Closeout checklist: Replace HVAC, Gentry Residential Treatment Center (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 60 items across Division 01, 3 trade divisions and the contract conditions, including 25 warranties, 13 training items and 9 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project H2409-01
- Location
- Cabool, MO
- Bid date
- 2025-09-23
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 241 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 60 items, by trade
Division 01 General requirements 13 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe Contractor shall submit to the Designer, within ten (10) ...Schedules01 32 00 3.1.A · PDF p. 90Spec wording“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...” | 01 32 00 3.1.A | 90 | – |
| Warranty | WarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.7.A · PDF p. 97Spec wording“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.” | 01 33 00 1.7.A | 97 | – |
| Warranty | WarrantyContractor shall submit the following information for materials and equipment ...Submittals01 33 00 3.1.A · PDF p. 97-98Spec wording“A. Contractor shall submit the following information for materials and equipment to be provided under this contract. SPEC SECTION TITLE CATEGORY 013200 Schedules Construction Schedule 013200 Schedules Schedule of Values 013200 Schedules List of Subcontractors 013200 Schedules Major Material Suppliers 033000 Cast-in-Place Concrete Product Data 099113 Exterior Painting Product Data 220517 Sleeves and Sleeve Seals for ...” | 01 33 00 3.1.A | 97-98 | – |
| Training | TrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 115Spec wording“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.” | 01 79 00 1.3.A | 115 | – |
| Training | TrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 115Spec wording“B. Attendance Record: For each training module, submit list of participants and length of instruction time.” | 01 79 00 1.3.B | 115 | – |
| Training | TrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 115Spec wording“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.” | 01 79 00 1.3.C | 115 | – |
| Training | TrainingFacilitator QualificationsDemonstration And Training01 79 00 1.4.A · PDF p. 115Spec wording“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.” | 01 79 00 1.4.A | 115 | – |
| Training | TrainingPreinstruction ConferenceDemonstration And Training01 79 00 1.4.C · PDF p. 115-116Spec wording“C. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Coordination". Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, ...” | 01 79 00 1.4.C | 115-116 | – |
| O&M | O&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.5.C · PDF p. 116Spec wording“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.” | 01 79 00 1.5.C | 116 | – |
| Warranty | WarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 116-117Spec wording“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...” | 01 79 00 2.1.B | 116-117 | – |
| Training | TrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 118Spec wording“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".” | 01 79 00 3.1.A | 118 | – |
| Training | TrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 118Spec wording“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Architect will furnish an instructor to describe basis of system design, operational requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names ...” | 01 79 00 3.2.A | 118 | – |
| Training | TrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 118Spec wording“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.” | 01 79 00 3.2.B | 118 | – |
Division 07 Roofing, insulation and waterproofing 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyThe contractor shall maintain the existing warranty for all new ...Existing Roofing Warranty07 50 00 1.01.A · PDF p. 122-123Spec wording“A. The contractor shall maintain the existing warranty for all new roof penetrations. Attached is the current roofing warranties for the facilities roofs applicable to this project. ROOFING INSTALLER'S WARRANTY” | 07 50 00 1.01.A | 122-123 | – |
| Warranty | WarrantyWHEREAS (~ooltq utSExisting Roofing Warranty07 50 00 1.01.A · PDF p. 123Spec wording“A. WHEREAS (~ooltq utS” | 07 50 00 1.01.A | 123 | – |
| Warranty | WarrantyOf C00 /' herein called the "Roofing Installer," has performed ...Existing Roofing Warranty07 50 00 1.01.B · PDF p. 123Spec wording“B. Of C00 /' herein called the "Roofing Installer," has performed roofing and associated work ("work") on the following project: , l,SsQur21 '1gvISl0'J OF /- ;9C)o7/l3 f0' 1jD66E70EA)T 1. Owner: S - ITE OF I 2. Address: sai) CJTy / I4, asou ~e 1 3. BuildingName/Type: Giapgr2`-? Re i DEk)7/)-')c ~E~aTIhEs ) T Crc-i ~ 4. Address: cM - OL t , SS Cx & r2 ► 5. Area of Work: ROOF V-A P IDLA 6. Acceptance Date: 1D/3 12 o ...” | 07 50 00 1.01.B | 123 | – |
| Warranty | WarrantyAND WHEREAS Roofing Installer has contracted (either directly with Owner ...Existing Roofing Warranty07 50 00 1.01.C · PDF p. 123Spec wording“C. AND WHEREAS Roofing Installer has contracted (either directly with Owner or indirectly as a subcontractor) to warrant said work against leaks and faulty or defective materials and workmanship for designated Warranty Period,” | 07 50 00 1.01.C | 123 | – |
| Warranty | WarrantyNOW THEREFORE Roofing Installer hereby warrants, subject to terms and ...Existing Roofing Warranty07 50 00 1.01.D · PDF p. 123Spec wording“D. NOW THEREFORE Roofing Installer hereby warrants, subject to terms and conditions herein set forth, that during Warranty Period he will, at his own cost and expense, make or cause to be made such repairs to or replacements of said work as are necessary to correct faulty and defective work and as are necessary to maintain said work in a watertight condition.” | 07 50 00 1.01.D | 123 | – |
| Warranty | WarrantyThis Warranty is made subject to the following terms and conditionsExisting Roofing Warranty07 50 00 1.01.E · PDF p. 123-124Spec wording“E. This Warranty is made subject to the following terms and conditions: Specifically excluded from this Warranty are damages to work and other parts of the building, and to building contents, caused by: a. lightning; b. peak gust wind speed exceeding 70 mph; c. fire; d. failure of roofing system substrate, including cracking, settlement, excessive deflection, deterioration, and decomposition; e. faulty construction ...” | 07 50 00 1.01.E | 123-124 | – |
| Warranty | WarrantyIN WITNESS THEREOF, this instrument has been duly executed this ...Existing Roofing Warranty07 50 00 1.01.F · PDF p. 124-126Spec wording“F. IN WITNESS THEREOF, this instrument has been duly executed this ,/(p day of OC 7-0 13,5e 1. Authorized Sign 2. Printed Name: Rrni)/ 3. Title: / Ple /I'16(' L. MW — - BUILDING PRODUCTS BUILDING PRODUCTS FOR THE PROFESSIONAL. Heritage® Vintage® Since 1944, building professionals and homeowners have looked to TAMKO for Heritage® Premium quality products that are built to perform. Our extensive line of residential ...” | 07 50 00 1.01.F | 124-126 | CD |
| Warranty | WarrantyC- = 02= (0 CC Co 0 o o 0 ...Existing Roofing Warranty07 50 00 1.01.A · PDF p. 126-128Spec wording“A. C- = 02= (0 CC Co 0 o o 0 0 0 0 0 - •=-= C = 5 Cf 5555555 0 CC 5 = CC 2 55 = 0 C 0000000 00 5 0 Co 02 0 CO CO CO 00 0Co Ct) . CO CO CO CO CO CO _o0oE ct .0 = 5 = 5 -SE oEQ E50- Co 5 SC :E .5 = - JO 0 Cfl C 0 = = - _5 0= 0 - EQ 0-CC 5 )5 CC.2 Co Co-0> 0 0 = 5 0.0=5 - C =CCc)C Ct 5 = < c.-o5 _.__00.0CoCflC S -= Co COO 0C 0 51 80 Uoo:o.S.22EQ5o 5 w 2 -JI U)0,g000 - CS 2 .5 5.5 5• co S O_OCtCt.°0C 55:5•5.5 =8 =5 ...” | 07 50 00 1.01.A | 126-128 | CD |
Division 22 Plumbing 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MOperation and Maintenance DataGeneral-Duty Valves For Plumbing Piping22 05 23 1.04.C · PDF p. 134Spec wording“C. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions, maintenance and repair data, and parts listings.” | 22 05 23 1.04.C | 134 | – |
Division 23 HVAC 26 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.TAB PlanTesting, Adjusting, And Balancing For Hvac23 05 93 1.04.B · PDF p. 155Spec wording“B. TAB Plan: Submit a written plan indicating the testing, adjusting, and balancing standard to be followed and the specific approach for each system and component. 1. Include at least the following in the plan: a. List of all air flow, water flow, sound level, system capacity and efficiency measurements to be performed and a description of specific test procedures, parameters, formulas to be used. b. Copy of field ...” | 23 05 93 1.04.B | 155 | – |
| O&M | O&MFinal ReportTesting, Adjusting, And Balancing For Hvac23 05 93 1.04.C · PDF p. 155-156Spec wording“C. Final Report: Indicate deficiencies in systems that would prevent proper testing, adjusting, and balancing of systems and equipment to achieve specified performance. 1. Revise TAB plan to reflect actual procedures and submit as part of final report. 2. Submit draft copies of report for review prior to final acceptance of Project. Provide final copies for Architect and for inclusion in operating and maintenance ...” | 23 05 93 1.04.C | 155-156 | – |
| O&M | O&MAll submittals and documentation including complete System engineering design submittal ...Direct-Digital Control System For Hvac23 09 23 1.05.C · PDF p. 165Spec wording“C. All submittals and documentation including complete System engineering design submittal & drawings, project record documents, application engineering documents, and Operation & Maintenance manuals shall be submitted electronically in the form of an ISO 32000 Portable Document Format (PDF). 1. All control schematics, wiring diagrams, riser diagrams, etc. shall be formatted for ANSI B (279 mm x 432 mm; 11" x 17") ...” | 23 09 23 1.05.C | 165 | electronically; PDF |
| Training | TrainingProvide training course outline and curricula at least six (6) ...Direct-Digital Control System For Hvac23 09 23 1.07.A · PDF p. 168Spec wording“A. Provide training course outline and curricula at least six (6) weeks prior to training. Engineer and/or Owner shall modify the curricula as necessary to meet the Owner's Project Requirements (OPR). Revised curricula shall be returned no later than three (3) weeks prior to the training.” | 23 09 23 1.07.A | 168 | – |
| Warranty | WarrantyThe System Manufacturer shall warranty all DDC controllers to be ...Direct-Digital Control System For Hvac23 09 23 1.08.A · PDF p. 168Spec wording“A. The System Manufacturer shall warranty all DDC controllers to be free of defect in material and workmanship under normal operation and expected service as published by the manufacturer in the unit's performance specifications for a period of five (5) years at a minimum. 1. Sensors and field components integral to DDC controllers shall be warrantied to be free of defect in material and workmanship under normal ...” | 23 09 23 1.08.A | 168 | – |
| Warranty | WarrantyThe System Contractor shall warranty the installation of all other ...Direct-Digital Control System For Hvac23 09 23 1.08.B · PDF p. 168Spec wording“B. The System Contractor shall warranty the installation of all other DDC materials and labor to be free of defects under normal expected service and use for a period of one (1) year from the date of final acceptance.” | 23 09 23 1.08.B | 168 | – |
| Warranty | WarrantyWarranty service response shall be during normal business hours within ...Direct-Digital Control System For Hvac23 09 23 1.08.C · PDF p. 168Spec wording“C. Warranty service response shall be during normal business hours within twenty-four (24) hours of the Owner's warranty service request. 1. Except in the event of property loss or damage, or as indicated otherwise in the Contract Documents, warranty service shall be provided during regular working hours Monday through Friday.” | 23 09 23 1.08.C | 168 | – |
| Warranty | WarrantyOperator workstation software, project-specific software, graphic software, database software, and ...Direct-Digital Control System For Hvac23 09 23 1.08.D · PDF p. 168Spec wording“D. Operator workstation software, project-specific software, graphic software, database software, and firmware provided under this specification required to resolve deficiencies shall be provided at no charge during the warranty period. If available, the owner can purchase an in-warranty service agreement to receive upgrades for functional enhancements associated with above-mentioned items. 1. After acceptance of ...” | 23 09 23 1.08.D | 168 | – |
| Training | TrainingThe Contractor shall provide instruction on the adjustment, operation and ...Direct-Digital Control System For Hvac23 09 23 3.07.A · PDF p. 175Spec wording“A. The Contractor shall provide instruction on the adjustment, operation and maintenance of the System including all hardware and software provided and installed in compliance with the requirements of this specification. 1. Training shall be performed by a manufacturer's representative and/or instructor or a manufacturer-trained application engineer and/or technician with a minimum of 5-years of experience in the ...” | 23 09 23 3.07.A | 175 | – |
| Training | TrainingTraining in the operation of the System shall be performed ...Direct-Digital Control System For Hvac23 09 23 3.07.B · PDF p. 175Spec wording“B. Training in the operation of the System shall be performed utilizing a BACnet network of working controllers representative of the installed network and/or the Owner's facility and shall include: 1. Overview of the installed system and network architecture. 2. System components. 3. Graphical User Interface (GUI) operation. 4. Day-to-day operations including modification of system setpoints, schedules, calendars, ...” | 23 09 23 3.07.B | 175 | – |
| Training | TrainingTraining videos that describe the operation of the System shall ...Direct-Digital Control System For Hvac23 09 23 3.07.C · PDF p. 175Spec wording“C. Training videos that describe the operation of the System shall be provided, and/or made accessible, to the Owner.” | 23 09 23 3.07.C | 175 | – |
| Training | TrainingOn-site walk-through shall cover the deployment and execution of the ...Direct-Digital Control System For Hvac23 09 23 3.07.D · PDF p. 175Spec wording“D. On-site walk-through shall cover the deployment and execution of the complete System and components including: 1. Sequences of Operation. 2. Location of all panels, enclosures, controllers, devices, sensors, etc. and equipment and panel lay-out. 3. Hardware preventive maintenance, calibration, troubleshooting, maintenance, and repair. 4. Proper use of service tools and materials.” | 23 09 23 3.07.D | 175 | – |
| O&M | O&MOperation And Maintenance DataDedicated Outdoor Air Units23 74 33 1.03.C · PDF p. 192Spec wording“C. Operation And Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listing.” | 23 74 33 1.03.C | 192 | – |
| Warranty | WarrantyWarrantyDedicated Outdoor Air Units23 74 33 1.03.D · PDF p. 192Spec wording“D. Warranty: Submit manufacturers warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.” | 23 74 33 1.03.D | 192 | – |
| Warranty | WarrantySee Section 01 78 00 - Closeout Submittals, for additional ...Dedicated Outdoor Air Units23 74 33 1.05.A · PDF p. 192Spec wording“A. See Section 01 78 00 - Closeout Submittals, for additional warranty requirements.” | 23 74 33 1.05.A | 192 | – |
| Warranty | WarrantyProvide five year manufacturers warranty for part and labor heat ...Dedicated Outdoor Air Units23 74 33 1.05.B · PDF p. 192Spec wording“B. Provide five year manufacturers warranty for part and labor heat pump compressor/condenser unit.” | 23 74 33 1.05.B | 192 | – |
| Warranty | WarrantyProvide twenty-five year manufacturers warranty for parts for heat exchanger ...Dedicated Outdoor Air Units23 74 33 1.05.C · PDF p. 192Spec wording“C. Provide twenty-five year manufacturers warranty for parts for heat exchanger.” | 23 74 33 1.05.C | 192 | – |
| Warranty | WarrantyManufacturer shall provide a limited "parts only" warranty for a ...Dedicated Outdoor Air Units23 74 33 1.05.D · PDF p. 192-193Spec wording“D. Manufacturer shall provide a limited "parts only" warranty for a period of 24 months from the date of original equipment shipment from the factory. Warranty shall cover material and workmanship that prove defective, within the specified warranty period, provided manufacturer's written instructions for Installation, Operation, and maintenance have been followed. Warranty excludes parts associated with routine ...” | 23 74 33 1.05.D | 192-193 | – |
| Test / cert. | Test / cert.Prepare and start equipment. Adjust for proper operationDedicated Outdoor Air Units23 74 33 3.02.A · PDF p. 197Spec wording“A. Prepare and start equipment. Adjust for proper operation.” | 23 74 33 3.02.A | 197 | – |
| Test / cert. | Test / cert.Engage a factory-authorized service representative to perform startup service ...Dedicated Outdoor Air Units23 74 33 3.02.B · PDF p. 197Spec wording“B. Engage a factory-authorized service representative to perform startup service.” | 23 74 33 3.02.B | 197 | – |
| Test / cert. | Test / cert.Complete installation and startup checks according to manufacturer's written instruction. ...Dedicated Outdoor Air Units23 74 33 3.02.C · PDF p. 197Spec wording“C. Complete installation and startup checks according to manufacturer's written instruction. Submit start up sheets to engineer for review.” | 23 74 33 3.02.C | 197 | – |
| Test / cert. | Test / cert.After startup and performance testing and prior to substantial completion, ...Dedicated Outdoor Air Units23 74 33 3.02.D · PDF p. 197Spec wording“D. After startup and performance testing and prior to substantial completion, replace existing filters with new filters.” | 23 74 33 3.02.D | 197 | – |
| Test / cert. | Test / cert.Manufacturer shall provide startup repair for a period of 12 ...Dedicated Outdoor Air Units23 74 33 3.02.E · PDF p. 197Spec wording“E. Manufacturer shall provide startup repair for a period of 12 months from the date of original equipment shipment from the factory. Program shall cover labor for materials and workmanship that prove defective, within the specified warranty period, provided manufacturer's written instructions for installation, operation and maintenance have been followed. Program excludes labor associated with routine maintenance, ...” | 23 74 33 3.02.E | 197 | – |
| Warranty | WarrantyWarrantySmall-Capacity Split-System Air Conditioners23 81 26.13 1.04.C · PDF p. 198Spec wording“C. Warranty: Submit manufacturers warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.” | 23 81 26.13 1.04.C | 198 | – |
| Warranty | WarrantySee Section 01 78 00 - Closeout Submittals, for additional ...Small-Capacity Split-System Air Conditioners23 81 26.13 1.05.A · PDF p. 198Spec wording“A. See Section 01 78 00 - Closeout Submittals, for additional warranty requirements.” | 23 81 26.13 1.05.A | 198 | – |
| Warranty | WarrantyProvide ten year manufacturers warranty for heat exchangersSmall-Capacity Split-System Air Conditioners23 81 26.13 1.05.B · PDF p. 198Spec wording“B. Provide ten year manufacturers warranty for heat exchangers.” | 23 81 26.13 1.05.B | 198 | – |
Front end Contract conditions (final payment, releases, retainage) 12 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 21Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 21 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 32Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 32 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 33Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 33 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 39Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 39 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 40Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 40 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 58Spec wording“The Contractor agrees to maintain all books, records and reports required under this contract for a period of not less than three years after final payment is made and all pending matters are closed. 17.0 Occupational Health and Safety Act All contracts and subcontracts that result from this solicitation incorporate by reference the requirements of 29 C.F.R. pt. 1910 with the same force and effect as if given in ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 58 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 32Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 32 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 32Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 32 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 32-33Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 32-33 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 33Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 33 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 37-38Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 37-38 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 38Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 38 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.