Closeout checklist: Geiger Quads G520 DOAS Replacement, Camp Lejeune (NAVFAC Mid-Atlantic, NC)

Every closeout item we found in the public spec book for this job: 81 items across Division 01, 4 trade divisions, including 33 tests and certificates, 17 O&M manual items and 8 warranties. Each one is tied to its spec section and the PDF page it sits on.

Owner
NAVFAC Mid-Atlantic (ROICC Camp Lejeune)
Number
Solicitation N40085-25-R-9027, project 25-0078
Location
Camp Lejeune, NC
Task order signed
2025-09-30
Public spec book
Solicitation notice on SAM.gov (spec book attached, marked public)
Spec book size
507 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Amendment 0005 re-issued section 23 73 33; its closeout items match the original book.

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

8Warranties
17O&M manuals
33Tests and certificates
6Training
5Record documents
2Spare parts
0Payment release
10Closeout steps

All 81 items, by trade

Division 01 General requirements 54 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepSD-11 Closeout Submittals Interim DD-1354, Transfer & Acceptance of Mi ...Transfer And Acceptance Of Military Real Property01 31 50 1.1 · PDF p. 29
Spec wording
“SD-11 Closeout Submittals Interim DD-1354, Transfer & Acceptance of Military Real Property 1.2 Interim DD-1354, Transfer & Acceptance of Military Real Property Submit Interim DD-1354 thirty (30) days prior to beneficial occupancy date (draft copy attached).”
01 31 50 1.129–
Test / cert.Test / cert.SD-07 Certificates Monthly Updates2001 32 16.00 1.1 · PDF p. 30
Spec wording
“SD-07 Certificates Monthly Updates”
01 32 16.00 1.130–
Closeout stepCloseout stepSD-11 Closeout Submittals Submittal register Complete Submittal Packag ...Submittal Procedures01 33 00 1.3 · PDF p. 38
Spec wording
“SD-11 Closeout Submittals Submittal register Complete Submittal Package 2 CD/DVD's”
01 33 00 1.338CD; DVD
WarrantyWarranty1.5.1 Reviewing, Certifying, Approving Authority QC organization shall be responsible ...Submittal Procedures01 33 00 1.5 · PDF p. 40-43
Spec wording
“1.5.1 Reviewing, Certifying, Approving Authority QC organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. The Contracting Officer is the approving authority for all submittals. 1.5.2 Constraints a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise. b. Submittals shall ...”
01 33 00 1.540-4320 copies
O&MO&M1.6.1 Complete Submittal Package Contractor shall make electronic copies of ...Submittal Procedures01 33 00 1.6 · PDF p. 44-46
Spec wording
“1.6.1 Complete Submittal Package Contractor shall make electronic copies of all submittals, including the approved transmittal sheets, and provide two (2) CD/DVD's containing all submittals for the project. The CD/DVD's shall be marked "Complete Submittal Package - Contract # ________" 1.6.2 Transmittal Form Transmit each submittal, except sample installations and sample panels, to office of approving authority. ...”
01 33 00 1.644-46electronic copies; CD; DVD; Full size
O&MO&M1.7.1 Number of Copies of Product DataSubmittal Procedures01 33 00 1.7 · PDF p. 46
Spec wording
“1.7.1 Number of Copies of Product Data a. Submit five copies of submittals of product data requiring review and approval only by the Contracting Officer. Submit three copies of submittals of product data for operation and maintenance manuals. 1.7.2 Number of Copies of Shop Drawings Submit shop drawings in compliance with quantity requirements specified for product data. 1.7.3 Number of Samples a. Submit two ...”
01 33 00 1.746five copies; three copies; two sets
O&MO&M1.8.1 Samples and Submittals Except as otherwise noted, submit samples ...Submittal Procedures01 33 00 1.8 · PDF p. 46-47
Spec wording
“1.8.1 Samples and Submittals Except as otherwise noted, submit samples and submittals to: ROICC/OICC Jacksonville, North Carolina Area 1005 Michael Road Camp Lejeune, NC 28542-2521 --OR--Architect-Engineer Firm Full Address 1.8.1.1 Administrative Submittals Submit administrative submittals for asbestos/lead removal and environmental protection plan to the Resident Officer in Charge of Construction (ROICC/OICC). ...”
01 33 00 1.846-47–
Test / cert.Test / cert.SD-06 Test Reports Monthly Exposure Reports Notifications and Reports ...Governmental Safety Requirements01 35 26 1.3 · PDF p. 67-68
Spec wording
“SD-06 Test Reports Monthly Exposure Reports Notifications and Reports Accident Reports; G LHE Inspection Reports”
01 35 26 1.367-68–
Test / cert.Test / cert.SD-07 Certificates Contractor Safety Self-Evaluation Checklist Crane O ...Governmental Safety Requirements01 35 26 1.3 · PDF p. 67-68
Spec wording
“SD-07 Certificates Contractor Safety Self-Evaluation Checklist Crane Operators/Riggers Standard Lift Plan; G Critical Lift Plan ; G Naval Architecture Analysis; G Activity Hazard Analysis (AHA) Confined Space Entry Permit Hot Work Permit Certificate of Compliance Third Party Certification of Floating Cranes and Barge-Mounted Mobile Cranes License Certificates Radiography Operation Planning Work Sheet; G Portable ...”
01 35 26 1.367-68–
Test / cert.Test / cert.SD-07 Certificates Certificate Of Worker/Visitor AcknowledgementHealth, Safety, And Emergency Response Procedures For Contaminated Sites01 35 29.13 1.3 · PDF p. 98
Spec wording
“SD-07 Certificates Certificate Of Worker/Visitor Acknowledgement”
01 35 29.13 1.398–
Closeout stepCloseout stepSD-11 Closeout Submittals Safety And Health Phase-Out Report; GHealth, Safety, And Emergency Response Procedures For Contaminated Sites01 35 29.13 1.3 · PDF p. 98
Spec wording
“SD-11 Closeout Submittals Safety And Health Phase-Out Report; G”
01 35 29.13 1.398–
TrainingTrainingIn conjunction with EM 385-1-1, Section 33D, meet the training ...Health, Safety, And Emergency Response Procedures For Contaminated Sites01 35 29.13 3.3 · PDF p. 106-107
Spec wording
“In conjunction with EM 385-1-1, Section 33D, meet the training program requirements for workers performing cleanup operations and who will be exposed to contaminants. 3.3.1 General HTRW Operations Training All Personnel performing duties with potential for exposure to onsite contaminants must meet and maintain the following 29 CFR 1910.120/ 29 CFR 1926.65 (e) training requirements: a. 40 hours of off site HTRW ...”
01 35 29.13 3.3106-107–
Test / cert.Test / cert.SD-06 Test Reports Verification StatementQuality Control01 45 00 1.3 · PDF p. 117-118
Spec wording
“SD-06 Test Reports Verification Statement”
01 45 00 1.3117-118–
Test / cert.Test / cert.Establish and maintain a QC program as described in this ...Quality Control01 45 00 1.5 · PDF p. 118-122
Spec wording
“Establish and maintain a QC program as described in this section. The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, QC certifications, and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and ...”
01 45 00 1.5118-122–
Test / cert.Test / cert.1.6.1 Quality Control (QC) Manager 1.6.1.1 Duties Provide a QC ...Quality Control01 45 00 1.6 · PDF p. 122-126
Spec wording
“1.6.1 Quality Control (QC) Manager 1.6.1.1 Duties Provide a QC Manager at the work site to implement and manage the QC program, and to serve as the Site Safety and Health Officer (SSHO) as detailed in Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. In addition to implementing and managing the QC program, the QC Manager may perform the duties of Project Superintendent. The QC Manager must attend the partnering ...”
01 45 00 1.6122-126–
Test / cert.Test / cert.1.11.1 Contractor Quality Control (CQC) Report Certification Contain the following ...Quality Control01 45 00 1.11 · PDF p. 132
Spec wording
“1.11.1 Contractor Quality Control (CQC) Report Certification Contain the following statement within the CQC Report: "On behalf of the Contractor, I certify that this report is complete and correct and equipment and material used, and work performed during this reporting period is in compliance with the Contract drawings and specifications to the best of my knowledge, except as noted in this report." 1.11.2 ...”
01 45 00 1.11132–
Test / cert.Test / cert.SD-06 Test Reports Backflow Preventer TestsTemporary Construction Facilities And Controls01 50 00 1.2 · PDF p. 136
Spec wording
“SD-06 Test Reports Backflow Preventer Tests”
01 50 00 1.2136–
Test / cert.Test / cert.SD-07 Certificates Backflow Tester Certification Backflow Preventers C ...Temporary Construction Facilities And Controls01 50 00 1.2 · PDF p. 136
Spec wording
“SD-07 Certificates Backflow Tester Certification Backflow Preventers Certificate of Full Approval”
01 50 00 1.2136–
Test / cert.Test / cert.SD-06 Test Reports Abrasive blasting waste materials - if applicable S ...Temporary Environmental Controls01 57 19 1.4 · PDF p. 144-145
Spec wording
“SD-06 Test Reports Abrasive blasting waste materials - if applicable Submit a copy of an approved laboratory analysis of materials collected as a result from abrasive blasting operations before disposing of waste materials.”
01 57 19 1.4144-145–
TrainingTrainingSD-11 Closeout Submittals Solid waste disposal permit Disposal permit ...Temporary Environmental Controls01 57 19 1.4 · PDF p. 144-145
Spec wording
“SD-11 Closeout Submittals Solid waste disposal permit Disposal permit for hazardous waste Environmental training documentation Permit to transport hazardous waste Hazardous waste certification Environmental Plan Review Annual Report of Products Containing Recovered Materials 1.4.1 Solid Waste Disposal Permit Submit one copy of a State permit or license for the solid waste disposal facility. If the contract permits ...”
01 57 19 1.4144-145one copy
Record docsRecord docsRequest the full set of electronic drawings, in the source ...Closeout Submittals01 78 00 1.3 · PDF p. 160
Spec wording
“Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use. 1.3.1 Terms and Conditions Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor ...”
01 78 00 1.3160electronic files; CAD
WarrantyWarrantySD-03 Product Data Warranty Management Plan Warranty Tags Final Cleani ...Closeout Submittals01 78 00 1.4 · PDF p. 160-161
Spec wording
“SD-03 Product Data Warranty Management Plan Warranty Tags Final Cleaning Spare Parts Data”
01 78 00 1.4160-161–
Closeout stepCloseout stepSD-08 Manufacturer's Instructions Posted InstructionsCloseout Submittals01 78 00 1.4 · PDF p. 160-161
Spec wording
“SD-08 Manufacturer's Instructions Posted Instructions”
01 78 00 1.4160-161–
O&MO&MSD-10 Operation and Maintenance Data Operation and Maintenance Manuals ...Closeout Submittals01 78 00 1.4 · PDF p. 160-161
Spec wording
“SD-10 Operation and Maintenance Data Operation and Maintenance Manuals; G”
01 78 00 1.4160-161–
Record docsRecord docsSD-11 Closeout Submittals As-Built Drawings; G Record Drawings; G As-B ...Closeout Submittals01 78 00 1.4 · PDF p. 160-161
Spec wording
“SD-11 Closeout Submittals As-Built Drawings; G Record Drawings; G As-Built Record of Equipment and Materials Final Approved Shop Drawings Construction Contract Specifications Certification of EPA Designated Items; G Certification Of USDA Designated Items; G Interim DD FORM 1354; G Checklist for DD FORM 1354; G Equipment Inventory Update; G As-Built Record of Exterior Materials and Submittals; G”
01 78 00 1.4160-161–
Spare partsSpare partsSubmit two copies of the Spare Parts Data listCloseout Submittals01 78 00 1.5 · PDF p. 161
Spec wording
“Submit two copies of the Spare Parts Data list. a. Indicate manufacturer's name, part number, nomenclature, and stock level required for maintenance and repair. List those items that may be standard to the normal maintenance of the system.”
01 78 00 1.5161two copies
WarrantyWarranty1.6.1 Warranty Management Plan Develop a warranty management plan which ...Closeout Submittals01 78 00 1.6 · PDF p. 161-164
Spec wording
“1.6.1 Warranty Management Plan Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The ...”
01 78 00 1.6161-164one set; binder; two (2) copies; one copy
Record docsRecord docsSubmit the As-Built Record of Exterior Materials and Submittals. Prepare ...Closeout Submittals01 78 00 1.7 · PDF p. 164-165
Spec wording
“Submit the As-Built Record of Exterior Materials and Submittals. Prepare and provide the final approved exterior finish material submittals created during the execution of the project. All submittals, regardless of the approving authority, shall be submitted. Include a finish schedule documenting all the exterior finish materials that were installed on the project, the submittals/shop drawings themselves, all ...”
01 78 00 1.7164-165PDF; CD; DVD
Test / cert.Test / cert.Submit the Certification of EPA Designated Items as required by ...Closeout Submittals01 78 00 2.1 · PDF p. 165
Spec wording
“Submit the Certification of EPA Designated Items as required by FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items and FAR 52-223-17 Affirmative Procurement of EPA designated items in Service and Construction Contracts.. Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and ...”
01 78 00 2.1165–
Test / cert.Test / cert.Submit the Certification of USDA Designated Items as required by ...Closeout Submittals01 78 00 2.2 · PDF p. 165
Spec wording
“Submit the Certification of USDA Designated Items as required by FAR 52-223-1 Bio-based Product Certifications and FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and certification. The certification will read as follows ...”
01 78 00 2.2165–
Test / cert.Test / cert.Submit information for each piece of equipment removed and supplied ...Closeout Submittals01 78 00 3.1 · PDF p. 165-168
Spec wording
“Submit information for each piece of equipment removed and supplied for purposes of this paragraph, inventoried equipment is defined as equipment listed on the Maximo Equipment Inventory Update form. 3.1.1 Requirements The contractor shall prepare and submit one Maximo Equipment Inventory Update form for each individual item of inventoried equipment that is demolished, removed, replaced, or installed. (ex: three ...”
01 78 00 3.1165-168–
Record docsRecord docsProvide and maintain two black line print copies of the ...Closeout Submittals01 78 00 3.2 · PDF p. 169-171
Spec wording
“Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. At a minimum of 30 days prior to Beneficial Occupancy Date (BOD), certify both sets of as-built drawings as correct, sign, and submit the As-Built Drawings for Contracting Officer approval. 3.2.1 Markup Guidelines Make comments and markup the drawings complete without reference to letters, memos, or materials that ...”
01 78 00 3.2169-171PDF
Record docsRecord docsPrepare and provide Record Drawings in accordance with FC 1-300-09N. ...Closeout Submittals01 78 00 3.3 · PDF p. 171
Spec wording
“Prepare and provide Record Drawings in accordance with FC 1-300-09N. Provide 2 copies of Record Drawings on two separate CDs or DVDs 30 days after BOD.”
01 78 00 3.31712 copies
O&MO&MProvide project operation and maintenance manuals as specified in Section ...Closeout Submittals01 78 00 3.4 · PDF p. 171
Spec wording
“Provide project operation and maintenance manuals as specified in Section 01 78 23 OPERATION AND MAINTENANCE MANUALS DATA. Provide four electronic copies of the Operation and Maintenance Manual files. Submit to the Contracting Officer for approval within 60 calendar days of the Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD. Provide one hard copy and place in cabinet in main ...”
01 78 00 3.4171four electronic copies; one hard copy
Spare partsSpare partsProvide final cleaning in accordance with ASTM E1971 and submit ...Closeout Submittals01 78 00 3.5 · PDF p. 171
Spec wording
“Provide final cleaning in accordance with ASTM E1971 and submit two copies of the listing of completed final clean-up items. Leave premises "broom clean." Comply with GS-37 for general purpose cleaning and bathroom cleaning. Use only nonhazardous cleaning materials, including natural cleaning materials, in the final cleanup. Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains ...”
01 78 00 3.5171two copies
Closeout stepCloseout stepNear the completion of Project, but a minimum of 60 ...Closeout Submittals01 78 00 3.6 · PDF p. 171
Spec wording
“Near the completion of Project, but a minimum of 60 days prior to final acceptance of the work, complete, update draft DD FORM 1354 attached to this section, and submit an accounting of all installed property with Interim DD FORM 1354. Include any additional assets, improvements, and alterations from the Draft DD FORM 1354. Contact the Contracting Officer for any project specific information necessary to complete ...”
01 78 00 3.6171PDF
Closeout stepCloseout stepProvide 2 copies of Final Approved Shop Drawings on two ...Closeout Submittals01 78 00 3.7 · PDF p. 172
Spec wording
“Provide 2 copies of Final Approved Shop Drawings on two separate CDs or DVDs within 30 days after BOD.”
01 78 00 3.71722 copies
O&MO&MSD-10 Operation and Maintenance Data O&M Database ; G Training Plan ; ...Operation And Maintenance Data01 78 23 1.2 · PDF p. 173
Spec wording
“SD-10 Operation and Maintenance Data O&M Database ; G Training Plan ; G Training Outline ; G Training Content ; G”
01 78 23 1.2173–
TrainingTrainingSD-11 Closeout Submittals Training Video Recording ; G Validation of T ...Operation And Maintenance Data01 78 23 1.2 · PDF p. 173
Spec wording
“SD-11 Closeout Submittals Training Video Recording ; G Validation of Training Completion ; G”
01 78 23 1.2173–
O&MO&MSubmit Operation and Maintenance (O&M) Data for the provided equipment, ...Operation And Maintenance Data01 78 23 1.3 · PDF p. 173-174
Spec wording
“Submit Operation and Maintenance (O&M) Data for the provided equipment, product, or system, defining the importance of system interactions, troubleshooting, and long-term preventive operation and maintenance. Compile, prepare, and aggregate O&M data to include clarifying and updating the original sequences of operation to as-built conditions. Organize and present information in sufficient detail to clearly explain ...”
01 78 23 1.3173-174–
O&MO&MAssemble data packages into electronic Operation and Maintenance Manuals. Assemble ...Operation And Maintenance Data01 78 23 1.4 · PDF p. 174-175
Spec wording
“Assemble data packages into electronic Operation and Maintenance Manuals. Assemble each manual into a composite electronically indexed file using the most current version of Adobe Acrobat or similar software capable of producing PDF file format. Provide compact disks (CD) or data digital versatile disk (DVD) as appropriate, so that each one contains operation, maintenance and record files, project record documents, ...”
01 78 23 1.4174-175electronically; PDF; CD; DVD; one hard copy; bookmarked
Test / cert.Test / cert.SD-03 Product Data submittals documented with the required approval. 1 ...Operation And Maintenance Data01 78 23 1.5 · PDF p. 175-180
Spec wording
“SD-03 Product Data submittals documented with the required approval. 1.5.4.2 Certificates Provide a copy of”
01 78 23 1.5175-180–
Test / cert.Test / cert.SD-07 Certificates submittals documented with the required approval. 1 ...Operation And Maintenance Data01 78 23 1.5 · PDF p. 175-180
Spec wording
“SD-07 Certificates submittals documented with the required approval. 1.5.4.3 Manufacturer's Instructions Provide a copy of”
01 78 23 1.5175-180–
O&MO&MSD-08 Manufacturer's Instructions submittals documented with the requi ...Operation And Maintenance Data01 78 23 1.5 · PDF p. 175-180
Spec wording
“SD-08 Manufacturer's Instructions submittals documented with the required approval. 1.5.4.4 O&M Submittal Data Provide a copy of”
01 78 23 1.5175-180–
WarrantyWarrantySD-10 Operation and Maintenance Data submittals documented with the re ...Operation And Maintenance Data01 78 23 1.5 · PDF p. 175-180
Spec wording
“SD-10 Operation and Maintenance Data submittals documented with the required approval. 1.5.4.5 Parts Identification Provide identification and coverage for the parts of each component, assembly, subassembly, and accessory of the end items subject to replacement. Include special hardware requirements, such as requirement to use high-strength bolts and nuts. Identify parts by make, model, serial number, and source of ...”
01 78 23 1.5175-180–
O&MO&MSD-06) submittals documented with the required approval. 1.5.4.12 Cont ...Operation And Maintenance Data01 78 23 1.5 · PDF p. 175-180
Spec wording
“SD-06) submittals documented with the required approval. 1.5.4.12 Contractor Information Provide a list that includes the name, address, and telephone number of the General Contractor and each Subcontractor who installed the product or equipment, or system. For each item, also provide the name address and telephone number of the manufacturer's representative and service organization that can provide replacements ...”
01 78 23 1.5175-180–
O&MO&MProvide the O&M data packages specified in individual technical sections. ...Operation And Maintenance Data01 78 23 1.6 · PDF p. 180-183
Spec wording
“Provide the O&M data packages specified in individual technical sections. The information required in each type of data package follows: 1.6.1 Data Package 1 a. Safety precautions and hazards b. Cleaning recommendations c. Maintenance and repair procedures d. Warranty information e. Extended warranty information f. Contractor information g. Spare parts and supply list 1.6.2 Data Package 2 a. Safety precautions and ...”
01 78 23 1.6180-183–
TrainingTrainingPrior to acceptance of the facility by the Contracting Officer ...Operation And Maintenance Data01 78 23 3.1 · PDF p. 183-185
Spec wording
“Prior to acceptance of the facility by the Contracting Officer for Beneficial Occupancy, provide comprehensive training for the systems and equipment specified in the technical specifications. The training must be targeted for the Facilities Management Specialist, building maintenance personnel, and applicable building occupants. Instructors must be well-versed in the particular systems that they are presenting. ...”
01 78 23 3.1183-185two copies; DVD; one copy
Test / cert.Test / cert.1.3.1 Be prepared to discuss the following during this meeting:2001 78 24.00 1.3 · PDF p. 186-187
Spec wording
“1.3.1 Be prepared to discuss the following during this meeting: a. eOMSI Manual Development Meetings b. Processes and methods of gathering eOMSI Manual information during construction. c. The eOMSI Submittals schedule. Include the eOMSI submittal schedule on the Baseline Construction Schedule. 1.3.2 eOMSI Manual Coordination Meeting Facilitate a meeting after the Post-Award Kickoff Meeting prior to the submission ...”
01 78 24.00 1.3186-187–
Closeout stepCloseout step1.4.1 eOMSI, Progress Submittal Submit the Progress submittal when construction ...2001 78 24.00 1.4 · PDF p. 187
Spec wording
“1.4.1 eOMSI, Progress Submittal Submit the Progress submittal when construction is approximately 50 percent complete, to the Contracting Officer for approval. Provide eOMSI Manual Files (Bookmarked PDF). Include the elements and portions of system construction completed up to this point. The purpose of this submittal is to verify progress is in accordance with contract requirements as discussed during the eOMSI ...”
01 78 24.00 1.4187Bookmarked; PDF
Closeout stepCloseout stepProvide eOMSI utilizing the English Inch-Pound units of measure2001 78 24.00 1.5 · PDF p. 187
Spec wording
“Provide eOMSI utilizing the English Inch-Pound units of measure”
01 78 24.00 1.5187–
Closeout stepCloseout stepSD-11 Closeout Submittals eOMSI, Progress Submittal; G eOMSI, Prefinal ...2001 78 24.00 1.6 · PDF p. 188
Spec wording
“SD-11 Closeout Submittals eOMSI, Progress Submittal; G eOMSI, Prefinal Submittal; G eOMSI, Final Submittal; G”
01 78 24.00 1.6188–
O&MO&M2.1 eOMSI FILES FORMAT Format eOMSI manuals and files in ...2001 78 24.00 · PDF p. 188-191
Spec wording
“2.1 eOMSI FILES FORMAT Format eOMSI manuals and files in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA. Include a complete electronically linked operation and maintenance directory. Provide four electronic copies of the eOMSI Manuals to the Contracting Officer for approval. Scan eOMSI Manuals and Files for viruses, malware, and spyware using a commercially available scanning program that is ...”
01 78 24.00188-191electronically; four electronic copies; one hard copy; PDF; CD; DVD
WarrantyWarrantyField verify eOMSI Maximo and Warranty Binder information with Contractor ...2001 78 24.00 3.1 · PDF p. 191
Spec wording
“Field verify eOMSI Maximo and Warranty Binder information with Contractor and Government personnel. Include the following personnel in this meeting: Contractor's eOMSI Manual and Quality Control Manager, and the Government's Contracting Officer's Representative and NAVFAC PW FMD. Request, and provide, an eOMSI Field Verification Meeting no sooner than 14 calendar days after submission of the Progress eOMSI ...”
01 78 24.00 3.1191Binder

Division 02 Existing conditions 2 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.SD-07 Certificates Notification; GDemolition02 41 00 1.5 · PDF p. 195
Spec wording
“SD-07 Certificates Notification; G”
02 41 00 1.5195–
Closeout stepCloseout stepSD-11 Closeout Submittals ReceiptsDemolition02 41 00 1.5 · PDF p. 195
Spec wording
“SD-11 Closeout Submittals Receipts”
02 41 00 1.5195–

Division 23 HVAC 15 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.SD-06 Test Reports Pre-Final Tab Report For Proportional Balancing; G ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.4 · PDF p. 217-219
Spec wording
“SD-06 Test Reports Pre-Final Tab Report For Proportional Balancing; G Pre-Final Tab Report For Season 1; G Final Tab Report For Proportional Balancing; G Final Tab Report For Season 1; G”
23 05 93 1.4217-219–
Test / cert.Test / cert.SD-07 Certificates Independent Tab Agency And Personnel Qualifications ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.4 · PDF p. 217-219
Spec wording
“SD-07 Certificates Independent Tab Agency And Personnel Qualifications; G 1.4.1 Design Review Report Submit typed report describing omissions and deficiencies in the HVAC system's design that would preclude the TAB team from accomplishing the duct leakage testing work and the TAB work requirements of this section. Provide a complete explanation including supporting documentation detailing the design deficiency. ...”
23 05 93 1.4217-219–
Test / cert.Test / cert.1.6.1 Pre-Construction Submittals Within 30 calendar days after date of ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.6 · PDF p. 225-226
Spec wording
“1.6.1 Pre-Construction Submittals Within 30 calendar days after date of contract award, submit the following: Independent TAB Agency and Personnel Qualifications and Certificates TAB Design Review Report Pre-Field TAB Engineering Report TAB Work Execution Schedule 1.6.2 Pre-TAB Meeting A minimum 14 calendar days prior to the start of TAB field work. 1.6.3 Pre-TAB Preliminary Notification A minimum of 7 calendar ...”
23 05 93 1.6225-226–
WarrantyWarrantyFurnish workmanship and performance warranty for the TAB system work ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.7 · PDF p. 226
Spec wording
“Furnish workmanship and performance warranty for the TAB system work performed for a period not less than 1 years from the date of Government acceptance of the work; issued directly to the Government. Include provisions that if within the warranty period the system shows evidence of major performance deterioration, or is significantly out of tolerance, resulting from defective TAB workmanship, the corrective repair ...”
23 05 93 1.7226–
Test / cert.Test / cert.SD-06 Test Reports Existing Conditions Report; G Control Contractor's ...Instrumentation And Control For Hvac23 09 00 1.6 · PDF p. 263-264
Spec wording
“SD-06 Test Reports Existing Conditions Report; G Control Contractor's Performance Verification Testing Plan; G Equipment Supplier's Performance Verification Testing Plan; G Performance Verification Testing Report; G Trends; G Bus Waveform Report; G”
23 09 00 1.6263-264–
TrainingTrainingSD-07 Certificates Contractor's Qualifications; G Contractor's Trainin ...Instrumentation And Control For Hvac23 09 00 1.6 · PDF p. 263-264
Spec wording
“SD-07 Certificates Contractor's Qualifications; G Contractor's Training Certifications; G”
23 09 00 1.6263-264–
O&MO&MSD-10 Operation and Maintenance Data Comply with requirements for data ...Instrumentation And Control For Hvac23 09 00 1.6 · PDF p. 263-264
Spec wording
“SD-10 Operation and Maintenance Data Comply with requirements for data packages in Section 01 78 23 OPERATION AND MAINTENANCE DATA and in Section 01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT INFORMATION (eOMSI), except as supplemented and modified in this specification. Controls System Operators Manuals; G, Data Package 4”
23 09 00 1.6263-264–
WarrantyWarrantySD-11 Closeout Submittals Training Documentation; G Warranty Informati ...Instrumentation And Control For Hvac23 09 00 1.6 · PDF p. 263-264
Spec wording
“SD-11 Closeout Submittals Training Documentation; G Warranty Information; G”
23 09 00 1.6263-264–
TrainingTrainingProvide a qualified instructor (or instructors) with two years minimum ...Instrumentation And Control For Hvac23 09 00 3.11 · PDF p. 284-286
Spec wording
“Provide a qualified instructor (or instructors) with two years minimum field experience with the installation and programming of similar BACnet DDC systems. Orient training to the specific systems installed. Coordinate training times and locations with the Contracting Officer and BAS Owner after receiving approval of the training course documentation. Training shall take place at the job site or a nearby ...”
23 09 00 3.11284-286hard-copy
Test / cert.Test / cert.SD-06 Test Reports Vfd Start-Up Test Documentation; GInstrumentation And Control Devices For Hvac23 09 13 1.4 · PDF p. 288-289
Spec wording
“SD-06 Test Reports Vfd Start-Up Test Documentation; G”
23 09 13 1.4288-289–
O&MO&MSD-10 Operation and Maintenance Data Comply with requirements for data ...Instrumentation And Control Devices For Hvac23 09 13 1.4 · PDF p. 288-289
Spec wording
“SD-10 Operation and Maintenance Data Comply with requirements for data packages in Section 01 78 23 OPERATION AND MAINTENANCE DATA and in Section 01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT INFORMATION (eOMSI), except as supplemented and modified in this specification. Vfd Service Manuals; G, Data Package 4”
23 09 13 1.4288-289–
Test / cert.Test / cert.SD-06 Test Reports Dedicated Outside Air System; GHeating, Ventilating, And Cooling System23 73 33 1.3 · PDF p. 305-306
Spec wording
“SD-06 Test Reports Dedicated Outside Air System; G”
23 73 33 1.3305-306–
Test / cert.Test / cert.SD-07 Certificates Certification of welders' qualifications Equipment ...Heating, Ventilating, And Cooling System23 73 33 1.3 · PDF p. 305-306
Spec wording
“SD-07 Certificates Certification of welders' qualifications Equipment field test plans”
23 73 33 1.3305-306–
O&MO&MSD-10 Operation and Maintenance Data Submit in accordance with Section ...Heating, Ventilating, And Cooling System23 73 33 1.3 · PDF p. 305-306
Spec wording
“SD-10 Operation and Maintenance Data Submit in accordance with Section 01 78 23, "Operation and Maintenance Data." Dedicated Outside Air System; G, Data Package 3”
23 73 33 1.3305-306–
Test / cert.Test / cert.SD-11 Closeout Submittals Air filter inventory 1.3.1 Temperature Contr ...Heating, Ventilating, And Cooling System23 73 33 1.3 · PDF p. 305-306
Spec wording
“SD-11 Closeout Submittals Air filter inventory 1.3.1 Temperature Control Systems Drawings shall include point-to-point electrical wiring diagrams. 1.3.2 Equipment layout drawings Submit drawings showing equipment layout including foot print, piping, conduit, control cabinets, door swings, and power disconnects. 1.3.3 Installation Manual Provide for each item of equipment. 1.3.4 Certification of Welders' ...”
23 73 33 1.3305-306–

Division 25 Building automation and controls 4 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.SD-06 Test Reports Wireless Communication Test Report; GCybersecurity For Facility-Related Control Systems - Isolated Systems25 05 11.00 1.6 · PDF p. 332-333
Spec wording
“SD-06 Test Reports Wireless Communication Test Report; G”
25 05 11.00 1.6332-333–
Test / cert.Test / cert.SD-07 Certificates Software Licenses; GSD-11 Closeout Submittals Passw ...Cybersecurity For Facility-Related Control Systems - Isolated Systems25 05 11.00 1.6 · PDF p. 332-333
Spec wording
“SD-07 Certificates Software Licenses; GSD-11 Closeout Submittals Password Summary Report; G Software Recovery And Reconstitution Images; G Device Audit Record Upload Software; G”
25 05 11.00 1.6332-333–
Test / cert.Test / cert.1.7.1 Qualifications 1.7.1.1 Control System Cybersecurity Subject Matter Expert The ...Cybersecurity For Facility-Related Control Systems - Isolated Systems25 05 11.00 1.7 · PDF p. 333
Spec wording
“1.7.1 Qualifications 1.7.1.1 Control System Cybersecurity Subject Matter Expert The individual will oversee all work within this specification. This position requires that the individual currently meets Information Assurance Manager Level II Certification in accordance with DoDI 8570 Information Workforce Improvement Program. Individuals for this position should have experience securing Marine Corps systems and ...”
25 05 11.00 1.7333–
WarrantyWarrantyAll work performed on the control system after acceptance must ...Cybersecurity For Facility-Related Control Systems - Isolated Systems25 05 11.00 1.11 · PDF p. 339
Spec wording
“All work performed on the control system after acceptance must be performed using Government Furnished Equipment . Access to systems and changes must be coordinated through Camp Lejeune FRCS Office and follow established change management procedures.”
25 05 11.00 1.11339–

Division 26 Electrical 6 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MSubmittals required in the sections which refer to this section ...Basic Electrical Materials And Methods26 00 00 1.5 · PDF p. 349-351
Spec wording
“Submittals required in the sections which refer to this section shall conform to the requirements of Section 01 33 00, "Submittal Procedures" and to the following additional requirements. Submittals shall include the manufacturer's name, trade name, place of manufacture, catalog model or number, nameplate data, size, layout dimensions, capacity, project specification and technical paragraph reference. Submittals ...”
26 00 00 1.5349-351–
Test / cert.Test / cert.SD-06 Test Reports Submit report of results of acceptance checks and t ...Grounding And Bonding26 06 00 1.2 · PDF p. 360
Spec wording
“SD-06 Test Reports Submit report of results of acceptance checks and tests specified by paragraph entitled "Field Quality Control" Ground resistance tests 1.2.1 Layout and location drawings Provide shop drawings showing location and size of ground rod and ground grid. 1.2.2 Ground resistance tests Upon completion and before final acceptance of the work, submit the measured ground resistance of each ground rod and ...”
26 06 00 1.2360–
Test / cert.Test / cert.SD-06 Test Reports 600-volt wiring test Grounding system test Ground-f ...Interior Distribution System26 20 00 1.3 · PDF p. 368-369
Spec wording
“SD-06 Test Reports 600-volt wiring test Grounding system test Ground-fault receptacle test”
26 20 00 1.3368-369–
Test / cert.Test / cert.SD-07 Certificates FusesInterior Distribution System26 20 00 1.3 · PDF p. 368-369
Spec wording
“SD-07 Certificates Fuses”
26 20 00 1.3368-369–
Test / cert.Test / cert.SD-09 Manufacturer's Field Reports Transformer factory testsInterior Distribution System26 20 00 1.3 · PDF p. 368-369
Spec wording
“SD-09 Manufacturer's Field Reports Transformer factory tests”
26 20 00 1.3368-369–
O&MO&MSD-10 Operation and Maintenance Data Electrical Systems, Data Package ...Interior Distribution System26 20 00 1.3 · PDF p. 368-369
Spec wording
“SD-10 Operation and Maintenance Data Electrical Systems, Data Package 5 Submit operation and maintenance data in accordance with Section 01 78 23, "Operation and Maintenance Data" and as specified herein.”
26 20 00 1.3368-369–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.