows: 1. Classification according to ASTM D 2487. 2. Laboratory compaction curve according to ASTM D 698 or ASTM D 1557 as noted herein.”
31 20 00 1.4.C323–
Test / cert.Test / cert.When testing agency reports that subgrades, fills, or backfills have ...Earth Moving31 20 00 3.19.E · PDF p. 329
Spec wording
“E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.”
31 20 00 3.19.E329–

Division 32 Paving and site improvements 1 item

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Material Test ReportsAsphalt Paving32 12 16 1.4.D · PDF p. 331
Spec wording
“D. Material Test Reports: For each paving material.”
32 12 16 1.4.D331–

Division 33 Utilities 19 items

TypeItemSpec sectionPDF pageCopies / format
Spare partsSpare partsProvide one (1) 12-ounce, minimum, aerosol can each of red-oxide ...Medium-Voltage Outdoor Sectionalizing Cabinets33 71 10 1.7.A · PDF p. 342
Spec wording
“A. Provide one (1) 12-ounce, minimum, aerosol can each of red-oxide primer and the Munsell 7GY3.29/1.5 topcoat paint for touching up scratches in the sectionalizing enclosure paint finish.”
33 71 10 1.7.A342–
Spare partsSpare partsProvide three (3) spare elbow type surge arrestersMedium-Voltage Outdoor Sectionalizing Cabinets33 71 10 1.7.B · PDF p. 342
Spec wording
“B. Provide three (3) spare elbow type surge arresters.”
33 71 10 1.7.B342–
TrainingTrainingSubmit qualification data for medium-voltage cable splice and termination installer ...Medium-Voltage Wiring33 71 49 1.4.B · PDF p. 354
Spec wording
“B. Submit qualification data for medium-voltage cable splice and termination installer certifying adequate training and experience for the specific type of splice and termination required for this project.”
33 71 49 1.4.B354–
Test / cert.Test / cert.Submit qualification data for medium-voltage cable DC HiPot testing technician ...Medium-Voltage Wiring33 71 49 1.4.C · PDF p. 354
Spec wording
“C. Submit qualification data for medium-voltage cable DC HiPot testing technician certifying adequate training and experience for the successful performance of the testing required.”
33 71 49 1.4.C354–
Test / cert.Test / cert.Submit 15 kV cable preparatory test report prior to commencement ...Medium-Voltage Wiring33 71 49 1.4.D · PDF p. 354
Spec wording
“D. Submit 15 kV cable preparatory test report prior to commencement of medium-voltage cable testing.”
33 71 49 1.4.D354–
Test / cert.Test / cert.Submit 15 kV cable acceptance test reportMedium-Voltage Wiring33 71 49 1.4.E · PDF p. 354
Spec wording
“E. Submit 15 kV cable acceptance test report.”
33 71 49 1.4.E354–
Test / cert.Test / cert.All test results shall be certified and submitted to and ...Medium-Voltage Wiring33 71 49 3.5.T · PDF p. 363
Spec wording
“T. All test results shall be certified and submitted to and approved by the Designer prior to energization of any cables or on the first business day after completion of the testing if the testing is performed at a time other than normal weekday business hours.”
33 71 49 3.5.T363–
TrainingTrainingField startup report and demonstration and Owner training certification signoff ...Medium-Voltage Pad-Mounted Switchgear33 77 10 1.4.F · PDF p. 365
Spec wording
“F. Field startup report and demonstration and Owner training certification signoff sheet.”
33 77 10 1.4.F365–
O&MO&MProvide O&M Manuals that describe installation, operation, and maintenance of ...Medium-Voltage Pad-Mounted Switchgear33 77 10 1.5.A · PDF p. 365
Spec wording
“A. Provide O&M Manuals that describe installation, operation, and maintenance of the equipment furnished, complete with all wiring and schematic diagrams.”
33 77 10 1.5.A365–
O&MO&MInstruction manuals shall be provided as follows:Medium-Voltage Pad-Mounted Switchgear33 77 10 1.5.B · PDF p. 365
Spec wording
“B. Instruction manuals shall be provided as follows: 1. Submit three (3) sets of manuals bound in 8-1/2-inch by 11-inch (A4) text pages, except drawings reduced to 11-inch by 17-inch pages may be folded for inclusion in the manuals. The manuals shall also be provided in electronic (.pdf) formal on a USB thumb drive as part of the Project O&M Manuals under Section 017823 – Operation and Maintenance Data. 2. Each ...”
33 77 10 1.5.B365three (3) sets; pdf; USB; thumb drive; hard copy; binders
Spare partsSpare partsProvide three (3) spare solid-material power fuse refill units of ...Medium-Voltage Pad-Mounted Switchgear33 77 10 1.7.A · PDF p. 366
Spec wording
“A. Provide three (3) spare solid-material power fuse refill units of each size and type used on this project.”
33 77 10 1.7.A366–
Spare partsSpare partsProvide two (2) 9-ounce, minimum, aerosol cans each of red-oxide ...Medium-Voltage Pad-Mounted Switchgear33 77 10 1.7.B · PDF p. 366
Spec wording
“B. Provide two (2) 9-ounce, minimum, aerosol cans each of red-oxide primer and the Munsell 7GY3.29/1.5 topcoat paint for touching up scratches in the switchgear enclosure paint finish.”
33 77 10 1.7.B366–
Test / cert.Test / cert.Provide startup and commissioning of the equipment in accordance with ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.2.A · PDF p. 376
Spec wording
“A. Provide startup and commissioning of the equipment in accordance with the equipment manufacturer's recommendations in the presence of the Construction Representative and Owner's maintenance personnel.”
33 77 10 3.2.A376–
Test / cert.Test / cert.Test functional operation of all interrupter switches and all power ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.2.B · PDF p. 376
Spec wording
“B. Test functional operation of all interrupter switches and all power fuse units.”
33 77 10 3.2.B376–
Test / cert.Test / cert.Repair and retest until equipment is fully functional as designedMedium-Voltage Pad-Mounted Switchgear33 77 10 3.2.C · PDF p. 376
Spec wording
“C. Repair and retest until equipment is fully functional as designed.”
33 77 10 3.2.C376–
Test / cert.Test / cert.Provide field startup report for Owner's records indicating the date ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.2.D · PDF p. 376
Spec wording
“D. Provide field startup report for Owner's records indicating the date and time and name of the person who performed the equipment startup and commissioning services.”
33 77 10 3.2.D376–
TrainingTrainingProvide demonstration and training in accordance with the requirements of ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.3.A · PDF p. 376
Spec wording
“A. Provide demonstration and training in accordance with the requirements of Section 017900 – Demonstration and Training.”
33 77 10 3.3.A376–
TrainingTrainingInstruct the Owner's maintenance personnel on the proper operation and ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.3.B · PDF p. 376
Spec wording
“B. Instruct the Owner's maintenance personnel on the proper operation and preventative maintenance of the switchgear and on servicing of all Owner serviceable components, including but not limited to: 1. Operation of interrupter switches 2. Opening interrupter switch termination access doors 3. Viewing position of switch blades 4. Opening fuse compartment access doors 5. Viewing the blown fuse indicator on power ...”
33 77 10 3.3.B376–
TrainingTrainingProvide sign-off sheet documenting the date and time of the ...Medium-Voltage Pad-Mounted Switchgear33 77 10 3.3.C · PDF p. 376
Spec wording
“C. Provide sign-off sheet documenting the date and time of the training, names of all attendees, name of person conducting the training and their Company contact information with sign-off by trainer and the Owner's Representative.”
33 77 10 3.3.C376–

Front end Contract conditions (final payment, releases, retainage) 11 items

TypeItemSpec sectionPDF pageCopies / format
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 24
Spec wording
“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...”
Conditions Of The Contract (Find Heading On The Cited Page)24–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 35
Spec wording
“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.”
Conditions Of The Contract (Find Heading On The Cited Page)35–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 36
Spec wording
“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.”
Conditions Of The Contract (Find Heading On The Cited Page)36three (4) copies
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 42
Spec wording
“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.”
Conditions Of The Contract (Find Heading On The Cited Page)42–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 43
Spec wording
“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...”
Conditions Of The Contract (Find Heading On The Cited Page)43–
WarrantyWarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 35
Spec wording
“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...”
Conditions Of The Contract ARTICLE.A35–
WarrantyWarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 35
Spec wording
“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.”
Conditions Of The Contract ARTICLE.B35–
O&MO&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 35-36
Spec wording
“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...”
Conditions Of The Contract ARTICLE.A35-36three (3) copies; three (4) copies
O&MO&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 36
Spec wording
“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...”
Conditions Of The Contract ARTICLE.B36binders; binder
O&MO&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 40-41
Spec wording
“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...”
Conditions Of The Contract ARTICLE.A40-41–
Test / cert.Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 41
Spec wording
“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...”
Conditions Of The Contract ARTICLE.C41–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.