Closeout checklist: Replace HVAC and Exterior Repairs, Ike Skelton Training Site (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 70 items across Division 01, 6 trade divisions and the contract conditions, including 17 training items, 16 tests and certificates and 14 warranties. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project T2406-01
- Location
- Jefferson City, MO
- Bid date
- 2025-06-24
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 415 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 70 items, by trade
Division 01 General requirements 20 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 68Spec wording“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...” | 01 32 00 3.1.A | 68 | – |
| Warranty | WarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 76Spec wording“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.” | 01 33 00 1.8.A | 76 | – |
| Warranty | WarrantyContractor shall submit the following general list of information for ...Submittals01 33 00 3.1.A · PDF p. 76-77Spec wording“A. Contractor shall submit the following general list of information for materials and equipment to be provided under this contract. SPEC SECTION TITLE CATEGORY 013100 Coordination Product Data 013200 Schedules - Bar Chart Construction Schedule 013300 Submittals Product Data 013513.28 Site Security and Health Requirements Construction Schedule 015000 Construction Facilities and Temporary Controls Construction ...” | 01 33 00 3.1.A | 76-77 | – |
| Training | TrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 96Spec wording“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.” | 01 79 00 1.3.A | 96 | – |
| Training | TrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 96Spec wording“B. Attendance Record: For each training module, submit list of participants and length of instruction time.” | 01 79 00 1.3.B | 96 | – |
| Training | TrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 96Spec wording“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.” | 01 79 00 1.3.C | 96 | – |
| Training | TrainingDemonstration and Training Video RecordingsDemonstration And Training01 79 00 1.4.A · PDF p. 96Spec wording“A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. Transcript: Prepared in PDF electronic format. ...” | 01 79 00 1.4.A | 96 | two copies; PDF; electronic format; electronic file |
| Training | TrainingFacilitator QualificationsDemonstration And Training01 79 00 1.5.A · PDF p. 97Spec wording“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.” | 01 79 00 1.5.A | 97 | – |
| Training | TrainingPreinstruction ConferenceDemonstration And Training01 79 00 1.5.C · PDF p. 97Spec wording“C. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Coordination". Review methods and procedures related to demonstration and training including, but not limited to, the following: 1. Inspect and discuss locations and other facilities required for instruction. 2. Review and finalize instruction schedule and verify availability of educational materials, ...” | 01 79 00 1.5.C | 97 | – |
| O&M | O&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.6.C · PDF p. 97Spec wording“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.” | 01 79 00 1.6.C | 97 | – |
| Warranty | WarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 97-99Spec wording“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...” | 01 79 00 2.1.B | 97-99 | – |
| Training | TrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 99Spec wording“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".” | 01 79 00 3.1.A | 99 | – |
| Training | TrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 99Spec wording“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Architect will furnish an instructor to describe basis of system design, operational requirements, criteria, and regulatory requirements. 2. Owner will furnish an instructor to describe Owner's operational philosophy. 3. Owner will furnish Contractor with names ...” | 01 79 00 3.2.A | 99 | – |
| Training | TrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 99Spec wording“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.” | 01 79 00 3.2.B | 99 | – |
| Training | TrainingGeneralDemonstration And Training01 79 00 3.3.A · PDF p. 99Spec wording“A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. 1. At beginning of each training module, record each chart containing learning objective and lesson outline.” | 01 79 00 3.3.A | 99 | – |
| Training | TrainingVideoDemonstration And Training01 79 00 3.3.B · PDF p. 99-100Spec wording“B. Video: Provide minimum 640 x 480 video resolution converted to format file type acceptable to Owner, on electronic media. 1. Electronic Media: Read-only format compact disc acceptable to Owner, with commercial-grade graphic label. 2. File Hierarchy: Organize folder structure and file locations according to project manual table of contents. Provide complete screen-based menu. 3. File Names: Utilize file names ...” | 01 79 00 3.3.B | 99-100 | electronic media; DVD |
| Training | TrainingLight LevelsDemonstration And Training01 79 00 3.3.D · PDF p. 100Spec wording“D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. 1. Furnish additional portable lighting as required.” | 01 79 00 3.3.D | 100 | – |
| Training | TrainingNarrationDemonstration And Training01 79 00 3.3.E · PDF p. 100Spec wording“E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.” | 01 79 00 3.3.E | 100 | – |
| Training | TrainingTranscriptDemonstration And Training01 79 00 3.3.F · PDF p. 100Spec wording“F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.” | 01 79 00 3.3.F | 100 | – |
| Training | TrainingPreproduced Video RecordingsDemonstration And Training01 79 00 3.3.G · PDF p. 100Spec wording“G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.” | 01 79 00 3.3.G | 100 | – |
Division 02 Existing conditions 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyWarrantiesSelective Demolition02 41 19 1.6.D · PDF p. 102Spec wording“D. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.” | 02 41 19 1.6.D | 102 | – |
| Closeout step | Closeout stepInventorySelective Demolition02 41 19 1.7.A · PDF p. 102Spec wording“A. Inventory: Submit a list of items that have been removed and salvaged.” | 02 41 19 1.7.A | 102 | – |
Division 07 Roofing, insulation and waterproofing 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Product test reportsFoamed-In-Place Insulation07 21 19 1.3.A · PDF p. 109Spec wording“A. Product test reports.” | 07 21 19 1.3.A | 109 | – |
| Test / cert. | Test / cert.Field Quality-Control ReportsJoint Sealants07 92 00 1.3.A · PDF p. 110Spec wording“A. Field Quality-Control Reports: For field-adhesion-test reports, for each sealant application tested.” | 07 92 00 1.3.A | 110 | – |
| Warranty | WarrantyWarranty Documentation:Joint Sealants07 92 00 1.4.A · PDF p. 110Spec wording“A. Warranty Documentation: 1. Manufacturers' special warranties. 2. Installer's special warranties.” | 07 92 00 1.4.A | 110 | – |
| Warranty | WarrantySpecial Installer's WarrantyJoint Sealants07 92 00 1.6.A · PDF p. 110Spec wording“A. Special Installer's Warranty: Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period. 1. Warranty Period: Two years from date of Substantial Completion.” | 07 92 00 1.6.A | 110 | – |
| Warranty | WarrantySpecial Manufacturer's WarrantyJoint Sealants07 92 00 1.6.B · PDF p. 110Spec wording“B. Special Manufacturer's Warranty: Manufacturer agrees to furnish joint sealants to repair or replace those joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period. 1. Warranty Period: Five years from date of Substantial Completion.” | 07 92 00 1.6.B | 110 | – |
| Warranty | WarrantySpecial warranties specified in this article exclude deterioration or failure ...Joint Sealants07 92 00 1.6.C · PDF p. 111Spec wording“C. Special warranties specified in this article exclude deterioration or failure of joint sealants from the following: 1. Movement of the structure caused by stresses on the sealant exceeding sealant manufacturer's written specifications for sealant elongation and compression. 2. Disintegration of joint substrates from causes exceeding design specifications. 3. Mechanical damage caused by individuals, tools, or ...” | 07 92 00 1.6.C | 111 | – |
Division 08 Doors, windows and hardware 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Storefront System Design CertificationAluminum Storefront And Doors08 42 10 1.4.D · PDF p. 115Spec wording“D. Storefront System Design Certification: Submit a written certification, signed and sealed by an engineer registered in the state where the structure is located, stating that the system and its anchorage to the structure has been designed to support the required design wind load as indicated in the General Notes found on the structural drawings without exceeding the allowable stresses of the material and without ...” | 08 42 10 1.4.D | 115 | – |
| Warranty | WarrantyWarrantyAluminum Storefront And Doors08 42 10 1.6.A · PDF p. 115Spec wording“A. Warranty: Manufacturer and/or Installer agrees to repair or replace components of aluminum-framed entrances that do not comply with requirements or that fail in materials or workmanship within specified warranty period. 1. Warranty Period: Two years from date of Substantial Completion. 2. Finish Warranty: Manufacturer agrees to repair finishes or replace aluminum that shows evidence of deterioration of ...” | 08 42 10 1.6.A | 115 | – |
| Test / cert. | Test / cert.Product test reportsGlazing08 80 00 1.5.B · PDF p. 120Spec wording“B. Product test reports.” | 08 80 00 1.5.B | 120 | – |
| Test / cert. | Test / cert.Preconstruction adhesion and compatibility test reportGlazing08 80 00 1.5.C · PDF p. 120Spec wording“C. Preconstruction adhesion and compatibility test report.” | 08 80 00 1.5.C | 120 | – |
| Warranty | WarrantyManufacturer's Special Warranty for Coated-Glass ProductsGlazing08 80 00 1.7.A · PDF p. 121Spec wording“A. Manufacturer's Special Warranty for Coated-Glass Products: Manufacturer agrees to replace coated-glass units that deteriorate within specified warranty period. Deterioration of coated glass is defined as defects developed from normal use that are not attributed to glass breakage or to maintaining and cleaning coated glass contrary to manufacturer's written instructions. Defects include peeling, cracking, and ...” | 08 80 00 1.7.A | 121 | – |
| Warranty | WarrantyManufacturer's Special Warranty for Insulating GlassGlazing08 80 00 1.7.B · PDF p. 121Spec wording“B. Manufacturer's Special Warranty for Insulating Glass: Manufacturer agrees to replace insulating-glass units that deteriorate within specified warranty period. Deterioration of insulating glass is defined as failure of hermetic seal under normal use that is not attributed to glass breakage or to maintaining and cleaning insulating glass contrary to manufacturer's written instructions. Evidence of failure is ...” | 08 80 00 1.7.B | 121 | – |
Division 09 Finishes 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Product Test ReportsAcoustical Tile Ceilings09 51 23 1.5.A · PDF p. 134Spec wording“A. Product Test Reports: For each acoustical tile ceiling, for tests performed by manufacturer and witnessed by a qualified testing agency.” | 09 51 23 1.5.A | 134 | – |
| Spare parts | Spare partsFurnish extra materials that match products installed and that are ...Acoustical Tile Ceilings09 51 23 1.6.A · PDF p. 134Spec wording“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Acoustical Ceiling Units: Full-size tiles equal to 2 percent of quantity installed. 2. Suspension-System Components: Quantity of each concealed grid and exposed component equal to 2 percent of quantity installed.” | 09 51 23 1.6.A | 134 | Full-size |
| Spare parts | Spare partsFurnish extra materials that match products installed and that are ...Resilient Tile Flooring09 65 10 1.7.A · PDF p. 142Spec wording“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Floor Tile: Furnish 3 boxes of each type, color, and pattern of floor tile installed.” | 09 65 10 1.7.A | 142 | – |
| Spare parts | Spare partsFurnish extra materials that match products installed and that are ...Resilient Base And Accessories09 65 13 1.4.A · PDF p. 145Spec wording“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Furnish not less than 10 linear feet for every 200 linear feet or fraction thereof, of each type, color, pattern, and size of resilient product installed.” | 09 65 13 1.4.A | 145 | – |
| Spare parts | Spare partsFurnish extra materials described below that are from same production ...Interior Painting09 91 23 1.9.A · PDF p. 150Spec wording“A. Furnish extra materials described below that are from same production run (batch mix) as materials applied and that are packaged for storage and identified with labels describing contents. 1. Quantity: Furnish an additional 5 percent, but not less than 1 gal. of each material and color applied” | 09 91 23 1.9.A | 150 | – |
| Test / cert. | Test / cert.Material test reportsIntumescent Painting09 96 46 1.4.A · PDF p. 154Spec wording“A. Material test reports.” | 09 96 46 1.4.A | 154 | – |
Division 23 HVAC 15 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Prepare test and inspection reportsVibration And Seismic Controls For Hvac Piping And Equipment23 05 48 3.5.E · PDF p. 210Spec wording“E. Prepare test and inspection reports.” | 23 05 48 3.5.E | 210 | – |
| Test / cert. | Test / cert.Take and report testing and balancing measurements in inch-pound (IP) ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.3.D · PDF p. 220Spec wording“D. Take and report testing and balancing measurements in inch-pound (IP) units.” | 23 05 93 3.3.D | 220 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsMetal Ducts23 31 13 3.8.D · PDF p. 329Spec wording“D. Prepare test and inspection reports.” | 23 31 13 3.8.D | 329 | – |
| O&M | O&MOperation and Maintenance DataHvac Power Ventilators23 34 23 1.4.B · PDF p. 346Spec wording“B. Operation and Maintenance Data: For power ventilators to include in emergency, operation, and maintenance manuals.” | 23 34 23 1.4.B | 346 | – |
| Spare parts | Spare partsFurnish extra materials described below that match products installed and ...Hvac Power Ventilators23 34 23 1.8.A · PDF p. 347Spec wording“A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Belts: One set for each belt-driven unit.” | 23 34 23 1.8.A | 347 | One set |
| O&M | O&MOperation and Maintenance DataAir Terminal Units23 36 00 1.3.C · PDF p. 350Spec wording“C. Operation and Maintenance Data: For air terminal units to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. Instructions for resetting minimum and maximum air volumes. 2. Instructions for adjusting software set points.” | 23 36 00 1.3.C | 350 | – |
| Test / cert. | Test / cert.Perform startup serviceAir Terminal Units23 36 00 3.7.A · PDF p. 354Spec wording“A. Perform startup service. 1. Complete installation and startup checks according to manufacturer's written instructions. 2. Verify that inlet duct connections are as recommended by air terminal unit manufacturer to achieve proper performance. 3. Verify that controls and control enclosure are accessible. 4. Verify that control connections are complete. 5. Verify that nameplate and identification tag are visible. 6. ...” | 23 36 00 3.7.A | 354 | – |
| Training | TrainingTrain Owner's maintenance personnel to adjust, operate, and maintain air ...Air Terminal Units23 36 00 3.8.A · PDF p. 354Spec wording“A. Train Owner's maintenance personnel to adjust, operate, and maintain air terminal units.” | 23 36 00 3.8.A | 354 | – |
| O&M | O&MOperation and Maintenance DataDiffusers, Registers, And Grilles23 37 13 1.4.B · PDF p. 358Spec wording“B. Operation and Maintenance Data: For air-handling units to include in emergency, operation, and maintenance manuals.” | 23 37 13 1.4.B | 358 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsDiffusers, Registers, And Grilles23 37 13 3.4.E · PDF p. 366Spec wording“E. Prepare test and inspection reports.” | 23 37 13 3.4.E | 366 | – |
| Test / cert. | Test / cert.Engage a factory-authorized service representative to perform startup service ...Diffusers, Registers, And Grilles23 37 13 3.5.A · PDF p. 366Spec wording“A. Engage a factory-authorized service representative to perform startup service. 1. Complete installation and startup checks according to manufacturer's written instructions. 2. Verify that shipping, blocking, and bracing are removed. 3. Verify that unit is secure on mountings and supporting devices and that connections to piping, ducts, and electrical systems are complete. Verify that proper thermal-overload ...” | 23 37 13 3.5.A | 366 | – |
| Test / cert. | Test / cert.Starting procedures for air-handling units include the following:Diffusers, Registers, And Grilles23 37 13 3.5.B · PDF p. 366Spec wording“B. Starting procedures for air-handling units include the following: 1. Energize motor; verify proper operation of motor, drive system, and fan wheel. 2. Measure and record motor electrical values for voltage and amperage. 3. Manually operate dampers from fully closed to fully open position and record fan performance.” | 23 37 13 3.5.B | 366 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Diffusers, Registers, And Grilles23 37 13 3.8.A · PDF p. 367Spec wording“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain air-handling units.” | 23 37 13 3.8.A | 367 | – |
| O&M | O&MOperation and maintenance dataCabinet Unit Heaters23 82 39.13 1.3.A · PDF p. 368Spec wording“A. Operation and maintenance data.” | 23 82 39.13 1.3.A | 368 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsCabinet Unit Heaters23 82 39.13 3.4.C · PDF p. 372Spec wording“C. Prepare test and inspection reports.” | 23 82 39.13 3.4.C | 372 | – |
Division 26 Electrical 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MProvide operating instructions and maintenance manuals in accordance with Section ...Common Work Results For Electrical26 05 00 1.6.H · PDF p. 375Spec wording“H. Provide operating instructions and maintenance manuals in accordance with Section 013300 – Submittals and Section 007000 – Conditions of the Contract.” | 26 05 00 1.6.H | 375 | – |
| Record docs | Record docsThe Contractor shall update a complete set of the construction ...Common Work Results For Electrical26 05 00 1.7.A · PDF p. 375Spec wording“A. The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work daily by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative in accordance with Section 007000 – Conditions of the Contract. The updates shall show all addenda, all field ...” | 26 05 00 1.7.A | 375 | electronic file |
| Record docs | Record docsNo deviations from the Contract Drawings or approved shop drawings ...Common Work Results For Electrical26 05 00 1.7.B · PDF p. 375Spec wording“B. No deviations from the Contract Drawings or approved shop drawings shall be made without prior approval from the Engineer or Construction Representative.” | 26 05 00 1.7.B | 375 | – |
| Warranty | WarrantyExisting WarrantiesSelective Demolition For Electrical26 05 05 1.9.A · PDF p. 387Spec wording“A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.” | 26 05 05 1.9.A | 387 | – |
Front end Contract conditions (final payment, releases, retainage) 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 24Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 24 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 35Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 35 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 36Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 36 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 42Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 42 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 43Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 43 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 35Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 35 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 35Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 35 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 35-36Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 35-36 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 36Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 36 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 40-41Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 40-41 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 41Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 41 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.