Free closeout checklist · State job · Missouri

Closeout checklist: Upgrades and Renovations, Missouri Veterans Home (Missouri FMDC, MO)

Every closeout item we found in the public spec book for this job: 297 items across Division 01, 15 trade divisions and the contract conditions, including 85 warranties, 63 tests and certificates and 54 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.

Owner
State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
Number
FMDC project U1805-01
Location
Cape Girardeau, MO
Bid date
2025-07-22
Public spec book
Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing
Spec book size
964 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

85Warranties
54O&M manuals
63Tests and certificates
34Training
18Record documents
23Spare parts
6Payment release
14Closeout steps

All 297 items, by trade

Division 01 General requirements 73 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 110
Spec wording
“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...”
01 32 00 3.1.A110–
WarrantyWarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 118
Spec wording
“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.”
01 33 00 1.8.A118–
WarrantyWarrantyContractor shall submit the following information for materials and equipment ...Submittals01 33 00 3.1.A · PDF p. 118-127
Spec wording
“A. Contractor shall submit the following information for materials and equipment to be provided under this contract. SPEC TITLE CATEGORY SECTION 013200 Schedules-Bar Chart Construction Schedule 013200 Schedules-Bar Chart Schedule of Values 013200 Schedules-Bar Chart List of Subcontractors 013200 Schedules-Bar Chart Major Material Suppliers 030505 Product Data Underslab Vapor Barrier 032000 Concrete Forming and ...”
01 33 00 3.1.A118-127–
Test / cert.Test / cert.Test ReportsQuality Requirements01 40 00 1.6.D · PDF p. 136
Spec wording
“D. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor. 1) Include: a. Date issued. b. Project title and number. c. Name of inspector. d. Date and time of sampling or inspection. e. Identification of product and specifications section. f. Location in the Project. g. Type of test/inspection. h. Date of test/inspection. i. Results of test/inspection. j. ...”
01 40 00 1.6.D136two copies
Test / cert.Test / cert.Testing Agency DutiesQuality Requirements01 40 00 2.4.B · PDF p. 139
Spec wording
“B. Testing Agency Duties: 1) Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services. 2) Perform specified sampling and testing of products in accordance with specified standards. 3) Ascertain compliance of materials and mixes with requirements of Contract Documents. 4) Promptly notify Architect and Contractor of observed irregularities or non-compliance of Work or ...”
01 40 00 2.4.B139–
Spare partsSpare partsFurnish extra materials, spare parts, tools, and software of types ...Product Requirements01 60 00 2.4.A · PDF p. 153
Spec wording
“A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.”
01 60 00 2.4.A153–
Spare partsSpare partsDeliver to Project site; obtain receipt prior to final paymentProduct Requirements01 60 00 2.4.B · PDF p. 153
Spec wording
“B. Deliver to Project site; obtain receipt prior to final payment.”
01 60 00 2.4.B153–
Closeout stepCloseout stepSurvey workExecution And Closeout Requirements01 70 00 1.4.B · PDF p. 159
Spec wording
“B. Survey work: Submit name, address, and telephone number of Surveyor before starting survey work. 1) On request, submit documentation verifying accuracy of survey work. 2) Submit a copy of site drawing signed by the Land Surveyor, that the elevations and locations of the work are in compliance with Contract Documents. 3) Submit surveys and survey logs for the project record.”
01 70 00 1.4.B159–
Test / cert.Test / cert.Coordinate schedule for start-up of various equipment and systemsExecution And Closeout Requirements01 70 00 3.10.A · PDF p. 167
Spec wording
“A. Coordinate schedule for start-up of various equipment and systems.”
01 70 00 3.10.A167–
Test / cert.Test / cert.Notify Architect and Owner seven days prior to start-up of each itemExecution And Closeout Requirements01 70 00 3.10.B · PDF p. 167
Spec wording
“B. Notify Architect and Owner seven days prior to start-up of each item.”
01 70 00 3.10.B167–
Test / cert.Test / cert.Verify that each piece of equipment or system has been ...Execution And Closeout Requirements01 70 00 3.10.C · PDF p. 167
Spec wording
“C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions that may cause damage.”
01 70 00 3.10.C167–
Test / cert.Test / cert.Verify tests, meter readings, and specified electrical characteristics agree with ...Execution And Closeout Requirements01 70 00 3.10.D · PDF p. 167
Spec wording
“D. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.”
01 70 00 3.10.D167–
Test / cert.Test / cert.Verify that wiring and support components for equipment are complete ...Execution And Closeout Requirements01 70 00 3.10.E · PDF p. 168
Spec wording
“E. Verify that wiring and support components for equipment are complete and tested.”
01 70 00 3.10.E168–
Test / cert.Test / cert.Execute start-up under supervision of applicable Contractor personnel in accordance ...Execution And Closeout Requirements01 70 00 3.10.F · PDF p. 168
Spec wording
“F. Execute start-up under supervision of applicable Contractor personnel in accordance with manufacturers' instructions.”
01 70 00 3.10.F168–
Test / cert.Test / cert.When specified in individual specification Sections, require manufacturer to provide ...Execution And Closeout Requirements01 70 00 3.10.G · PDF p. 168
Spec wording
“G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.”
01 70 00 3.10.G168–
Test / cert.Test / cert.Submit a written report that equipment or system has been ...Execution And Closeout Requirements01 70 00 3.10.H · PDF p. 168
Spec wording
“H. Submit a written report that equipment or system has been properly installed and is functioning correctly.”
01 70 00 3.10.H168–
TrainingTrainingRefer to Section 01 7900 - Demonstration and Training for ...Execution And Closeout Requirements01 70 00 3.11.A · PDF p. 168
Spec wording
“A. Refer to Section 01 7900 - Demonstration and Training for additional State of Missouri Requirements.”
01 70 00 3.11.A168–
TrainingTrainingDemonstrate operation and maintenance of products to Owner's personnel two ...Execution And Closeout Requirements01 70 00 3.11.B · PDF p. 168
Spec wording
“B. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion.”
01 70 00 3.11.B168–
TrainingTrainingDemonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown ...Execution And Closeout Requirements01 70 00 3.11.C · PDF p. 168
Spec wording
“C. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.”
01 70 00 3.11.C168–
TrainingTrainingFor equipment or systems requiring seasonal operation, perform demonstration for ...Execution And Closeout Requirements01 70 00 3.11.D · PDF p. 168
Spec wording
“D. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.”
01 70 00 3.11.D168–
TrainingTrainingProvide a qualified person who is knowledgeable about the Project ...Execution And Closeout Requirements01 70 00 3.11.E · PDF p. 168
Spec wording
“E. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of Owner's personnel.”
01 70 00 3.11.E168–
TrainingTrainingUtilize operation and maintenance manuals as basis for instruction. Review ...Execution And Closeout Requirements01 70 00 3.11.F · PDF p. 168
Spec wording
“F. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.”
01 70 00 3.11.F168–
TrainingTrainingPrepare and insert additional data in operations and maintenance manuals ...Execution And Closeout Requirements01 70 00 3.11.G · PDF p. 168
Spec wording
“G. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.”
01 70 00 3.11.G168–
Closeout stepCloseout stepMake submittals that are required by governing or other authoritiesExecution And Closeout Requirements01 70 00 3.14.A · PDF p. 169
Spec wording
“A. Make submittals that are required by governing or other authorities.”
01 70 00 3.14.A169–
TrainingTrainingRefer to Section 01 7900 - Demonstration and for additional ...Execution And Closeout Requirements01 70 00 3.14.B · PDF p. 169
Spec wording
“B. Refer to Section 01 7900 - Demonstration and for additional State of Missouri Requirements.”
01 70 00 3.14.B169–
Test / cert.Test / cert.Accompany Project Coordinator on preliminary inspection to determine items to ...Execution And Closeout Requirements01 70 00 3.14.C · PDF p. 169
Spec wording
“C. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.”
01 70 00 3.14.C169–
Test / cert.Test / cert.Notify Architect when work is considered ready for Architect's Substantial ...Execution And Closeout Requirements01 70 00 3.14.D · PDF p. 169
Spec wording
“D. Notify Architect when work is considered ready for Architect's Substantial Completion inspection.”
01 70 00 3.14.D169–
Test / cert.Test / cert.Submit written certification containing Contractor's Correction Punch List, that Contract ...Execution And Closeout Requirements01 70 00 3.14.E · PDF p. 169
Spec wording
“E. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's Substantial Completion inspection.”
01 70 00 3.14.E169–
Closeout stepCloseout stepOwner will occupy portions of the building as specified in ...Execution And Closeout Requirements01 70 00 3.14.F · PDF p. 169
Spec wording
“F. Owner will occupy portions of the building as specified in Section 01 1000.”
01 70 00 3.14.F169–
Test / cert.Test / cert.Conduct Substantial Completion inspection and create Final Correction Punch List ...Execution And Closeout Requirements01 70 00 3.14.G · PDF p. 169
Spec wording
“G. Conduct Substantial Completion inspection and create Final Correction Punch List containing Architect's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Architect.”
01 70 00 3.14.G169–
Closeout stepCloseout stepCorrect items of work listed in Final Correction Punch List ...Execution And Closeout Requirements01 70 00 3.14.H · PDF p. 169
Spec wording
“H. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas.”
01 70 00 3.14.H169–
Test / cert.Test / cert.Notify Architect when work is considered finally complete and ready ...Execution And Closeout Requirements01 70 00 3.14.I · PDF p. 169
Spec wording
“I. Notify Architect when work is considered finally complete and ready for Architect's Substantial Completion final inspection.”
01 70 00 3.14.I169–
Test / cert.Test / cert.Complete items of work determined by Architect listed in executed ...Execution And Closeout Requirements01 70 00 3.14.J · PDF p. 169
Spec wording
“J. Complete items of work determined by Architect listed in executed Certificate of Substantial Completion.”
01 70 00 3.14.J169–
Record docsRecord docsProject Record DocumentsCloseout Submittals01 78 00 1.3.A · PDF p. 175
Spec wording
“A. Project Record Documents: Submit documents to Architect with claim for final Application for Payment.”
01 78 00 1.3.A175–
O&MO&MOperation and Maintenance DataCloseout Submittals01 78 00 1.3.B · PDF p. 175
Spec wording
“B. Operation and Maintenance Data: 1) Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect will review draft and return one copy with comments. 2) For equipment, or component parts of equipment put into service during construction and operated by Owner, submit completed documents within ten days after acceptance. 3) Submit one copy of completed ...”
01 78 00 1.3.B175two copies; one copy; two sets
WarrantyWarrantyWarranties and BondsCloseout Submittals01 78 00 1.3.C · PDF p. 175
Spec wording
“C. Warranties and Bonds: 1) For equipment or component parts of equipment put into service during construction with Owner's permission, submit documents within 10 days after acceptance. 2) Make other submittals within 10 days after Date of Substantial Completion, prior to final Application for Payment. 3) For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within 10 days ...”
01 78 00 1.3.C175–
O&MO&MProduct DataCloseout Submittals01 78 00 2.1.B · PDF p. 176
Spec wording
“B. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information.”
01 78 00 2.1.B176–
O&MO&MDrawingsCloseout Submittals01 78 00 2.1.C · PDF p. 176
Spec wording
“C. Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams. Do not use Project Record Documents as maintenance drawings.”
01 78 00 2.1.C176–
O&MO&MTyped TextCloseout Submittals01 78 00 2.1.D · PDF p. 176
Spec wording
“D. Typed Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions.”
01 78 00 2.1.D176–
O&MO&MMoisture protection and weather-exposed productsCloseout Submittals01 78 00 2.2.C · PDF p. 176
Spec wording
“C. Moisture protection and weather-exposed products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.”
01 78 00 2.2.C176–
O&MO&MFor Each Item of Equipment and Each SystemCloseout Submittals01 78 00 2.3.A · PDF p. 176
Spec wording
“A. For Each Item of Equipment and Each System: 1) Description of unit or system, and component parts. 2) Identify function, normal operating characteristics, and limiting conditions. 3) Include performance curves, with engineering data and tests. 4) Complete nomenclature and model number of replaceable parts.”
01 78 00 2.3.A176–
O&MO&MPanelboard Circuit DirectoriesCloseout Submittals01 78 00 2.3.C · PDF p. 177
Spec wording
“C. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and communications; typed.”
01 78 00 2.3.C177–
O&MO&MInclude color coded wiring diagrams as installedCloseout Submittals01 78 00 2.3.D · PDF p. 177
Spec wording
“D. Include color coded wiring diagrams as installed.”
01 78 00 2.3.D177–
O&MO&MOperating ProceduresCloseout Submittals01 78 00 2.3.E · PDF p. 177
Spec wording
“E. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and any special operating instructions.”
01 78 00 2.3.E177–
O&MO&MMaintenance RequirementsCloseout Submittals01 78 00 2.3.F · PDF p. 177
Spec wording
“F. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.”
01 78 00 2.3.F177–
O&MO&MProvide servicing and lubrication schedule, and list of lubricants required ...Closeout Submittals01 78 00 2.3.G · PDF p. 177
Spec wording
“G. Provide servicing and lubrication schedule, and list of lubricants required.”
01 78 00 2.3.G177–
O&MO&MInclude manufacturer's printed operation and maintenance instructionsCloseout Submittals01 78 00 2.3.H · PDF p. 177
Spec wording
“H. Include manufacturer's printed operation and maintenance instructions.”
01 78 00 2.3.H177–
O&MO&MInclude sequence of operation by controls manufacturerCloseout Submittals01 78 00 2.3.I · PDF p. 177
Spec wording
“I. Include sequence of operation by controls manufacturer.”
01 78 00 2.3.I177–
O&MO&MProvide original manufacturer's parts list, illustrations, assembly drawings, and diagrams ...Closeout Submittals01 78 00 2.3.J · PDF p. 177
Spec wording
“J. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.”
01 78 00 2.3.J177–
O&MO&MAssemble operation and maintenance data into durable manuals for Owner's ...Closeout Submittals01 78 00 2.4.A · PDF p. 177
Spec wording
“A. Assemble operation and maintenance data into durable manuals for Owner's personnel use, with data arranged in the same sequence as, and identified by, the specification sections.”
01 78 00 2.4.A177–
O&MO&MWhere systems involve more than one specification section, provide separate ...Closeout Submittals01 78 00 2.4.B · PDF p. 177
Spec wording
“B. Where systems involve more than one specification section, provide separate tabbed divider for each system.”
01 78 00 2.4.B177–
O&MO&MTables of ContentsCloseout Submittals01 78 00 2.4.F · PDF p. 177
Spec wording
“F. Tables of Contents: List every item separated by a divider, using the same identification as on the divider tab; where multiple volumes are required, include all volumes Tables of Contents in each volume, with the current volume clearly identified.”
01 78 00 2.4.F177–
O&MO&MDividersCloseout Submittals01 78 00 2.4.G · PDF p. 177
Spec wording
“G. Dividers: Provide tabbed dividers for each separate product and system; identify the contents on the divider tab; immediately following the divider tab include a description of product and major component parts of equipment.”
01 78 00 2.4.G177–
O&MO&MDrawingsCloseout Submittals01 78 00 2.4.I · PDF p. 178
Spec wording
“I. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.”
01 78 00 2.4.I178binder
WarrantyWarrantyObtain warranties and bonds, executed in duplicate by responsible Subcontractors, ...Closeout Submittals01 78 00 2.5.A · PDF p. 178
Spec wording
“A. Obtain warranties and bonds, executed in duplicate by responsible Subcontractors, suppliers, and manufacturers, within 10 days after completion of the applicable item of work. Except for items put into use with Owner's permission, leave date of beginning of time of warranty until Date of Substantial completion is determined.”
01 78 00 2.5.A178–
WarrantyWarrantySeparate each warranty or bond with index tab sheets keyed ...Closeout Submittals01 78 00 2.5.H · PDF p. 178
Spec wording
“H. Separate each warranty or bond with index tab sheets keyed to the Table of Contents listing. Provide full information, using separate typed sheets as necessary. List Subcontractor, supplier, and manufacturer, with name, address, and telephone number of responsible principal.”
01 78 00 2.5.H178–
TrainingTrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 179
Spec wording
“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.”
01 79 00 1.3.A179–
TrainingTrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 179
Spec wording
“B. Attendance Record: For each training module, submit list of participants and length of instruction time.”
01 79 00 1.3.B179–
TrainingTrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 179
Spec wording
“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.”
01 79 00 1.3.C179–
TrainingTrainingDemonstration and Training Video RecordingsDemonstration And Training01 79 00 1.4.A · PDF p. 179-180
Spec wording
“A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. Transcript: Prepared in PDF electronic format. ...”
01 79 00 1.4.A179-180two copies; PDF; electronic format; electronic file
TrainingTrainingFacilitator QualificationsDemonstration And Training01 79 00 1.5.A · PDF p. 180
Spec wording
“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.”
01 79 00 1.5.A180–
TrainingTrainingPre-instruction ConferenceDemonstration And Training01 79 00 1.5.C · PDF p. 180
Spec wording
“C. Pre-instruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Coordination". Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, ...”
01 79 00 1.5.C180–
O&MO&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.6.C · PDF p. 180
Spec wording
“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.”
01 79 00 1.6.C180–
WarrantyWarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 180-182
Spec wording
“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...”
01 79 00 2.1.B180-182–
TrainingTrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 182
Spec wording
“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".”
01 79 00 3.1.A182–
TrainingTrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 182
Spec wording
“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Architect will furnish an instructor to describe basis of system design, operational requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names ...”
01 79 00 3.2.A182–
TrainingTrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 182
Spec wording
“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.”
01 79 00 3.2.B182–
TrainingTrainingGeneralDemonstration And Training01 79 00 3.3.A · PDF p. 183
Spec wording
“A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. 1. At beginning of each training module, record each chart containing learning objective and lesson outline.”
01 79 00 3.3.A183–
TrainingTrainingVideoDemonstration And Training01 79 00 3.3.B · PDF p. 183
Spec wording
“B. Video: Provide minimum 640 x 480 video resolution converted to format file type acceptable to Owner, on electronic media. 1. Electronic Media: Read-only format compact disc acceptable to Owner, with commercial-grade graphic label. 2. File Hierarchy: Organize folder structure and file locations according to project manual table of contents. Provide complete screen-based menu. 3. File Names: Utilize file names ...”
01 79 00 3.3.B183electronic media; DVD
TrainingTrainingLight LevelsDemonstration And Training01 79 00 3.3.D · PDF p. 183-184
Spec wording
“D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. 1. Furnish additional portable lighting as required.”
01 79 00 3.3.D183-184–
TrainingTrainingNarrationDemonstration And Training01 79 00 3.3.E · PDF p. 184
Spec wording
“E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.”
01 79 00 3.3.E184–
TrainingTrainingTranscriptDemonstration And Training01 79 00 3.3.F · PDF p. 184
Spec wording
“F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.”
01 79 00 3.3.F184–
TrainingTrainingPreproduced Video RecordingsDemonstration And Training01 79 00 3.3.G · PDF p. 184
Spec wording
“G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.”
01 79 00 3.3.G184–

Division 02 Existing conditions 1 item

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsProject Record DocumentsDemolition02 41 00 1.4.C · PDF p. 185
Spec wording
“C. Project Record Documents: Accurately record actual locations of capped and active utilities and subsurface construction.”
02 41 00 1.4.C185–

Division 03 Concrete 6 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test ReportsCast-In-Place Concrete03 30 00 1.4.F · PDF p. 203
Spec wording
“F. Test Reports: Submit report for each test or series of tests specified.”
03 30 00 1.4.F203–
WarrantyWarrantyWarrantyCast-In-Place Concrete03 30 00 1.4.G · PDF p. 203
Spec wording
“G. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.”
03 30 00 1.4.G203–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Cast-In-Place Concrete03 30 00 1.6.A · PDF p. 203
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
03 30 00 1.6.A203–
WarrantyWarrantySlabs with Moisture Vapor Reducing Admixture (MVRA)Cast-In-Place Concrete03 30 00 1.6.B · PDF p. 203
Spec wording
“B. Slabs with Moisture Vapor Reducing Admixture (MVRA): Provide warranty to cover the cost of flooring failures due to moisture migration from slabs for life of the concrete. 1) Include cost of repair or removal of failed flooring, placement of topical moisture remediation system, and replacement of flooring with comparable flooring system. 2) Provide warranty by manufacturer of MVRA matching terms of flooring ...”
03 30 00 1.6.B203–
WarrantyWarrantyMoisture Emission Reducing Curing and Sealing CompoundCast-In-Place Concrete03 30 00 1.6.C · PDF p. 204
Spec wording
“C. Moisture Emission Reducing Curing and Sealing Compound: Provide warranty to cost of flooring delamination failures for 10 years. 1) Include cost of repair or removal of failed flooring, remediation with a moisture vapor impermeable surface coating, and replacement of flooring with comparable flooring system.”
03 30 00 1.6.C204–
O&MO&MMaintenance DataStamped Concrete Finishing03 35 33 1.5.F · PDF p. 215
Spec wording
“F. Maintenance Data: Provide data on maintenance and renewal of applied finishes.”
03 35 33 1.5.F215–

Division 06 Wood and plastics 1 item

TypeItemSpec sectionPDF pageCopies / format
Spare partsSpare partsMaintenance MaterialsFiberglass Reinforced Paneling06 83 16 1.3.D · PDF p. 294
Spec wording
“D. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Panels: Quantity equal to 5 percent of total installed.”
06 83 16 1.3.D294–

Division 07 Roofing, insulation and waterproofing 11 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyWarranty DocumentationAsphalt Shingles07 31 13 1.4.G · PDF p. 311
Spec wording
“G. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
07 31 13 1.4.G311–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Asphalt Shingles07 31 13 1.7.A · PDF p. 311
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
07 31 13 1.7.A311–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Plastic Siding07 46 33 1.7.A · PDF p. 318
Spec wording
“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.”
07 46 33 1.7.A318–
WarrantyWarrantyExtended Correction PeriodPlastic Siding07 46 33 1.7.B · PDF p. 318
Spec wording
“B. Extended Correction Period: Correct defective work within 2-year period commencing on Date of Substantial Completion.”
07 46 33 1.7.B318–
WarrantyWarrantyWarrantyPlastic Siding07 46 33 1.7.C · PDF p. 318
Spec wording
“C. Warranty: Manufacturer agrees to replace or refund the purchase price of nonconforming products that fail within the specified warranty period. 1) Failure Methods: Splitting, splintering, cracking, rotting or structural damage from termites or fungal decay. 2) Commercial Warranty Period: 20 years from date of purchase”
07 46 33 1.7.C318–
Test / cert.Test / cert.Test ReportFiber-Cement Siding07 46 46 1.4.C · PDF p. 322
Spec wording
“C. Test Report: Applicable model code authority evaluation report (e.g. ICC-ES).”
07 46 46 1.4.C322–
WarrantyWarrantyWarrantyFiber-Cement Siding07 46 46 1.4.G · PDF p. 322
Spec wording
“G. Warranty: Submit copy of manufacturer's warranty, made out in Owner's name, showing that it has been registered with manufacturer.”
07 46 46 1.4.G322–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Fiber-Cement Siding07 46 46 1.7.A · PDF p. 323
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
07 46 46 1.7.A323–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Joint Sealants07 92 00 1.6.A · PDF p. 336
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
07 92 00 1.6.A336–
WarrantyWarrantyCorrect defective work within a five year period after Date ...Joint Sealants07 92 00 1.6.B · PDF p. 336
Spec wording
“B. Correct defective work within a five year period after Date of Substantial Completion.”
07 92 00 1.6.B336–
WarrantyWarrantyWarrantyJoint Sealants07 92 00 1.6.C · PDF p. 336
Spec wording
“C. Warranty: Include coverage for installed sealants and accessories that fail to achieve watertight seal , exhibit loss of adhesion or cohesion, or do not cure.”
07 92 00 1.6.C336–

Division 08 Doors, windows and hardware 35 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyInterior DoorsFlush Wood Doors08 14 16 1.7.A · PDF p. 358
Spec wording
“A. Interior Doors: Provide manufacturer's warranty for the life of the installation.”
08 14 16 1.7.A358–
WarrantyWarrantyInclude coverage for delamination of veneer, warping beyond specified installation ...Flush Wood Doors08 14 16 1.7.B · PDF p. 358
Spec wording
“B. Include coverage for delamination of veneer, warping beyond specified installation tolerances, defective materials, and telegraphing core construction.”
08 14 16 1.7.B358–
WarrantyWarrantyCloseout SubmittalsSliding Automatic Entrances08 42 29 1.5.E · PDF p. 368
Spec wording
“E. Closeout Submittals: 1) Owner's Manual and operating instructions. 2) Maintenance Data 3) Warranties.”
08 42 29 1.5.E368–
WarrantyWarrantyAutomatic Entrances shall be free of defects in material and ...Sliding Automatic Entrances08 42 29 1.9.A · PDF p. 369
Spec wording
“A. Automatic Entrances shall be free of defects in material and workmanship for a period of one (1) year from the date of substantial completion.”
08 42 29 1.9.A369–
WarrantyWarrantyDuring the warranty period the Contractor shall engage a factory-trained ...Sliding Automatic Entrances08 42 29 1.9.B · PDF p. 369
Spec wording
“B. During the warranty period the Contractor shall engage a factory-trained technician to perform service and affect repairs. A safety inspection shall be performed after each adjustment or repair and a completed inspection form shall be submitted to the Owner.”
08 42 29 1.9.B369–
WarrantyWarrantyDuring the warranty period all warranty work, including but not ...Sliding Automatic Entrances08 42 29 1.9.C · PDF p. 369
Spec wording
“C. During the warranty period all warranty work, including but not limited to emergency service, shall be performed during normal working hours. PRODUCTS”
08 42 29 1.9.C369–
WarrantyWarrantyWarrantyAluminum-Framed Storefronts08 43 13 1.5.K · PDF p. 379
Spec wording
“K. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.”
08 43 13 1.5.K379–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Aluminum-Framed Storefronts08 43 13 1.9.A · PDF p. 380
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
08 43 13 1.9.A380–
WarrantyWarrantyCorrect defective Work within a five-year period after Date of ...Aluminum-Framed Storefronts08 43 13 1.9.B · PDF p. 380
Spec wording
“B. Correct defective Work within a five-year period after Date of Substantial Completion.”
08 43 13 1.9.B380–
WarrantyWarrantyProvide five-year manufacturer warranty against failure of glass seal on ...Aluminum-Framed Storefronts08 43 13 1.9.C · PDF p. 380
Spec wording
“C. Provide five-year manufacturer warranty against failure of glass seal on insulating glass units, including interpane dusting or misting. Include provision for replacement of failed units.”
08 43 13 1.9.C380–
WarrantyWarrantyProvide 10-year manufacturer warranty against excessive degradation of exterior finish. ...Aluminum-Framed Storefronts08 43 13 1.9.D · PDF p. 380
Spec wording
“D. Provide 10-year manufacturer warranty against excessive degradation of exterior finish. Include provision for replacement of units with excessive fading, chalking, or flaking.”
08 43 13 1.9.D380–
Test / cert.Test / cert.Provide services of storefront manufacturer's field representative to observe for ...Aluminum-Framed Storefronts08 43 13 3.4.A · PDF p. 385
Spec wording
“A. Provide services of storefront manufacturer's field representative to observe for proper installation of system and submit report.”
08 43 13 3.4.A385–
Test / cert.Test / cert.Grade SubstantiationFiberglass Windows08 54 13 1.5.G · PDF p. 388
Spec wording
“G. Grade Substantiation: Prior to submitting shop drawings or starting fabrication, submit one of the following showing compliance with specified grade: 1) Evidence of AAMA Certification. 2) Evidence of WDMA Certification. 3) Evidence of CSA Certification. 4) Test report(s) by independent testing agency itemizing compliance and acceptable to authorities having jurisdiction.”
08 54 13 1.5.G388–
WarrantyWarrantyWarranty DocumentationFiberglass Windows08 54 13 1.5.I · PDF p. 388
Spec wording
“I. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
08 54 13 1.5.I388–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Fiberglass Windows08 54 13 1.9.A · PDF p. 388
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
08 54 13 1.9.A388–
WarrantyWarrantyProvide ten year manufacturer warranty for insulated glass units from ...Fiberglass Windows08 54 13 1.9.B · PDF p. 388
Spec wording
“B. Provide ten year manufacturer warranty for insulated glass units from seal failure, interpane dusting or misting, and replacement of same. Include coverage for degradation of color finish.”
08 54 13 1.9.B388–
Test / cert.Test / cert.Provide services of fiberglass window manufacturer's field representative to observe ...Fiberglass Windows08 54 13 3.4.A · PDF p. 392
Spec wording
“A. Provide services of fiberglass window manufacturer's field representative to observe for proper installation of system and submit report.”
08 54 13 3.4.A392–
WarrantyWarrantyWarrantyService And Teller Window Units08 56 59 1.4.E · PDF p. 393
Spec wording
“E. Warranty: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
08 56 59 1.4.E393–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Service And Teller Window Units08 56 59 1.7.A · PDF p. 394
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
08 56 59 1.7.A394–
TrainingTrainingTrain Owner's maintenance personnel to adjust, operate, and maintain operable ...Service And Teller Window Units08 56 59 3.5.A · PDF p. 396
Spec wording
“A. Train Owner's maintenance personnel to adjust, operate, and maintain operable units. 1) Instructor: Manufacturer's training personnel. 2) Location: At project site. 3) Use operation and maintenance manual as training reference, supplemented with additional training materials as required.”
08 56 59 3.5.A396–
WarrantyWarrantyDoor Hardware ScheduleDoor Hardware08 71 00 1.3.B · PDF p. 398
Spec wording
“B. Door Hardware Schedule: Prepared by or under the supervision of supplier, detailing, fabrication and assembly of door hardware, as well as procedures and diagrams. Coordinate the final Door Hardware Schedule with doors, frames, and related work to ensure proper size, thickness, hand, function, and finish of door hardware. 1. Format: Comply with scheduling sequence and vertical format in DHI's "Sequence and ...”
08 71 00 1.3.B398–
Test / cert.Test / cert.Informational Submittals:Door Hardware08 71 00 1.3.E · PDF p. 399
Spec wording
“E. Informational Submittals: 1. Product Test Reports: Indicating compliance with cycle testing requirements, based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified independent testing agency.”
08 71 00 1.3.E399–
O&MO&MOperating and Maintenance ManualsDoor Hardware08 71 00 1.4.A · PDF p. 399
Spec wording
“A. Operating and Maintenance Manuals: Provide manufacturers operating and maintenance manuals for each item comprising the complete door hardware installation in quantity as required in Division 01, Closeout Procedures. 1. Maintenance manual must be provided for tornado/hurricane storm shelter impact protective systems.”
08 71 00 1.4.A399–
Record docsRecord docsProject Record DocumentsDoor Hardware08 71 00 1.4.B · PDF p. 399
Spec wording
“B. Project Record Documents: Provide record documentation of as-built door hardware sets in digital format (.pdf, .docx, .xlsx, .csv) and as required in Division 01, Project Record Documents.”
08 71 00 1.4.B399digital format; pdf
Record docsRecord docsProject Record DocumentsDoor Hardware08 71 00 1.4.C · PDF p. 399
Spec wording
“C. Project Record Documents: Provide record documentation of as-built door hardware sets in digital format (.pdf, .docx, .xlsx, .csv) or acceptable integrated file format for updating of Openings Studio™ management software and as required in Division 01, Project Record Documents.”
08 71 00 1.4.C399digital format; pdf
WarrantyWarrantyGeneral WarrantyDoor Hardware08 71 00 1.8.A · PDF p. 402
Spec wording
“A. General Warranty: Reference Division 01, General Requirements. Special warranties specified in this Article shall not deprive Owner of other rights Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by Contractor under requirements of the Contract Documents.”
08 71 00 1.8.A402–
WarrantyWarrantyWarranty PeriodDoor Hardware08 71 00 1.8.B · PDF p. 402
Spec wording
“B. Warranty Period: Written warranty, executed by manufacturer(s), agreeing to repair or replace components of standard and electrified door hardware that fails in materials or workmanship within specified warranty period after final acceptance by the Owner. Failures include, but are not limited to, the following: 1. Structural failures including excessive deflection, cracking, or breakage. 2. Faulty operation of ...”
08 71 00 1.8.B402–
WarrantyWarrantyWarranty PeriodDoor Hardware08 71 00 1.8.C · PDF p. 402
Spec wording
“C. Warranty Period: Unless otherwise indicated, warranty shall be one year from date of Substantial Completion.”
08 71 00 1.8.C402–
TrainingTrainingInstruct Owner's maintenance personnel to adjust, operate, and maintain mechanical ...Door Hardware08 71 00 3.6.A · PDF p. 416
Spec wording
“A. Instruct Owner's maintenance personnel to adjust, operate, and maintain mechanical and electromechanical door hardware.”
08 71 00 3.6.A416–
WarrantyWarrantyWarranty DocumentationGlazing08 80 00 1.5.E · PDF p. 436
Spec wording
“E. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
08 80 00 1.5.E436–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Glazing08 80 00 1.8.A · PDF p. 436
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
08 80 00 1.8.A436–
WarrantyWarrantyInsulating Glass UnitsGlazing08 80 00 1.8.B · PDF p. 436
Spec wording
“B. Insulating Glass Units: Provide a five (5) year manufacturer warranty to include coverage for seal failure, interpane dusting or misting, including providing products to replace failed units.”
08 80 00 1.8.B436–
Test / cert.Test / cert.Test ReportsLouvers08 91 00 1.4.E · PDF p. 447
Spec wording
“E. Test Reports: Independent agency reports showing compliance with specified performance criteria.”
08 91 00 1.4.E447–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Louvers08 91 00 1.6.A · PDF p. 447
Spec wording
“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.”
08 91 00 1.6.A447–
WarrantyWarrantyProvide five year manufacturer's warranty against distortion, metal degradation, and ...Louvers08 91 00 1.6.B · PDF p. 448
Spec wording
“B. Provide five year manufacturer's warranty against distortion, metal degradation, and connection failures of louver components. 1) Finish: Include ten year coverage against degradation of exterior finish.”
08 91 00 1.6.B448–

Division 09 Finishes 21 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Testing Agency's ReportCommon Work Results For Flooring Preparation09 05 61 1.5.D · PDF p. 452
Spec wording
“D. Testing Agency's Report: 1) Description of areas tested; include floor plans and photographs if helpful. 2) Summary of conditions encountered. 3) Moisture and alkalinity (pH) test reports. 4) Copies of specified test methods. 5) Recommendations for remediation of unsatisfactory surfaces. 6) Product data for recommended remedial coating. 7) Submit report to Architect. 8) Submit report not more than two business ...”
09 05 61 1.5.D452–
WarrantyWarrantyAdhesive Bond and Compatibility Test ReportCommon Work Results For Flooring Preparation09 05 61 1.5.E · PDF p. 453
Spec wording
“E. Adhesive Bond and Compatibility Test Report.”
09 05 61 1.5.E453–
Test / cert.Test / cert.Remedial Materials Product DataCommon Work Results For Flooring Preparation09 05 61 1.5.G · PDF p. 453
Spec wording
“G. Remedial Materials Product Data: Manufacturer's published data on each product to be used for remediation. 1) Manufacturer's statement of compatibility with types of flooring applied over remedial product. 2) Test reports indicating compliance with specified performance requirements, performed by nationally recognized independent testing agency. 3) Manufacturer's installation instructions.”
09 05 61 1.5.G453–
Test / cert.Test / cert.ReportCommon Work Results For Flooring Preparation09 05 61 3.4.F · PDF p. 456
Spec wording
“F. Report: Report the information required by the test method.”
09 05 61 3.4.F456–
Test / cert.Test / cert.ReportCommon Work Results For Flooring Preparation09 05 61 3.5.F · PDF p. 457
Spec wording
“F. Report: Report the information required by the test method.”
09 05 61 3.5.F457–
O&MO&MMaintenance DataTiling09 30 00 1.4.E · PDF p. 472
Spec wording
“E. Maintenance Data: Include recommended cleaning methods, cleaning materials, and stain removal methods.”
09 30 00 1.4.E472–
Spare partsSpare partsMaintenance MaterialsTiling09 30 00 1.4.F · PDF p. 472
Spec wording
“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Tile: 10 square feet of each size, color, and surface finish combination.”
09 30 00 1.4.F472–
Spare partsSpare partsMaintenance MaterialsAcoustical Ceilings09 51 00 1.5.E · PDF p. 480
Spec wording
“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Acoustical Units: Quantity equal to 5 percent of total installed.”
09 51 00 1.5.E480–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Linear Metal Ceilings09 54 23 1.8.A · PDF p. 489
Spec wording
“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.”
09 54 23 1.8.A489–
WarrantyWarrantyManufacturer WarrantyLinear Metal Ceilings09 54 23 1.8.B · PDF p. 489
Spec wording
“B. Manufacturer Warranty: Provide 5-year manufacturer warranty; include coverage for corrosion resistance and discoloration of surface finish.”
09 54 23 1.8.B489–
Test / cert.Test / cert.Concrete Sub-floor Test ReportResilient Flooring09 65 00 1.4.F · PDF p. 495
Spec wording
“F. Concrete Sub-floor Test Report: Submit a copy of the moisture and alkalinity (pH) test reports.”
09 65 00 1.4.F495–
O&MO&MMaintenance DataResilient Flooring09 65 00 1.4.H · PDF p. 495
Spec wording
“H. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning, stripping, and re-waxing.”
09 65 00 1.4.H495–
Spare partsSpare partsMaintenance MaterialsResilient Flooring09 65 00 1.4.I · PDF p. 495
Spec wording
“I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Flooring Material: 5 percent or not less than one full carton of each type and color. 3) Extra Wall Base: 5 percent or not less than 1 full carton of each type and color.”
09 65 00 1.4.I495–
O&MO&MMaintenance DataFluid-Applied Flooring09 67 00 1.4.E · PDF p. 502
Spec wording
“E. Maintenance Data: Include maintenance procedures, recommended maintenance materials, procedures for stain removal, repairing surface, and suggested schedule for cleaning.”
09 67 00 1.4.E502–
Test / cert.Test / cert.Concrete Sub-floor Test ReportTile Carpeting09 68 13 1.4.F · PDF p. 506
Spec wording
“F. Concrete Sub-floor Test Report: Submit a copy of the moisture and alkalinity (pH) test reports.”
09 68 13 1.4.F506–
O&MO&MMaintenance DataTile Carpeting09 68 13 1.4.G · PDF p. 506
Spec wording
“G. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning.”
09 68 13 1.4.G506–
Spare partsSpare partsMaintenance MaterialsTile Carpeting09 68 13 1.4.H · PDF p. 506-507
Spec wording
“H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Carpet Tiles: Quantity equal to 5 percent of total installed of each color and pattern installed.”
09 68 13 1.4.H506-507–
O&MO&MMaintenance DataExterior Painting09 91 13 1.5.D · PDF p. 513
Spec wording
“D. Maintenance Data: Submit data including finish schedule showing where each product/color/finish was used, product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.”
09 91 13 1.5.D513–
Spare partsSpare partsMaintenance MaterialsExterior Painting09 91 13 1.5.E · PDF p. 513
Spec wording
“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Paint and Finish Materials: 1 gallon of each color; from the same product run, store where directed. 3) Label each container with color in addition to the manufacturer's label.”
09 91 13 1.5.E513–
O&MO&MMaintenance DataInterior Painting09 91 23 1.4.E · PDF p. 521
Spec wording
“E. Maintenance Data: Submit data including product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.”
09 91 23 1.4.E521–
Spare partsSpare partsMaintenance MaterialsInterior Painting09 91 23 1.4.F · PDF p. 521
Spec wording
“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Paint and Finish Materials: Fuurnish an additional 5 percent, but not less than 1 gallon of each color; from the same product run, store where directed. 3) Label each container with color in addition to the manufacturer's label.”
09 91 23 1.4.F521–

Division 10 Specialties 19 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Display Cases10 12 00 1.8.A · PDF p. 529
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
10 12 00 1.8.A529–
WarrantyWarrantyCorrect defective Work within a five year period after Date ...Display Cases10 12 00 1.8.B · PDF p. 529
Spec wording
“B. Correct defective Work within a five year period after Date of Substantial Completion.”
10 12 00 1.8.B529–
WarrantyWarrantyProvide five year manufacturer warranty against defects and in materials, ...Display Cases10 12 00 1.8.C · PDF p. 529
Spec wording
“C. Provide five year manufacturer warranty against defects and in materials, finish product and workmanship.”
10 12 00 1.8.C529–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsDisplay Cases10 12 00 3.4.A · PDF p. 532
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
10 12 00 3.4.A532–
Spare partsSpare partsMaintenance MaterialsSignage10 14 00 1.3.G · PDF p. 533
Spec wording
“G. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.”
10 14 00 1.3.G533–
O&MO&MMaintenance DataFolding Panel Partitions10 22 39 1.4.H · PDF p. 542
Spec wording
“H. Maintenance Data: Include recommended cleaning methods, cleaning materials, and stain removal methods. Describe cleaning materials detrimental to finish surfaces and hardware finish.”
10 22 39 1.4.H542–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Folding Panel Partitions10 22 39 1.7.A · PDF p. 542
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
10 22 39 1.7.A542–
WarrantyWarrantyCorrect defective Work within five year period after Date of ...Folding Panel Partitions10 22 39 1.7.B · PDF p. 542
Spec wording
“B. Correct defective Work within five year period after Date of Substantial Completion.”
10 22 39 1.7.B542–
WarrantyWarrantyProvide two year manufacturer warranty against defects in material and ...Folding Panel Partitions10 22 39 1.7.C · PDF p. 542
Spec wording
“C. Provide two year manufacturer warranty against defects in material and workmanship, excluding abuse.”
10 22 39 1.7.C542–
TrainingTrainingDemonstrate operation of partition and identify potential operational problems ...Folding Panel Partitions10 22 39 3.5.A · PDF p. 545
Spec wording
“A. Demonstrate operation of partition and identify potential operational problems.”
10 22 39 3.5.A545–
WarrantyWarrantyWarranty DocumentationWall And Door Protection10 26 00 1.4.F · PDF p. 547
Spec wording
“F. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
10 26 00 1.4.F547–
Spare partsSpare partsMaintenance MaterialsWall And Door Protection10 26 00 1.4.G · PDF p. 547
Spec wording
“G. Maintenance Materials: Furnish the following for Owner's use in maintenance of project: 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Stock Materials: Three units minimum 96 inches long unit of each kind of covers for corner guards, bumper rails, and protective corridor handrails from same production run as installed materials. 3) Extra Stock Materials: 5 percent extra of ...”
10 26 00 1.4.G547–
O&MO&MMaintenance DataWall And Door Protection10 26 00 1.4.H · PDF p. 547
Spec wording
“H. Maintenance Data: For each type of product . Include information regarding recommended and potentially detrimental cleaning materials and methods.”
10 26 00 1.4.H547–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Wall And Door Protection10 26 00 1.6.A · PDF p. 547
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
10 26 00 1.6.A547–
WarrantyWarrantyProvide five year manufacturer and installer warranty for metal crash ...Wall And Door Protection10 26 00 1.6.B · PDF p. 547
Spec wording
“B. Provide five year manufacturer and installer warranty for metal crash rails.”
10 26 00 1.6.B547–
O&MO&MMaintenance DataFire Protection Specialties10 44 00 1.4.F · PDF p. 564
Spec wording
“F. Maintenance Data: Include test, refill or recharge schedules and re-certification requirements.”
10 44 00 1.4.F564–
O&MO&MOperation and Maintenance DataGround Set Flagpoles10 75 16 1.4.A · PDF p. 571
Spec wording
“A. Operation and Maintenance Data: For flagpoles to include in operation and maintenance manuals.”
10 75 16 1.4.A571–
WarrantyWarrantyWarranty DocumentationGround Set Flagpoles10 75 16 1.6.C · PDF p. 571
Spec wording
“C. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
10 75 16 1.6.C571–
WarrantyWarrantyProduct shall carry a minimum 5-year guarantee against manufacturer's defect ...Bird Control Devices10 81 13 1.6.A · PDF p. 575
Spec wording
“A. Product shall carry a minimum 5-year guarantee against manufacturer's defect and U.V. breakdown.”
10 81 13 1.6.A575–

Division 12 Furnishings 2 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test ReportsCountertops12 36 00 1.4.F · PDF p. 579
Spec wording
“F. Test Reports: Chemical resistance testing, showing compliance with specified requirements.”
12 36 00 1.4.F579–
O&MO&MMaintenance DataCountertops12 36 00 1.4.I · PDF p. 579
Spec wording
“I. Maintenance Data: Manufacturer's instructions and recommendations for maintenance and repair of countertop surfaces.”
12 36 00 1.4.I579–

Division 21 Fire suppression (sprinklers) 5 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Field quality control test reportsVibration And Seismic Controls For Fire Suppression Piping And21 05 48 1.6.F · PDF p. 586
Spec wording
“F. Field quality control test reports.”
21 05 48 1.6.F586–
Test / cert.Test / cert.Provide manufacturer representative or authorized technician services to assist with ...Vibration And Seismic Controls For Fire Suppression Piping And21 05 48 3.4.C · PDF p. 590
Spec wording
“C. Provide manufacturer representative or authorized technician services to assist with inspection and testing of vibration isolation systems and seismic controls. Submit a detailed copy of manufacturer recommended inspection, testing, and field report procedures.”
21 05 48 3.4.C590–
Test / cert.Test / cert.Submit detailed reports indicating inspection and testing results and corrective ...Vibration And Seismic Controls For Fire Suppression Piping And21 05 48 3.4.E · PDF p. 591
Spec wording
“E. Submit detailed reports indicating inspection and testing results and corrective actions taken.”
21 05 48 3.4.E591–
Spare partsSpare partsMaintenance MaterialsFire-Suppression Sprinkler Systems21 13 00 1.3.D · PDF p. 592
Spec wording
“D. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Sprinklers: Type and size matching those installed, in quantity required by referenced NFPA design and installation standard. 3) Sprinkler Wrenches: For each sprinkler type.”
21 13 00 1.3.D592–
Record docsRecord docsProject Record DocumentsFire-Suppression Sprinkler Systems21 13 00 1.3.E · PDF p. 592
Spec wording
“E. Project Record Documents: Record actual locations of sprinklers and deviations of piping from drawings. Indicate drain and test locations.”
21 13 00 1.3.E592–

Division 22 Plumbing 2 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Provide manufacturer representative or authorized technician services to assist with ...Vibration And Seismic Controls For Plumbing Piping And22 05 48 3.3.C · PDF p. 615
Spec wording
“C. Provide manufacturer representative or authorized technician services to assist with inspection and testing of vibration isolation systems and seismic controls. Submit a detailed copy of manufacturer recommended inspection, testing, and field report proceures.”
22 05 48 3.3.C615–
Test / cert.Test / cert.Submit detailed reports indicating inspection and testing results and corrective ...Vibration And Seismic Controls For Plumbing Piping And22 05 48 3.3.E · PDF p. 615
Spec wording
“E. Submit detailed reports indicating inspection and testing results and corrective actions taken.”
22 05 48 3.3.E615–

Division 23 HVAC 22 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MFinal ReportTesting, Adjusting, And Balancing For Hvac23 05 93 1.3.B · PDF p. 670
Spec wording
“B. Final Report: Indicate deficiencies in systems that would prevent proper testing, adjusting, and balancing of systems and equipment to achieve specified performance. 1) Revise TAB plan to reflect actual procedures and submit as part of final report. 2) Submit draft copies of report for review prior to final acceptance of Project. Provide final copies for Architect and for inclusion in operating and maintenance ...”
23 05 93 1.3.B670–
Closeout stepCloseout stepMark on drawings the locations where traverse and other critical ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.4.C · PDF p. 672
Spec wording
“C. Mark on drawings the locations where traverse and other critical measurements were taken and cross reference the location in the final report.”
23 05 93 3.4.C672–
O&MO&MMaintenance DataHvac Power Ventilators23 34 23 1.3.D · PDF p. 732
Spec wording
“D. Maintenance Data: Include instructions for lubrication, motor and drive replacement, spare parts list, and wiring diagrams.”
23 34 23 1.3.D732–
Spare partsSpare partsMaintenance MaterialsHvac Power Ventilators23 34 23 1.3.E · PDF p. 732
Spec wording
“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Fan Belts: One set for each individual fan.”
23 34 23 1.3.E732One set
Test / cert.Test / cert.Field quality-control reportsHigh-Efficiency Particulate Filtration23 41 33 1.3.A · PDF p. 744
Spec wording
“A. Field quality-control reports.”
23 41 33 1.3.A744–
O&MO&MOperation and Maintenance DataHigh-Efficiency Particulate Filtration23 41 33 1.4.A · PDF p. 744
Spec wording
“A. Operation and Maintenance Data: For each type of filter and rack to include in emergency, operation, and maintenance manuals.”
23 41 33 1.4.A744–
Spare partsSpare partsFurnish extra materials that match products installed and that are ...High-Efficiency Particulate Filtration23 41 33 1.5.A · PDF p. 744
Spec wording
“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1) Provide one complete set(s) of filters for each filter bank. If system includes prefilters, provide only prefilters.”
23 41 33 1.5.A744one complete set
Test / cert.Test / cert.Prepare test and inspection reportsHigh-Efficiency Particulate Filtration23 41 33 3.2.C · PDF p. 746
Spec wording
“C. Prepare test and inspection reports.”
23 41 33 3.2.C746–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Modular Indoor Central-Station Air-Handling Units23 73 13 1.8.A · PDF p. 749
Spec wording
“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.”
23 73 13 1.8.A749–
WarrantyWarrantyProvide minimum one year manufacturer warranty covering repair or replacement ...Modular Indoor Central-Station Air-Handling Units23 73 13 1.8.B · PDF p. 749
Spec wording
“B. Provide minimum one year manufacturer warranty covering repair or replacement due to defective materials or workmanship.”
23 73 13 1.8.B749–
Test / cert.Test / cert.Prepare and start equipment and systems in accordance with manufacturers' ...Modular Indoor Central-Station Air-Handling Units23 73 13 3.2.K · PDF p. 756
Spec wording
“K. Prepare and start equipment and systems in accordance with manufacturers' instructions and recommendations.”
23 73 13 3.2.K756–
Test / cert.Test / cert.Adjust for proper operation within manufacturer's published tolerancesModular Indoor Central-Station Air-Handling Units23 73 13 3.2.L · PDF p. 756
Spec wording
“L. Adjust for proper operation within manufacturer's published tolerances.”
23 73 13 3.2.L756–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals for closeout submittalsModular Indoor Central-Station Air-Handling Units23 73 13 3.3.M · PDF p. 756
Spec wording
“M. See Section 01 7800 - Closeout Submittals for closeout submittals.”
23 73 13 3.3.M756–
O&MO&MTrainingModular Indoor Central-Station Air-Handling Units23 73 13 3.3.N · PDF p. 756
Spec wording
“N. Training: Train Owner's personnel on operation and maintenance of system. 1) Use operation and maintenance manual as training reference, supplemented with additional training materials as required. 2) Provide minimum of two hours of training.”
23 73 13 3.3.N756–
O&MO&MOperation And Maintenance DataDedicated Outdoor Air Units23 74 33 1.3.D · PDF p. 757
Spec wording
“D. Operation And Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listing.”
23 74 33 1.3.D757–
WarrantyWarrantyWarrantyDedicated Outdoor Air Units23 74 33 1.3.E · PDF p. 757
Spec wording
“E. Warranty: Submit manufacturers warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.”
23 74 33 1.3.E757–
Spare partsSpare partsMaintenance MaterialsDedicated Outdoor Air Units23 74 33 1.3.F · PDF p. 757
Spec wording
“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements for additional provisions. 2) Extra Filters: One set of each type and size.”
23 74 33 1.3.F757One set
WarrantyWarrantySee Section 01 7800 - Closeout Submittals for additional warranty ...Dedicated Outdoor Air Units23 74 33 1.4.A · PDF p. 758
Spec wording
“A. See Section 01 7800 - Closeout Submittals for additional warranty requirements.”
23 74 33 1.4.A758–
O&MO&MOperation and Maintenance DataConvection Heating And Cooling Units23 82 00 1.4.E · PDF p. 762
Spec wording
“E. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listings.”
23 82 00 1.4.E762–
WarrantyWarrantyWarrantyConvection Heating And Cooling Units23 82 00 1.4.F · PDF p. 762
Spec wording
“F. Warranty: Submit manufacturer's warranty and ensure forms have been completed in Owner's name and registered with manufacturer.”
23 82 00 1.4.F762–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Convection Heating And Cooling Units23 82 00 1.6.A · PDF p. 762
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
23 82 00 1.6.A762–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsConvection Heating And Cooling Units23 82 00 3.4.A · PDF p. 763
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
23 82 00 3.4.A763–

Division 26 Electrical 65 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.At completion of work, provide written certification that all systems ...Basic Electrical Requirements26 00 10 3.4.B · PDF p. 776
Spec wording
“B. At completion of work, provide written certification that all systems are functioning properly without defects.”
26 00 10 3.4.B776–
Test / cert.Test / cert.Assign a Start-Up Coordinator to this projectBasic Electrical Requirements26 00 10 3.5.A · PDF p. 776
Spec wording
“A. Assign a Start-Up Coordinator to this project.”
26 00 10 3.5.A776–
Test / cert.Test / cert.The Start-Up Coordinator shall develop detailed start-up procedures, equipment checkout ...Basic Electrical Requirements26 00 10 3.5.B · PDF p. 776
Spec wording
“B. The Start-Up Coordinator shall develop detailed start-up procedures, equipment checkout procedure and data forms for recording compliance with contract document performance criteria, and will assist in developing schedules for checkout and Owner acceptance.”
26 00 10 3.5.B776–
Test / cert.Test / cert.The Start-Up Coordinator shall be responsible for maintaining documentation of ...Basic Electrical Requirements26 00 10 3.5.C · PDF p. 776
Spec wording
“C. The Start-Up Coordinator shall be responsible for maintaining documentation of Start-Up activities until final acceptance of the project.”
26 00 10 3.5.C776–
Test / cert.Test / cert.The documentation shall be kept current by the Start-Up Coordinator ...Basic Electrical Requirements26 00 10 3.5.D · PDF p. 776-777
Spec wording
“D. The documentation shall be kept current by the Start-Up Coordinator and shall be available for inspection at all times. At the time of acceptance of the project, the Start-Up Coordinator shall surrender 3 completed copies of the documentation to the Owner's representative. 1) Coordinate with the mechanical installation the requirements for the startup of mechanical and plumbing systems: a. All equipment, ...”
26 00 10 3.5.D776-777–
TrainingTrainingRefer to Division 1 sections of the specifications regarding requirements ...Basic Electrical Requirements26 00 10 3.6.A · PDF p. 777
Spec wording
“A. Refer to Division 1 sections of the specifications regarding requirements of Record Drawings, Operation and Maintenance Manual submittal and systems training. 1) Demonstrate that each system operates properly. 2) Explain the operation of each system to the Owner's Representative. 3) Explain use of O&M manual in operating and maintaining systems. 4) Date, time, and duration of training will be determined by ...”
26 00 10 3.6.A777DVD
TrainingTrainingFor specific systems requiring extended instruction, refer to individual Division ...Basic Electrical Requirements26 00 10 3.6.B · PDF p. 777
Spec wording
“B. For specific systems requiring extended instruction, refer to individual Division 26 sections.”
26 00 10 3.6.B777–
Record docsRecord docsProject Record DocumentsLow-Voltage Electrical Power Conductors And Cables26 05 19 1.5.C · PDF p. 779
Spec wording
“C. Project Record Documents: Record actual installed circuiting arrangements. Record actual routing for underground circuits.”
26 05 19 1.5.C779–
Test / cert.Test / cert.Field quality control test reportsGrounding And Bonding For Electrical Systems26 05 26 1.5.D · PDF p. 789
Spec wording
“D. Field quality control test reports.”
26 05 26 1.5.D789–
Record docsRecord docsProject Record DocumentsGrounding And Bonding For Electrical Systems26 05 26 1.5.E · PDF p. 789
Spec wording
“E. Project Record Documents: Record actual locations of grounding electrode system components and connections.”
26 05 26 1.5.E789–
Test / cert.Test / cert.Submit detailed reports indicating inspection and testing results and corrective ...Grounding And Bonding For Electrical Systems26 05 26 3.3.F · PDF p. 791
Spec wording
“F. Submit detailed reports indicating inspection and testing results and corrective actions taken.”
26 05 26 3.3.F791–
Record docsRecord docsProject Record DocumentsConduit For Electrical Systems26 05 33.13 1.5.D · PDF p. 802
Spec wording
“D. Project Record Documents: Record actual routing for conduits installed underground, conduits embedded within concrete slabs, and conduits 2 inch (53 mm) trade size and larger.”
26 05 33.13 1.5.D802–
Record docsRecord docsProject Record DocumentsBoxes26 05 33.16 1.5.E · PDF p. 815
Spec wording
“E. Project Record Documents: Record actual locations for outlet and device boxes, pull boxes, cabinets and enclosures, and floor boxes.”
26 05 33.16 1.5.E815–
Spare partsSpare partsMaintenance MaterialsBoxes26 05 33.16 1.5.F · PDF p. 815
Spec wording
“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Keys for Lockable Enclosures: Two of each different key.”
26 05 33.16 1.5.F815–
Test / cert.Test / cert.Field Quality Control ReportsLighting Control Devices26 09 23 1.5.E · PDF p. 833
Spec wording
“E. Field Quality Control Reports.”
26 09 23 1.5.E833–
O&MO&MOperation and Maintenance DataLighting Control Devices26 09 23 1.5.G · PDF p. 833
Spec wording
“G. Operation and Maintenance Data: Include detailed information on device programming and setup.”
26 09 23 1.5.G833–
Spare partsSpare partsMaintenance MaterialsLighting Control Devices26 09 23 1.5.H · PDF p. 833
Spec wording
“H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Locking Receptacle-Mounted Outdoor Photo Controls: Five percent of total quantity installed for each type, but not less than two of each type.”
26 09 23 1.5.H833–
Record docsRecord docsProject Record DocumentsLighting Control Devices26 09 23 1.5.I · PDF p. 833
Spec wording
“I. Project Record Documents: Record actual installed locations and settings for lighting control devices.”
26 09 23 1.5.I833–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Lighting Control Devices26 09 23 1.9.A · PDF p. 834
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
26 09 23 1.9.A834–
WarrantyWarrantyProvide five year manufacturer warranty for all occupancy sensorsLighting Control Devices26 09 23 1.9.B · PDF p. 834
Spec wording
“B. Provide five year manufacturer warranty for all occupancy sensors.”
26 09 23 1.9.B834–
WarrantyWarrantyProvide five year manufacturer warranty for utility grade locking receptacle-mounted ...Lighting Control Devices26 09 23 1.9.C · PDF p. 834
Spec wording
“C. Provide five year manufacturer warranty for utility grade locking receptacle-mounted outdoor photo controls.”
26 09 23 1.9.C834–
WarrantyWarrantyProvide two year manufacturer warranty for all daylighting controlsLighting Control Devices26 09 23 1.9.D · PDF p. 834
Spec wording
“D. Provide two year manufacturer warranty for all daylighting controls.”
26 09 23 1.9.D834–
Test / cert.Test / cert.Test occupancy sensors to verify proper operation, including time delays ...Lighting Control Devices26 09 23 3.4.C · PDF p. 841
Spec wording
“C. Test occupancy sensors to verify proper operation, including time delays and ambient light thresholds where applicable. Verify optimal coverage for entire room or area. Record test results in written report to be included with submittals.”
26 09 23 3.4.C841–
Test / cert.Test / cert.Test daylighting controls to verify proper operation, including light level ...Lighting Control Devices26 09 23 3.4.F · PDF p. 841
Spec wording
“F. Test daylighting controls to verify proper operation, including light level measurements and time delays where applicable. Record test results in written report to be included with submittals.”
26 09 23 3.4.F841–
Record docsRecord docsAdjust time switch settings to achieve desired operation schedule as ...Lighting Control Devices26 09 23 3.5.E · PDF p. 842
Spec wording
“E. Adjust time switch settings to achieve desired operation schedule as indicated or as directed by Architect. Record settings in written report to be included with submittals.”
26 09 23 3.5.E842–
Record docsRecord docsAdjust daylighting controls under optimum lighting conditions after all room ...Lighting Control Devices26 09 23 3.5.G · PDF p. 842
Spec wording
“G. Adjust daylighting controls under optimum lighting conditions after all room finishes, furniture, and window treatments have been installed to achieve desired operation as indicated or as directed by Architect. Record settings in written report to be included with submittals. Readjust controls calibrated prior to installation of final room finishes, furniture, and window treatments that do not function properly ...”
26 09 23 3.5.G842–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsLighting Control Devices26 09 23 3.7.A · PDF p. 842
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
26 09 23 3.7.A842–
TrainingTrainingSee Section 01 7900 - Demonstration and Training, for additional ...Lighting Control Devices26 09 23 3.7.B · PDF p. 842
Spec wording
“B. See Section 01 7900 - Demonstration and Training, for additional requirements.”
26 09 23 3.7.B842–
TrainingTrainingDemonstrationLighting Control Devices26 09 23 3.7.C · PDF p. 842
Spec wording
“C. Demonstration: Demonstrate proper operation of lighting control devices to Architect, and correct deficiencies or make adjustments as directed.”
26 09 23 3.7.C842–
O&MO&MTrainingLighting Control Devices26 09 23 3.7.D · PDF p. 842-843
Spec wording
“D. Training: Train Owner's personnel on operation, adjustment, programming, and maintenance of lighting control devices. 1) Use operation and maintenance manual as training reference, supplemented with additional training materials as required. 2) Provide minimum of two hours of training. 3) Instructor: Qualified contractor familiar with the project and with sufficient knowledge of the installed lighting control ...”
26 09 23 3.7.D842-843–
Test / cert.Test / cert.Field Quality Control Test ReportsPanelboards26 24 16 1.5.E · PDF p. 846
Spec wording
“E. Field Quality Control Test Reports.”
26 24 16 1.5.E846–
Record docsRecord docsProject Record DocumentsPanelboards26 24 16 1.5.G · PDF p. 846
Spec wording
“G. Project Record Documents: Record actual installed locations of panelboards and actual installed circuiting arrangements.”
26 24 16 1.5.G846–
O&MO&MMaintenance DataPanelboards26 24 16 1.5.H · PDF p. 846
Spec wording
“H. Maintenance Data: Include information on replacement parts and recommended maintenance procedures and intervals.”
26 24 16 1.5.H846–
Spare partsSpare partsMaintenance MaterialsPanelboards26 24 16 1.5.I · PDF p. 846
Spec wording
“I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Panelboard Keys: Two of each different key. 3) See Section 26 2813 for requirements for spare fuses and spare fuse cabinets.”
26 24 16 1.5.I846–
Test / cert.Test / cert.Procure services of a qualified manufacturer's representative to observe installation ...Panelboards26 24 16 3.3.H · PDF p. 852
Spec wording
“H. Procure services of a qualified manufacturer's representative to observe installation and assist in inspection, testing, and adjusting. Include manufacturer's reports with field quality control submittals.”
26 24 16 3.3.H852–
O&MO&MOperation and Maintenance DataWiring Devices26 27 26 1.5.C · PDF p. 854
Spec wording
“C. Operation and Maintenance Data: 1) Wall Dimmers: Include information on operation and setting of presets. 2) GFCI Receptacles: Include information on status indicators.”
26 27 26 1.5.C854–
Record docsRecord docsProject Record DocumentsWiring Devices26 27 26 1.5.D · PDF p. 854
Spec wording
“D. Project Record Documents: Record actual installed locations of wiring devices.”
26 27 26 1.5.D854–
Spare partsSpare partsMaintenance MaterialsWiring Devices26 27 26 1.5.E · PDF p. 854
Spec wording
“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions.”
26 27 26 1.5.E854–
Spare partsSpare partsMaintenance MaterialsFuses26 28 13 1.5.C · PDF p. 862-863
Spec wording
“C. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Fuses: One set(s) of three for each type and size installed. 3) Fuse Pullers: One set(s) compatible with each type and size installed. 4) Spare Fuse Cabinet Keys: Two.”
26 28 13 1.5.C862-863One set
Test / cert.Test / cert.Field Quality Control Test ReportsEnclosed Switches26 28 16.16 1.5.D · PDF p. 866
Spec wording
“D. Field Quality Control Test Reports.”
26 28 16.16 1.5.D866–
Record docsRecord docsProject Record DocumentsEnclosed Switches26 28 16.16 1.5.F · PDF p. 866
Spec wording
“F. Project Record Documents: Record actual locations of enclosed switches.”
26 28 16.16 1.5.F866–
O&MO&MMaintenance DataEnclosed Switches26 28 16.16 1.5.G · PDF p. 866
Spec wording
“G. Maintenance Data: Include information on replacement parts and recommended maintenance procedures and intervals.”
26 28 16.16 1.5.G866–
Spare partsSpare partsMaintenance MaterialsEnclosed Switches26 28 16.16 1.5.H · PDF p. 866
Spec wording
“H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions.”
26 28 16.16 1.5.H866–
Test / cert.Test / cert.Field quality control reportsInterior Lighting26 51 00 1.5.G · PDF p. 873
Spec wording
“G. Field quality control reports.”
26 51 00 1.5.G873–
O&MO&MOperation and Maintenance DataInterior Lighting26 51 00 1.5.I · PDF p. 873
Spec wording
“I. Operation and Maintenance Data: Instructions for each product including information on replacement parts.”
26 51 00 1.5.I873–
Spare partsSpare partsMaintenance MaterialsInterior Lighting26 51 00 1.5.J · PDF p. 873-874
Spec wording
“J. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Lenses and Louvers: Two percent of total quantity installed for each type, but not less than one of each type. 3) Extra Lamps: Ten percent of total quantity installed for each type, but not less than two of each type. 4) Extra Ballasts: Two ...”
26 51 00 1.5.J873-874–
Record docsRecord docsProject Record DocumentsInterior Lighting26 51 00 1.5.K · PDF p. 874
Spec wording
“K. Project Record Documents: Record actual connections and locations of luminaires and any associated remote components.”
26 51 00 1.5.K874–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Interior Lighting26 51 00 1.9.A · PDF p. 874
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
26 51 00 1.9.A874–
WarrantyWarrantyProvide three year manufacturer warranty for all LED luminaires, including ...Interior Lighting26 51 00 1.9.B · PDF p. 874
Spec wording
“B. Provide three year manufacturer warranty for all LED luminaires, including drivers.”
26 51 00 1.9.B874–
WarrantyWarrantyProvide two year manufacturer warranty for all linear fluorescent ballasts ...Interior Lighting26 51 00 1.9.C · PDF p. 874
Spec wording
“C. Provide two year manufacturer warranty for all linear fluorescent ballasts.”
26 51 00 1.9.C874–
WarrantyWarrantyProvide five year pro-rata warranty for batteries for emergency lighting ...Interior Lighting26 51 00 1.9.D · PDF p. 874
Spec wording
“D. Provide five year pro-rata warranty for batteries for emergency lighting units.”
26 51 00 1.9.D874–
WarrantyWarrantyProvide ten year pro-rata warranty for batteries for self-powered exit ...Interior Lighting26 51 00 1.9.E · PDF p. 874
Spec wording
“E. Provide ten year pro-rata warranty for batteries for self-powered exit signs.”
26 51 00 1.9.E874–
WarrantyWarrantyProvide three year full warranty for fluorescent emergency power supply ...Interior Lighting26 51 00 1.9.F · PDF p. 874
Spec wording
“F. Provide three year full warranty for fluorescent emergency power supply units.”
26 51 00 1.9.F874–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsInterior Lighting26 51 00 3.7.A · PDF p. 880
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
26 51 00 3.7.A880–
TrainingTrainingSee Section 01 7900 - Demonstration and Training, for additional ...Interior Lighting26 51 00 3.7.B · PDF p. 880
Spec wording
“B. See Section 01 7900 - Demonstration and Training, for additional requirements.”
26 51 00 3.7.B880–
TrainingTrainingDemonstrationInterior Lighting26 51 00 3.7.C · PDF p. 880
Spec wording
“C. Demonstration: Demonstrate proper operation of luminaires to Architect, and correct deficiencies or make adjustments as directed.”
26 51 00 3.7.C880–
Closeout stepCloseout stepJust prior to Substantial Completion, replace all lamps that have ...Interior Lighting26 51 00 3.7.D · PDF p. 880
Spec wording
“D. Just prior to Substantial Completion, replace all lamps that have failed.”
26 51 00 3.7.D880–
Test / cert.Test / cert.Field Quality Control Reports. 1) Include test report indicating measured ...Exterior Lighting26 56 00 1.5.G · PDF p. 883
Spec wording
“G. Field Quality Control Reports. 1) Include test report indicating measured illumination levels.”
26 56 00 1.5.G883–
O&MO&MOperation and Maintenance DataExterior Lighting26 56 00 1.5.I · PDF p. 883
Spec wording
“I. Operation and Maintenance Data: Instructions for each product including information on replacement parts.”
26 56 00 1.5.I883–
Spare partsSpare partsMaintenance MaterialsExterior Lighting26 56 00 1.5.J · PDF p. 883
Spec wording
“J. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1) See Section 01 6000 - Product Requirements, for additional provisions. 2) Extra Lamps: Ten percent of total quantity installed for each type, but not less than two of each type. 3) Extra Ballasts: Two percent of total quantity installed for each type, but not less than one of each type. 4) Extra LED drivers: Ten percent of ...”
26 56 00 1.5.J883–
Record docsRecord docsProject Record DocumentsExterior Lighting26 56 00 1.5.K · PDF p. 883
Spec wording
“K. Project Record Documents: Record actual connections and locations of pole foundations, luminaires, and any pull or junction boxes.”
26 56 00 1.5.K883–
WarrantyWarrantySee Section 01 7800 - Closeout Submittals, for additional warranty ...Exterior Lighting26 56 00 1.8.A · PDF p. 884
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.”
26 56 00 1.8.A884–
WarrantyWarrantyProvide three year manufacturer warranty for all LED luminaires, including ...Exterior Lighting26 56 00 1.8.B · PDF p. 884
Spec wording
“B. Provide three year manufacturer warranty for all LED luminaires, including drivers.”
26 56 00 1.8.B884–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsExterior Lighting26 56 00 3.7.A · PDF p. 888
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
26 56 00 3.7.A888–
Closeout stepCloseout stepJust prior to Substantial Completion, replace all lamps that have ...Exterior Lighting26 56 00 3.7.B · PDF p. 888
Spec wording
“B. Just prior to Substantial Completion, replace all lamps that have failed.”
26 56 00 3.7.B888–

Division 31 Earthwork 3 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Field Quality Control SubmittalsExcavation31 23 16 1.3.B · PDF p. 891
Spec wording
“B. Field Quality Control Submittals: Document visual inspection of load-bearing excavated surfaces.”
31 23 16 1.3.B891–
Test / cert.Test / cert.Compaction Density Test ReportsTrenching31 23 16.13 1.5.B · PDF p. 894
Spec wording
“B. Compaction Density Test Reports.”
31 23 16.13 1.5.B894–
Test / cert.Test / cert.Compaction Density Test ReportsFill31 23 23 1.5.B · PDF p. 898
Spec wording
“B. Compaction Density Test Reports.”
31 23 23 1.5.B898–

Division 32 Paving and site improvements 18 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Aggregate Composition Test ReportsAggregate Base Courses32 11 23 1.4.C · PDF p. 902
Spec wording
“C. Aggregate Composition Test Reports: Results of laboratory tests on proposed and actual materials used.”
32 11 23 1.4.C902–
WarrantyWarrantyManufacturer's WarrantyDecorative Metal Fences And Gates32 31 19 1.3.D · PDF p. 909
Spec wording
“D. Manufacturer's Warranty.”
32 31 19 1.3.D909–
Closeout stepCloseout stepSee Section 01 7800 - Closeout Submittals, for closeout submittalsDecorative Metal Fences And Gates32 31 19 3.6.A · PDF p. 914
Spec wording
“A. See Section 01 7800 - Closeout Submittals, for closeout submittals.”
32 31 19 3.6.A914–
TrainingTrainingSee Section 01 7900 - Demonstration and Training, for additional ...Decorative Metal Fences And Gates32 31 19 3.6.B · PDF p. 914
Spec wording
“B. See Section 01 7900 - Demonstration and Training, for additional requirements.”
32 31 19 3.6.B914–
TrainingTrainingDemonstrate proper operation of equipment to Owner's designated representative ...Decorative Metal Fences And Gates32 31 19 3.6.C · PDF p. 914
Spec wording
“C. Demonstrate proper operation of equipment to Owner's designated representative.”
32 31 19 3.6.C914–
O&MO&MDemonstrationDecorative Metal Fences And Gates32 31 19 3.6.D · PDF p. 914
Spec wording
“D. Demonstration: Demonstrate operation of system to Owner's personnel. 1) Use operation and maintenance data as reference during demonstration. 2) Conduct walking tour of project. 3) Briefly describe function, operation, and maintenance of each component.”
32 31 19 3.6.D914–
O&MO&MTrainingDecorative Metal Fences And Gates32 31 19 3.6.E · PDF p. 914
Spec wording
“E. Training: Train Owner's personnel on operation and maintenance of system. 1) Use operation and maintenance manual as training reference, supplemented with additional training materials as required. 2) Provide minimum of two hours of training.”
32 31 19 3.6.E914–
Test / cert.Test / cert.Initial Soil SubmittalsLandscape Soil Preparation32 91 15 1.7.A · PDF p. 918
Spec wording
“A. Initial Soil Submittals: 1) Samples – For each bulk-supplied material in sealed containers labeled with content, source, and date obtained: providing an accurate representation of composition, color and texture. 2) Test Reports – For each bulk-supplied material as outlined in the Test Procedures and Reporting section. 3) Soil Analysis – Provide Initial Planting Soil Analysis for bulk-supplied material as ...”
32 91 15 1.7.A918–
Test / cert.Test / cert.Amended Soil MixesLandscape Soil Preparation32 91 15 1.7.B · PDF p. 918
Spec wording
“B. Amended Soil Mixes: 1) Samples – For each specified type of amended soil. 2) Test Reports – For each amended soil mix as outlined in the Test Procedures and Reporting section. 3) Soil Analysis – Provide Amended Planting Soil Analysis for each amended soil mix as outlined in the Test Procedures and Reporting section.”
32 91 15 1.7.B918–
Test / cert.Test / cert.Prepare test and inspection reportsLandscape Soil Preparation32 91 15 3.4.C · PDF p. 925
Spec wording
“C. Prepare test and inspection reports.”
32 91 15 3.4.C925–
Test / cert.Test / cert.Label each sample and test report with the date, location ...Landscape Soil Preparation32 91 15 3.4.D · PDF p. 925
Spec wording
“D. Label each sample and test report with the date, location keyed to a site plan or other location system, visible conditions when and where sample was taken, and sampling depth.”
32 91 15 3.4.D925–
O&MO&MMaintenance ManualTurf32 92 00 1.4.F · PDF p. 928-929
Spec wording
“F. Maintenance Manual: As part of awarding Substantial Completion Approval contractor shall provide to the owner and Landscape Architect a maintenance manual which consists of the following: 1) Contact information for the installation contractor company, company owner, and project foreman for both the installation and maintenance. 2) Installation date(s) of the work or phases of work as well as a copy of the ...”
32 92 00 1.4.F928-929hardcopy; binder; digital file
WarrantyWarrantyGeneral WarrantyTurf32 92 00 1.9.A · PDF p. 931
Spec wording
“A. General Warranty: The special warranty specified in this Article shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by the Contractor under requirements of the Contract Documents.”
32 92 00 1.9.A931–
WarrantyWarrantySpecial WarrantyTurf32 92 00 1.9.B · PDF p. 931
Spec wording
“B. Special Warranty: Warrant the lawn's installed, living materials for a period of 90 days after date of Final Acceptance, against defects including death and unsatisfactory growth, except for defects resulting from lack of adequate maintenance, neglect, or abuse by Owner, abnormal weather conditions unusual for warranty period, or incidents beyond Contractor's control.”
32 92 00 1.9.B931–
WarrantyWarrantyWarranty/MaintenancePlant Material & Accessories32 93 00 1.3.C · PDF p. 938
Spec wording
“C. Warranty/Maintenance: Submit the following at the Final Completion Inspection: 1) Warranty: Provide a one (1) year written guarantee for all plant material. 2) Maintenance Instructions: Submit written recommendations procedures for landscape maintenance for one (1) calendar year.”
32 93 00 1.3.C938–
WarrantyWarrantySpecial WarrantyPlant Material & Accessories32 93 00 1.7.A · PDF p. 940-941
Spec wording
“A. Special Warranty: Installer agrees to repair or replace plantings and accessories that fail in materials, workmanship, or growth within specified warranty period. 1) Failures include, but are not limited to, the following: a. Death and unsatisfactory growth, except for defects resulting from abuse, lack of adequate maintenance, or neglect by Owner, or incidents that are beyond Contractor's control. b. Structural ...”
32 93 00 1.7.A940-941–
O&MO&MProject Close-out SubmittalLandscape Maintenance32 94 47 1.4.B · PDF p. 951
Spec wording
“B. Project Close-out Submittal: Prepare a landscape maintenance manual in the form of a single 3-ring binder containing an indexed collection of documents to i include the following: 1) All plant material and accessories schedules, including final plant installation schedule showing substitutions made. 2) Records and permits required as listed above. 3) Documentation of accepted condition of planting at Final ...”
32 94 47 1.4.B9513-ring; binder
WarrantyWarrantyFor specific requirements, refer to the following sectionsLandscape Maintenance32 94 47 1.8.A · PDF p. 952
Spec wording
“A. For specific requirements, refer to the following sections: 1) Section 32 9200 - Turf 2) Section 32 9300 - Plant Material & Accessories”
32 94 47 1.8.A952–

Division 33 Utilities 1 item

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsProject Record DocumentsStormwater Gravity Piping33 42 11 1.5.D · PDF p. 963
Spec wording
“D. Project Record Documents: 1) Record location of pipe runs, connections, catch basins, cleanouts, and invert elevations.”
33 42 11 1.5.D963–

Front end Contract conditions (final payment, releases, retainage) 12 items

TypeItemSpec sectionPDF pageCopies / format
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 31
Spec wording
“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...”
Conditions Of The Contract (Find Heading On The Cited Page)31–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 58
Spec wording
“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.”
Conditions Of The Contract (Find Heading On The Cited Page)58–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 59
Spec wording
“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.”
Conditions Of The Contract (Find Heading On The Cited Page)59three (4) copies
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 65
Spec wording
“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.”
Conditions Of The Contract (Find Heading On The Cited Page)65–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 66
Spec wording
“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...”
Conditions Of The Contract (Find Heading On The Cited Page)66–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 83
Spec wording
“The Contractor agrees to maintain all books, records and reports required under this contract for a period of not less than three years after final payment is made and all pending matters are closed. 17.0 Occupational Health and Safety Act All contracts and subcontracts that result from this solicitation incorporate by reference the requirements of 29 C.F.R. pt. 1910 with the same force and effect as if given in ...”
Conditions Of The Contract (Find Heading On The Cited Page)83–
WarrantyWarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 58
Spec wording
“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...”
Conditions Of The Contract ARTICLE.A58–
WarrantyWarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 58
Spec wording
“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.”
Conditions Of The Contract ARTICLE.B58–
O&MO&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 58-59
Spec wording
“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...”
Conditions Of The Contract ARTICLE.A58-59three (3) copies; three (4) copies
O&MO&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 59
Spec wording
“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...”
Conditions Of The Contract ARTICLE.B59binders; binder
O&MO&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 63-64
Spec wording
“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...”
Conditions Of The Contract ARTICLE.A63-64–
Test / cert.Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 64
Spec wording
“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...”
Conditions Of The Contract ARTICLE.C64–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.