Free closeout checklist · Federal job · North Dakota

Closeout checklist: Perform Site Prep for Sterile Processing (SPS) Equipment, Fargo VA Medical Center (U.S. Department of Veterans Affairs, ND)

Every closeout item we found in the public spec book for this job: 492 items across Division 01, 13 trade divisions, including 231 tests and certificates, 66 O&M manual items and 66 training items. Each one is tied to its spec section and the PDF page it sits on.

Owner
U.S. Department of Veterans Affairs, Network Contracting Office 23
Number
Solicitation 36C26325B0025, VA project 437-CSI-241
Location
Fargo, ND
Contract signed
2025-10-02
Public spec book
Solicitation notice on SAM.gov (spec book attached, marked public)
Spec book size
1,553 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

The spec book was posted in two volumes; this checklist covers both.

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

63Warranties
66O&M manuals
231Tests and certificates
66Training
51Record documents
10Spare parts
0Payment release
5Closeout steps

All 492 items, by trade

Division 01 General requirements 105 items

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsThe contractor must maintain two full size sets of as-built ...General01 00 00 1.15.A · PDF p. 38
Spec wording
“A. The contractor must maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.”
01 00 00 1.15.A38two full size sets
Record docsRecord docsAll variations must be shown in the same general detail ...General01 00 00 1.15.B · PDF p. 38
Spec wording
“B. All variations must be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings must be made available for the COR review, as often as requested.”
01 00 00 1.15.B38–
Record docsRecord docsContractor must deliver two approved completed sets of as-built drawings ...General01 00 00 1.15.C · PDF p. 38-39
Spec wording
“C. Contractor must deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR or, Chief Engineer, or Chief of Facilities Management within 21 calendar days after each completed phase and after the acceptance of the project by the COR.”
01 00 00 1.15.C38-39electronic version; PDF
Record docsRecord docsParagraphs A, B, & C must also apply to all shop drawingsGeneral01 00 00 1.15.D · PDF p. 39
Spec wording
“D. Paragraphs A, B, & C must also apply to all shop drawings.”
01 00 00 1.15.D39–
WarrantyWarrantyWarranty Management PlanGeneral01 00 00 1.16.A · PDF p. 39-41
Spec wording
“A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan ...”
01 00 00 1.16.A39-41one set; binder
WarrantyWarrantyPerformance & Payment BondsGeneral01 00 00 1.16.B · PDF p. 41-42
Spec wording
“B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period. 1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the ...”
01 00 00 1.16.B41-42–
WarrantyWarrantyPre-Warranty ConferenceGeneral01 00 00 1.16.C · PDF p. 42
Spec wording
“C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor must meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for ...”
01 00 00 1.16.C42–
WarrantyWarrantyContractor's Response to Construction Warranty Service Requirements. Must be as ...General01 00 00 1.16.D · PDF p. 43
Spec wording
“D. Contractor's Response to Construction Warranty Service Requirements. Must be as follows:”
01 00 00 1.16.D43–
WarrantyWarrantyFollowing oral or written notification by the Contracting Officer, the ...General01 00 00 1.16.E · PDF p. 43-45
Spec wording
“E. Following oral or written notification by the Contracting Officer, the Contractor must respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date ...”
01 00 00 1.16.E43-45–
WarrantyWarrantyWarranty TagsGeneral01 00 00 1.16.F · PDF p. 45-46
Spec wording
“F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for ...”
01 00 00 1.16.F45-46–
O&MO&MContractor must furnish Maintenance and Operating manuals (hard copies and ...General01 00 00 1.23.A · PDF p. 52
Spec wording
“A. Contractor must furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.”
01 00 00 1.23.A52–
O&MO&MManualsGeneral01 00 00 1.23.B · PDF p. 53
Spec wording
“B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment must be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals must be complete, detailed guides for the maintenance and operation of equipment. They must include complete information necessary for starting, adjusting, ...”
01 00 00 1.23.B53four hard copies; one electronic copy
TrainingTrainingInstructionsGeneral01 00 00 1.23.C · PDF p. 53-54
Spec wording
“C. Instructions: Contractor must provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of ...”
01 00 00 1.23.C53-54–
O&MO&MSubmit data specified for a given item within 30 calendar ...(Untitled)01 33 23 1.8.A · PDF p. 76
Spec wording
“A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.”
01 33 23 1.8.A76–
O&MO&MIn the event the Contractor fails to deliver O&M Data ...(Untitled)01 33 23 1.8.B · PDF p. 76
Spec wording
“B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.”
01 33 23 1.8.B76–
TrainingTrainingThe designated Prime Contractor SSHO must meet the requirements of ...Table Of Contents01 35 26 1.10.A · PDF p. 98
Spec wording
“A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project.”
01 35 26 1.10.A98–
TrainingTrainingAs a minimum the SSHO must have completed the OSHA ...Table Of Contents01 35 26 1.10.B · PDF p. 98
Spec wording
“B. As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety Outreach class within the past five (5) years and: 1. Seven (7) years of construction industry safety related experience. 2. OR have a safety and health degree from an accredited university or college and five (5) years of construction industry safety related experience 3. OR hold as current, a Certified Safety Professional (CSP) or a ...”
01 35 26 1.10.B98–
TrainingTrainingThe Alternate Safety Officer must meet, at a minimum, the ...Table Of Contents01 35 26 1.10.C · PDF p. 99
Spec wording
“C. The Alternate Safety Officer must meet, at a minimum, the requirements of EM 385-1-1 Section 1 and have five (5) years of construction industry safety experience If the SSHO does not have a current certification, certification must be obtained within 90 days, maximum, of contract award.”
01 35 26 1.10.C99–
TrainingTrainingAll designated CPs must have completed the OSHA 30-hour Construction ...Table Of Contents01 35 26 1.10.D · PDF p. 99
Spec wording
“D. All designated CPs must have completed the OSHA 30-hour Construction Safety course and/or EM 385-1-1 40-hour training within the past 5 years. In addition, all CPs with high hazard work operations (such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations) must have a specialized formal ...”
01 35 26 1.10.D99–
TrainingTrainingAll other construction workers must have the OSHA 10-hour Construction ...Table Of Contents01 35 26 1.10.E · PDF p. 99
Spec wording
“E. All other construction workers must have the OSHA 10-hour Construction Safety Outreach course within the past 5 years and any necessary safety training to be able to identify hazards within their work environment.”
01 35 26 1.10.E99–
TrainingTrainingSubmit training records associated with the above training requirements to ...Table Of Contents01 35 26 1.10.F · PDF p. 99
Spec wording
“F. Submit training records associated with the above training requirements to Facility Safety Officer or Contracting Officer Representative for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction safety conference for acceptance.”
01 35 26 1.10.F99–
TrainingTrainingPrior to any worker for the contractor or subcontractors beginning ...Table Of Contents01 35 26 1.10.G · PDF p. 99
Spec wording
“G. Prior to any worker for the contractor or subcontractors beginning work, they must undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, this briefing must include information on the site-specific hazards, construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, emergency procedures, accident ...”
01 35 26 1.10.G99–
TrainingTrainingOngoing safety training will be accomplished in the form of ...Table Of Contents01 35 26 1.10.H · PDF p. 99
Spec wording
“H. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.”
01 35 26 1.10.H99–
Test / cert.Test / cert.Government approval is required for all submittals. CQC inspection reports ...(Untitled)01 45 00 1.3 · PDF p. 129
Spec wording
“Government approval is required for all submittals. CQC inspection reports must be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Initial, or Follow-Up)]: [Applicable Specification section] naming convention. 1. Preconstruction Submittals a. Interim CQC Plan b. CQC Plan c. Additional Requirements for Design Quality Control (DQC) Plan 2. Design Data a. ...”
01 45 00 1.3129–
Test / cert.Test / cert.Personnel Requirements(Untitled)01 45 00 3.4.A · PDF p. 134
Spec wording
“A. Personnel Requirements: The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager (if applicable), and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager must satisfy the requirements of Specification 01 35 26 Safety Requirements and reports directly to a senior project (or ...”
01 45 00 3.4.A134–
Test / cert.Test / cert.CQC Personnel(Untitled)01 45 00 3.4.C · PDF p. 135-136
Spec wording
“C. CQC Personnel: In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist in the CQC System Manager for the following areas, as applicable: electrical, mechanical, civil, structural, environmental, architectural, materials technician submittals clerk, Commissioning Agent/LEED specialist, and low voltage systems. These individuals or ...”
01 45 00 3.4.C135-136–
Test / cert.Test / cert.Organizational Changes(Untitled)01 45 00 3.4.E · PDF p. 136-137
Spec wording
“E. Organizational Changes: Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer or Authorized designee for acceptance. 3.5 SUBMITTALS AND DELIVERABLES: Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Product Data, and Samples. The CQC ...”
01 45 00 3.4.E136-137–
Test / cert.Test / cert.Record on daily reports any problems in complying with laws, ...Temporary Environmental Controls01 57 19 1.2.B · PDF p. 168
Spec wording
“B. Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.”
01 57 19 1.2.B168–
TrainingTrainingIn accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT ...Temporary Environmental Controls01 57 19 1.4.A · PDF p. 168
Spec wording
“A. In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following: 1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor must meet with the Contracting Officer's Representative (COR) to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental ...”
01 57 19 1.4.A168–
Closeout stepCloseout stepCloseout Submittals(Untitled)01 81 13 1.5.G · PDF p. 188
Spec wording
“G. Closeout Submittals: Within 14 days after Substantial Completion provide the following: 1. Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet. 2. Manufacturer's cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction if permanently installed air handling units are used during construction. ...”
01 81 13 1.5.G188–
Test / cert.Test / cert.This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS must form ...(Untitled)01 91 00 1.1.A · PDF p. 199
Spec wording
“A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS must form the basis of the construction phase commissioning process and procedures. The Commissioning Agent must add, modify, and refine the commissioning procedures, as approved by the Department of Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed ...”
01 91 00 1.1.A199–
Test / cert.Test / cert.Various sections of the project specifications require equipment startup, testing, ...(Untitled)01 91 00 1.1.B · PDF p. 199
Spec wording
“B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the Division 7, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not ...”
01 91 00 1.1.B199–
Test / cert.Test / cert.Where individual testing, adjusting, or related services are required in ...(Untitled)01 91 00 1.1.C · PDF p. 199
Spec wording
“C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services must be provided and copies of documentation, as required by those specifications must be submitted to the VA and the Commissioning Agent to be indexed for future reference.”
01 91 00 1.1.C199–
Test / cert.Test / cert.Where training or educational services for VA are required and ...(Untitled)01 91 00 1.1.D · PDF p. 199
Spec wording
“D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 7, Division 8, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.”
01 91 00 1.1.D199–
Test / cert.Test / cert.Commissioning is a systematic process of verifying that the building ...(Untitled)01 91 00 1.1.E · PDF p. 199-200
Spec wording
“E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA's operational needs. The commissioning process must encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy ...”
01 91 00 1.1.E199-200–
Test / cert.Test / cert.The commissioning process does not take away from or reduce ...(Untitled)01 91 00 1.1.F · PDF p. 200
Spec wording
“F. The commissioning process does not take away from or reduce the responsibility of the Contractor to provide a finished and fully functioning product.”
01 91 00 1.1.F200–
Test / cert.Test / cert.The commissioning team must consist of, but not be limited ...(Untitled)01 91 00 1.8.A · PDF p. 215
Spec wording
“A. The commissioning team must consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning Agent.”
01 91 00 1.8.A215–
Test / cert.Test / cert.Members Appointed by Contractor:(Untitled)01 91 00 1.8.B · PDF p. 215-216
Spec wording
“B. Members Appointed by Contractor: 1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The GC must engage the CxA. The CxA must be completely independent of, and divested from, the Contractor, the installer, the manufacturer, and the supplier of material or item being inspected. Submit inspector ...”
01 91 00 1.8.B215-216–
Test / cert.Test / cert.Members Appointed by VA:(Untitled)01 91 00 1.8.C · PDF p. 216
Spec wording
“C. Members Appointed by VA: 1. User: Representatives of the facility user and operation and maintenance personnel. 2. A/E: Representative of the Architect and engineering design professionals.”
01 91 00 1.8.C216–
Test / cert.Test / cert.Assign operation and maintenance personnel and schedule them to participate ...(Untitled)01 91 00 1.9.A · PDF p. 216
Spec wording
“A. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following: 1. Coordination meetings. 2. Training in operation and maintenance of systems, subsystems, and equipment. 3. Testing meetings. 4. Witness and assist in Systems Functional Performance Testing. 5. Demonstration of operation of systems, subsystems, and equipment.”
01 91 00 1.9.A216–
Test / cert.Test / cert.Provide the Construction Documents, prepared by Architect and approved by ...(Untitled)01 91 00 1.9.B · PDF p. 216
Spec wording
“B. Provide the Construction Documents, prepared by Architect and approved by VA, to the Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.”
01 91 00 1.9.B216–
Test / cert.Test / cert.Appoint an individual, company or firm to act as the ...(Untitled)01 91 00 1.10.A · PDF p. 216
Spec wording
“A. Appoint an individual, company or firm to act as the Commissioning Agent.”
01 91 00 1.10.A216–
Test / cert.Test / cert.The Contractor must assign a Commissioning Manager to manage commissioning ...(Untitled)01 91 00 1.10.B · PDF p. 216
Spec wording
“B. The Contractor must assign a Commissioning Manager to manage commissioning activities of the Contractor, and subcontractors.”
01 91 00 1.10.B216–
Test / cert.Test / cert.The Contractor must ensure that the commissioning responsibilities outlined in ...(Untitled)01 91 00 1.10.C · PDF p. 217
Spec wording
“C. The Contractor must ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.”
01 91 00 1.10.C217–
Test / cert.Test / cert.The Contractor must ensure that each installing subcontractor must assign ...(Untitled)01 91 00 1.10.D · PDF p. 217
Spec wording
“D. The Contractor must ensure that each installing subcontractor must assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the following: 1. Participate in commissioning coordination meetings. 2. Conduct operation and maintenance training sessions in accordance with ...”
01 91 00 1.10.D217–
Test / cert.Test / cert.Organize and lead the commissioning team(Untitled)01 91 00 1.11.A · PDF p. 217
Spec wording
“A. Organize and lead the commissioning team.”
01 91 00 1.11.A217–
Test / cert.Test / cert.Prepare the commissioning plan. See Paragraph 1.11-A of this specification ...(Untitled)01 91 00 1.11.B · PDF p. 218
Spec wording
“B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.”
01 91 00 1.11.B218–
Test / cert.Test / cert.Review and comment on selected submittals from the Contractor for ...(Untitled)01 91 00 1.11.C · PDF p. 218
Spec wording
“C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems ...”
01 91 00 1.11.C218–
Test / cert.Test / cert.At the beginning of the construction phase, conduct an initial ...(Untitled)01 91 00 1.11.D · PDF p. 218
Spec wording
“D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre-Functional Checklists, Systems Functional Performance Testing; and project completion.”
01 91 00 1.11.D218–
Test / cert.Test / cert.Convene commissioning team meetings for the purpose of coordination, communication, ...(Untitled)01 91 00 1.11.E · PDF p. 218
Spec wording
“E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The Commissioning Agent must prepare and distribute minutes to commissioning team members and attendees within five workdays of the ...”
01 91 00 1.11.E218–
Test / cert.Test / cert.Observe construction and report progress, observations and issues. Observe systems ...(Untitled)01 91 00 1.11.F · PDF p. 218
Spec wording
“F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.”
01 91 00 1.11.F218–
Test / cert.Test / cert.Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test ...(Untitled)01 91 00 1.11.G · PDF p. 218
Spec wording
“G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.”
01 91 00 1.11.G218–
Test / cert.Test / cert.Coordinate Systems Functional Performance Testing schedule with the Contractor ...(Untitled)01 91 00 1.11.H · PDF p. 218
Spec wording
“H. Coordinate Systems Functional Performance Testing schedule with the Contractor.”
01 91 00 1.11.H218–
Test / cert.Test / cert.Witness selected systems startups(Untitled)01 91 00 1.11.I · PDF p. 218
Spec wording
“I. Witness selected systems startups.”
01 91 00 1.11.I218–
Test / cert.Test / cert.Verify selected Pre-Functional Checklists completed and submitted by the Contractor ...(Untitled)01 91 00 1.11.J · PDF p. 218
Spec wording
“J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.”
01 91 00 1.11.J218–
Test / cert.Test / cert.Witness and document Systems Functional Performance Testing(Untitled)01 91 00 1.11.K · PDF p. 218
Spec wording
“K. Witness and document Systems Functional Performance Testing.”
01 91 00 1.11.K218–
Test / cert.Test / cert.Compile test data, inspection reports, and certificates and include them ...(Untitled)01 91 00 1.11.L · PDF p. 218
Spec wording
“L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.”
01 91 00 1.11.L218–
Test / cert.Test / cert.Review and comment on operation and maintenance (O&M) documentation and ...(Untitled)01 91 00 1.11.M · PDF p. 219
Spec wording
“M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.”
01 91 00 1.11.M219–
Test / cert.Test / cert.Review operation and maintenance training program developed by the Contractor. ...(Untitled)01 91 00 1.11.N · PDF p. 219
Spec wording
“N. Review operation and maintenance training program developed by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.”
01 91 00 1.11.N219–
Test / cert.Test / cert.Prepare commissioning Field Observation Reports(Untitled)01 91 00 1.11.O · PDF p. 219
Spec wording
“O. Prepare commissioning Field Observation Reports.”
01 91 00 1.11.O219–
Test / cert.Test / cert.Prepare the Final Commissioning Report(Untitled)01 91 00 1.11.P · PDF p. 219
Spec wording
“P. Prepare the Final Commissioning Report.”
01 91 00 1.11.P219–
Test / cert.Test / cert.Return to the site at 10 months into the 12 ...(Untitled)01 91 00 1.11.Q · PDF p. 219
Spec wording
“Q. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Systems Functional Performance Testing. Also interview facility staff and identify problems or concerns they have operating the building as originally intended. Make suggestions for improvements and for ...”
01 91 00 1.11.Q219–
Test / cert.Test / cert.Assemble the final commissioning documentation, including the Final Commissioning Report ...(Untitled)01 91 00 1.11.R · PDF p. 219
Spec wording
“R. Assemble the final commissioning documentation, including the Final Commissioning Report and Addendum to the Final Commissioning Report.”
01 91 00 1.11.R219–
Test / cert.Test / cert.Commissioning Plan(Untitled)01 91 00 1.12.A · PDF p. 219-220
Spec wording
“A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and must include, but is not limited, to the following: 1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a ...”
01 91 00 1.12.A219-220–
Test / cert.Test / cert.Systems Functional Performance Test Procedures(Untitled)01 91 00 1.12.B · PDF p. 220
Spec wording
“B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested. Preliminary Systems Functional ...”
01 91 00 1.12.B220–
Test / cert.Test / cert.Pre-Functional Checklists(Untitled)01 91 00 1.12.C · PDF p. 221
Spec wording
“C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre-Functional Checklists. Pre-Functional Checklists must be completed and signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing. Inaccurate or incomplete Pre-Functional ...”
01 91 00 1.12.C221–
Test / cert.Test / cert.Test and Inspection Reports(Untitled)01 91 00 1.12.D · PDF p. 221
Spec wording
“D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application must be included with data. Commissioning Agent Will compile test and inspection reports and test and ...”
01 91 00 1.12.D221–
Test / cert.Test / cert.Corrective Action Documents(Untitled)01 91 00 1.12.E · PDF p. 221
Spec wording
“E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results.”
01 91 00 1.12.E221–
Test / cert.Test / cert.Commissioning Issues Log(Untitled)01 91 00 1.12.F · PDF p. 221-222
Spec wording
“F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues Log will identify and track issues as they are ...”
01 91 00 1.12.F221-222–
Test / cert.Test / cert.Final Commissioning Report(Untitled)01 91 00 1.12.G · PDF p. 222-223
Spec wording
“G. Final Commissioning Report: The Commissioning Agent will document results of the commissioning process, including unresolved issues, and performance of systems, subsystems, and equipment. The Commissioning Report will indicate whether systems, subsystems, and equipment have been properly installed and are performing according to the Contract Documents. This report will be used by the Department of Veterans ...”
01 91 00 1.12.G222-223–
Test / cert.Test / cert.Addendum to Final Commissioning Report(Untitled)01 91 00 1.12.H · PDF p. 223
Spec wording
“H. Addendum to Final Commissioning Report: The Commissioning Agent will prepare an Addendum to the Final Commissioning Report near the end of the Warranty Period. The Addendum will indicate whether systems, subsystems, and equipment are complete and continue to perform according to the Contract Documents. The Addendum to the Final Commissioning Report must include, but is not limited to, the following: 1. ...”
01 91 00 1.12.H223–
Test / cert.Test / cert.Systems Manual(Untitled)01 91 00 1.12.I · PDF p. 223-224
Spec wording
“I. Systems Manual: The Commissioning Agent will gather required information and compile the Systems Manual. The Systems Manual will include, but is not limited to, the following: 1. Design Narrative, including system narratives, schematics, single-line diagrams, flow diagrams, equipment schedules, and changes made throughout the Project. 2. Reference to Final Commissioning Plan. 3. Reference to Final Commissioning ...”
01 91 00 1.12.I223-224–
Test / cert.Test / cert.Preliminary Commissioning Plan Submittal(Untitled)01 91 00 1.13.A · PDF p. 224
Spec wording
“A. Preliminary Commissioning Plan Submittal: The Commissioning Agent has prepared a Preliminary Commissioning Plan based on the final Construction Documents. The Preliminary Commissioning Plan is included as an Appendix to this specification section. The Preliminary Commissioning Plan is provided for information only. It contains preliminary information about the following commissioning activities: 1. The ...”
01 91 00 1.13.A224–
Test / cert.Test / cert.Final Commissioning Plan Submittal(Untitled)01 91 00 1.13.B · PDF p. 225
Spec wording
“B. Final Commissioning Plan Submittal: Based on the Final Construction Documents and the Contractor's project team, the Commissioning Agent will prepare the Final Commissioning Plan as described in this section. The Commissioning Agent will submit three hard copies and three sets of electronic files of Final Commissioning Plan. The Contractor must review the Commissioning Plan and provide any comments to the VA. ...”
01 91 00 1.13.B225three hard copies; three sets; electronic files
Test / cert.Test / cert.Systems Functional Performance Test Procedure(Untitled)01 91 00 1.13.C · PDF p. 225
Spec wording
“C. Systems Functional Performance Test Procedure: The Commissioning Agent will submit preliminary Systems Functional Performance Test Procedures to the Contractor, and the VA for review and comment. The Contractor must return review comments to the VA and the Commissioning Agent. The VA will also return review comments to the Commissioning Agent. The Commissioning Agent will incorporate review comments into the ...”
01 91 00 1.13.C225–
Test / cert.Test / cert.Pre-Functional Checklists(Untitled)01 91 00 1.13.D · PDF p. 225
Spec wording
“D. Pre-Functional Checklists: The Commissioning Agent will submit Pre-Functional Checklists to be completed by the Contractor.”
01 91 00 1.13.D225–
Test / cert.Test / cert.Test and Inspection Reports(Untitled)01 91 00 1.13.E · PDF p. 225
Spec wording
“E. Test and Inspection Reports: The Commissioning Agent will submit test and inspection reports to the VA with copies to the Contractor and the Architect/Engineer.”
01 91 00 1.13.E225–
Test / cert.Test / cert.Corrective Action Documents(Untitled)01 91 00 1.13.F · PDF p. 225
Spec wording
“F. Corrective Action Documents: The Commissioning Agent will submit corrective action documents to the VHA COR with copies to the Contractor and Architect.”
01 91 00 1.13.F225–
Test / cert.Test / cert.Preliminary Commissioning Report Submittal(Untitled)01 91 00 1.13.G · PDF p. 225
Spec wording
“G. Preliminary Commissioning Report Submittal: The Commissioning Agent will submit three electronic copies of the preliminary commissioning report. One electronic copy, with review comments, will be returned to the Commissioning Agent for preparation of the final submittal.”
01 91 00 1.13.G225three electronic copies; One electronic copy
Test / cert.Test / cert.Final Commissioning Report Submittal(Untitled)01 91 00 1.13.H · PDF p. 225
Spec wording
“H. Final Commissioning Report Submittal: The Commissioning Agent will submit four sets of electronically formatted information of the final commissioning report to the VA. The final submittal will incorporate comments as directed by the VA.”
01 91 00 1.13.H225four sets; electronically
Test / cert.Test / cert.Data for Commissioning:(Untitled)01 91 00 1.13.I · PDF p. 225-226
Spec wording
“I. Data for Commissioning: 1. The Commissioning Agent will request in writing from the Contractor specific information needed about each piece of commissioned equipment or system to fulfill requirements of the Commissioning Plan. 2. The Commissioning Agent may request further documentation as is necessary for the commissioning process or to support other VA data collection requirements, including Construction ...”
01 91 00 1.13.I225-226–
Test / cert.Test / cert.The Commissioning Agent will be responsible for the overall management ...(Untitled)01 91 00 1.14.A · PDF p. 226
Spec wording
“A. The Commissioning Agent will be responsible for the overall management of the commissioning process as well as coordinating scheduling of commissioning tasks with the VA and the Contractor. As directed by the VA, the Contractor must incorporate Commissioning tasks, including, but not limited to, Systems Functional Performance Testing (including predecessors) with the Master Construction Schedule.”
01 91 00 1.14.A226–
Test / cert.Test / cert.Within 21 days of contract award, the Contractor must designate ...(Untitled)01 91 00 1.14.B · PDF p. 226
Spec wording
“B. Within 21 days of contract award, the Contractor must designate a specific individual as the Commissioning Manager (CxM) to manage and lead the commissioning effort on behalf of the Contractor. The Commissioning Manager must be the single point of contact and communications for all commissioning related services by the Contractor.”
01 91 00 1.14.B226–
Test / cert.Test / cert.Within 30 days of contract award, the Contractor must ensure ...(Untitled)01 91 00 1.14.C · PDF p. 226
Spec wording
“C. Within 30 days of contract award, the Contractor must ensure that each subcontractor designates specific individuals as Commissioning Representatives (CXR) to be responsible for commissioning related tasks. The Contractor must ensure the designated Commissioning Representatives participate in the commissioning process as team members providing commissioning testing services, equipment operation, adjustments, and ...”
01 91 00 1.14.C226–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...(Untitled)01 91 00 3.1.A · PDF p. 229-231
Spec wording
“A. The following table outlines the roles and responsibilities for the Commissioning Team members during the Construction Phase: Construction Phase CxA = Commissioning Agent L = Lead RE = VHA COR P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M Notes ...”
01 91 00 3.1.A229-231–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...(Untitled)01 91 00 3.1.B · PDF p. 231-233
Spec wording
“B. The following table outlines the roles and responsibilities for the Commissioning Team members during the Acceptance Phase: Acceptance Phase CxA = Commissioning Agent L = Lead RE = VHA COR P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M Notes Meetings ...”
01 91 00 3.1.B231-233–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...(Untitled)01 91 00 3.1.C · PDF p. 233-234
Spec wording
“C. The following table outlines the roles and responsibilities for the Commissioning Team members during the Warranty Phase: Warranty Phase CxA = Commissioning Agent L = Lead RE = VHA COR P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M Notes Meetings ...”
01 91 00 3.1.C233-234–
Test / cert.Test / cert.The following procedures must apply to all equipment and systems ...(Untitled)01 91 00 3.2.A · PDF p. 235-236
Spec wording
“A. The following procedures must apply to all equipment and systems to be commissioned, according to Part 1, Systems to Be Commissioned. 1. Pre-Functional Checklists are important to ensure that the equipment and systems are hooked up and operational. These ensure that Systems Functional Performance Testing may proceed without unnecessary delays. Each system to be commissioned must have a full Pre-Functional ...”
01 91 00 3.2.A235-236–
Test / cert.Test / cert.The Contractor must clearly list any outstanding items of the ...(Untitled)01 91 00 3.3.A · PDF p. 236
Spec wording
“A. The Contractor must clearly list any outstanding items of the initial startup and Pre-Functional Checklist procedures that were not completed successfully, at the bottom of the procedures form or on an attached sheet. The procedures form and any outstanding deficiencies must be provided to the VA and the Commissioning Agent within two days of completion.”
01 91 00 3.3.A236–
Test / cert.Test / cert.The Commissioning Agent will review the report and submit comments ...(Untitled)01 91 00 3.3.B · PDF p. 237
Spec wording
“B. The Commissioning Agent will review the report and submit comments to the VA. The Commissioning Agent will work with the Contractor to correct and verify deficiencies or uncompleted items. The Commissioning Agent will involve the VA and others as necessary. The Contractor must correct all areas that are noncompliant or incomplete in the checklists in a timely manner, and must notify the VA and Commissioning ...”
01 91 00 3.3.B237–
Test / cert.Test / cert.The Contractor must be responsible for resolution of deficiencies as ...(Untitled)01 91 00 3.3.C · PDF p. 237
Spec wording
“C. The Contractor must be responsible for resolution of deficiencies as directed the VA.”
01 91 00 3.3.C237–
Test / cert.Test / cert.Trending is a method of testing as a standalone method ...(Untitled)01 91 00 3.5.A · PDF p. 237
Spec wording
“A. Trending is a method of testing as a standalone method or to augment manual testing. The Contractor must trend any and all points of the system or systems at intervals specified below.”
01 91 00 3.5.A237–
Test / cert.Test / cert.Alarms are a means to notify the system operator that ...(Untitled)01 91 00 3.5.B · PDF p. 237-238
Spec wording
“B. Alarms are a means to notify the system operator that abnormal conditions are present in the system. Alarms must be structured into three tiers – Critical, Priority, and Maintenance. 1. Critical alarms are intended to be alarms that require the immediate attention of and action by the Operator. These alarms must be displayed on the Operator Workstation in a popup style window that is graphically linked to the ...”
01 91 00 3.5.B237-238–
Test / cert.Test / cert.The Contractor must provide a wireless internet network in the ...(Untitled)01 91 00 3.5.C · PDF p. 238
Spec wording
“C. The Contractor must provide a wireless internet network in the building for use during controls programming, checkout, and commissioning. This network will allow project team members to more effectively program, view, manipulate and test control devices while being in the same room as the controlled device.”
01 91 00 3.5.C238–
Test / cert.Test / cert.The Contractor must provide graphical trending through the DDC control ...(Untitled)01 91 00 3.5.D · PDF p. 238-254
Spec wording
“D. The Contractor must provide graphical trending through the DDC control system of systems being commissioned. Trending requirements are indicated below and included with the Systems Functional Performance Test Procedures. Trending must occur before, during and after Systems Functional Performance Testing. The Contractor must be responsible for producing graphical representations of the trended DDC points that ...”
01 91 00 3.5.D238-254–
Test / cert.Test / cert.The Contractor must provide the following information prior to Systems ...(Untitled)01 91 00 3.5.E · PDF p. 254-255
Spec wording
“E. The Contractor must provide the following information prior to Systems Functional Performance Testing. Any documentation that is modified after submission must be recorded and resubmitted to the VHA COR and Commissioning Agent. 1. Point-to-Point checkout documentation; 2. Sensor field calibration documentation including system name, sensor/point name, measured value, DDC value, and Correction Factor. 3. A sensor ...”
01 91 00 3.5.E254-255–
O&MO&MTraining Preparation Conference(Untitled)01 91 00 3.9.A · PDF p. 262
Spec wording
“A. Training Preparation Conference: Before operation and maintenance training, the Commissioning Agent will convene a training preparation conference to include VA's VHA COR, VA's Operations and Maintenance personnel, and the Contractor. The purpose of this conference will be to discuss and plan for Training and Demonstration of VA Operations and Maintenance personnel.”
01 91 00 3.9.A262–
O&MO&MThe Contractor must provide training and demonstration as required by ...(Untitled)01 91 00 3.9.B · PDF p. 263
Spec wording
“B. The Contractor must provide training and demonstration as required by other Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 sections. The Training and Demonstration must include, but is not limited to, the following: 1. Review the Contract Documents. 2. Review installed systems, subsystems, and equipment. 3. Review instructor qualifications. 4. Review instructional ...”
01 91 00 3.9.B263–
O&MO&MTraining Module Submittals(Untitled)01 91 00 3.9.C · PDF p. 263-264
Spec wording
“C. Training Module Submittals: The Contractor must submit the following information to the VA and the Commissioning Agent: 1. Instruction Program: Submit two copies of outline of instructional program for demonstration and training, including a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training ...”
01 91 00 3.9.C263-264two copies; DVD; 3-ring; binders; binder
O&MO&MQuality Assurance:(Untitled)01 91 00 3.9.D · PDF p. 264
Spec wording
“D. Quality Assurance: 1. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. 2. Instructor Qualifications: A factory authorized service representative, complying with ...”
01 91 00 3.9.D264–
O&MO&MTraining Coordination:(Untitled)01 91 00 3.9.E · PDF p. 264-265
Spec wording
“E. Training Coordination: 1. Coordinate instruction schedule with VA's operations. Adjust schedule as required to minimize disrupting VA's operations. 2. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. 3. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction ...”
01 91 00 3.9.E264-265–
O&MO&MInstruction Program:(Untitled)01 91 00 3.9.F · PDF p. 265
Spec wording
“F. Instruction Program: 1. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections, and as follows: a. Fire protection systems, including fire alarm, fire pumps, and fire suppression systems. b. Intrusion detection systems. c. Conveying systems, including elevators, wheelchair ...”
01 91 00 3.9.F265–
O&MO&MTraining Modules(Untitled)01 91 00 3.9.G · PDF p. 266-267
Spec wording
“G. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participants are expected to master. For each module, include instruction for the following: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment descriptions. b. Performance and design criteria if ...”
01 91 00 3.9.G266-267–
O&MO&MTraining Execution:(Untitled)01 91 00 3.9.H · PDF p. 267-268
Spec wording
“H. Training Execution: 1. Preparation: Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a combined training manual. Set up instructional equipment at instruction location. 2. Instruction: a. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate ...”
01 91 00 3.9.H267-268–
O&MO&MDemonstration and Training Recording:(Untitled)01 91 00 3.9.I · PDF p. 268-269
Spec wording
“I. Demonstration and Training Recording: 1. General: Engage a qualified commercial photographer to record demonstration and training. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. At beginning of each training module, record each chart containing learning objective and lesson outline. 2. Video Format: ...”
01 91 00 3.9.I268-269DVD

Division 03 Concrete 2 items

TypeItemSpec sectionPDF pageCopies / format
TrainingTrainingManufacturer's Literature and Data:(Short Form) Cast-In-Place Concrete03 30 53 1.4.C · PDF p. 277
Spec wording
“C. Manufacturer's Literature and Data: 1. Concrete Mix Design. 2. Air-entraining admixture, chemical admixtures, and curing compounds. 3. Indicate manufacturer's recommendation for each application.”
03 30 53 1.4.C277–
WarrantyWarrantyConstruction Warranty(Short Form) Cast-In-Place Concrete03 30 53 1.6.A · PDF p. 277
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
03 30 53 1.6.A277–

Division 07 Roofing, insulation and waterproofing 20 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyConstruction Warranty(Untitled)07 21 13 1.7.A · PDF p. 321
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
07 21 13 1.7.A321–
WarrantyWarrantyConstruction Warranty(Untitled)07 22 00 1.9.A · PDF p. 329
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
07 22 00 1.9.A329–
WarrantyWarrantyManufacturer's Warranty(Untitled)07 22 00 1.9.B · PDF p. 329
Spec wording
“B. Manufacturer's Warranty: Warrant substrate board, vapor retarder, insulation, and cover board against material and manufacturing defects as part of Division 07 roofing system warranty.”
07 22 00 1.9.B329–
WarrantyWarrantyWarranty(Untitled)07 25 00 1.5.F · PDF p. 335
Spec wording
“F. Warranty: Submit manufacturer's sample warranty.”
07 25 00 1.5.F335–
WarrantyWarrantyConstruction Warranty(Untitled)07 25 00 1.8.A · PDF p. 336
Spec wording
“A. Construction Warranty: FAR clause 52.246 21, "Warranty of Construction."”
07 25 00 1.8.A336–
WarrantyWarrantyManufacturer's Product Warranty(Untitled)07 25 00 1.8.B · PDF p. 336
Spec wording
“B. Manufacturer's Product Warranty: Provide manufacturer's product warranty for a minimum of ten years from date of Substantial Completion with installation completed by a certified 3M applicator.”
07 25 00 1.8.B336–
WarrantyWarrantyInstaller's Workmanship Warranty(Untitled)07 25 00 1.8.C · PDF p. 336
Spec wording
“C. Installer's Workmanship Warranty: Provide workmanship warranty for a minimum of one year from date of Substantial Completion including all air barrier assembly materials and accessories, against failures including loss of air tight seal, loss of watertight seal, loss of attachment, loss of adhesion, and failure to cure properly.”
07 25 00 1.8.C336–
Test / cert.Test / cert.Fire Test Report(Untitled)07 40 00 1.4.F · PDF p. 345
Spec wording
“F. Fire Test Report: Report of fire test by recognized testing laboratory for fire rating specified, showing details of construction.”
07 40 00 1.4.F345–
WarrantyWarrantyManufacturer warranty(Untitled)07 40 00 1.4.I · PDF p. 346
Spec wording
“I. Manufacturer warranty.”
07 40 00 1.4.I346–
WarrantyWarrantyConstruction Warranty(Untitled)07 40 00 1.6.A · PDF p. 346
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
07 40 00 1.6.A346–
WarrantyWarrantyManufacturer Warranty(Untitled)07 40 00 1.6.B · PDF p. 346
Spec wording
“B. Manufacturer Warranty: Manufacturer shall warranty their metal wall panels for a minimum of ten (5) years from the date of installation and final acceptance by the Government. Submit manufacturer warranty.”
07 40 00 1.6.B346–
WarrantyWarrantyWarranty on Panel Finishes(Untitled)07 40 00 1.6.C · PDF p. 346
Spec wording
“C. Warranty on Panel Finishes: Manufacturer's shall warrant their and wall panel finish and provide standard agreement to repair finish or replace metal panels that show evidence of deterioration of factory-applied finishes within specified warranty period. 1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following: a. Color fading more than 5 Hunter units when tested according to ASTM ...”
07 40 00 1.6.C346–
WarrantyWarrantyManufacturer's Literature and Data:(Untitled)07 54 19 1.5.C · PDF p. 357-358
Spec wording
“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Minimum fastener pull out resistance. 3. Installation instructions. 4. Warranty. 5. Product Data for Federally-Mandated Bio-Based Materials: For roof materials, indicating USDA designation and compliance with definitions for bio-based products, Rapidly Renewable Materials, and certified sustainable wood content.”
07 54 19 1.5.C357-358–
Test / cert.Test / cert.Field quality control reports(Untitled)07 54 19 1.5.H · PDF p. 358
Spec wording
“H. Field quality control reports.”
07 54 19 1.5.H358–
O&MO&MOperation and Maintenance Data:(Untitled)07 54 19 1.5.J · PDF p. 358
Spec wording
“J. Operation and Maintenance Data: 1. Maintenance manuals.”
07 54 19 1.5.J358–
WarrantyWarrantyConstruction Warranty(Untitled)07 54 19 1.10.A · PDF p. 359
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
07 54 19 1.10.A359–
WarrantyWarrantyManufacturer's Warranty(Untitled)07 54 19 1.10.B · PDF p. 359
Spec wording
“B. Manufacturer's Warranty: Warrant roofing system against material and manufacturing defects and agree to repair any leak caused by a defect in the roofing system materials or workmanship of the installer. 1. Warranty Period: 10 years.”
07 54 19 1.10.B359–
Test / cert.Test / cert.Furnish service of approved inspector to inspect firestopping in accordance ...Firestopping07 84 00 3.5.B · PDF p. 394
Spec wording
“B. Furnish service of approved inspector to inspect firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results. Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers.”
07 84 00 3.5.B394–
WarrantyWarrantyConstruction Warranty(Untitled)07 92 00 1.9.A · PDF p. 397
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
07 92 00 1.9.A397–
WarrantyWarrantyManufacturer Warranty(Untitled)07 92 00 1.9.B · PDF p. 398
Spec wording
“B. Manufacturer Warranty: Manufacturer must warranty their sealant for a minimum of five (5) years from the date of installation and final acceptance by the Government. Submit manufacturer warranty.”
07 92 00 1.9.B398–

Division 08 Doors, windows and hardware 16 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test reports(Untitled)08 11 13 1.4.E · PDF p. 409
Spec wording
“E. Test reports: Certify products comply with specifications. 1. Sound rated door.”
08 11 13 1.4.E409–
WarrantyWarrantyConstruction Warranty(Untitled)08 11 13 1.8.A · PDF p. 409
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 11 13 1.8.A409–
WarrantyWarrantyConstruction Warranty(Untitled)08 31 13 1.8.A · PDF p. 418
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 31 13 1.8.A418–
WarrantyWarrantyAutomatic door operators shall be subject to the terms of ...Door Hardware08 71 00 1.4.A · PDF p. 424
Spec wording
“A. Automatic door operators shall be subject to the terms of FAR Clause 52.246-21, except that the Warranty period shall be two years in lieu of one year for all items except as noted below: 1. Locks, latchsets, and panic hardware: 5 years. 2. Door closers and continuous hinges: 10 years.”
08 71 00 1.4.A424–
O&MO&MIn accordance with Section 01 00 00, GENERAL REQUIREMENTS Article ...Door Hardware08 71 00 1.5.A · PDF p. 424
Spec wording
“A. In accordance with Section 01 00 00, GENERAL REQUIREMENTS Article titled "INSTRUCTIONS", furnish maintenance manuals and instructions on all door hardware. Provide installation instructions with the submittal documentation.”
08 71 00 1.5.A424–
Test / cert.Test / cert.Certificate of Compliance and Test ReportsDoor Hardware08 71 00 1.6.D · PDF p. 425
Spec wording
“D. Certificate of Compliance and Test Reports: Submit certificates that hardware conforms to the requirements specified herein. Certificates shall be accompanied by copies of reports as referenced. The testing shall have been conducted either in the manufacturer's plant and certified by an independent testing laboratory or conducted in an independent laboratory, within four years of submittal of reports for approval.”
08 71 00 1.6.D425–
Closeout stepCloseout stepHardware Set Symbols on DrawingsDoor Hardware08 71 00 1.9.A · PDF p. 426
Spec wording
“A. Hardware Set Symbols on Drawings: Except for protective plates, door stops, mutes, thresholds and the like specified herein, hardware requirements for each door are indicated on drawings by symbols. Symbols for hardware sets consist of letters (e.g., "HW") followed by a number. Each number designates a set of hardware items applicable to a door type.”
08 71 00 1.9.A426–
Closeout stepCloseout stepKeyingDoor Hardware08 71 00 1.9.B · PDF p. 426
Spec wording
“B. Keying: All cylinders shall be keyed into existing 7-Pin BEST, Great Grand Master Key System . Provide removable core cylinders that are removable only with a special key or tool without disassembly of knob or lockset . Cylinders shall be 7 pin type. Keying information shall be furnished at a later date by the COR.”
08 71 00 1.9.B426–
TrainingTrainingDemonstrate efficacy of mechanical hardware and electrical, and electronic hardware ...Door Hardware08 71 00 3.4.A · PDF p. 440
Spec wording
“A. Demonstrate efficacy of mechanical hardware and electrical, and electronic hardware systems, including adjustment and maintenance procedures, to satisfaction of Resident/Project Engineer and VA Locksmith.”
08 71 00 3.4.A440–
WarrantyWarrantyManufacturer's Literature and Data:(Untitled)08 71 13.11 1.5.C · PDF p. 445-446
Spec wording
“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Maintenance manuals. 3. Installation instructions. 4. Warranty.”
08 71 13.11 1.5.C445-446–
O&MO&MOperation and Maintenance Data:(Untitled)08 71 13.11 1.5.E · PDF p. 446
Spec wording
“E. Operation and Maintenance Data: 1. Care instructions for each exposed finish product. 2. Start-up, maintenance, troubleshooting, emergency, and shut-down instructions for each operational product.”
08 71 13.11 1.5.E446–
WarrantyWarrantyConstruction Warranty(Untitled)08 71 13.11 1.9.A · PDF p. 446
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 71 13.11 1.9.A446–
WarrantyWarrantyManufacturer's Warranty(Untitled)08 71 13.11 1.9.B · PDF p. 446
Spec wording
“B. Manufacturer's Warranty: Warrant automatic door operators against material and manufacturing defects. 1. Warranty Period: 10 years.”
08 71 13.11 1.9.B446–
TrainingTrainingInstruct VA personnel in proper door operator operation and maintenance ...(Untitled)08 71 13.11 3.4.A · PDF p. 449
Spec wording
“A. Instruct VA personnel in proper door operator operation and maintenance. 1. Trainer: Manufacturer approved instructor.”
08 71 13.11 3.4.A449–
TrainingTrainingSubmit training plan and trainer qualifications. See Section 01 91 ...(Untitled)08 71 13.11 3.4.B · PDF p. 449
Spec wording
“B. Submit training plan and trainer qualifications. See Section 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS.”
08 71 13.11 3.4.B449–
TrainingTrainingAcceptance Condition(Untitled)08 71 13.11 3.4.C · PDF p. 449
Spec wording
“C. Acceptance Condition: After completing work, operate door operators 15 consecutive calendar days without breakdown.”
08 71 13.11 3.4.C449–

Division 09 Finishes 14 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyTest Data:(Untitled)09 05 16 1.3.D · PDF p. 451
Spec wording
“D. Test Data: 1. Moisture test and pH results performed by a qualified independent testing agency or warranty holding manufacturer's technical representative.”
09 05 16 1.3.D451–
WarrantyWarrantyConstruction WarrantyCeramic/Porcelain Tiling09 30 13 1.6.A · PDF p. 481
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".”
09 30 13 1.6.A481–
WarrantyWarrantyManufacturer's Literature and Data:(Untitled)09 51 00 1.5.C · PDF p. 500
Spec wording
“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Ceiling suspension system indicating manufacturer recommendation for each application. 3. Installation instructions. 4. Warranty.”
09 51 00 1.5.C500–
O&MO&MOperation and Maintenance Data:(Untitled)09 51 00 1.5.H · PDF p. 501
Spec wording
“H. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
09 51 00 1.5.H501–
WarrantyWarrantyConstruction Warranty(Untitled)09 51 00 1.10.A · PDF p. 502
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
09 51 00 1.10.A502–
O&MO&MOperation and Maintenance Data:Resilient Base And Accessories09 65 13 1.4.E · PDF p. 510
Spec wording
“E. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
09 65 13 1.4.E510–
WarrantyWarrantyConstruction WarrantyResilient Base And Accessories09 65 13 1.8.A · PDF p. 510
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
09 65 13 1.8.A510–
WarrantyWarrantyManufacturer's Literature and Data:(Untitled)09 65 16 1.4.B · PDF p. 513
Spec wording
“B. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.”
09 65 16 1.4.B513–
WarrantyWarrantyConstruction Warranty(Untitled)09 65 16 1.9.A · PDF p. 515
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
09 65 16 1.9.A515–
WarrantyWarrantyManufacturer's Warranty(Untitled)09 65 16 1.9.B · PDF p. 515
Spec wording
“B. Manufacturer's Warranty: Warrant resilient sheet flooring against material and manufacturing defects. 1. Warranty Period: 2 years.”
09 65 16 1.9.B515–
WarrantyWarrantyWarranty(Untitled)09 67 23.50 1.3.H · PDF p. 522
Spec wording
“H. Warranty: As specified in this section.”
09 67 23.50 1.3.H522–
WarrantyWarrantyWork subject to the terms of the Article "Warranty of ...(Untitled)09 67 23.50 1.7.A · PDF p. 526
Spec wording
“A. Work subject to the terms of the Article "Warranty of Construction" FAR clause 52.246-21.”
09 67 23.50 1.7.A526–
WarrantyWarrantyWarranty(Untitled)09 67 23.50 1.7.B · PDF p. 526
Spec wording
“B. Warranty: Manufacture must furnish a single, written warranty covering the full assembly (including substrata) for both material and workmanship for a extended period of (3) full years from date of installation, or provide a joint and several warranty signed on a single document by manufacturer and applicator jointly and severally warranting the materials and workmanship for a period of (3) full years from date ...”
09 67 23.50 1.7.B526–
O&MO&MMaintenance DataHigh Performance Resinous Wall Coatings09 96 00 1.2.D · PDF p. 561
Spec wording
“D. Maintenance Data: For maintenance manuals.”
09 96 00 1.2.D561–

Division 10 Specialties 7 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyConstruction Warranty(Untitled)10 14 00 1.6.A · PDF p. 568
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".”
10 14 00 1.6.A568–
Test / cert.Test / cert.Test Report(Untitled)10 26 00 1.4.E · PDF p. 575
Spec wording
“E. Test Report: Showing that resilient material complies with specified fire and safety code requirements.”
10 26 00 1.4.E575–
WarrantyWarrantyManufacturer's warranty(Untitled)10 26 00 1.4.H · PDF p. 575
Spec wording
“H. Manufacturer's warranty.”
10 26 00 1.4.H575–
WarrantyWarrantyConstruction Warranty(Untitled)10 26 00 1.6.A · PDF p. 576
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
10 26 00 1.6.A576–
WarrantyWarrantyManufacturer Warranty(Untitled)10 26 00 1.6.B · PDF p. 576
Spec wording
“B. Manufacturer Warranty: Manufacturer must warranty their wall and door protection for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer warranty.”
10 26 00 1.6.B576–
O&MO&MOperation and Maintenance Data:(Untitled)10 28 00 1.4.G · PDF p. 583
Spec wording
“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
10 28 00 1.4.G583–
WarrantyWarrantyConstruction Warranty(Untitled)10 28 00 1.8.A · PDF p. 583
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
10 28 00 1.8.A583–

Division 21 Fire suppression (sprinklers) 2 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MSubmit as one package in accordance with Section 01 33 ...(Untitled)21 13 13 1.4.A · PDF p. 605-607
Spec wording
“A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting ...”
21 13 13 1.4.A605-607binders; electronically; pdf; full size; One complete set; AutoCAD
O&MO&MFurnish the services of a competent instructor for not less ...(Untitled)21 13 13 3.3.A · PDF p. 614
Spec wording
“A. Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.”
21 13 13 3.3.A614–

Division 22 Plumbing 146 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MPlumbing Maintenance Data and Operating Instructions:Common Work Results For Plumbing22 05 11 1.4.J · PDF p. 626
Spec wording
“J. Plumbing Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all ...”
22 05 11 1.4.J626–
Test / cert.Test / cert.Provide copies of approved plumbing equipment submittals to the TAB ...Common Work Results For Plumbing22 05 11 1.4.K · PDF p. 626
Spec wording
“K. Provide copies of approved plumbing equipment submittals to the TAB and Commissioning Subcontractor.”
22 05 11 1.4.K626–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Common Work Results For Plumbing22 05 11 1.4.L · PDF p. 626
Spec wording
“L. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 11 1.4.L626–
Test / cert.Test / cert.Submit training plans, trainer qualifications and instructor qualifications in accordance ...Common Work Results For Plumbing22 05 11 1.4.M · PDF p. 626
Spec wording
“M. Submit training plans, trainer qualifications and instructor qualifications in accordance with the requirements of Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 11 1.4.M626–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.A · PDF p. 631
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 05 11 1.7.A631–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.B · PDF p. 631
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions will be in electronic version on CD or DVD inserted into a three─ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence ...”
22 05 11 1.7.B631electronic version; CD; DVD; binder
Record docsRecord docsThe installing Contractor will maintain as-built drawings of each completed ...Common Work Results For Plumbing22 05 11 1.7.C · PDF p. 631-632
Spec wording
“C. The installing Contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
22 05 11 1.7.C631-632AutoCAD; CD; DVD; CAD
Record docsRecord docsThe as-built drawings will indicate the location and type of ...Common Work Results For Plumbing22 05 11 1.7.D · PDF p. 632
Spec wording
“D. The as-built drawings will indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
22 05 11 1.7.D632–
Record docsRecord docsCertification documentation will be provided to COR 21 working days ...Common Work Results For Plumbing22 05 11 1.7.E · PDF p. 632
Spec wording
“E. Certification documentation will be provided to COR 21 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results will ...”
22 05 11 1.7.E632–
Test / cert.Test / cert.Startup of equipment will be performed as described in the ...Common Work Results For Plumbing22 05 11 3.8.A · PDF p. 651
Spec wording
“A. Startup of equipment will be performed as described in the equipment specifications. Vibration within specified tolerance will be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.”
22 05 11 3.8.A651–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Common Work Results For Plumbing22 05 11 3.8.B · PDF p. 651
Spec wording
“B. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the Contracting Officer's Representative and CxA. Provide a minimum of 4 weeks prior notice.”
22 05 11 3.8.B651–
O&MO&MAll new and temporary equipment and all elements of each ...Common Work Results For Plumbing22 05 11 3.10.A · PDF p. 652
Spec wording
“A. All new and temporary equipment and all elements of each assembly will be included.”
22 05 11 3.10.A652–
O&MO&MData sheet on each device listing model, size, capacity, pressure, ...Common Work Results For Plumbing22 05 11 3.10.B · PDF p. 652
Spec wording
“B. Data sheet on each device listing model, size, capacity, pressure, speed, horsepower, impeller size, and other information will be included.”
22 05 11 3.10.B652–
O&MO&MManufacturer's installation, maintenance, repair, and operation instructions for each device ...Common Work Results For Plumbing22 05 11 3.10.C · PDF p. 652
Spec wording
“C. Manufacturer's installation, maintenance, repair, and operation instructions for each device will be included. Assembly drawings and parts lists will also be included. A summary of operating precautions and reasons for precautions will be included in the Operations and Maintenance Manual.”
22 05 11 3.10.C652–
O&MO&MLubrication instructions, type and quantity of lubricant will be included ...Common Work Results For Plumbing22 05 11 3.10.D · PDF p. 652
Spec wording
“D. Lubrication instructions, type and quantity of lubricant will be included.”
22 05 11 3.10.D652–
O&MO&MSchematic diagrams and wiring diagrams of all control systems corrected ...Common Work Results For Plumbing22 05 11 3.10.E · PDF p. 652
Spec wording
“E. Schematic diagrams and wiring diagrams of all control systems corrected to include all field modifications will be included.”
22 05 11 3.10.E652–
O&MO&MSet points of all interlock devices will be listedCommon Work Results For Plumbing22 05 11 3.10.F · PDF p. 652
Spec wording
“F. Set points of all interlock devices will be listed.”
22 05 11 3.10.F652–
O&MO&MTrouble-shooting guide for the control system troubleshooting will be inserted ...Common Work Results For Plumbing22 05 11 3.10.G · PDF p. 652
Spec wording
“G. Trouble-shooting guide for the control system troubleshooting will be inserted into the Operations and Maintenance Manual.”
22 05 11 3.10.G652–
O&MO&MThe control system sequence of operation corrected with submittal review ...Common Work Results For Plumbing22 05 11 3.10.H · PDF p. 652
Spec wording
“H. The control system sequence of operation corrected with submittal review comments will be inserted into the Operations and Maintenance Manual.”
22 05 11 3.10.H652–
O&MO&MEmergency procedures for shutdown and startup of equipment and systemsCommon Work Results For Plumbing22 05 11 3.10.I · PDF p. 652
Spec wording
“I. Emergency procedures for shutdown and startup of equipment and systems.”
22 05 11 3.10.I652–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Plumbing22 05 11 3.11.A · PDF p. 652
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 11 3.11.A652–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Common Work Results For Plumbing22 05 11 3.11.B · PDF p. 652
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 05 11 3.11.B652–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Plumbing22 05 11 3.12.A · PDF p. 652
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 11 3.12.A652–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Plumbing22 05 11 3.12.B · PDF p. 653
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 11 3.12.B653–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.F · PDF p. 656
Spec wording
“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 05 12 1.4.F656–
Test / cert.Test / cert.CertificationGeneral Motor Requirements For Plumbing Equipment22 05 12 1.4.G · PDF p. 656
Spec wording
“G. Certification: Two weeks prior to final inspection, unless otherwise noted, the following certification shall be submitted to the Contracting Officer's Representative (COR). 1. Certification shall be submitted stating that the motors have been properly applied, installed, adjusted, lubricated, and tested.”
22 05 12 1.4.G656–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.H · PDF p. 656
Spec wording
“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 12 1.4.H656–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.I · PDF p. 656
Spec wording
“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 12 1.4.I656–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...General Motor Requirements For Plumbing Equipment22 05 12 1.6.A · PDF p. 656
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 05 12 1.6.A656–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.A · PDF p. 663
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 05 12 3.3.A663–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.B · PDF p. 663
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 05 12 3.3.B663–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.C · PDF p. 663
Spec wording
“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
22 05 12 3.3.C663–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General Motor Requirements For Plumbing Equipment22 05 12 3.4.A · PDF p. 663
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 12 3.4.A663–
Test / cert.Test / cert.Components provided under this section of the specification shall be ...General Motor Requirements For Plumbing Equipment22 05 12 3.4.B · PDF p. 663
Spec wording
“B. Components provided under this section of the specification shall be tested as part of a larger system.”
22 05 12 3.4.B663–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...General Motor Requirements For Plumbing Equipment22 05 12 3.5.A · PDF p. 663
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 12 3.5.A663–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Plumbing Equipment22 05 12 3.5.B · PDF p. 664
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 12 3.5.B664–
O&MO&MComplete operating and maintenance manual shall including wiring diagrams, technical ...Meters And Gauges For Plumbing Piping22 05 19 1.4.D · PDF p. 667-668
Spec wording
“D. Complete operating and maintenance manual shall including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the system. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and ...”
22 05 19 1.4.D667-668–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Meters And Gauges For Plumbing Piping22 05 19 1.4.E · PDF p. 668
Spec wording
“E. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 19 1.4.E668–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Meters And Gauges For Plumbing Piping22 05 19 1.4.F · PDF p. 668
Spec wording
“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 19 1.4.F668–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Meters And Gauges For Plumbing Piping22 05 19 1.5.A · PDF p. 668
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 05 19 1.5.A668–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Meters And Gauges For Plumbing Piping22 05 19 3.3.A · PDF p. 669
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 05 19 3.3.A669–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Meters And Gauges For Plumbing Piping22 05 19 3.3.B · PDF p. 670
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 05 19 3.3.B670–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Meters And Gauges For Plumbing Piping22 05 19 3.3.C · PDF p. 670
Spec wording
“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
22 05 19 3.3.C670–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Meters And Gauges For Plumbing Piping22 05 19 3.4.A · PDF p. 670
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 19 3.4.A670–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Meters And Gauges For Plumbing Piping22 05 19 3.4.B · PDF p. 670
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 05 19 3.4.B670–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Meters And Gauges For Plumbing Piping22 05 19 3.5.A · PDF p. 670
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 19 3.5.A670–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Meters And Gauges For Plumbing Piping22 05 19 3.5.B · PDF p. 670
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 19 3.5.B670–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General-Duty Valves For Plumbing Piping22 05 23 1.4.E · PDF p. 675
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance. ...”
22 05 23 1.4.E675–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General-Duty Valves For Plumbing Piping22 05 23 1.4.F · PDF p. 675
Spec wording
“F. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 23 1.4.F675–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...General-Duty Valves For Plumbing Piping22 05 23 1.4.G · PDF p. 675
Spec wording
“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 23 1.4.G675–
Test / cert.Test / cert.Testing and adjusting of balancing valves shall be performed by ...General-Duty Valves For Plumbing Piping22 05 23 3.4.D · PDF p. 687-688
Spec wording
“D. Testing and adjusting of balancing valves shall be performed by an independent NEBB Accredited Test and Balance Contractor. A final settings and flow report shall be submitted to the VA Contracting Officer's Representative (COR).”
22 05 23 3.4.D687-688–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General-Duty Valves For Plumbing Piping22 05 23 3.5.A · PDF p. 688
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 05 23 3.5.A688–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...General-Duty Valves For Plumbing Piping22 05 23 3.5.B · PDF p. 688
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 05 23 3.5.B688–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...General-Duty Valves For Plumbing Piping22 05 23 3.5.C · PDF p. 688
Spec wording
“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
22 05 23 3.5.C688–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General-Duty Valves For Plumbing Piping22 05 23 3.6.A · PDF p. 688
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 23 3.6.A688–
Test / cert.Test / cert.Components provided under this section of the specification will be ...General-Duty Valves For Plumbing Piping22 05 23 3.6.B · PDF p. 688
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 05 23 3.6.B688–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...General-Duty Valves For Plumbing Piping22 05 23 3.7.A · PDF p. 688
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 23 3.7.A688–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...General-Duty Valves For Plumbing Piping22 05 23 3.7.B · PDF p. 688
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 23 3.7.B688–
Test / cert.Test / cert.Field quality control test reports shall be submittedHeat Tracing For Plumbing Piping22 05 33 1.4.E · PDF p. 691
Spec wording
“E. Field quality control test reports shall be submitted.”
22 05 33 1.4.E691–
O&MO&MComplete operating and maintenance manuals including wiring diagram, technical data ...Heat Tracing For Plumbing Piping22 05 33 1.4.F · PDF p. 691
Spec wording
“F. Complete operating and maintenance manuals including wiring diagram, technical data sheets, information for ordering replaceable parts, and troubleshoot guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 05 33 1.4.F691–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Heat Tracing For Plumbing Piping22 05 33 1.4.G · PDF p. 691
Spec wording
“G. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 33 1.4.G691–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Heat Tracing For Plumbing Piping22 05 33 1.4.H · PDF p. 692
Spec wording
“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 33 1.4.H692–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION of Section 22 ...Heat Tracing For Plumbing Piping22 05 33 1.6.A · PDF p. 692
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 05 33 1.6.A692–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Heat Tracing For Plumbing Piping22 05 33 3.4.A · PDF p. 697
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 33 3.4.A697–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Heat Tracing For Plumbing Piping22 05 33 3.4.B · PDF p. 697
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 05 33 3.4.B697–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Heat Tracing For Plumbing Piping22 05 33 3.5.A · PDF p. 697
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 33 3.5.A697–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Heat Tracing For Plumbing Piping22 05 33 3.5.B · PDF p. 697
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 05 33 3.5.B697–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Plumbing Insulation22 07 11 1.4.E · PDF p. 703
Spec wording
“E. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 07 11 1.4.E703–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.A · PDF p. 704
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 07 11 1.6.A704–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.B · PDF p. 704-705
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 07 11 1.6.B704-705electronic version; DVD; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Plumbing Insulation22 07 11 1.6.C · PDF p. 705
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version 2023 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it ...”
22 07 11 1.6.C705CAD; DVD
Record docsRecord docsCertification documentation shall be provided prior to submitting the request ...Plumbing Insulation22 07 11 1.6.D · PDF p. 705
Spec wording
“D. Certification documentation shall be provided prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.”
22 07 11 1.6.D705–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Plumbing Insulation22 07 11 3.3.A · PDF p. 720
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 07 11 3.3.A720–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Plumbing Insulation22 07 11 3.3.B · PDF p. 720
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 07 11 3.3.B720–
Test / cert.Test / cert.The commissioning process requires review of selected Submittals. The Commissioning ...Commissioning Of Plumbing Systems22 08 00 1.6.A · PDF p. 723
Spec wording
“A. The commissioning process requires review of selected Submittals. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.”
22 08 00 1.6.A723–
Test / cert.Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Plumbing Systems22 08 00 1.6.B · PDF p. 723
Spec wording
“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.”
22 08 00 1.6.B723–
Test / cert.Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Plumbing Systems22 08 00 3.4.A · PDF p. 724
Spec wording
“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the VA COR. The ...”
22 08 00 3.4.A724–
TrainingTrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Plumbing Systems22 08 00 3.5.A · PDF p. 724-725
Spec wording
“A. Training of the VA operation and maintenance personnel is required in cooperation with the VA COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...”
22 08 00 3.5.A724-725–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Water Distribution22 11 00 1.4.D · PDF p. 731
Spec wording
“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets and information for ordering replacement parts: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 11 00 1.4.D731–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Facility Water Distribution22 11 00 1.4.E · PDF p. 731
Spec wording
“E. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 11 00 1.4.E731–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Facility Water Distribution22 11 00 1.4.F · PDF p. 731
Spec wording
“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 11 00 1.4.F731–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Facility Water Distribution22 11 00 1.6.A · PDF p. 732
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 11 00 1.6.A732–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Facility Water Distribution22 11 00 1.6.B · PDF p. 732-733
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 11 00 1.6.B732-733electronic version; DVD; three-ring; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Facility Water Distribution22 11 00 1.6.C · PDF p. 733
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version 2023 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it ...”
22 11 00 1.6.C733CAD; DVD
Record docsRecord docsCertification documentation shall be provided to COR 10 working days ...Facility Water Distribution22 11 00 1.6.D · PDF p. 733
Spec wording
“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certificate if applicable that all results of tests were within limits specified. If a certificate is not ...”
22 11 00 1.6.D733–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Facility Water Distribution22 11 00 3.4.A · PDF p. 743
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 11 00 3.4.A743–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Facility Water Distribution22 11 00 3.4.B · PDF p. 743
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 11 00 3.4.B743–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Facility Water Distribution22 11 00 3.5.A · PDF p. 743
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.”
22 11 00 3.5.A743–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Facility Water Distribution22 11 00 3.5.B · PDF p. 744
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 11 00 3.5.B744–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Sanitary And Vent Piping22 13 00 1.4.E · PDF p. 750
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 13 00 1.4.E750–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CXA and completed ...Facility Sanitary And Vent Piping22 13 00 1.4.F · PDF p. 750
Spec wording
“F. Completed System Readiness Checklist provided by the CXA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 13 00 1.4.F750–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Facility Sanitary And Vent Piping22 13 00 1.4.G · PDF p. 750
Spec wording
“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 13 00 1.4.G750–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Facility Sanitary And Vent Piping22 13 00 1.6.A · PDF p. 751
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 13 00 1.6.A751–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Facility Sanitary And Vent Piping22 13 00 3.6.A · PDF p. 762
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 13 00 3.6.A762–
Test / cert.Test / cert.Components provided under this section of the specification shall be ...Facility Sanitary And Vent Piping22 13 00 3.6.B · PDF p. 763
Spec wording
“B. Components provided under this section of the specification shall be tested as part of a larger system.”
22 13 00 3.6.B763–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Facility Sanitary And Vent Piping22 13 00 3.7.A · PDF p. 763
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 13 00 3.7.A763–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Facility Sanitary And Vent Piping22 13 00 3.7.B · PDF p. 763
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 13 00 3.7.B763–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Electric Domestic Water Heaters22 33 00 1.4.G · PDF p. 766
Spec wording
“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 33 00 1.4.G766–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Electric Domestic Water Heaters22 33 00 1.4.H · PDF p. 766
Spec wording
“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 33 00 1.4.H766–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Electric Domestic Water Heaters22 33 00 1.4.I · PDF p. 767
Spec wording
“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 33 00 1.4.I767–
Record docsRecord docsComply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 ...Electric Domestic Water Heaters22 33 00 1.6.A · PDF p. 767
Spec wording
“A. Comply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 33 00 1.6.A767–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Electric Domestic Water Heaters22 33 00 3.4.A · PDF p. 771
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 33 00 3.4.A771–
Test / cert.Test / cert.The tests shall include system capacity, control function, and alarm ...Electric Domestic Water Heaters22 33 00 3.4.B · PDF p. 771
Spec wording
“B. The tests shall include system capacity, control function, and alarm functions.”
22 33 00 3.4.B771–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Electric Domestic Water Heaters22 33 00 3.4.C · PDF p. 771
Spec wording
“C. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 33 00 3.4.C771–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Electric Domestic Water Heaters22 33 00 3.4.D · PDF p. 772
Spec wording
“D. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
22 33 00 3.4.D772–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Electric Domestic Water Heaters22 33 00 3.5.A · PDF p. 772
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 33 00 3.5.A772–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Electric Domestic Water Heaters22 33 00 3.5.B · PDF p. 772
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 33 00 3.5.B772–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Electric Domestic Water Heaters22 33 00 3.6.A · PDF p. 772
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 33 00 3.6.A772–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Electric Domestic Water Heaters22 33 00 3.6.B · PDF p. 772
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 33 00 3.6.B772–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Plumbing Fixtures22 40 00 1.4.E · PDF p. 775
Spec wording
“E. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 40 00 1.4.E775–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Plumbing Fixtures22 40 00 1.4.F · PDF p. 776
Spec wording
“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 40 00 1.4.F776–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.A · PDF p. 776
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 40 00 1.6.A776–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.B · PDF p. 776
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions will be in electronic version on compact disc or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation ...”
22 40 00 1.6.B776electronic version; DVD; three-ring; binder
Record docsRecord docsThe installing contractor will maintain as-built drawings of each completed ...Plumbing Fixtures22 40 00 1.6.C · PDF p. 776
Spec wording
“C. The installing contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in AutoCAD version 2023 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it will ...”
22 40 00 1.6.C776AutoCAD; DVD
Record docsRecord docsCertification documentation will be provided to COR 10 working days ...Plumbing Fixtures22 40 00 1.6.D · PDF p. 777
Spec wording
“D. Certification documentation will be provided to COR 10 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.”
22 40 00 1.6.D777–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Plumbing Fixtures22 40 00 3.4.A · PDF p. 783
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 40 00 3.4.A783–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Plumbing Fixtures22 40 00 3.4.B · PDF p. 783
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 40 00 3.4.B783–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Plumbing Fixtures22 40 00 3.5.A · PDF p. 783
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.”
22 40 00 3.5.A783–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Plumbing Fixtures22 40 00 3.5.B · PDF p. 783
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 40 00 3.5.B783–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Instrument Compressed-Air Piping22 61 13.74 1.4.I · PDF p. 787
Spec wording
“I. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 61 13.74 1.4.I787–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Instrument Compressed-Air Piping22 61 13.74 1.4.J · PDF p. 787
Spec wording
“J. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 61 13.74 1.4.J787–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Instrument Compressed-Air Piping22 61 13.74 1.4.K · PDF p. 787
Spec wording
“K. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 61 13.74 1.4.K787–
Record docsRecord docsComply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 ...Instrument Compressed-Air Piping22 61 13.74 1.6.A · PDF p. 789
Spec wording
“A. Comply with requirements in Paragraph AS-BUILT DOCUMENTATION of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 61 13.74 1.6.A789–
Test / cert.Test / cert.Initial blow down, initial pressure test for positive–pressure gas systems ...Instrument Compressed-Air Piping22 61 13.74 3.3.A · PDF p. 794
Spec wording
“A. Initial blow down, initial pressure test for positive–pressure gas systems and copper Category 3 vacuum piping, initial cross-connection test, initial piping purge test, and initial standing positive-pressure gas piping tests shall be conducted for a Category 3 compressed air system as required by NFPA 99. All test results shall be documented and submitted to the COR.”
22 61 13.74 3.3.A794–
Test / cert.Test / cert.Verifier standing pressure test, verifier cross-connection test, verifier Category 3 ...Instrument Compressed-Air Piping22 61 13.74 3.3.B · PDF p. 795
Spec wording
“B. Verifier standing pressure test, verifier cross-connection test, verifier Category 3 warning system test, verifier piping purge test, verifier final tie-in test, verifier operational pressure test, verifier piping particulate test, verifier piping purity test, labeling, use of source equipment for pipeline verification test, and test of secondary equipment shall be conducted for a Category 3 compressed air ...”
22 61 13.74 3.3.B795–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Instrument Compressed-Air Piping22 61 13.74 3.3.C · PDF p. 795
Spec wording
“C. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 61 13.74 3.3.C795–
Test / cert.Test / cert.The tests shall include system capacity, control function, and alarm ...Instrument Compressed-Air Piping22 61 13.74 3.3.D · PDF p. 795
Spec wording
“D. The tests shall include system capacity, control function, and alarm functions.”
22 61 13.74 3.3.D795–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Instrument Compressed-Air Piping22 61 13.74 3.3.E · PDF p. 795
Spec wording
“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 61 13.74 3.3.E795–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Instrument Compressed-Air Piping22 61 13.74 3.3.F · PDF p. 795
Spec wording
“F. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
22 61 13.74 3.3.F795–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Instrument Compressed-Air Piping22 61 13.74 3.4.A · PDF p. 795
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 61 13.74 3.4.A795–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Instrument Compressed-Air Piping22 61 13.74 3.4.B · PDF p. 795
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 61 13.74 3.4.B795–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Instrument Compressed-Air Piping22 61 13.74 3.5.A · PDF p. 795
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 61 13.74 3.5.A795–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Instrument Compressed-Air Piping22 61 13.74 3.5.B · PDF p. 795
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 61 13.74 3.5.B795–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Reverse-Osmosis Water Equipment22 67 19.16 1.4.E · PDF p. 798
Spec wording
“E. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 67 19.16 1.4.E798–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Reverse-Osmosis Water Equipment22 67 19.16 1.4.F · PDF p. 798
Spec wording
“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 67 19.16 1.4.F798–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Reverse-Osmosis Water Equipment22 67 19.16 1.7.A · PDF p. 799
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 67 19.16 1.7.A799–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Reverse-Osmosis Water Equipment22 67 19.16 1.7.B · PDF p. 799
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 67 19.16 1.7.B799electronic version; DVD; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Reverse-Osmosis Water Equipment22 67 19.16 1.7.C · PDF p. 799
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version 2023 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it ...”
22 67 19.16 1.7.C799CAD; DVD
Record docsRecord docsCertification documentation shall be provided to COR 10 working days ...Reverse-Osmosis Water Equipment22 67 19.16 1.7.D · PDF p. 799
Spec wording
“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and a certification that all results of tests were within limits specified.”
22 67 19.16 1.7.D799–
Test / cert.Test / cert.OperatingReverse-Osmosis Water Equipment22 67 19.16 3.3.A · PDF p. 804
Spec wording
“A. Operating: Tests shall be run in presence of COR.”
22 67 19.16 3.3.A804–
Test / cert.Test / cert.Procedure:Reverse-Osmosis Water Equipment22 67 19.16 3.3.B · PDF p. 804
Spec wording
“B. Procedure: 1. Operate RO system at constant maximum required capacity for one hour after demineralized RO product water is produced. When necessary, waste product water to sewer to maintain above flow rate. Product water production shall begin when a sample shows that demineralization complies with requirements. 2. Demonstrate all features of the control system including diagnostics and flow and cycle indications.”
22 67 19.16 3.3.B804–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Reverse-Osmosis Water Equipment22 67 19.16 3.3.C · PDF p. 804
Spec wording
“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Contractor shall provide a minimum of 10 working days prior to startup and testing.”
22 67 19.16 3.3.C804–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Reverse-Osmosis Water Equipment22 67 19.16 3.4.A · PDF p. 804
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 67 19.16 3.4.A804–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Reverse-Osmosis Water Equipment22 67 19.16 3.4.B · PDF p. 804
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
22 67 19.16 3.4.B804–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Reverse-Osmosis Water Equipment22 67 19.16 3.5.A · PDF p. 805
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.”
22 67 19.16 3.5.A805–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Reverse-Osmosis Water Equipment22 67 19.16 3.5.B · PDF p. 805
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.”
22 67 19.16 3.5.B805–

Division 23 HVAC 70 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MHVAC Maintenance Data and Operating Instructions:Common Work Results For Hvac23 05 11 1.4.K · PDF p. 815
Spec wording
“K. HVAC Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, paragraph INSTRUCTIONS for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all components ...”
23 05 11 1.4.K815–
Test / cert.Test / cert.Provide copies of approved HVAC equipment submittals to the TAB ...Common Work Results For Hvac23 05 11 1.4.L · PDF p. 815
Spec wording
“L. Provide copies of approved HVAC equipment submittals to the TAB and Commissioning Subcontractor.”
23 05 11 1.4.L815–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Common Work Results For Hvac23 05 11 1.4.M · PDF p. 816
Spec wording
“M. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 05 11 1.4.M816–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Common Work Results For Hvac23 05 11 1.4.N · PDF p. 816
Spec wording
“N. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 05 11 1.4.N816–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.A · PDF p. 820
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
23 05 11 1.7.A820–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.B · PDF p. 821
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
23 05 11 1.7.B821electronic version; CD; DVD; three-ring; binder
Record docsRecord docsThe installing Contractor shall maintain as-built drawings of each completed ...Common Work Results For Hvac23 05 11 1.7.C · PDF p. 821
Spec wording
“C. The installing Contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
23 05 11 1.7.C821AutoCAD; CD; DVD; CAD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Common Work Results For Hvac23 05 11 1.7.D · PDF p. 821
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
23 05 11 1.7.D821–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Common Work Results For Hvac23 05 11 1.7.E · PDF p. 821-822
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
23 05 11 1.7.E821-822–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Common Work Results For Hvac23 05 11 3.10.A · PDF p. 843
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 05 11 3.10.A843–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Common Work Results For Hvac23 05 11 3.10.B · PDF p. 843
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 05 11 3.10.B843–
Test / cert.Test / cert.The CxA will observe startup and Contractor testing of selected ...Common Work Results For Hvac23 05 11 3.10.C · PDF p. 843
Spec wording
“C. The CxA will observe startup and Contractor testing of selected equipment. Coordinate the startup and Contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
23 05 11 3.10.C843–
Test / cert.Test / cert.Startup of equipment shall be performed as described in equipment ...Common Work Results For Hvac23 05 11 3.10.D · PDF p. 843
Spec wording
“D. Startup of equipment shall be performed as described in equipment specifications. Vibration within specified tolerance shall be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, paragraph TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.”
23 05 11 3.10.D843–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Hvac23 05 11 3.12.A · PDF p. 844
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 05 11 3.12.A844–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Common Work Results For Hvac23 05 11 3.12.B · PDF p. 844
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
23 05 11 3.12.B844–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Hvac23 05 11 3.13.A · PDF p. 844
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 05 11 3.13.A844–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Hvac23 05 11 3.13.B · PDF p. 844
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 05 11 3.13.B844–
Test / cert.Test / cert.Submit the following for review and approval:Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.E · PDF p. 848
Spec wording
“E. Submit the following for review and approval: 1. Design Review Report within 90 days for conventional design projects after the system layout on air and water side is completed by the Contractor. 2. Systems inspection report on equipment and installation for conformance with design. 3. Duct Air Leakage Test Report. 4. Systems Readiness Report. 5. Intermediate and Final TAB reports covering flow balance and ...”
23 05 93 1.4.E848–
Test / cert.Test / cert.Prior to request for Final or Partial Final inspection, submit ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.F · PDF p. 849
Spec wording
“F. Prior to request for Final or Partial Final inspection, submit completed Test and Balance report for the area with noted critical paths.”
23 05 93 1.4.F849–
Test / cert.Test / cert.Record initial measurements for each unit of equipment on test ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.8.B · PDF p. 856
Spec wording
“B. Record initial measurements for each unit of equipment on test forms and submit a report to the COR. Where vibration readings exceed the allowable tolerance Contractor shall be directed to correct the problem. The TAB agency shall verify that the corrections are done and submit a final report to the COR.”
23 05 93 3.8.B856–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.14.A · PDF p. 859
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 05 93 3.14.A859–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.14.B · PDF p. 859
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system.”
23 05 93 3.14.B859–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of section ...Hvac And Boiler Plant Insulation23 07 11 3.4.A · PDF p. 883
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.”
23 07 11 3.4.A883–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Hvac And Boiler Plant Insulation23 07 11 3.4.B · PDF p. 883
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.”
23 07 11 3.4.B883–
Test / cert.Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Hvac Systems23 08 00 1.6.A · PDF p. 887
Spec wording
“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.”
23 08 00 1.6.A887–
Test / cert.Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Hvac Systems23 08 00 1.6.B · PDF p. 887
Spec wording
“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.”
23 08 00 1.6.B887–
Test / cert.Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Hvac Systems23 08 00 3.4.A · PDF p. 889
Spec wording
“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the VA COR. The ...”
23 08 00 3.4.A889–
TrainingTrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Hvac Systems23 08 00 3.5.A · PDF p. 889-891
Spec wording
“A. Training of the VA operation and maintenance personnel is required in cooperation with the VA COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...”
23 08 00 3.5.A889-891–
WarrantyWarrantyLabor and materials for control systems shall be warranted for ...Direct-Digital Control System For Hvac23 09 23 1.6 · PDF p. 909-910
Spec wording
“Labor and materials for control systems shall be warranted for a period as specified under Warranty in FAR clause 52.246-21. Control system failures during the warranty period shall be adjusted, repaired, or replaced at no cost or reduction in service to the owner. The system includes all computer equipment, transmission equipment, and all sensors and control devices. The on-line support service shall allow the ...”
23 09 23 1.6909-910–
WarrantyWarrantySubmit shop drawings in accordance with Section 01 33 23, ...Direct-Digital Control System For Hvac23 09 23 1.7 · PDF p. 910-912
Spec wording
“Submit shop drawings in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Information and material submitted under this section shall be marked "SUBMITTED UNDER SECTION 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC", with applicable paragraph identification. Manufacturer's Literature and Data Including: 1. A wiring diagram for each type of input device and output device including DDC ...”
23 09 23 1.7910-912three (3) copies; one (1) set; CD-ROM; CAD; One copy
TrainingTrainingFirst PhaseDirect-Digital Control System For Hvac23 09 23 1.8.1 · PDF p. 913
Spec wording
“1. First Phase: Formal instructions to the VA facilities personnel for a total of 16 hours, given in multiple training sessions (each no longer than four hours in length), conducted sometime between the completed installation and prior to the performance test period of the control system, at a time mutually agreeable to the Contractor and the VA.”
23 09 23 1.8.1913–
TrainingTrainingSecond PhaseDirect-Digital Control System For Hvac23 09 23 1.8.2 · PDF p. 913
Spec wording
“2. Second Phase: This phase of training shall comprise of on the job training during startup, checkout period, and performance test period. VA facilities personnel will work with the Contractor's installation and test personnel on a daily basis during startup and checkout period. During the performance test period, controls subcontractor will provide 8 hours of instructions, given in multiple training sessions ...”
23 09 23 1.8.2913–
TrainingTrainingThe O/M Manuals shall contain approved submittals as outlined in ...Direct-Digital Control System For Hvac23 09 23 1.8.3 · PDF p. 913
Spec wording
“3. The O/M Manuals shall contain approved submittals as outlined in Article 1.7, SUBMITTALS. The Controls subcontractor will review the manual contents with VA facilities personnel during second phase of training.”
23 09 23 1.8.3913–
TrainingTrainingTraining shall be given by direct employees of THE CONTROLS ...Direct-Digital Control System For Hvac23 09 23 1.8.4 · PDF p. 913
Spec wording
“4. Training shall be given by direct employees of THE CONTROLS system subcontractor.”
23 09 23 1.8.4913–
TrainingTrainingAs part of final system acceptance, a system demonstration is ...Direct-Digital Control System For Hvac23 09 23 3.2 · PDF p. 954-956
Spec wording
“As part of final system acceptance, a system demonstration is required (see below). Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the controls and instrumentation system. When formal commissioning is included in the project the system validation/test shall be part of the commissioning and shall be witnessed by the CxA. Validation 1. Prepare and submit for ...”
23 09 23 3.2954-956–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Direct-Digital Control System For Hvac23 09 23 3.3 · PDF p. 957
Spec wording
“Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part. When any defects are detected, correct defects and repeat test at no additional cost or time to ...”
23 09 23 3.3957–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Direct-Digital Control System For Hvac23 09 23 3.4 · PDF p. 957
Spec wording
“Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS. Components provided under this section of the specification will be tested as part of a larger system.”
23 09 23 3.4957–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Direct-Digital Control System For Hvac23 09 23 3.5 · PDF p. 957-958
Spec wording
“Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in the operation and maintenance of the system. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 09 23 3.5957-958–
Record docsRecord docsAs-Built Piping DiagramsSteam And Condensate Heating Piping23 22 13 1.4.F · PDF p. 963
Spec wording
“F. As-Built Piping Diagrams: Provide drawing as follows for steam and steam condensate piping and other central plant equipment. 1. One wall-mounted stick file for prints. Mount stick file in the chiller plant or adjacent control room along with control diagram stick file. 2. One set of reproducible drawings.”
23 22 13 1.4.F963One set
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Steam And Condensate Heating Piping23 22 13 1.4.G · PDF p. 963
Spec wording
“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
23 22 13 1.4.G963–
Test / cert.Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Steam And Condensate Heating Piping23 22 13 1.4.H · PDF p. 963
Spec wording
“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 22 13 1.4.H963–
Test / cert.Test / cert.Submit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 1.4.I · PDF p. 963
Spec wording
“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 22 13 1.4.I963–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.A · PDF p. 964
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
23 22 13 1.6.A964–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.B · PDF p. 964-965
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
23 22 13 1.6.B964-965electronic version; CD; DVD; three-ring; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Steam And Condensate Heating Piping23 22 13 1.6.C · PDF p. 965
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
23 22 13 1.6.C965AutoCAD; CD; DVD; CAD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Steam And Condensate Heating Piping23 22 13 1.6.D · PDF p. 965
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
23 22 13 1.6.D965–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Steam And Condensate Heating Piping23 22 13 1.6.E · PDF p. 965
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
23 22 13 1.6.E965–
Test / cert.Test / cert.Prepare and submit test and inspection reports to the COR ...Steam And Condensate Heating Piping23 22 13 3.6.D · PDF p. 984
Spec wording
“D. Prepare and submit test and inspection reports to the COR within 5 working days of test completion and prior to covering the pipe.”
23 22 13 3.6.D984–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Steam And Condensate Heating Piping23 22 13 3.8.A · PDF p. 985
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 22 13 3.8.A985–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Steam And Condensate Heating Piping23 22 13 3.8.B · PDF p. 985
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 22 13 3.8.B985–
Test / cert.Test / cert.The CxA shall observe startup and contractor testing of selected ...Steam And Condensate Heating Piping23 22 13 3.8.C · PDF p. 985
Spec wording
“C. The CxA shall observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
23 22 13 3.8.C985–
Test / cert.Test / cert.Adjust red set hand on pressure gauges to normal working pressureSteam And Condensate Heating Piping23 22 13 3.8.D · PDF p. 985
Spec wording
“D. Adjust red set hand on pressure gauges to normal working pressure.”
23 22 13 3.8.D985–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Steam And Condensate Heating Piping23 22 13 3.9.A · PDF p. 985
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 22 13 3.9.A985–
Test / cert.Test / cert.Components provided under this section of the specification shall be ...Steam And Condensate Heating Piping23 22 13 3.9.B · PDF p. 985
Spec wording
“B. Components provided under this section of the specification shall be tested as part of a larger system.”
23 22 13 3.9.B985–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Steam And Condensate Heating Piping23 22 13 3.10.A · PDF p. 985
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 22 13 3.10.A985–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 3.10.B · PDF p. 985
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.”
23 22 13 3.10.B985–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Ducts And Casings23 31 00 1.4.E · PDF p. 989
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 31 00 1.4.E989–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Ducts And Casings23 31 00 1.6.A · PDF p. 990
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 31 00 1.6.A990–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Outlets And Inlets23 37 00 1.4.D · PDF p. 1003
Spec wording
“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 37 00 1.4.D1003–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Outlets And Inlets23 37 00 1.6.A · PDF p. 1003
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 37 00 1.6.A1003–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Outlets And Inlets23 37 00 3.3.A · PDF p. 1008
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 37 00 3.3.A1008–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Air Outlets And Inlets23 37 00 3.3.B · PDF p. 1008
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 37 00 3.3.B1008–
WarrantyWarrantySuppliers warrantyHvac Air Cleaning Devices23 40 00 1.4.E · PDF p. 1011
Spec wording
“E. Suppliers warranty.”
23 40 00 1.4.E1011–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Air Cleaning Devices23 40 00 1.4.F · PDF p. 1011-1012
Spec wording
“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 40 00 1.4.F1011-1012–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Air Cleaning Devices23 40 00 1.6.A · PDF p. 1013
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 40 00 1.6.A1013–
Test / cert.Test / cert.Clean and vacuum air handling units and plenums prior to ...Hvac Air Cleaning Devices23 40 00 3.2.A · PDF p. 1026
Spec wording
“A. Clean and vacuum air handling units and plenums prior to starting air handling systems.”
23 40 00 3.2.A1026–
Test / cert.Test / cert.Replace pre-filters and install clean filter units prior to final ...Hvac Air Cleaning Devices23 40 00 3.2.B · PDF p. 1026
Spec wording
“B. Replace pre-filters and install clean filter units prior to final inspection as directed by the COR.”
23 40 00 3.2.B1026–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Air Cleaning Devices23 40 00 3.2.C · PDF p. 1026
Spec wording
“C. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 40 00 3.2.C1026–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Air Cleaning Devices23 40 00 3.2.D · PDF p. 1026
Spec wording
“D. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 40 00 3.2.D1026–
Test / cert.Test / cert.The CxA will observe startup and contractor testing of selected ...Hvac Air Cleaning Devices23 40 00 3.2.E · PDF p. 1026
Spec wording
“E. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.”
23 40 00 3.2.E1026–

Division 26 Electrical 39 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.All submittals shall include six copies of adequate descriptive literature, ...(Untitled)26 05 11 1.12.C · PDF p. 1035
Spec wording
“C. All submittals shall include six copies of adequate descriptive literature, catalog cuts, shop drawings, test reports, certifications, samples, and other data necessary for the Government to ascertain that the proposed materials and equipment comply with drawing and specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify specific materials and equipment being ...”
26 05 11 1.12.C1035six copies
O&MO&MThe submittals shall include the following:(Untitled)26 05 11 1.12.E · PDF p. 1035
Spec wording
“E. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, manuals, pictures, nameplate data, and test reports as required. 3. Elementary and interconnection wiring diagrams for communication and signal systems, control systems, and equipment ...”
26 05 11 1.12.E1035–
O&MO&MMaintenance and Operation Manuals:(Untitled)26 05 11 1.12.F · PDF p. 1035-1036
Spec wording
“F. Maintenance and Operation Manuals: 1. Submit as required for systems and equipment specified in the technical sections. Furnish in hardcover binders or an approved equivalent. 2. Inscribe the following identification on the cover: the words "MAINTENANCE AND OPERATION MANUAL," the name and location of the system, material, equipment, building, name of Contractor, and contract name and number. Include in the ...”
26 05 11 1.12.F1035-1036binders
Test / cert.Test / cert.Approvals will be based on complete submission of shop drawings, ...(Untitled)26 05 11 1.12.G · PDF p. 1036
Spec wording
“G. Approvals will be based on complete submission of shop drawings, manuals, test reports, certifications, and samples as applicable.”
26 05 11 1.12.G1036–
WarrantyWarrantyAll work performed and all equipment and material furnished under ...(Untitled)26 05 11 1.16.A · PDF p. 1037
Spec wording
“A. All work performed and all equipment and material furnished under this Division shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer for the Government.”
26 05 11 1.16.A1037–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Medium-Voltage Cables26 05 13 1.5.A · PDF p. 1040-1041
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Complete electrical ratings. 2) Installation instructions. 2. Samples: a. After approval of submittal and prior to ...”
26 05 13 1.5.A1040-1041–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 05 19 1.4.A · PDF p. 1050-1051
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings and insulation type for each conductor and cable. 2) Splicing materials and pulling lubricant. ...”
26 05 19 1.4.A1050-1051–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 05 26 1.4.A · PDF p. 1058-1059
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit plans showing the location of system grounding electrodes and connections, and the routing of aboveground and underground grounding electrode ...”
26 05 26 1.4.A1058-1059–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 05 33 1.4.A · PDF p. 1067
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Size and location of main feeders. b. Size and location of panels and pull-boxes. c. Layout of required conduit penetrations through structural elements. d. Submit the following data for approval: 1) Raceway types and sizes. 2) Conduit bodies, ...”
26 05 33 1.4.A1067–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 05 41 1.4.A · PDF p. 1080-1081
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit information on manholes, pullboxes, ducts, and hardware. Submit manhole plan and elevation drawings, showing openings, pulling irons, cable supports, ...”
26 05 41 1.4.A1080-1081–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Overcurrent Protective Device Coordination Study26 05 73 1.4.A · PDF p. 1090-1091
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Product data on the software program to be used for the study. Software shall be in mainstream use in the industry, shall provide device settings and ratings, and shall show selective coordination by time-current drawings. 2. Complete study as described in paragraph ...”
26 05 73 1.4.A1090-1091–
Test / cert.Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Electrical Systems26 08 00 1.6.A · PDF p. 1095
Spec wording
“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.”
26 08 00 1.6.A1095–
Test / cert.Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Electrical Systems26 08 00 1.6.B · PDF p. 1095
Spec wording
“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.”
26 08 00 1.6.B1095–
Test / cert.Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Electrical Systems26 08 00 3.4.A · PDF p. 1096
Spec wording
“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. ...”
26 08 00 3.4.A1096–
TrainingTrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Electrical Systems26 08 00 3.5.A · PDF p. 1096-1097
Spec wording
“A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the ...”
26 08 00 3.5.A1096-1097–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 09 23 1.4.A · PDF p. 1098-1099
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting controls. b. Material and construction details. c. Physical dimensions and description. d. Wiring schematic and connection diagram. e. Installation details. 2. Manuals: a. Submit, ...”
26 09 23 1.4.A1098-1099–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 12 19 1.5.A · PDF p. 1105
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, nameplate data, impedance, outline drawing with dimensions and front, top, and side views, weight, mounting details, decibel ...”
26 12 19 1.5.A1105–
Test / cert.Test / cert.Certifications:(Untitled)26 12 19 1.5.B · PDF p. 1106
Spec wording
“B. Certifications: 1. Two weeks prior to the final inspection, submit the following certifications. a. Certification by the manufacturer that the transformers conform to the requirements of the drawings and specifications. b. Certification by the Contractor that the transformers have been properly installed, connected, and tested.”
26 12 19 1.5.B1106–
Spare partsSpare partsDeliver the following spare parts for the project to the ...(Untitled)26 12 19 3.4.A · PDF p. 1113
Spec wording
“A. Deliver the following spare parts for the project to the VA COR two weeks prior to final inspection: 1. Six insulated protective caps. 2. One spare set of medium-voltage fuses for each size and type of fuse used in the project.”
26 12 19 3.4.A1113–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 13 16 1.5.A · PDF p. 1115-1116
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Shop drawings shall be submitted simultaneously with or after the Overcurrent Protective Device Coordination Study. b. Submit sufficient information to demonstrate compliance with drawings and specifications. c. Provide information such as complete ...”
26 13 16 1.5.A1115-1116–
Spare partsSpare partsTwo weeks prior to the final inspection, provide one (1) ...(Untitled)26 13 16 3.4.A · PDF p. 1120
Spec wording
“A. Two weeks prior to the final inspection, provide one (1) set of spare fuses for each switch installed on this project. 3.5ONE LINE DIAGRAM AND SEQUENCE OF OPERATION”
26 13 16 3.4.A1120one (1) set
Spare partsSpare partsAt final inspection, an as-built one line diagram shall be ...(Untitled)26 13 16 3.4.A · PDF p. 1120
Spec wording
“A. At final inspection, an as-built one line diagram shall be laminated or mounted under acrylic glass, and installed in a frame mounted in the switchgear room or in the outdoor switchgear enclosure.”
26 13 16 3.4.A1120–
Spare partsSpare partsFurnish a written sequence of operation for the switchgear and ...(Untitled)26 13 16 3.4.B · PDF p. 1120
Spec wording
“B. Furnish a written sequence of operation for the switchgear and connected line side/load side electrical distribution equipment. The sequence of operation shall be laminated or mounted under acrylic glass, and installed in a frame mounted in the switchgear room or in the outdoor switchgear enclosure.”
26 13 16 3.4.B1120–
Spare partsSpare partsDeliver an additional four copies of the as-built one line ...(Untitled)26 13 16 3.4.C · PDF p. 1120
Spec wording
“C. Deliver an additional four copies of the as-built one line diagram and sequence of operation to the VA COR.”
26 13 16 3.4.C1120four copies
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 22 00 1.4.A · PDF p. 1122-1123
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, temperature rise, wiring and connection ...”
26 22 00 1.4.A1122-1123–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 24 13 1.5.A · PDF p. 1129-1130
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Switchboard shop drawings shall be submitted simultaneously with or after the Overcurrent Protective Device Coordination Study. b. Submit sufficient information to demonstrate compliance with drawings and specifications. c. Prior to fabrication of ...”
26 24 13 1.5.A1129-1130–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 24 16 1.4.A · PDF p. 1140-1141
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, circuit breakers, wiring and connection ...”
26 24 16 1.4.A1140-1141–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 27 26 1.4.A · PDF p. 1146-1147
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, construction materials, grade, and termination information. 2. Manuals: a. Submit, simultaneously ...”
26 27 26 1.4.A1146-1147–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Enclosed Switches And Circuit Breakers26 29 21 1.4.A · PDF p. 1152-1153
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, ...”
26 29 21 1.4.A1152-1153–
Spare partsSpare partsTwo weeks prior to the final inspection, furnish one complete ...Enclosed Switches And Circuit Breakers26 29 21 3.3.A · PDF p. 1155
Spec wording
“A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the VA COR. ---END---”
26 29 21 3.3.A1155one complete set
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 32 13 1.5.A · PDF p. 1157-1158
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Scaled drawings, showing plan views, side views, elevations, and cross-sections. 2. Diagrams: a. Control system diagrams, control sequence diagrams or ...”
26 32 13 1.5.A1157-1158–
Spare partsSpare partsFor each engine generator:(Untitled)26 32 13 2.17.A · PDF p. 1175
Spec wording
“A. For each engine generator: 1. Six lubricating oil filters. 2. Six primary fuel oil filters. 3. Six secondary fuel oil filters. 4. Six intake air filters.”
26 32 13 2.17.A1175–
Spare partsSpare partsFor each battery charger:(Untitled)26 32 13 2.17.B · PDF p. 1175
Spec wording
“B. For each battery charger: 1. Three complete sets of fuses.”
26 32 13 2.17.B1175Three complete sets
Spare partsSpare partsFor each control panel:(Untitled)26 32 13 2.17.C · PDF p. 1175
Spec wording
“C. For each control panel: 1. Three complete sets of fuses, if applicable.”
26 32 13 2.17.C1175Three complete sets
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 36 23 1.5.A · PDF p. 1181-1182
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include voltage rating, continuous current rating, number of phases, withstand and closing rating, dimensions, weights, mounting details, conduit entry ...”
26 36 23 1.5.A1181-1182–
Test / cert.Test / cert.An authorized representative of the automatic transfer switch manufacturer shall ...(Untitled)26 36 23 3.2.A · PDF p. 1189
Spec wording
“A. An authorized representative of the automatic transfer switch manufacturer shall technically supervise and participate during all of the field adjustments and tests. Major adjustments and field tests shall be witnessed by the VA COR. The manufacturer's representative shall certify in writing that the equipment has been installed, adjusted and tested in accordance with the manufacturer's recommendations.”
26 36 23 3.2.A1189–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Surge Protective Devices26 43 13 1.4.A · PDF p. 1192
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings and device nameplate data. 2. Manuals: a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance ...”
26 43 13 1.4.A1192–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 51 00 1.4.A · PDF p. 1196-1197
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...”
26 51 00 1.4.A1196-1197–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...(Untitled)26 56 00 1.4.A · PDF p. 1206-1207
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...”
26 56 00 1.4.A1206-1207–

Division 27 Communications 23 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MProvide parts list including quantity of spare partsRequirements For Communications Installations27 05 11 1.7.B · PDF p. 1234
Spec wording
“B. Provide parts list including quantity of spare parts.”
27 05 11 1.7.B1234–
Test / cert.Test / cert.Furnish electronic certified test reports to COR prior to final ...Requirements For Communications Installations27 05 11 1.7.K · PDF p. 1236
Spec wording
“K. Furnish electronic certified test reports to COR prior to final inspection and not more than 90 days after completion of tests.”
27 05 11 1.7.K1236–
WarrantyWarrantyProvide following closeout submittals prior to project closeout date:Requirements For Communications Installations27 05 11 1.8.A · PDF p. 1236
Spec wording
“A. Provide following closeout submittals prior to project closeout date: 1. Warranty certificate. 2. Evidence of compliance with requirements such as low voltage certificate of inspection. 3. Project record documents. 4. Instruction manuals and software that are a part of system.”
27 05 11 1.8.A1236–
WarrantyWarrantyMaintenance and Operation ManualsRequirements For Communications Installations27 05 11 1.8.B · PDF p. 1236-1237
Spec wording
“B. Maintenance and Operation Manuals: Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS. 1. Prepare a manual for each system and equipment specified. 2. Furnish on portable storage drive in PDF format or equivalent accepted by COR. 3. Furnish complete manual as specified in specification section, fifteen days prior to performance of systems or equipment test. 4. Furnish remaining manuals prior to ...”
27 05 11 1.8.B1236-1237PDF
Test / cert.Test / cert.Record Wiring Diagrams:Requirements For Communications Installations27 05 11 1.8.C · PDF p. 1237-1238
Spec wording
“C. Record Wiring Diagrams: 1. Red Line Drawings: Keep one E size 91.44 cm x 121.92 cm (36 inches x 48 inches) set of floor plans, on site during work hours, showing installation progress marked and backbone cable labels noted. Make these drawings available for examination during construction meetings or field inspections. 2. General Drawing Specifications: Detail and elevation drawings to be D size 61 cm x 91.44 cm ...”
27 05 11 1.8.C1237-1238CAD; four complete sets
Closeout stepCloseout stepService QualificationsRequirements For Communications Installations27 05 11 1.8.D · PDF p. 1238
Spec wording
“D. Service Qualifications: Submit name and contact information of service organizations providing service to this installation within eight hours of receipt of notification service is needed.”
27 05 11 1.8.D1238–
Spare partsSpare partsAfter approval and prior to installation, furnish COR with the ...Requirements For Communications Installations27 05 11 1.9.A · PDF p. 1238
Spec wording
“A. After approval and prior to installation, furnish COR with the following: 1. A 300 mm (12 inch) length of each type and size of wire and cable along with tag from coils of reels from which samples were taken. 2. One coupling, bushing and termination fitting for each type of conduit. 3. Samples of each hanger, clamp and supports for conduit and pathways. 4. Duct sealing compound.”
27 05 11 1.9.A1238–
WarrantyWarrantyComply with FAR clause 52.246-21, except as follows:Requirements For Communications Installations27 05 11 1.13.A · PDF p. 1241
Spec wording
“A. Comply with FAR clause 52.246-21, except as follows: 1. Warranty material and equipment to be free from defects, workmanship, and remain so for a period of one year for Emergency Systems from date of final acceptance of system by Government; provide OEM's equipment warranty document to COR. 2. Government maintenance personnel must have ability to contact OEM for emergency maintenance and logistic assistance, ...”
27 05 11 1.13.A1241–
Test / cert.Test / cert.Proof of Performance Certification:Requirements For Communications Installations27 05 11 3.6.M · PDF p. 1252
Spec wording
“M. Proof of Performance Certification: 1. If system is declared acceptable, AHJ (SMCS 005OP2H3) provides COR notice stating system processes to required operating standards and functions and is Government accepted for use by facility. 2. Validate items with COR needing to be provided to complete project contract (i.e. charts & diagrams, manuals, spare parts, system warranty documents executed, etc.). Once items ...”
27 05 11 3.6.M1252–
TrainingTrainingProvide training in accordance with subsection, INSTRUCTIONS, of Section 01 ...Requirements For Communications Installations27 05 11 3.8.A · PDF p. 1253
Spec wording
“A. Provide training in accordance with subsection, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.”
27 05 11 3.8.A1253–
TrainingTrainingProvide training for equipment or system as required in each ...Requirements For Communications Installations27 05 11 3.8.B · PDF p. 1253
Spec wording
“B. Provide training for equipment or system as required in each associated specification.”
27 05 11 3.8.B1253–
TrainingTrainingDevelop and submit training schedule for approval by COR, at ...Requirements For Communications Installations27 05 11 3.8.C · PDF p. 1253
Spec wording
“C. Develop and submit training schedule for approval by COR, at least 30 days prior to planned training.”
27 05 11 3.8.C1253–
Test / cert.Test / cert.Closeout SubmittalsGrounding And Bonding For Communications Systems27 05 26 1.5.C · PDF p. 1255
Spec wording
“C. Closeout Submittals: Provide test reports of ground resistance to each primary or secondary bonding busbar (PBB/SBB) located in each telecommunications space impacted by the work.”
27 05 26 1.5.C1255–
Test / cert.Test / cert.CertificationConduits And Backboxes For Communications Systems27 05 33 1.3.B · PDF p. 1260
Spec wording
“B. Certification: Provide letter prior to final inspection, certifying material is in accordance with construction documents and properly installed.”
27 05 33 1.3.B1260–
Closeout stepCloseout stepSubmit in accordance with Section 27 05 11, REQUIREMENTS FOR ...Communications Copper Horizontal Cabling27 15 13 1.5.A · PDF p. 1286
Spec wording
“A. Submit in accordance with Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 27 78 00 CLOSEOUT SUBMITTALS FOR COMMUNICATIONS.”
27 15 13 1.5.A1286–
O&MO&MProvide parts list including quantity of spare partsCloseout Submittals For Communications27 78 00 1.5.E · PDF p. 1292
Spec wording
“E. Provide parts list including quantity of spare parts.”
27 78 00 1.5.E1292–
Test / cert.Test / cert.Furnish electronic certified test reports to COR prior to final ...Closeout Submittals For Communications27 78 00 1.5.H · PDF p. 1293
Spec wording
“H. Furnish electronic certified test reports to COR prior to final inspection and not more than 90 days after completion of tests.”
27 78 00 1.5.H1293–
WarrantyWarrantyProvide following closeout submittals prior to project closeout date:Closeout Submittals For Communications27 78 00 1.6.A · PDF p. 1293
Spec wording
“A. Provide following closeout submittals prior to project closeout date: 1. Warranty certificate. 2. Evidence of compliance with requirements such as low voltage certificate of inspection. 3. Project record documents. 4. Instruction manuals and software that are a part of system.”
27 78 00 1.6.A1293–
WarrantyWarrantyMaintenance and Operation ManualsCloseout Submittals For Communications27 78 00 1.6.B · PDF p. 1293
Spec wording
“B. Maintenance and Operation Manuals: Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS. 1. Prepare a manual for each system and equipment specified. 2. Furnish on portable storage drive in PDF format or equivalent accepted by COR. 3. Furnish complete manual as specified in specification section, fifteen days prior to performance of systems or equipment test. 4. Furnish remaining manuals prior to ...”
27 78 00 1.6.B1293PDF
WarrantyWarrantyComply with FAR clause 52.246-21 except as follows:Closeout Submittals For Communications27 78 00 1.10.A · PDF p. 1295
Spec wording
“A. Comply with FAR clause 52.246-21 except as follows: 1. Warranty material and equipment to be free from defects, workmanship, and remain so for a period of one year for Emergency Systems from date of final acceptance of system by Government; provide OEM's equipment warranty document to COR. 2. Government maintenance personnel must have ability to contact OEM for emergency maintenance and logistic assistance, ...”
27 78 00 1.10.A1295–
TrainingTrainingProvide training in accordance with subsection, INSTRUCTIONS, of Section 01 ...Closeout Submittals For Communications27 78 00 3.4.A · PDF p. 1298
Spec wording
“A. Provide training in accordance with subsection, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.”
27 78 00 3.4.A1298–
TrainingTrainingProvide training for equipment or system as required in each ...Closeout Submittals For Communications27 78 00 3.4.B · PDF p. 1298
Spec wording
“B. Provide training for equipment or system as required in each associated specification.”
27 78 00 3.4.B1298–
TrainingTrainingDevelop and submit training schedule for approval by COR, at ...Closeout Submittals For Communications27 78 00 3.4.C · PDF p. 1298
Spec wording
“C. Develop and submit training schedule for approval by COR, at least 30 days prior to planned training.”
27 78 00 3.4.C1298–

Division 28 Fire alarm and security 40 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MThe submittals shall include the following:Common Work Results For Electronic Safety And Security28 05 00 1.6.D · PDF p. 1307
Spec wording
“D. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required. 2. Submittals are required for all equipment anchors and supports. Submittals shall include weights, dimensions, center of ...”
28 05 00 1.6.D1307–
WarrantyWarrantySubmittals shall be in full compliance of the Contract Documents. ...Common Work Results For Electronic Safety And Security28 05 00 1.6.E · PDF p. 1308-1313
Spec wording
“E. Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. All submittals ...”
28 05 00 1.6.E1308-1313AutoCAD; CAD; Binders; binder; four copies
Record docsRecord docsGroup 1 Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.F · PDF p. 1313-1319
Spec wording
“F. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA CAD Standards Guide. All text associated with security details shall be 1/8" ...”
28 05 00 1.6.F1313-1319CAD; AutoCAD
Record docsRecord docsGroup IV Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.I · PDF p. 1320-1322
Spec wording
“I. Group IV Technical Data Package 1. Performance Verification Test a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to the ...”
28 05 00 1.6.I1320-1322CAD; hard copy
O&MO&MGroup V Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.J · PDF p. 1322-1325
Spec wording
“J. Group V Technical Data Package: Final copies of the manuals shall be delivered to the Resident Engineer as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing ...”
28 05 00 1.6.J1322-1325CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD
Test / cert.Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Common Work Results For Electronic Safety And Security28 05 00 1.6.N · PDF p. 1327
Spec wording
“N. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 05 00 1.6.N1327–
WarrantyWarrantyThe Contractor shall, as a condition precedent to the final ...Common Work Results For Electronic Safety And Security28 05 00 1.20.A · PDF p. 1345-1346
Spec wording
“A. The Contractor shall, as a condition precedent to the final payment, execute a written guarantee (warranty) to the COTR certifying all contract requirements have been completed according to the final specifications. Contract drawings and the warranty of all materials and equipment furnished under this contract are to remain in satisfactory operating condition (ordinary wear and tear, abuse and causes beyond his ...”
28 05 00 1.20.A1345-1346–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Electronic Safety And Security28 05 00 3.3.A · PDF p. 1348-1349
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.”
28 05 00 3.3.A1348-1349–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Common Work Results For Electronic Safety And Security28 05 00 3.3.B · PDF p. 1349
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS and related sections for contractor responsibilities for system commissioning.”
28 05 00 3.3.B1349–
TrainingTrainingTraining shall be provided in accordance with Article, INSTRUCTIONS, of ...Common Work Results For Electronic Safety And Security28 05 00 3.4.A · PDF p. 1349
Spec wording
“A. Training shall be provided in accordance with Article, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.”
28 05 00 3.4.A1349–
TrainingTrainingTraining shall be provided for the particular equipment or system ...Common Work Results For Electronic Safety And Security28 05 00 3.4.B · PDF p. 1349
Spec wording
“B. Training shall be provided for the particular equipment or system as required in each associated specification.”
28 05 00 3.4.B1349–
TrainingTrainingA training schedule shall be developed and submitted by the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.C · PDF p. 1349
Spec wording
“C. A training schedule shall be developed and submitted by the contractor and approved by the Resident Engineer at least 30 days prior to the planned training.”
28 05 00 3.4.C1349–
TrainingTrainingProvide services of manufacturer's technical representative for 30 hours min, ...Common Work Results For Electronic Safety And Security28 05 00 3.4.D · PDF p. 1349
Spec wording
“D. Provide services of manufacturer's technical representative for 30 hours min, to instruct VA personnel in operation and maintenance of units.”
28 05 00 3.4.D1349–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.E · PDF p. 1349
Spec wording
“E. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 05 00 3.4.E1349–
Test / cert.Test / cert.The inspection and test will be conducted by a factory-certified ...Common Work Results For Electronic Safety And Security28 05 00 3.7.B · PDF p. 1353
Spec wording
“B. The inspection and test will be conducted by a factory-certified contractor representative and witnessed by a Government Representative. The results of the inspection will be officially recorded by a designated Government Representative and maintained on file by the Resident Engineer (RE), until completion of the entire project. The results will be compared to the Acceptance Test results.”
28 05 00 3.7.B1353–
Test / cert.Test / cert.Document data for each measurement. Print data for submittals in ...Conductors And Cables For Electronic Safety And Security28 05 13 3.8.D · PDF p. 1365
Spec wording
“D. Document data for each measurement. Print data for submittals in a summary report that is formatted using Table 10.1 in BICSI TDMM as a guide, or transfer the data from the instrument to the computer, save as text files, print, and submit.”
28 05 13 3.8.D1365–
Test / cert.Test / cert.Prepare test and inspection reportsConductors And Cables For Electronic Safety And Security28 05 13 3.8.F · PDF p. 1365
Spec wording
“F. Prepare test and inspection reports.”
28 05 13 3.8.F1365–
Test / cert.Test / cert.Test ReportsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.C · PDF p. 1366
Spec wording
“C. Test Reports: Provide certified test reports of ground resistance.”
28 05 26 1.3.C1366–
Test / cert.Test / cert.CertificationsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.D · PDF p. 1366
Spec wording
“D. Certifications: Two weeks prior to final inspection, submit four copies of the following to the COTR: 1. Certification that the materials and installation are in accordance with the drawings and specifications. 2. Certification by the contractor that the complete installation has been properly installed and tested.”
28 05 26 1.3.D1366four copies
Record docsRecord docsProvide a complete and thorough pre-installation and as-built design package ...Physical Access Control System28 13 00 1.4.C · PDF p. 1384
Spec wording
“C. Provide a complete and thorough pre-installation and as-built design package in both electronic format and on paper, minimum size 48 x 48 inches (1220 x 1220 millimeters); drawing submittals shall be per the established project schedule.”
28 13 00 1.4.C1384electronic format
Test / cert.Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.H · PDF p. 1386
Spec wording
“H. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 1.4.H1386–
WarrantyWarrantyGeneralPhysical Access Control System28 13 00 1.4.I · PDF p. 1386-1391
Spec wording
“I. General: Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. Additional ...”
28 13 00 1.4.I1386-1391AutoCAD; CAD; Binders; binder
Record docsRecord docsGroup 1 Technical Data PackagePhysical Access Control System28 13 00 1.4.J · PDF p. 1391-1397
Spec wording
“J. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA Special Conditions and CAD Standards Documents. All text associated with ...”
28 13 00 1.4.J1391-1397CAD; AutoCAD
Record docsRecord docsGroup IV Technical Data PackagePhysical Access Control System28 13 00 1.4.M · PDF p. 1398-1400
Spec wording
“M. Group IV Technical Data Package 1. Performance Verification Test a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to the ...”
28 13 00 1.4.M1398-1400CAD; hard copy
O&MO&MGroup V Technical Data PackagePhysical Access Control System28 13 00 1.4.N · PDF p. 1400-1404
Spec wording
“N. Group V Technical Data Package: Final copies of the manuals shall be delivered to the Resident Engineer as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing ...”
28 13 00 1.4.N1400-1404CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD
Test / cert.Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.Q · PDF p. 1405
Spec wording
“Q. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 1.4.Q1405–
WarrantyWarrantyWarrant PACS work subject to the Article "Warranty of Construction" ...Physical Access Control System28 13 00 1.11.A · PDF p. 1417
Spec wording
“A. Warrant PACS work subject to the Article "Warranty of Construction" of FAR clause 52.246-21.”
28 13 00 1.11.A1417–
WarrantyWarrantyDemonstration and training shall be performed prior to system acceptance ...Physical Access Control System28 13 00 1.11.B · PDF p. 1417
Spec wording
“B. Demonstration and training shall be performed prior to system acceptance.”
28 13 00 1.11.B1417–
Test / cert.Test / cert.Manufacturer's Field ServicePhysical Access Control System28 13 00 3.10.A · PDF p. 1454
Spec wording
“A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing.”
28 13 00 3.10.A1454–
Test / cert.Test / cert.Testing AgencyPhysical Access Control System28 13 00 3.10.B · PDF p. 1454
Spec wording
“B. Testing Agency: Engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports:”
28 13 00 3.10.B1454–
Test / cert.Test / cert.Perform the following field tests and inspections and prepare test ...Physical Access Control System28 13 00 3.10.C · PDF p. 1454
Spec wording
“C. Perform the following field tests and inspections and prepare test reports: 1. LAN Cable Procedures: Inspect for physical damage and test each conductor signal path for continuity and shorts. Use Class 2, bidirectional, Category 5 tester. Test for faulty connectors, splices, and terminations. Test according to TIA/EIA-568-1, "Commercial Building Telecommunications Cabling Standards - Part 1 General ...”
28 13 00 3.10.C1454–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Physical Access Control System28 13 00 3.12.A · PDF p. 1455
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.”
28 13 00 3.12.A1455–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Physical Access Control System28 13 00 3.12.B · PDF p. 1455
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS and related sections for contractor responsibilities for system commissioning.”
28 13 00 3.12.B1455–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Physical Access Control System28 13 00 3.13.A · PDF p. 1455
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA personnel in operation and maintenance of units.”
28 13 00 3.13.A1455–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Physical Access Control System28 13 00 3.13.B · PDF p. 1455
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 3.13.B1455–
TrainingTrainingDevelop separate training modules for the following:Physical Access Control System28 13 00 3.13.C · PDF p. 1455
Spec wording
“C. Develop separate training modules for the following: 1. Computer system administration personnel to manage and repair the LAN and databases and to update and maintain software. 2. Operators who prepare and input credentials to man the control station and workstations and to enroll personnel. 3. Security personnel. 4. Hardware maintenance personnel. 5. Corporate management.”
28 13 00 3.13.C1455–
TrainingTrainingAll testing and training shall be compliant with the VA ...Physical Access Control System28 13 00 3.13.D · PDF p. 1455
Spec wording
“D. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS. ----END----”
28 13 00 3.13.D1455–
Record docsRecord docsDrawings:(Untitled)28 31 00 1.4.B · PDF p. 1458-1459
Spec wording
“B. Drawings: 1. Prepare drawings using AutoCAD software and include all contractors information. Layering shall be by VA criteria as provided by the Contracting Officer's Representative (COR). Bid drawing files on AutoCAD will be provided to the Contractor at the pre-construction meeting. The contractor shall be responsible for verifying all critical dimensions shown on the drawings provided by VA. 2. Floor plans: ...”
28 31 00 1.4.B1458-1459AutoCAD; 3 sets; one set
O&MO&MManuals:(Untitled)28 31 00 1.4.C · PDF p. 1459-1460
Spec wording
“C. Manuals: 1. Submit simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets for all items used in the system, power requirements, device wiring diagrams, dimensions, and information for ordering replacement parts. a. Wiring diagrams shall have their terminals identified to facilitate installation, operation, expansion and maintenance. ...”
28 31 00 1.4.C1459-1460binder; 4 copies
WarrantyWarrantyAll work performed and all material and equipment furnished under ...(Untitled)28 31 00 1.5.A · PDF p. 1461
Spec wording
“A. All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer.”
28 31 00 1.5.A1461–

Division 32 Paving and site improvements 3 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test reports(Untitled)32 05 23 1.5.E · PDF p. 1492
Spec wording
“E. Test reports: Certify products comply with specifications. 1. Concrete materials. 2. Select subbase materials. 3. Field test reports.”
32 05 23 1.5.E1492–
WarrantyWarrantyConstruction Warranty(Untitled)32 05 23 1.10.A · PDF p. 1494
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
32 05 23 1.10.A1494–
Test / cert.Test / cert.Test Reports:(Untitled)32 32 23 1.05.C · PDF p. 1511
Spec wording
“C. Test Reports: 1. Independent Laboratory reports indicating compressive strength, moisture absorption and freeze-thaw durability of the concrete retaining wall units from the proposed production facility. 2. Independent test reports verifying the long-term design strength properties (creep, installation damage, and durability) and soil interaction properties of the geosynthetic reinforcement. 3. Independent test ...”
32 32 23 1.05.C1511–

Division 33 Utilities 5 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Site Utility Systems33 08 00 1.6.A · PDF p. 1519
Spec wording
“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.”
33 08 00 1.6.A1519–
Test / cert.Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Site Utility Systems33 08 00 1.6.B · PDF p. 1519
Spec wording
“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.”
33 08 00 1.6.B1519–
Test / cert.Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Site Utility Systems33 08 00 3.4.A · PDF p. 1520
Spec wording
“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Resident Engineer. ...”
33 08 00 3.4.A1520–
TrainingTrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Site Utility Systems33 08 00 3.5.A · PDF p. 1520-1521
Spec wording
“A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the ...”
33 08 00 3.5.A1520-1521–
WarrantyWarrantyThe Contractor shall remedy any defect due to faulty material ...Sanitary Sewer Utilities33 30 00 1.10.A · PDF p. 1526
Spec wording
“A. The Contractor shall remedy any defect due to faulty material or workmanship and pay for any damage to other work resulting therefrom within a period of one year from final acceptance. Further, the Contractor will provide all manufacturers' and supplier's written guarantees and warranties covering materials and equipment furnished under this Contract.”
33 30 00 1.10.A1526–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.