Closeout checklist: Outdoor Pavilion, Missouri Veterans Home (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 185 items across Division 01, 12 trade divisions and the contract conditions, including 43 tests and certificates, 40 warranties and 37 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project U2415-01
- Location
- Cape Girardeau, MO
- Bid date
- 2025-06-03
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 578 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 185 items, by trade
Division 01 General requirements 73 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 70Spec wording“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...” | 01 32 00 3.1.A | 70 | – |
| Warranty | WarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 78Spec wording“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.” | 01 33 00 1.8.A | 78 | – |
| Warranty | WarrantyContractor shall submit the following information for materials and equipment ...Submittals01 33 00 3.1.A · PDF p. 78-83Spec wording“A. Contractor shall submit the following information for materials and equipment to be provided under this contract. SPEC TITLE CATEGORY SECTION 013200 Schedules-Bar Chart Construction Schedule 013200 Schedules-Bar Chart Schedule of Values 013200 Schedules-Bar Chart List of Subcontractors 013200 Schedules-Bar Chart Major Material Suppliers 032000 Concrete Forming and Accessories Product Data 032000 Concrete ...” | 01 33 00 3.1.A | 78-83 | – |
| Test / cert. | Test / cert.Test ReportsQuality Requirements01 40 00 1.6.D · PDF p. 92Spec wording“D. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor. 1) Include: a. Date issued. b. Project title and number. c. Name of inspector. d. Date and time of sampling or inspection. e. Identification of product and specifications section. f. Location in the Project. g. Type of test/inspection. h. Date of test/inspection. i. Results of test/inspection. j. ...” | 01 40 00 1.6.D | 92 | two copies |
| Test / cert. | Test / cert.Testing Agency DutiesQuality Requirements01 40 00 2.4.B · PDF p. 95Spec wording“B. Testing Agency Duties: 1) Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services. 2) Perform specified sampling and testing of products in accordance with specified standards. 3) Ascertain compliance of materials and mixes with requirements of Contract Documents. 4) Promptly notify Architect and Contractor of observed irregularities or non-compliance of Work or ...” | 01 40 00 2.4.B | 95 | – |
| Spare parts | Spare partsFurnish extra materials, spare parts, tools, and software of types ...Product Requirements01 60 00 2.4.A · PDF p. 108Spec wording“A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.” | 01 60 00 2.4.A | 108 | – |
| Spare parts | Spare partsDeliver to Project site; obtain receipt prior to final paymentProduct Requirements01 60 00 2.4.B · PDF p. 108Spec wording“B. Deliver to Project site; obtain receipt prior to final payment.” | 01 60 00 2.4.B | 108 | – |
| Closeout step | Closeout stepSurvey workExecution And Closeout Requirements01 70 00 1.4.B · PDF p. 115Spec wording“B. Survey work: Submit name, address, and telephone number of Surveyor before starting survey work. 1) On request, submit documentation verifying accuracy of survey work. 2) Submit a copy of site drawing signed by the Land Surveyor, that the elevations and locations of the work are in compliance with Contract Documents. 3) Submit surveys and survey logs for the project record.” | 01 70 00 1.4.B | 115 | – |
| Test / cert. | Test / cert.Coordinate schedule for start-up of various equipment and systemsExecution And Closeout Requirements01 70 00 3.10.A · PDF p. 123Spec wording“A. Coordinate schedule for start-up of various equipment and systems.” | 01 70 00 3.10.A | 123 | – |
| Test / cert. | Test / cert.Notify Architect and Owner seven days prior to start-up of each itemExecution And Closeout Requirements01 70 00 3.10.B · PDF p. 123Spec wording“B. Notify Architect and Owner seven days prior to start-up of each item.” | 01 70 00 3.10.B | 123 | – |
| Test / cert. | Test / cert.Verify that each piece of equipment or system has been ...Execution And Closeout Requirements01 70 00 3.10.C · PDF p. 123Spec wording“C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions that may cause damage.” | 01 70 00 3.10.C | 123 | – |
| Test / cert. | Test / cert.Verify tests, meter readings, and specified electrical characteristics agree with ...Execution And Closeout Requirements01 70 00 3.10.D · PDF p. 124Spec wording“D. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.” | 01 70 00 3.10.D | 124 | – |
| Test / cert. | Test / cert.Verify that wiring and support components for equipment are complete ...Execution And Closeout Requirements01 70 00 3.10.E · PDF p. 124Spec wording“E. Verify that wiring and support components for equipment are complete and tested.” | 01 70 00 3.10.E | 124 | – |
| Test / cert. | Test / cert.Execute start-up under supervision of applicable Contractor personnel in accordance ...Execution And Closeout Requirements01 70 00 3.10.F · PDF p. 124Spec wording“F. Execute start-up under supervision of applicable Contractor personnel in accordance with manufacturers' instructions.” | 01 70 00 3.10.F | 124 | – |
| Test / cert. | Test / cert.When specified in individual specification Sections, require manufacturer to provide ...Execution And Closeout Requirements01 70 00 3.10.G · PDF p. 124Spec wording“G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.” | 01 70 00 3.10.G | 124 | – |
| Test / cert. | Test / cert.Submit a written report that equipment or system has been ...Execution And Closeout Requirements01 70 00 3.10.H · PDF p. 124Spec wording“H. Submit a written report that equipment or system has been properly installed and is functioning correctly.” | 01 70 00 3.10.H | 124 | – |
| Training | TrainingRefer to Section 01 7900 - Demonstration and Training for ...Execution And Closeout Requirements01 70 00 3.11.A · PDF p. 124Spec wording“A. Refer to Section 01 7900 - Demonstration and Training for additional State of Missouri Requirements.” | 01 70 00 3.11.A | 124 | – |
| Training | TrainingDemonstrate operation and maintenance of products to Owner's personnel two ...Execution And Closeout Requirements01 70 00 3.11.B · PDF p. 124Spec wording“B. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion.” | 01 70 00 3.11.B | 124 | – |
| Training | TrainingDemonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown ...Execution And Closeout Requirements01 70 00 3.11.C · PDF p. 124Spec wording“C. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.” | 01 70 00 3.11.C | 124 | – |
| Training | TrainingFor equipment or systems requiring seasonal operation, perform demonstration for ...Execution And Closeout Requirements01 70 00 3.11.D · PDF p. 124Spec wording“D. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.” | 01 70 00 3.11.D | 124 | – |
| Training | TrainingProvide a qualified person who is knowledgeable about the Project ...Execution And Closeout Requirements01 70 00 3.11.E · PDF p. 124Spec wording“E. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of Owner's personnel.” | 01 70 00 3.11.E | 124 | – |
| Training | TrainingUtilize operation and maintenance manuals as basis for instruction. Review ...Execution And Closeout Requirements01 70 00 3.11.F · PDF p. 124Spec wording“F. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.” | 01 70 00 3.11.F | 124 | – |
| Training | TrainingPrepare and insert additional data in operations and maintenance manuals ...Execution And Closeout Requirements01 70 00 3.11.G · PDF p. 124Spec wording“G. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.” | 01 70 00 3.11.G | 124 | – |
| Closeout step | Closeout stepMake submittals that are required by governing or other authoritiesExecution And Closeout Requirements01 70 00 3.14.A · PDF p. 125Spec wording“A. Make submittals that are required by governing or other authorities.” | 01 70 00 3.14.A | 125 | – |
| Training | TrainingRefer to Section 01 7900 - Demonstration and for additional ...Execution And Closeout Requirements01 70 00 3.14.B · PDF p. 125Spec wording“B. Refer to Section 01 7900 - Demonstration and for additional State of Missouri Requirements.” | 01 70 00 3.14.B | 125 | – |
| Test / cert. | Test / cert.Accompany Project Coordinator on preliminary inspection to determine items to ...Execution And Closeout Requirements01 70 00 3.14.C · PDF p. 125Spec wording“C. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.” | 01 70 00 3.14.C | 125 | – |
| Test / cert. | Test / cert.Notify Architect when work is considered ready for Architect's Substantial ...Execution And Closeout Requirements01 70 00 3.14.D · PDF p. 125Spec wording“D. Notify Architect when work is considered ready for Architect's Substantial Completion inspection.” | 01 70 00 3.14.D | 125 | – |
| Test / cert. | Test / cert.Submit written certification containing Contractor's Correction Punch List, that Contract ...Execution And Closeout Requirements01 70 00 3.14.E · PDF p. 125Spec wording“E. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's Substantial Completion inspection.” | 01 70 00 3.14.E | 125 | – |
| Closeout step | Closeout stepOwner will occupy portions of the building as specified in ...Execution And Closeout Requirements01 70 00 3.14.F · PDF p. 125Spec wording“F. Owner will occupy portions of the building as specified in Section 01 1000.” | 01 70 00 3.14.F | 125 | – |
| Test / cert. | Test / cert.Conduct Substantial Completion inspection and create Final Correction Punch List ...Execution And Closeout Requirements01 70 00 3.14.G · PDF p. 125Spec wording“G. Conduct Substantial Completion inspection and create Final Correction Punch List containing Architect's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Architect.” | 01 70 00 3.14.G | 125 | – |
| Closeout step | Closeout stepCorrect items of work listed in Final Correction Punch List ...Execution And Closeout Requirements01 70 00 3.14.H · PDF p. 125Spec wording“H. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas.” | 01 70 00 3.14.H | 125 | – |
| Test / cert. | Test / cert.Notify Architect when work is considered finally complete and ready ...Execution And Closeout Requirements01 70 00 3.14.I · PDF p. 125Spec wording“I. Notify Architect when work is considered finally complete and ready for Architect's Substantial Completion final inspection.” | 01 70 00 3.14.I | 125 | – |
| Test / cert. | Test / cert.Complete items of work determined by Architect listed in executed ...Execution And Closeout Requirements01 70 00 3.14.J · PDF p. 125Spec wording“J. Complete items of work determined by Architect listed in executed Certificate of Substantial Completion.” | 01 70 00 3.14.J | 125 | – |
| Record docs | Record docsProject Record DocumentsCloseout Submittals01 78 00 1.3.A · PDF p. 131Spec wording“A. Project Record Documents: Submit documents to Architect with claim for final Application for Payment.” | 01 78 00 1.3.A | 131 | – |
| O&M | O&MOperation and Maintenance DataCloseout Submittals01 78 00 1.3.B · PDF p. 131Spec wording“B. Operation and Maintenance Data: 1) Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect will review draft and return one copy with comments. 2) For equipment, or component parts of equipment put into service during construction and operated by Owner, submit completed documents within ten days after acceptance. 3) Submit one copy of completed ...” | 01 78 00 1.3.B | 131 | two copies; one copy; two sets |
| Warranty | WarrantyWarranties and BondsCloseout Submittals01 78 00 1.3.C · PDF p. 131Spec wording“C. Warranties and Bonds: 1) For equipment or component parts of equipment put into service during construction with Owner's permission, submit documents within 10 days after acceptance. 2) Make other submittals within 10 days after Date of Substantial Completion, prior to final Application for Payment. 3) For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within 10 days ...” | 01 78 00 1.3.C | 131 | – |
| O&M | O&MProduct DataCloseout Submittals01 78 00 2.1.B · PDF p. 132Spec wording“B. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information.” | 01 78 00 2.1.B | 132 | – |
| O&M | O&MDrawingsCloseout Submittals01 78 00 2.1.C · PDF p. 132Spec wording“C. Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams. Do not use Project Record Documents as maintenance drawings.” | 01 78 00 2.1.C | 132 | – |
| O&M | O&MTyped TextCloseout Submittals01 78 00 2.1.D · PDF p. 132Spec wording“D. Typed Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions.” | 01 78 00 2.1.D | 132 | – |
| O&M | O&MMoisture protection and weather-exposed productsCloseout Submittals01 78 00 2.2.C · PDF p. 132Spec wording“C. Moisture protection and weather-exposed products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.” | 01 78 00 2.2.C | 132 | – |
| O&M | O&MFor Each Item of Equipment and Each SystemCloseout Submittals01 78 00 2.3.A · PDF p. 132Spec wording“A. For Each Item of Equipment and Each System: 1) Description of unit or system, and component parts. 2) Identify function, normal operating characteristics, and limiting conditions. 3) Include performance curves, with engineering data and tests. 4) Complete nomenclature and model number of replaceable parts.” | 01 78 00 2.3.A | 132 | – |
| O&M | O&MPanelboard Circuit DirectoriesCloseout Submittals01 78 00 2.3.C · PDF p. 133Spec wording“C. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and communications; typed.” | 01 78 00 2.3.C | 133 | – |
| O&M | O&MInclude color coded wiring diagrams as installedCloseout Submittals01 78 00 2.3.D · PDF p. 133Spec wording“D. Include color coded wiring diagrams as installed.” | 01 78 00 2.3.D | 133 | – |
| O&M | O&MOperating ProceduresCloseout Submittals01 78 00 2.3.E · PDF p. 133Spec wording“E. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and any special operating instructions.” | 01 78 00 2.3.E | 133 | – |
| O&M | O&MMaintenance RequirementsCloseout Submittals01 78 00 2.3.F · PDF p. 133Spec wording“F. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.” | 01 78 00 2.3.F | 133 | – |
| O&M | O&MProvide servicing and lubrication schedule, and list of lubricants required ...Closeout Submittals01 78 00 2.3.G · PDF p. 133Spec wording“G. Provide servicing and lubrication schedule, and list of lubricants required.” | 01 78 00 2.3.G | 133 | – |
| O&M | O&MInclude manufacturer's printed operation and maintenance instructionsCloseout Submittals01 78 00 2.3.H · PDF p. 133Spec wording“H. Include manufacturer's printed operation and maintenance instructions.” | 01 78 00 2.3.H | 133 | – |
| O&M | O&MInclude sequence of operation by controls manufacturerCloseout Submittals01 78 00 2.3.I · PDF p. 133Spec wording“I. Include sequence of operation by controls manufacturer.” | 01 78 00 2.3.I | 133 | – |
| O&M | O&MProvide original manufacturer's parts list, illustrations, assembly drawings, and diagrams ...Closeout Submittals01 78 00 2.3.J · PDF p. 133Spec wording“J. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.” | 01 78 00 2.3.J | 133 | – |
| O&M | O&MAssemble operation and maintenance data into durable manuals for Owner's ...Closeout Submittals01 78 00 2.4.A · PDF p. 133Spec wording“A. Assemble operation and maintenance data into durable manuals for Owner's personnel use, with data arranged in the same sequence as, and identified by, the specification sections.” | 01 78 00 2.4.A | 133 | – |
| O&M | O&MWhere systems involve more than one specification section, provide separate ...Closeout Submittals01 78 00 2.4.B · PDF p. 133Spec wording“B. Where systems involve more than one specification section, provide separate tabbed divider for each system.” | 01 78 00 2.4.B | 133 | – |
| O&M | O&MTables of ContentsCloseout Submittals01 78 00 2.4.F · PDF p. 133Spec wording“F. Tables of Contents: List every item separated by a divider, using the same identification as on the divider tab; where multiple volumes are required, include all volumes Tables of Contents in each volume, with the current volume clearly identified.” | 01 78 00 2.4.F | 133 | – |
| O&M | O&MDividersCloseout Submittals01 78 00 2.4.G · PDF p. 133Spec wording“G. Dividers: Provide tabbed dividers for each separate product and system; identify the contents on the divider tab; immediately following the divider tab include a description of product and major component parts of equipment.” | 01 78 00 2.4.G | 133 | – |
| O&M | O&MDrawingsCloseout Submittals01 78 00 2.4.I · PDF p. 134Spec wording“I. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.” | 01 78 00 2.4.I | 134 | binder |
| Warranty | WarrantyObtain warranties and bonds, executed in duplicate by responsible Subcontractors, ...Closeout Submittals01 78 00 2.5.A · PDF p. 134Spec wording“A. Obtain warranties and bonds, executed in duplicate by responsible Subcontractors, suppliers, and manufacturers, within 10 days after completion of the applicable item of work. Except for items put into use with Owner's permission, leave date of beginning of time of warranty until Date of Substantial completion is determined.” | 01 78 00 2.5.A | 134 | – |
| Warranty | WarrantySeparate each warranty or bond with index tab sheets keyed ...Closeout Submittals01 78 00 2.5.H · PDF p. 134Spec wording“H. Separate each warranty or bond with index tab sheets keyed to the Table of Contents listing. Provide full information, using separate typed sheets as necessary. List Subcontractor, supplier, and manufacturer, with name, address, and telephone number of responsible principal.” | 01 78 00 2.5.H | 134 | – |
| Training | TrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 135Spec wording“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.” | 01 79 00 1.3.A | 135 | – |
| Training | TrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 135Spec wording“B. Attendance Record: For each training module, submit list of participants and length of instruction time.” | 01 79 00 1.3.B | 135 | – |
| Training | TrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 135Spec wording“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.” | 01 79 00 1.3.C | 135 | – |
| Training | TrainingDemonstration and Training Video RecordingsDemonstration And Training01 79 00 1.4.A · PDF p. 135-136Spec wording“A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. Transcript: Prepared in PDF electronic format. ...” | 01 79 00 1.4.A | 135-136 | two copies; PDF; electronic format; electronic file |
| Training | TrainingFacilitator QualificationsDemonstration And Training01 79 00 1.5.A · PDF p. 136Spec wording“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.” | 01 79 00 1.5.A | 136 | – |
| Training | TrainingPre-instruction ConferenceDemonstration And Training01 79 00 1.5.C · PDF p. 136Spec wording“C. Pre-instruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Coordination". Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, ...” | 01 79 00 1.5.C | 136 | – |
| O&M | O&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.6.C · PDF p. 136Spec wording“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.” | 01 79 00 1.6.C | 136 | – |
| Warranty | WarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 136-138Spec wording“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...” | 01 79 00 2.1.B | 136-138 | – |
| Training | TrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 138Spec wording“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".” | 01 79 00 3.1.A | 138 | – |
| Training | TrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 138Spec wording“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Architect will furnish an instructor to describe basis of system design, operational requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names ...” | 01 79 00 3.2.A | 138 | – |
| Training | TrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 138Spec wording“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.” | 01 79 00 3.2.B | 138 | – |
| Training | TrainingGeneralDemonstration And Training01 79 00 3.3.A · PDF p. 139Spec wording“A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. 1. At beginning of each training module, record each chart containing learning objective and lesson outline.” | 01 79 00 3.3.A | 139 | – |
| Training | TrainingVideoDemonstration And Training01 79 00 3.3.B · PDF p. 139Spec wording“B. Video: Provide minimum 640 x 480 video resolution converted to format file type acceptable to Owner, on electronic media. 1. Electronic Media: Read-only format compact disc acceptable to Owner, with commercial-grade graphic label. 2. File Hierarchy: Organize folder structure and file locations according to project manual table of contents. Provide complete screen-based menu. 3. File Names: Utilize file names ...” | 01 79 00 3.3.B | 139 | electronic media; DVD |
| Training | TrainingLight LevelsDemonstration And Training01 79 00 3.3.D · PDF p. 139-140Spec wording“D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. 1. Furnish additional portable lighting as required.” | 01 79 00 3.3.D | 139-140 | – |
| Training | TrainingNarrationDemonstration And Training01 79 00 3.3.E · PDF p. 140Spec wording“E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.” | 01 79 00 3.3.E | 140 | – |
| Training | TrainingTranscriptDemonstration And Training01 79 00 3.3.F · PDF p. 140Spec wording“F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.” | 01 79 00 3.3.F | 140 | – |
| Training | TrainingPreproduced Video RecordingsDemonstration And Training01 79 00 3.3.G · PDF p. 140Spec wording“G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.” | 01 79 00 3.3.G | 140 | – |
Division 03 Concrete 5 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test ReportsCast-In-Place Concrete03 30 00 1.4.F · PDF p. 149Spec wording“F. Test Reports: Submit report for each test or series of tests specified.” | 03 30 00 1.4.F | 149 | – |
| Warranty | WarrantyWarrantyCast-In-Place Concrete03 30 00 1.4.G · PDF p. 149Spec wording“G. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.” | 03 30 00 1.4.G | 149 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Cast-In-Place Concrete03 30 00 1.6.A · PDF p. 149Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 03 30 00 1.6.A | 149 | – |
| Warranty | WarrantySlabs with Moisture Vapor Reducing Admixture (MVRA)Cast-In-Place Concrete03 30 00 1.6.B · PDF p. 149Spec wording“B. Slabs with Moisture Vapor Reducing Admixture (MVRA): Provide warranty to cover the cost of flooring failures due to moisture migration from slabs for life of the concrete. 1) Include cost of repair or removal of failed flooring, placement of topical moisture remediation system, and replacement of flooring with comparable flooring system. 2) Provide warranty by manufacturer of MVRA matching terms of flooring ...” | 03 30 00 1.6.B | 149 | – |
| Warranty | WarrantyMoisture Emission Reducing Curing and Sealing CompoundCast-In-Place Concrete03 30 00 1.6.C · PDF p. 149Spec wording“C. Moisture Emission Reducing Curing and Sealing Compound: Provide warranty to cost of flooring delamination failures for 10 years. 1) Include cost of repair or removal of failed flooring, remediation with a moisture vapor impermeable surface coating, and replacement of flooring with comparable flooring system.” | 03 30 00 1.6.C | 149 | – |
Division 07 Roofing, insulation and waterproofing 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyWarranty DocumentationAsphalt Shingles07 31 13 1.4.G · PDF p. 203Spec wording“G. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.” | 07 31 13 1.4.G | 203 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Asphalt Shingles07 31 13 1.7.A · PDF p. 203Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 07 31 13 1.7.A | 203 | – |
| Test / cert. | Test / cert.Test ReportFiber-Cement Siding07 46 46 1.4.C · PDF p. 209Spec wording“C. Test Report: Applicable model code authority evaluation report (e.g. ICC-ES).” | 07 46 46 1.4.C | 209 | – |
| Warranty | WarrantyWarrantyFiber-Cement Siding07 46 46 1.4.G · PDF p. 209Spec wording“G. Warranty: Submit copy of manufacturer's warranty, made out in Owner's name, showing that it has been registered with manufacturer.” | 07 46 46 1.4.G | 209 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Fiber-Cement Siding07 46 46 1.7.A · PDF p. 210Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 07 46 46 1.7.A | 210 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Joint Sealants07 92 00 1.6.A · PDF p. 216Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 07 92 00 1.6.A | 216 | – |
| Warranty | WarrantyCorrect defective work within a five year period after Date ...Joint Sealants07 92 00 1.6.B · PDF p. 216Spec wording“B. Correct defective work within a five year period after Date of Substantial Completion.” | 07 92 00 1.6.B | 216 | – |
| Warranty | WarrantyWarrantyJoint Sealants07 92 00 1.6.C · PDF p. 216Spec wording“C. Warranty: Include coverage for installed sealants and accessories that fail to achieve watertight seal , exhibit loss of adhesion or cohesion, or do not cure.” | 07 92 00 1.6.C | 216 | – |
Division 08 Doors, windows and hardware 10 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyDoor Hardware ScheduleDoor Hardware08 71 00 1.3.B · PDF p. 237Spec wording“B. Door Hardware Schedule: Prepared by or under the supervision of supplier, detailing, fabrication and assembly of door hardware, as well as procedures and diagrams. Coordinate the final Door Hardware Schedule with doors, frames, and related work to ensure proper size, thickness, hand, function, and finish of door hardware. 1. Format: Comply with scheduling sequence and vertical format in DHI's "Sequence and ...” | 08 71 00 1.3.B | 237 | – |
| Test / cert. | Test / cert.Informational Submittals:Door Hardware08 71 00 1.3.E · PDF p. 238Spec wording“E. Informational Submittals: 1. Product Test Reports: Indicating compliance with cycle testing requirements, based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified independent testing agency.” | 08 71 00 1.3.E | 238 | – |
| O&M | O&MOperating and Maintenance ManualsDoor Hardware08 71 00 1.3.F · PDF p. 238Spec wording“F. Operating and Maintenance Manuals: Provide manufacturers operating and maintenance manuals for each item comprising the complete door hardware installation in quantity as required in Division 01, Closeout Procedures.” | 08 71 00 1.3.F | 238 | – |
| Warranty | WarrantyGeneral WarrantyDoor Hardware08 71 00 1.7.A · PDF p. 240Spec wording“A. General Warranty: Reference Division 01, General Requirements. Special warranties specified in this Article shall not deprive Owner of other rights Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by Contractor under requirements of the Contract Documents.” | 08 71 00 1.7.A | 240 | – |
| Warranty | WarrantyWarranty PeriodDoor Hardware08 71 00 1.7.B · PDF p. 240Spec wording“B. Warranty Period: Written warranty, executed by manufacturer(s), agreeing to repair or replace components of standard and electrified door hardware that fails in materials or workmanship within specified warranty period after final acceptance by the Owner. Failures include, but are not limited to, the following: 1. Structural failures including excessive deflection, cracking, or breakage. 2. Faulty operation of ...” | 08 71 00 1.7.B | 240 | – |
| Warranty | WarrantyWarranty PeriodDoor Hardware08 71 00 1.7.C · PDF p. 240Spec wording“C. Warranty Period: Unless otherwise indicated, warranty shall be one year from date of Substantial Completion.” | 08 71 00 1.7.C | 240 | – |
| Training | TrainingInstruct Owner's maintenance personnel to adjust, operate, and maintain mechanical ...Door Hardware08 71 00 3.6.A · PDF p. 250Spec wording“A. Instruct Owner's maintenance personnel to adjust, operate, and maintain mechanical and electromechanical door hardware.” | 08 71 00 3.6.A | 250 | – |
| Test / cert. | Test / cert.Test ReportsLouvers08 91 00 1.4.E · PDF p. 252Spec wording“E. Test Reports: Independent agency reports showing compliance with specified performance criteria.” | 08 91 00 1.4.E | 252 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Louvers08 91 00 1.6.A · PDF p. 252Spec wording“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.” | 08 91 00 1.6.A | 252 | – |
| Warranty | WarrantyProvide five year manufacturer's warranty against distortion, metal degradation, and ...Louvers08 91 00 1.6.B · PDF p. 252-253Spec wording“B. Provide five year manufacturer's warranty against distortion, metal degradation, and connection failures of louver components. 1) Finish: Include ten year coverage against degradation of exterior finish.” | 08 91 00 1.6.B | 252-253 | – |
Division 09 Finishes 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MMaintenance DataExterior Painting09 91 13 1.5.D · PDF p. 263Spec wording“D. Maintenance Data: Submit data including finish schedule showing where each product/color/finish was used, product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.” | 09 91 13 1.5.D | 263 | – |
| Spare parts | Spare partsMaintenance MaterialsExterior Painting09 91 13 1.5.E · PDF p. 263Spec wording“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Paint and Finish Materials: 1 gallon of each color; from the same product run, store where directed. 3) Label each container with color in addition to the manufacturer's label.” | 09 91 13 1.5.E | 263 | – |
| O&M | O&MMaintenance DataInterior Painting09 91 23 1.4.E · PDF p. 271Spec wording“E. Maintenance Data: Submit data including product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.” | 09 91 23 1.4.E | 271 | – |
| Spare parts | Spare partsMaintenance MaterialsInterior Painting09 91 23 1.4.F · PDF p. 271Spec wording“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Paint and Finish Materials: Fuurnish an additional 5 percent, but not less than 1 gallon of each color; from the same product run, store where directed. 3) Label each container with color in addition to the manufacturer's label.” | 09 91 23 1.4.F | 271 | – |
Division 10 Specialties 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsMaintenance MaterialsSignage10 14 00 1.3.G · PDF p. 278Spec wording“G. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.” | 10 14 00 1.3.G | 278 | – |
| O&M | O&MMaintenance DataFire Protection Specialties10 44 00 1.4.F · PDF p. 288Spec wording“F. Maintenance Data: Include test, refill or recharge schedules and re-certification requirements.” | 10 44 00 1.4.F | 288 | – |
| Warranty | WarrantyProduct shall carry a minimum 5-year guarantee against manufacturer's defect ...Bird Control Devices10 81 13 1.6.A · PDF p. 291Spec wording“A. Product shall carry a minimum 5-year guarantee against manufacturer's defect and U.V. breakdown.” | 10 81 13 1.6.A | 291 | – |
Division 12 Furnishings 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MMaintenance DataCountertops12 36 00 1.4.G · PDF p. 301Spec wording“G. Maintenance Data: Manufacturer's instructions and recommendations for maintenance and repair of countertop surfaces.” | 12 36 00 1.4.G | 301 | – |
Division 22 Plumbing 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Heat Tracing For Plumbing Piping22 05 33 1.6.A · PDF p. 318Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 22 05 33 1.6.A | 318 | – |
| Warranty | WarrantyProvide two year manufacturer warranty for cables, connection kits, accessories, ...Heat Tracing For Plumbing Piping22 05 33 1.6.B · PDF p. 318Spec wording“B. Provide two year manufacturer warranty for cables, connection kits, accessories, and controls.” | 22 05 33 1.6.B | 318 | – |
| Test / cert. | Test / cert.Provide manufacturer representative or authorized technician services to assist with ...Vibration And Seismic Controls For Plumbing Piping And22 05 48 3.3.C · PDF p. 326Spec wording“C. Provide manufacturer representative or authorized technician services to assist with inspection and testing of vibration isolation systems and seismic controls. Submit a detailed copy of manufacturer recommended inspection, testing, and field report proceures.” | 22 05 48 3.3.C | 326 | – |
| Test / cert. | Test / cert.Submit detailed reports indicating inspection and testing results and corrective ...Vibration And Seismic Controls For Plumbing Piping And22 05 48 3.3.E · PDF p. 326Spec wording“E. Submit detailed reports indicating inspection and testing results and corrective actions taken.” | 22 05 48 3.3.E | 326 | – |
Division 23 HVAC 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MFinal ReportTesting, Adjusting, And Balancing For Hvac23 05 93 1.3.B · PDF p. 359Spec wording“B. Final Report: Indicate deficiencies in systems that would prevent proper testing, adjusting, and balancing of systems and equipment to achieve specified performance. 1) Revise TAB plan to reflect actual procedures and submit as part of final report. 2) Submit draft copies of report for review prior to final acceptance of Project. Provide final copies for Architect and for inclusion in operating and maintenance ...” | 23 05 93 1.3.B | 359 | – |
| Closeout step | Closeout stepMark on drawings the locations where traverse and other critical ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.4.C · PDF p. 361Spec wording“C. Mark on drawings the locations where traverse and other critical measurements were taken and cross reference the location in the final report.” | 23 05 93 3.4.C | 361 | – |
| O&M | O&MMaintenance DataHvac Power Ventilators23 34 23 1.3.D · PDF p. 376Spec wording“D. Maintenance Data: Include instructions for lubrication, motor and drive replacement, spare parts list, and wiring diagrams.” | 23 34 23 1.3.D | 376 | – |
| Spare parts | Spare partsMaintenance MaterialsHvac Power Ventilators23 34 23 1.3.E · PDF p. 376Spec wording“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Fan Belts: One set for each individual fan.” | 23 34 23 1.3.E | 376 | One set |
| O&M | O&MOperation and Maintenance DataConvection Heating And Cooling Units23 82 00 1.4.E · PDF p. 380Spec wording“E. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listings.” | 23 82 00 1.4.E | 380 | – |
| Warranty | WarrantyWarrantyConvection Heating And Cooling Units23 82 00 1.4.F · PDF p. 380Spec wording“F. Warranty: Submit manufacturer's warranty and ensure forms have been completed in Owner's name and registered with manufacturer.” | 23 82 00 1.4.F | 380 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Convection Heating And Cooling Units23 82 00 1.6.A · PDF p. 381Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 23 82 00 1.6.A | 381 | – |
| Closeout step | Closeout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsConvection Heating And Cooling Units23 82 00 3.4.A · PDF p. 382Spec wording“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.” | 23 82 00 3.4.A | 382 | – |
Division 26 Electrical 40 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.At completion of work, provide written certification that all systems ...Basic Electrical Requirements26 00 10 3.4.B · PDF p. 389Spec wording“B. At completion of work, provide written certification that all systems are functioning properly without defects.” | 26 00 10 3.4.B | 389 | – |
| Test / cert. | Test / cert.Assign a Start-Up Coordinator to this projectBasic Electrical Requirements26 00 10 3.5.A · PDF p. 389Spec wording“A. Assign a Start-Up Coordinator to this project.” | 26 00 10 3.5.A | 389 | – |
| Test / cert. | Test / cert.The Start-Up Coordinator shall develop detailed start-up procedures, equipment checkout ...Basic Electrical Requirements26 00 10 3.5.B · PDF p. 389Spec wording“B. The Start-Up Coordinator shall develop detailed start-up procedures, equipment checkout procedure and data forms for recording compliance with contract document performance criteria, and will assist in developing schedules for checkout and Owner acceptance.” | 26 00 10 3.5.B | 389 | – |
| Test / cert. | Test / cert.The Start-Up Coordinator shall be responsible for maintaining documentation of ...Basic Electrical Requirements26 00 10 3.5.C · PDF p. 389Spec wording“C. The Start-Up Coordinator shall be responsible for maintaining documentation of Start-Up activities until final acceptance of the project.” | 26 00 10 3.5.C | 389 | – |
| Test / cert. | Test / cert.The documentation shall be kept current by the Start-Up Coordinator ...Basic Electrical Requirements26 00 10 3.5.D · PDF p. 389Spec wording“D. The documentation shall be kept current by the Start-Up Coordinator and shall be available for inspection at all times. At the time of acceptance of the project, the Start-Up Coordinator shall surrender 3 completed copies of the documentation to the Owner's representative. 1) Coordinate with the mechanical installation the requirements for the startup of mechanical and plumbing systems: a. All equipment, ...” | 26 00 10 3.5.D | 389 | – |
| Training | TrainingRefer to Division 1 sections of the specifications regarding requirements ...Basic Electrical Requirements26 00 10 3.6.A · PDF p. 389Spec wording“A. Refer to Division 1 sections of the specifications regarding requirements of Record Drawings, Operation and Maintenance Manual submittal and systems training. 1) Demonstrate that each system operates properly. 2) Explain the operation of each system to the Owner's Representative. 3) Explain use of O&M manual in operating and maintaining systems. 4) Date, time, and duration of training will be determined by ...” | 26 00 10 3.6.A | 389 | DVD |
| Training | TrainingFor specific systems requiring extended instruction, refer to individual Division ...Basic Electrical Requirements26 00 10 3.6.B · PDF p. 390Spec wording“B. For specific systems requiring extended instruction, refer to individual Division 26 sections.” | 26 00 10 3.6.B | 390 | – |
| Record docs | Record docsProject Record DocumentsLow-Voltage Electrical Power Conductors And Cables26 05 19 1.5.C · PDF p. 392Spec wording“C. Project Record Documents: Record actual installed circuiting arrangements. Record actual routing for underground circuits.” | 26 05 19 1.5.C | 392 | – |
| Test / cert. | Test / cert.Field quality control test reportsGrounding And Bonding For Electrical Systems26 05 26 1.5.D · PDF p. 402Spec wording“D. Field quality control test reports.” | 26 05 26 1.5.D | 402 | – |
| Record docs | Record docsProject Record DocumentsGrounding And Bonding For Electrical Systems26 05 26 1.5.E · PDF p. 402Spec wording“E. Project Record Documents: Record actual locations of grounding electrode system components and connections.” | 26 05 26 1.5.E | 402 | – |
| Test / cert. | Test / cert.Submit detailed reports indicating inspection and testing results and corrective ...Grounding And Bonding For Electrical Systems26 05 26 3.3.F · PDF p. 404Spec wording“F. Submit detailed reports indicating inspection and testing results and corrective actions taken.” | 26 05 26 3.3.F | 404 | – |
| Record docs | Record docsProject Record DocumentsConduit For Electrical Systems26 05 33.13 1.5.D · PDF p. 414Spec wording“D. Project Record Documents: Record actual routing for conduits installed underground, conduits embedded within concrete slabs, and conduits 2 inch (53 mm) trade size and larger.” | 26 05 33.13 1.5.D | 414 | – |
| Record docs | Record docsProject Record DocumentsBoxes26 05 33.16 1.5.E · PDF p. 427Spec wording“E. Project Record Documents: Record actual locations for outlet and device boxes, pull boxes, cabinets and enclosures, and floor boxes.” | 26 05 33.16 1.5.E | 427 | – |
| Spare parts | Spare partsMaintenance MaterialsBoxes26 05 33.16 1.5.F · PDF p. 427Spec wording“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Keys for Lockable Enclosures: Two of each different key.” | 26 05 33.16 1.5.F | 427 | – |
| Test / cert. | Test / cert.Field Quality Control Test ReportsPanelboards26 24 16 1.5.E · PDF p. 445Spec wording“E. Field Quality Control Test Reports.” | 26 24 16 1.5.E | 445 | – |
| Record docs | Record docsProject Record DocumentsPanelboards26 24 16 1.5.G · PDF p. 446Spec wording“G. Project Record Documents: Record actual installed locations of panelboards and actual installed circuiting arrangements.” | 26 24 16 1.5.G | 446 | – |
| O&M | O&MMaintenance DataPanelboards26 24 16 1.5.H · PDF p. 446Spec wording“H. Maintenance Data: Include information on replacement parts and recommended maintenance procedures and intervals.” | 26 24 16 1.5.H | 446 | – |
| Spare parts | Spare partsMaintenance MaterialsPanelboards26 24 16 1.5.I · PDF p. 446Spec wording“I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Panelboard Keys: Two of each different key.” | 26 24 16 1.5.I | 446 | – |
| Test / cert. | Test / cert.Procure services of a qualified manufacturer's representative to observe installation ...Panelboards26 24 16 3.3.F · PDF p. 451Spec wording“F. Procure services of a qualified manufacturer's representative to observe installation and assist in inspection, testing, and adjusting. Include manufacturer's reports with field quality control submittals.” | 26 24 16 3.3.F | 451 | – |
| Record docs | Record docsProject Record DocumentsWiring Devices26 27 26 1.5.C · PDF p. 453Spec wording“C. Project Record Documents: Record actual installed locations of wiring devices.” | 26 27 26 1.5.C | 453 | – |
| Spare parts | Spare partsMaintenance MaterialsWiring Devices26 27 26 1.5.D · PDF p. 453Spec wording“D. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions.” | 26 27 26 1.5.D | 453 | – |
| Test / cert. | Test / cert.Field quality control reportsInterior Lighting26 51 00 1.5.F · PDF p. 461Spec wording“F. Field quality control reports.” | 26 51 00 1.5.F | 461 | – |
| O&M | O&MOperation and Maintenance DataInterior Lighting26 51 00 1.5.H · PDF p. 461Spec wording“H. Operation and Maintenance Data: Instructions for each product including information on replacement parts.” | 26 51 00 1.5.H | 461 | – |
| Spare parts | Spare partsMaintenance MaterialsInterior Lighting26 51 00 1.5.I · PDF p. 461Spec wording“I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Lenses and Louvers: Two percent of total quantity installed for each type, but not less than one of each type.” | 26 51 00 1.5.I | 461 | – |
| Record docs | Record docsProject Record DocumentsInterior Lighting26 51 00 1.5.J · PDF p. 461Spec wording“J. Project Record Documents: Record actual connections and locations of luminaires and any associated remote components.” | 26 51 00 1.5.J | 461 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Interior Lighting26 51 00 1.9.A · PDF p. 462Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 26 51 00 1.9.A | 462 | – |
| Warranty | WarrantyProvide three year manufacturer warranty for all LED luminaires, including ...Interior Lighting26 51 00 1.9.B · PDF p. 462Spec wording“B. Provide three year manufacturer warranty for all LED luminaires, including drivers.” | 26 51 00 1.9.B | 462 | – |
| Warranty | WarrantyProvide five year pro-rata warranty for batteries for emergency lighting ...Interior Lighting26 51 00 1.9.C · PDF p. 462Spec wording“C. Provide five year pro-rata warranty for batteries for emergency lighting units.” | 26 51 00 1.9.C | 462 | – |
| Closeout step | Closeout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsInterior Lighting26 51 00 3.7.A · PDF p. 464Spec wording“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.” | 26 51 00 3.7.A | 464 | – |
| Training | TrainingSee Section 01 7900 - Demonstration and Training, for additional ...Interior Lighting26 51 00 3.7.B · PDF p. 464Spec wording“B. See Section 01 7900 - Demonstration and Training, for additional requirements.” | 26 51 00 3.7.B | 464 | – |
| Training | TrainingDemonstrationInterior Lighting26 51 00 3.7.C · PDF p. 464Spec wording“C. Demonstration: Demonstrate proper operation of luminaires to Architect, and correct deficiencies or make adjustments as directed.” | 26 51 00 3.7.C | 464 | – |
| Closeout step | Closeout stepJust prior to Substantial Completion, replace all lamps that have ...Interior Lighting26 51 00 3.7.D · PDF p. 464Spec wording“D. Just prior to Substantial Completion, replace all lamps that have failed.” | 26 51 00 3.7.D | 464 | – |
| Test / cert. | Test / cert.Field Quality Control Reports. 1) Include test report indicating measured ...Exterior Lighting26 56 00 1.5.G · PDF p. 467Spec wording“G. Field Quality Control Reports. 1) Include test report indicating measured illumination levels.” | 26 56 00 1.5.G | 467 | – |
| O&M | O&MOperation and Maintenance DataExterior Lighting26 56 00 1.5.I · PDF p. 467Spec wording“I. Operation and Maintenance Data: Instructions for each product including information on replacement parts.” | 26 56 00 1.5.I | 467 | – |
| Spare parts | Spare partsMaintenance MaterialsExterior Lighting26 56 00 1.5.J · PDF p. 467Spec wording“J. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Lamps: Ten percent of total quantity installed for each type, but not less than two of each type. 3) Extra Ballasts: Two percent of total quantity installed for each type, but not less than one of each type. 4) Extra LED drivers: Ten percent of ...” | 26 56 00 1.5.J | 467 | – |
| Record docs | Record docsProject Record DocumentsExterior Lighting26 56 00 1.5.K · PDF p. 467Spec wording“K. Project Record Documents: Record actual connections and locations of pole foundations, luminaires, and any pull or junction boxes.” | 26 56 00 1.5.K | 467 | – |
| Warranty | WarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Exterior Lighting26 56 00 1.8.A · PDF p. 468Spec wording“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.” | 26 56 00 1.8.A | 468 | – |
| Warranty | WarrantyProvide three year manufacturer warranty for all LED luminaires, including ...Exterior Lighting26 56 00 1.8.B · PDF p. 468Spec wording“B. Provide three year manufacturer warranty for all LED luminaires, including drivers.” | 26 56 00 1.8.B | 468 | – |
| Closeout step | Closeout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsExterior Lighting26 56 00 3.7.A · PDF p. 470Spec wording“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.” | 26 56 00 3.7.A | 470 | – |
| Closeout step | Closeout stepJust prior to Substantial Completion, replace all lamps that have ...Exterior Lighting26 56 00 3.7.B · PDF p. 470Spec wording“B. Just prior to Substantial Completion, replace all lamps that have failed.” | 26 56 00 3.7.B | 470 | – |
Division 31 Earthwork 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Field Quality Control SubmittalsExcavation31 23 16 1.4.B · PDF p. 473Spec wording“B. Field Quality Control Submittals: Document visual inspection of load-bearing excavated surfaces.” | 31 23 16 1.4.B | 473 | – |
| Test / cert. | Test / cert.Compaction Density Test ReportsTrenching31 23 16.13 1.5.B · PDF p. 476Spec wording“B. Compaction Density Test Reports.” | 31 23 16.13 1.5.B | 476 | – |
| Test / cert. | Test / cert.Compaction Density Test ReportsFill31 23 23 1.5.B · PDF p. 480Spec wording“B. Compaction Density Test Reports.” | 31 23 23 1.5.B | 480 | – |
Division 32 Paving and site improvements 12 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Aggregate Composition Test ReportsAggregate Base Courses32 11 23 1.4.C · PDF p. 484Spec wording“C. Aggregate Composition Test Reports: Results of laboratory tests on proposed and actual materials used.” | 32 11 23 1.4.C | 484 | – |
| Test / cert. | Test / cert.Initial Soil SubmittalsLandscape Soil Preparation32 91 15 1.7.A · PDF p. 494Spec wording“A. Initial Soil Submittals: 1) Samples – For each bulk-supplied material in sealed containers labeled with content, source, and date obtained: providing an accurate representation of composition, color and texture. 2) Test Reports – For each bulk-supplied material as outlined in the Test Procedures and Reporting section. 3) Soil Analysis – Provide Initial Planting Soil Analysis for bulk-supplied material as ...” | 32 91 15 1.7.A | 494 | – |
| Test / cert. | Test / cert.Amended Soil MixesLandscape Soil Preparation32 91 15 1.7.B · PDF p. 494Spec wording“B. Amended Soil Mixes: 1) Samples – For each specified type of amended soil. 2) Test Reports – For each amended soil mix as outlined in the Test Procedures and Reporting section. 3) Soil Analysis – Provide Amended Planting Soil Analysis for each amended soil mix as outlined in the Test Procedures and Reporting section.” | 32 91 15 1.7.B | 494 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsLandscape Soil Preparation32 91 15 3.4.C · PDF p. 501Spec wording“C. Prepare test and inspection reports.” | 32 91 15 3.4.C | 501 | – |
| Test / cert. | Test / cert.Label each sample and test report with the date, location ...Landscape Soil Preparation32 91 15 3.4.D · PDF p. 501Spec wording“D. Label each sample and test report with the date, location keyed to a site plan or other location system, visible conditions when and where sample was taken, and sampling depth.” | 32 91 15 3.4.D | 501 | – |
| O&M | O&MMaintenance ManualTurf32 92 00 1.4.F · PDF p. 504-505Spec wording“F. Maintenance Manual: As part of awarding Substantial Completion Approval contractor shall provide to the owner and Landscape Architect a maintenance manual which consists of the following: 1) Contact information for the installation contractor company, company owner, and project foreman for both the installation and maintenance. 2) Installation date(s) of the work or phases of work as well as a copy of the ...” | 32 92 00 1.4.F | 504-505 | hardcopy; binder; digital file |
| Warranty | WarrantyGeneral WarrantyTurf32 92 00 1.9.A · PDF p. 507Spec wording“A. General Warranty: The special warranty specified in this Article shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by the Contractor under requirements of the Contract Documents.” | 32 92 00 1.9.A | 507 | – |
| Warranty | WarrantySpecial WarrantyTurf32 92 00 1.9.B · PDF p. 507Spec wording“B. Special Warranty: Warrant the lawn's installed, living materials for a period of 90 days after date of Final Acceptance, against defects including death and unsatisfactory growth, except for defects resulting from lack of adequate maintenance, neglect, or abuse by Owner, abnormal weather conditions unusual for warranty period, or incidents beyond Contractor's control.” | 32 92 00 1.9.B | 507 | – |
| Warranty | WarrantyWarranty/MaintenancePlant Material & Accessories32 93 00 1.3.C · PDF p. 514Spec wording“C. Warranty/Maintenance: Submit the following at the Final Completion Inspection: 1) Warranty: Provide a one (1) year written guarantee for all plant material. 2) Maintenance Instructions: Submit written recommendations procedures for landscape maintenance for one (1) calendar year.” | 32 93 00 1.3.C | 514 | – |
| Warranty | WarrantySpecial WarrantyPlant Material & Accessories32 93 00 1.7.A · PDF p. 516-517Spec wording“A. Special Warranty: Installer agrees to repair or replace plantings and accessories that fail in materials, workmanship, or growth within specified warranty period. 1) Failures include, but are not limited to, the following: a. Death and unsatisfactory growth, except for defects resulting from abuse, lack of adequate maintenance, or neglect by Owner, or incidents that are beyond Contractor's control. b. Structural ...” | 32 93 00 1.7.A | 516-517 | – |
| O&M | O&MProject Close-out SubmittalLandscape Maintenance32 94 47 1.4.B · PDF p. 526Spec wording“B. Project Close-out Submittal: Prepare a landscape maintenance manual in the form of a single 3-ring binder containing an indexed collection of documents to i include the following: 1) All plant material and accessories schedules, including final plant installation schedule showing substitutions made. 2) Records and permits required as listed above. 3) Documentation of accepted condition of planting at Final ...” | 32 94 47 1.4.B | 526 | 3-ring; binder |
| Warranty | WarrantyFor specific requirements, refer to the following sectionsLandscape Maintenance32 94 47 1.8.A · PDF p. 527Spec wording“A. For specific requirements, refer to the following sections: 1) Section 32 9200 - Turf 2) Section 32 9300 - Plant Material & Accessories” | 32 94 47 1.8.A | 527 | – |
Division 33 Utilities 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsProject Record DocumentsSite Water Utility Distribution Piping33 14 16 1.4.D · PDF p. 538Spec wording“D. Project Record Documents: Record actual locations of piping mains, valves, connections, thrust restraints, and invert elevations. Identify and describe unexpected variations to subsoil conditions or discovery of uncharted utilities.” | 33 14 16 1.4.D | 538 | – |
| Test / cert. | Test / cert.Field Quality Control SubmittalsSite Sanitary Sewerage Gravity Piping33 31 13 1.5.E · PDF p. 540Spec wording“E. Field Quality Control Submittals: Document results of field quality control testing.” | 33 31 13 1.5.E | 540 | – |
| Record docs | Record docsProject Record DocumentsSite Sanitary Sewerage Gravity Piping33 31 13 1.5.F · PDF p. 540Spec wording“F. Project Record Documents: 1) Record location of pipe runs, connections, manholes, cleanouts, and invert elevations.” | 33 31 13 1.5.F | 540 | – |
Front end Contract conditions (final payment, releases, retainage) 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 26Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 26 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 37Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 37 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 38Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 38 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 44Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 44 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 45Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 45 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 37Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 37 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 37Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 37 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 37-38Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 37-38 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 38Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 38 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 42-43Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 42-43 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 43Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 43 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.