Closeout checklist: Renovate 3B for Patient Privacy and Intensive Care Unit, Marion VA Medical Center (U.S. Department of Veterans Affairs, IL)
Every closeout item we found in the public spec book for this job: 555 items across Division 01, 17 trade divisions, including 273 tests and certificates, 75 warranties and 71 training items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- U.S. Department of Veterans Affairs, Network Contracting Office 15
- Number
- Solicitation 36C25525R0015
- Location
- Marion, IL
- Contract signed
- 2025-03-18
- Spec book size
- 1,723 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 555 items, by trade
Division 01 General requirements 105 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsThe contractor shall maintain two full size sets of as-built ...General Requirements01 00 00 1.11.A · PDF p. 31Spec wording“A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.” | 01 00 00 1.11.A | 31 | two full size sets |
| Record docs | Record docsAll variations shall be shown in the same general detail ...General Requirements01 00 00 1.11.B · PDF p. 31Spec wording“B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.” | 01 00 00 1.11.B | 31 | – |
| Record docs | Record docsContractor shall deliver two approved completed sets of as-built drawings ...General Requirements01 00 00 1.11.C · PDF p. 32Spec wording“C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR [Chief Engineer][Chief of Facilities Management] within 15 calendar days after each completed phase and after the acceptance of the project by the COR.” | 01 00 00 1.11.C | 32 | electronic version; PDF |
| Record docs | Record docsParagraphs A, B, & C shall also apply to all shop drawingsGeneral Requirements01 00 00 1.11.D · PDF p. 32Spec wording“D. Paragraphs A, B, & C shall also apply to all shop drawings.” | 01 00 00 1.11.D | 32 | – |
| Warranty | WarrantyWarranty Management PlanGeneral Requirements01 00 00 1.12.A · PDF p. 32-34Spec wording“A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan ...” | 01 00 00 1.12.A | 32-34 | one set; binder |
| Warranty | WarrantyPerformance & Payment BondsGeneral Requirements01 00 00 1.12.B · PDF p. 34-35Spec wording“B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period. 1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the ...” | 01 00 00 1.12.B | 34-35 | – |
| Warranty | WarrantyPre-Warranty ConferenceGeneral Requirements01 00 00 1.12.C · PDF p. 35-36Spec wording“C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for ...” | 01 00 00 1.12.C | 35-36 | – |
| Warranty | WarrantyContractor's Response to Construction Warranty Service Requirements:General Requirements01 00 00 1.12.D · PDF p. 36Spec wording“D. Contractor's Response to Construction Warranty Service Requirements:” | 01 00 00 1.12.D | 36 | – |
| Warranty | WarrantyFollowing oral or written notification by the Contracting Officer, the ...General Requirements01 00 00 1.12.E · PDF p. 36-38Spec wording“E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date ...” | 01 00 00 1.12.E | 36-38 | – |
| Warranty | WarrantyWarranty TagsGeneral Requirements01 00 00 1.12.F · PDF p. 38-39Spec wording“F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for ...” | 01 00 00 1.12.F | 38-39 | – |
| O&M | O&MContractor shall furnish Maintenance and Operating manuals (hard copies and ...General Requirements01 00 00 1.20.A · PDF p. 46Spec wording“A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.” | 01 00 00 1.20.A | 46 | – |
| O&M | O&MManualsGeneral Requirements01 00 00 1.20.B · PDF p. 46Spec wording“B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, ...” | 01 00 00 1.20.B | 46 | four hard copies; one electronic copy |
| Training | TrainingInstructionsGeneral Requirements01 00 00 1.20.C · PDF p. 46-47Spec wording“C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of ...” | 01 00 00 1.20.C | 46-47 | – |
| O&M | O&MSubmit data specified for a given item within 30 calendar ...Shop Drawings, Product Data, And Samples01 33 23 1.8.A · PDF p. 70Spec wording“A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.” | 01 33 23 1.8.A | 70 | – |
| O&M | O&MIn the event the Contractor fails to deliver O&M Data ...Shop Drawings, Product Data, And Samples01 33 23 1.8.B · PDF p. 70Spec wording“B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.” | 01 33 23 1.8.B | 70 | – |
| Training | TrainingThe designated Prime Contractor SSHO must meet the requirements of ...Safety Requirements01 35 26 1.10.A · PDF p. 93Spec wording“A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project.” | 01 35 26 1.10.A | 93 | – |
| Training | TrainingAs a minimum the SSHO must have completed the OSHA ...Safety Requirements01 35 26 1.10.B · PDF p. 93Spec wording“B. As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety Outreach class within the past five (5) years and: 1. Seven (7) years of construction industry safety related experience. 2. OR have a safety and health degree from an accredited university or college and five (5) years of construction industry safety related experience 3. OR hold as current, a Certified Safety Professional (CSP) or a ...” | 01 35 26 1.10.B | 93 | – |
| Training | TrainingThe Alternate Safety Officer shall meet, at a minimum, the ...Safety Requirements01 35 26 1.10.C · PDF p. 93-94Spec wording“C. The Alternate Safety Officer shall meet, at a minimum, the requirements of EM 385-1-1 Section 1 and have five (5) years of construction industry safety experience If the SSHO does not have a current certification, certification must be obtained within 90 days, maximum, of contract award.” | 01 35 26 1.10.C | 93-94 | – |
| Training | TrainingAll designated CPs shall have completed the OSHA 30-hour Construction ...Safety Requirements01 35 26 1.10.D · PDF p. 94Spec wording“D. All designated CPs shall have completed the OSHA 30-hour Construction Safety course and/or EM 385-1-1 40-hour training within the past 5 years. In addition, all CPs with high hazard work operations (such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations) shall have a specialized formal ...” | 01 35 26 1.10.D | 94 | – |
| Training | TrainingAll other construction workers shall have the OSHA 10-hour Construction ...Safety Requirements01 35 26 1.10.E · PDF p. 94Spec wording“E. All other construction workers shall have the OSHA 10-hour Construction Safety Outreach course within the past 5 years and any necessary safety training to be able to identify hazards within their work environment.” | 01 35 26 1.10.E | 94 | – |
| Training | TrainingSubmit training records associated with the above training requirements to ...Safety Requirements01 35 26 1.10.F · PDF p. 94Spec wording“F. Submit training records associated with the above training requirements to COR or Government Designated Authorityfor review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance.” | 01 35 26 1.10.F | 94 | – |
| Training | TrainingPrior to any worker for the contractor or subcontractors beginning ...Safety Requirements01 35 26 1.10.G · PDF p. 94Spec wording“G. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, this briefing shall include information on the site-specific hazards, construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, emergency procedures, ...” | 01 35 26 1.10.G | 94 | – |
| Training | TrainingOngoing safety training will be accomplished in the form of ...Safety Requirements01 35 26 1.10.H · PDF p. 94Spec wording“H. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.” | 01 35 26 1.10.H | 94 | – |
| Test / cert. | Test / cert.Government approval is required for all submittals. CQC inspection reports ...Quality Control01 45 00 1.3 · PDF p. 122Spec wording“Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Initial, or Follow-Up)]: [Applicable Specification section] naming convention. 1. Preconstruction Submittals a. Interim CQC Plan b. CQC Plan c. Additional Requirements for Design Quality Control (DQC) Plan 2. Design Data a. ...” | 01 45 00 1.3 | 122 | – |
| Test / cert. | Test / cert.Personnel RequirementsQuality Control01 45 00 3.4.A · PDF p. 127Spec wording“A. Personnel Requirements: The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager (if applicable), and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager shall satisfy the requirements of Specification 01 35 26 Safety Requirements and reports directly to a senior project (or ...” | 01 45 00 3.4.A | 127 | – |
| Test / cert. | Test / cert.CQC PersonnelQuality Control01 45 00 3.4.C · PDF p. 128-129Spec wording“C. CQC Personnel: In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist in the CQC System Manager for the following areas, as applicable: electrical, mechanical, civil, structural, environmental, architectural, materials technician submittals clerk, Commissioning Agent/LEED specialist, and low voltage systems. These individuals or ...” | 01 45 00 3.4.C | 128-129 | – |
| Test / cert. | Test / cert.Organizational ChangesQuality Control01 45 00 3.4.E · PDF p. 130Spec wording“E. Organizational Changes: Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer or Authorized designee for acceptance. 3.5 SUBMITTALS AND DELIVERABLES: Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Product Data, and Samples. The CQC ...” | 01 45 00 3.4.E | 130 | – |
| Closeout step | Closeout stepCloseout SubmittalsSustainable Construction Requirements01 81 13 1.5.G · PDF p. 171Spec wording“G. Closeout Submittals: Within 14 days after Substantial Completion provide the following: 1. Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet. 2. Manufacturer's cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction if permanently installed air handling units are used during construction. ...” | 01 81 13 1.5.G | 171 | – |
| Test / cert. | Test / cert.This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form ...General Commissioning Requirements01 91 00 1.1.A · PDF p. 182Spec wording“A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form the basis of the construction phase commissioning process and procedures. The Commissioning Agent shall add, modify, and refine the commissioning procedures, as approved by the Department of Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed ...” | 01 91 00 1.1.A | 182 | – |
| Test / cert. | Test / cert.Various sections of the project specifications require equipment startup, testing, ...General Commissioning Requirements01 91 00 1.1.B · PDF p. 182Spec wording“B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the Division 7, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not ...” | 01 91 00 1.1.B | 182 | – |
| Test / cert. | Test / cert.Where individual testing, adjusting, or related services are required in ...General Commissioning Requirements01 91 00 1.1.C · PDF p. 182Spec wording“C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services shall be provided and copies of documentation, as required by those specifications shall be submitted to the VA and the Commissioning Agent to be indexed for future reference.” | 01 91 00 1.1.C | 182 | – |
| Test / cert. | Test / cert.Where training or educational services for VA are required and ...General Commissioning Requirements01 91 00 1.1.D · PDF p. 182Spec wording“D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 7, Division 8, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.” | 01 91 00 1.1.D | 182 | – |
| Test / cert. | Test / cert.Commissioning is a systematic process of verifying that the building ...General Commissioning Requirements01 91 00 1.1.E · PDF p. 182-183Spec wording“E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA's operational needs. The commissioning process shall encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy ...” | 01 91 00 1.1.E | 182-183 | – |
| Test / cert. | Test / cert.The commissioning process does not take away from or reduce ...General Commissioning Requirements01 91 00 1.1.F · PDF p. 183Spec wording“F. The commissioning process does not take away from or reduce the responsibility of the Contractor to provide a finished and fully functioning product.” | 01 91 00 1.1.F | 183 | – |
| Test / cert. | Test / cert.Commissioning Tests to be performed as follows:General Commissioning Requirements01 91 00 1.1.G · PDF p. 183Spec wording“G. Commissioning Tests to be performed as follows: 1. CXA will review and witness specified systems tests. 2. The contractor is responsible for notifying CXA and Architect when specified tests are to commence. 3. The tests shall be grouped to limit interruption to the VA. 4. Proposed tests shall be reviewed by Cx prior to Cx site visit. 5. Pre-functional and functional checklist shall be reviewed by Cx prior to Cx ...” | 01 91 00 1.1.G | 183 | – |
| Test / cert. | Test / cert.The commissioning team shall consist of, but not be limited ...General Commissioning Requirements01 91 00 1.8.A · PDF p. 203Spec wording“A. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning Agent.” | 01 91 00 1.8.A | 203 | – |
| Test / cert. | Test / cert.Members Appointed by Contractor:General Commissioning Requirements01 91 00 1.8.B · PDF p. 203-204Spec wording“B. Members Appointed by Contractor: 1. Contractor' Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team. 2. Contractor's Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through ...” | 01 91 00 1.8.B | 203-204 | – |
| Test / cert. | Test / cert.Members Appointed by VA:General Commissioning Requirements01 91 00 1.8.C · PDF p. 204Spec wording“C. Members Appointed by VA: 1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA will engage the CxA under a separate contract. 2. User: Representatives of the facility user and operation and maintenance personnel. 3. A/E: Representative of the Architect and engineering design professionals.” | 01 91 00 1.8.C | 204 | – |
| Test / cert. | Test / cert.Appoint an individual, company or firm to act as the ...General Commissioning Requirements01 91 00 1.9.A · PDF p. 204Spec wording“A. Appoint an individual, company or firm to act as the Commissioning Agent.” | 01 91 00 1.9.A | 204 | – |
| Test / cert. | Test / cert.Assign operation and maintenance personnel and schedule them to participate ...General Commissioning Requirements01 91 00 1.9.B · PDF p. 204Spec wording“B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following: 1. Coordination meetings. 2. Training in operation and maintenance of systems, subsystems, and equipment. 3. Testing meetings. 4. Witness and assist in Systems Functional Performance Testing. 5. Demonstration of operation of systems, subsystems, and equipment.” | 01 91 00 1.9.B | 204 | – |
| Test / cert. | Test / cert.Provide the Construction Documents, prepared by Architect and approved by ...General Commissioning Requirements01 91 00 1.9.C · PDF p. 204Spec wording“C. Provide the Construction Documents, prepared by Architect and approved by VA, to the Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.” | 01 91 00 1.9.C | 204 | – |
| Test / cert. | Test / cert.The Contractor shall assign a Commissioning Manager to manage commissioning ...General Commissioning Requirements01 91 00 1.10.A · PDF p. 204Spec wording“A. The Contractor shall assign a Commissioning Manager to manage commissioning activities of the Contractor, and subcontractors.” | 01 91 00 1.10.A | 204 | – |
| Test / cert. | Test / cert.The Contractor shall ensure that the commissioning responsibilities outlined in ...General Commissioning Requirements01 91 00 1.10.B · PDF p. 204Spec wording“B. The Contractor shall ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.” | 01 91 00 1.10.B | 204 | – |
| Test / cert. | Test / cert.The Contractor shall ensure that each installing subcontractor shall assign ...General Commissioning Requirements01 91 00 1.10.C · PDF p. 204-205Spec wording“C. The Contractor shall ensure that each installing subcontractor shall assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the 1. Participate in commissioning coordination meetings. 2. Conduct operation and maintenance training sessions in accordance with approved ...” | 01 91 00 1.10.C | 204-205 | – |
| Test / cert. | Test / cert.Organize and lead the commissioning teamGeneral Commissioning Requirements01 91 00 1.11.A · PDF p. 205Spec wording“A. Organize and lead the commissioning team.” | 01 91 00 1.11.A | 205 | – |
| Test / cert. | Test / cert.Prepare the commissioning plan. See Paragraph 1.11-A of this specification ...General Commissioning Requirements01 91 00 1.11.B · PDF p. 205Spec wording“B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.” | 01 91 00 1.11.B | 205 | – |
| Test / cert. | Test / cert.Review and comment on selected submittals from the Contractor for ...General Commissioning Requirements01 91 00 1.11.C · PDF p. 205-206Spec wording“C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems ...” | 01 91 00 1.11.C | 205-206 | – |
| Test / cert. | Test / cert.At the beginning of the construction phase, conduct an initial ...General Commissioning Requirements01 91 00 1.11.D · PDF p. 206Spec wording“D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre-Functional Checklists, Systems Functional Performance Testing; and project completion.” | 01 91 00 1.11.D | 206 | – |
| Test / cert. | Test / cert.Convene commissioning team meetings for the purpose of coordination, communication, ...General Commissioning Requirements01 91 00 1.11.E · PDF p. 206Spec wording“E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The Commissioning Agent shall prepare and distribute minutes to commissioning team members and attendees within five workdays of the ...” | 01 91 00 1.11.E | 206 | – |
| Test / cert. | Test / cert.Observe construction and report progress, observations and issues. Observe systems ...General Commissioning Requirements01 91 00 1.11.F · PDF p. 206Spec wording“F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.” | 01 91 00 1.11.F | 206 | – |
| Test / cert. | Test / cert.Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test ...General Commissioning Requirements01 91 00 1.11.G · PDF p. 206Spec wording“G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.” | 01 91 00 1.11.G | 206 | – |
| Test / cert. | Test / cert.Coordinate Systems Functional Performance Testing schedule with the Contractor ...General Commissioning Requirements01 91 00 1.11.H · PDF p. 206Spec wording“H. Coordinate Systems Functional Performance Testing schedule with the Contractor.” | 01 91 00 1.11.H | 206 | – |
| Test / cert. | Test / cert.Witness selected systems startupsGeneral Commissioning Requirements01 91 00 1.11.I · PDF p. 206Spec wording“I. Witness selected systems startups.” | 01 91 00 1.11.I | 206 | – |
| Test / cert. | Test / cert.Verify selected Pre-Functional Checklists completed and submitted by the Contractor ...General Commissioning Requirements01 91 00 1.11.J · PDF p. 206Spec wording“J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.” | 01 91 00 1.11.J | 206 | – |
| Test / cert. | Test / cert.Witness and document Systems Functional Performance TestingGeneral Commissioning Requirements01 91 00 1.11.K · PDF p. 206Spec wording“K. Witness and document Systems Functional Performance Testing.” | 01 91 00 1.11.K | 206 | – |
| Test / cert. | Test / cert.Compile test data, inspection reports, and certificates and include them ...General Commissioning Requirements01 91 00 1.11.L · PDF p. 206Spec wording“L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.” | 01 91 00 1.11.L | 206 | – |
| Test / cert. | Test / cert.Review and comment on operation and maintenance (O&M) documentation and ...General Commissioning Requirements01 91 00 1.11.M · PDF p. 206Spec wording“M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.” | 01 91 00 1.11.M | 206 | – |
| Test / cert. | Test / cert.Review operation and maintenance training program developed by the Contractor. ...General Commissioning Requirements01 91 00 1.11.N · PDF p. 206Spec wording“N. Review operation and maintenance training program developed by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.” | 01 91 00 1.11.N | 206 | – |
| Test / cert. | Test / cert.Prepare commissioning Field Observation ReportsGeneral Commissioning Requirements01 91 00 1.11.O · PDF p. 207Spec wording“O. Prepare commissioning Field Observation Reports.” | 01 91 00 1.11.O | 207 | – |
| Test / cert. | Test / cert.Prepare the Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.11.P · PDF p. 207Spec wording“P. Prepare the Final Commissioning Report.” | 01 91 00 1.11.P | 207 | – |
| Test / cert. | Test / cert.Return to the site at 10 months into the 12 ...General Commissioning Requirements01 91 00 1.11.Q · PDF p. 207Spec wording“Q. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Systems Functional Performance Testing. Also interview facility staff and identify problems or concerns they have operating the building as originally intended. Make suggestions for improvements and for ...” | 01 91 00 1.11.Q | 207 | – |
| Test / cert. | Test / cert.Assemble the final commissioning documentation, including the Final Commissioning Report ...General Commissioning Requirements01 91 00 1.11.R · PDF p. 207Spec wording“R. Assemble the final commissioning documentation, including the Final Commissioning Report and Addendum to the Final Commissioning Report.” | 01 91 00 1.11.R | 207 | – |
| Test / cert. | Test / cert.Commissioning PlanGeneral Commissioning Requirements01 91 00 1.12.A · PDF p. 207-208Spec wording“A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited, to the following: 1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a ...” | 01 91 00 1.12.A | 207-208 | – |
| Test / cert. | Test / cert.Systems Functional Performance Test ProceduresGeneral Commissioning Requirements01 91 00 1.12.B · PDF p. 208Spec wording“B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested. Preliminary Systems Functional ...” | 01 91 00 1.12.B | 208 | – |
| Test / cert. | Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.12.C · PDF p. 208-209Spec wording“C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre-Functional Checklists. Pre-Functional Checklists shall be completed and signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing. Inaccurate or incomplete Pre-Functional ...” | 01 91 00 1.12.C | 208-209 | – |
| Test / cert. | Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.12.D · PDF p. 209Spec wording“D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application shall be included with data. Commissioning Agent Will compile test and inspection reports and test and ...” | 01 91 00 1.12.D | 209 | – |
| Test / cert. | Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.12.E · PDF p. 209Spec wording“E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results.” | 01 91 00 1.12.E | 209 | – |
| Test / cert. | Test / cert.Commissioning Issues LogGeneral Commissioning Requirements01 91 00 1.12.F · PDF p. 209-210Spec wording“F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues Log will identify and track issues as they are ...” | 01 91 00 1.12.F | 209-210 | – |
| Test / cert. | Test / cert.Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.G · PDF p. 210-211Spec wording“G. Final Commissioning Report: The Commissioning Agent will document results of the commissioning process, including unresolved issues, and performance of systems, subsystems, and equipment. The Commissioning Report will indicate whether systems, subsystems, and equipment have been properly installed and are performing according to the Contract Documents. This report will be used by the Department of Veterans ...” | 01 91 00 1.12.G | 210-211 | – |
| Test / cert. | Test / cert.Addendum to Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.H · PDF p. 211Spec wording“H. Addendum to Final Commissioning Report: The Commissioning Agent will prepare an Addendum to the Final Commissioning Report near the end of the Warranty Period. The Addendum will indicate whether systems, subsystems, and equipment are complete and continue to perform according to the Contract Documents. The Addendum to the Final Commissioning Report shall include, but is not limited to, the following: 1. ...” | 01 91 00 1.12.H | 211 | – |
| Test / cert. | Test / cert.Systems ManualGeneral Commissioning Requirements01 91 00 1.12.I · PDF p. 211Spec wording“I. Systems Manual: The Commissioning Agent will gather required information and compile the Systems Manual. The Systems Manual will include, but is not limited to, the following: 1. Design Narrative, including system narratives, schematics, single-line diagrams, flow diagrams, equipment schedules, and changes made throughout the Project. 2. Reference to Final Commissioning Plan. 3. Reference to Final Commissioning ...” | 01 91 00 1.12.I | 211 | – |
| Test / cert. | Test / cert.Preliminary Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.A · PDF p. 211-212Spec wording“A. Preliminary Commissioning Plan Submittal: The Commissioning Agent has prepared a Preliminary Commissioning Plan based on the final Construction Documents. The Preliminary Commissioning Plan is included as an Appendix to this specification section. The Preliminary Commissioning Plan is provided for information only. It contains preliminary information about the following commissioning activities: 1. The ...” | 01 91 00 1.13.A | 211-212 | – |
| Test / cert. | Test / cert.Final Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.B · PDF p. 212-213Spec wording“B. Final Commissioning Plan Submittal: Based on the Final Construction Documents and the Contractor's project team, the Commissioning Agent will prepare the Final Commissioning Plan as described in this section. The Commissioning Agent will submit three hard copies and three sets of electronic files of Final Commissioning Plan. The Contractor shall review the Commissioning Plan and provide any comments to the VA. ...” | 01 91 00 1.13.B | 212-213 | three hard copies; three sets; electronic files |
| Test / cert. | Test / cert.Systems Functional Performance Test ProcedureGeneral Commissioning Requirements01 91 00 1.13.C · PDF p. 213Spec wording“C. Systems Functional Performance Test Procedure: The Commissioning Agent will submit preliminary Systems Functional Performance Test Procedures to the Contractor, and the VA for review and comment. The Contractor shall return review comments to the VA and the Commissioning Agent. The VA will also return review comments to the Commissioning Agent. The Commissioning Agent will incorporate review comments into the ...” | 01 91 00 1.13.C | 213 | – |
| Test / cert. | Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.13.D · PDF p. 213Spec wording“D. Pre-Functional Checklists: The Commissioning Agent will submit Pre-Functional Checklists to be completed by the Contractor.” | 01 91 00 1.13.D | 213 | – |
| Test / cert. | Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.13.E · PDF p. 213Spec wording“E. Test and Inspection Reports: The Commissioning Agent will submit test and inspection reports to the VA with copies to the Contractor and the Architect/Engineer.” | 01 91 00 1.13.E | 213 | – |
| Test / cert. | Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.13.F · PDF p. 213Spec wording“F. Corrective Action Documents: The Commissioning Agent will submit corrective action documents to the VA COR with copies to the Contractor and Architect.” | 01 91 00 1.13.F | 213 | – |
| Test / cert. | Test / cert.Preliminary Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.G · PDF p. 213Spec wording“G. Preliminary Commissioning Report Submittal: The Commissioning Agent will submit three electronic copies of the preliminary commissioning report. One electronic copy, with review comments, will be returned to the Commissioning Agent for preparation of the final submittal.” | 01 91 00 1.13.G | 213 | three electronic copies; One electronic copy |
| Test / cert. | Test / cert.Final Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.H · PDF p. 213Spec wording“H. Final Commissioning Report Submittal: The Commissioning Agent will submit four sets of electronically formatted information of the final commissioning report to the VA. The final submittal will incorporate comments as directed by the VA.” | 01 91 00 1.13.H | 213 | four sets; electronically |
| Test / cert. | Test / cert.Data for Commissioning:General Commissioning Requirements01 91 00 1.13.I · PDF p. 213Spec wording“I. Data for Commissioning: 1. The Commissioning Agent will request in writing from the Contractor specific information needed about each piece of commissioned equipment or system to fulfill requirements of the Commissioning Plan. 2. The Commissioning Agent may request further documentation as is necessary for the commissioning process or to support other VA data collection requirements, including Construction ...” | 01 91 00 1.13.I | 213 | – |
| Test / cert. | Test / cert.The Commissioning Agent will be responsible for the overall management ...General Commissioning Requirements01 91 00 1.14.A · PDF p. 214Spec wording“A. The Commissioning Agent will be responsible for the overall management of the commissioning process as well as coordinating scheduling of commissioning tasks with the VA and the Contractor. As directed by the VA, the Contractor shall incorporate Commissioning tasks, including, but not limited to, Systems Functional Performance Testing (including predecessors) with the Master Construction Schedule.” | 01 91 00 1.14.A | 214 | – |
| Test / cert. | Test / cert.Within 30 days of contract award, the Contractor shall designate ...General Commissioning Requirements01 91 00 1.14.B · PDF p. 214Spec wording“B. Within 30 days of contract award, the Contractor shall designate a specific individual as the Commissioning Manager (CxM) to manage and lead the commissioning effort on behalf of the Contractor. The Commissioning Manager shall be the single point of contact and communications for all commissioning related services by the Contractor.” | 01 91 00 1.14.B | 214 | – |
| Test / cert. | Test / cert.Within 30 days of contract award, the Contractor shall ensure ...General Commissioning Requirements01 91 00 1.14.C · PDF p. 214Spec wording“C. Within 30 days of contract award, the Contractor shall ensure that each subcontractor designates specific individuals as Commissioning Representatives (CXR) to be responsible for commissioning related tasks. The Contractor shall ensure the designated Commissioning Representatives participate in the commissioning process as team members providing commissioning testing services, equipment operation, adjustments, ...” | 01 91 00 1.14.C | 214 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.A · PDF p. 218-220Spec wording“A. The following table outlines the roles and responsibilities for the Commissioning Team members during the Construction Phase: Construction Phase CxA = Commissioning Agent L = Lead = COR COR P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA COR A/E PC O&M Notes Meetings ...” | 01 91 00 3.1.A | 218-220 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.B · PDF p. 220-222Spec wording“B. The following table outlines the roles and responsibilities for the Commissioning Team members during the Acceptance Phase: Acceptance Phase CxA = Commissioning Agent L = Lead COR P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA COR A/E PC O&M Notes Meetings ...” | 01 91 00 3.1.B | 220-222 | – |
| Test / cert. | Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.C · PDF p. 222-223Spec wording“C. The following table outlines the roles and responsibilities for the Commissioning Team members during the Warranty Phase: Warranty Phase Commissioning Roles & Responsibilities Category Task Description Meetings Post-Occupancy User Review Meeting Site Periodic Site Visits Observations Functional Deferred and/or seasonal Testing Test Protocols Technical Issues Resolution Meetings Activities Post-Occupancy Warranty ...” | 01 91 00 3.1.C | 222-223 | – |
| Test / cert. | Test / cert.The following procedures shall apply to all equipment and systems ...General Commissioning Requirements01 91 00 3.2.A · PDF p. 224-225Spec wording“A. The following procedures shall apply to all equipment and systems to be commissioned, according to Part 1, Systems to Be Commissioned. 1. Pre-Functional Checklists are important to ensure that the equipment and systems are hooked up and operational. These ensure that Systems Functional Performance Testing may proceed without unnecessary delays. Each system to be commissioned shall have a full Pre-Functional ...” | 01 91 00 3.2.A | 224-225 | – |
| Test / cert. | Test / cert.The Contractor shall clearly list any outstanding items of the ...General Commissioning Requirements01 91 00 3.3.A · PDF p. 225Spec wording“A. The Contractor shall clearly list any outstanding items of the initial startup and Pre-Functional Checklist procedures that were not completed successfully, at the bottom of the procedures form or on an attached sheet. The procedures form and any outstanding deficiencies shall be provided to the VA and the Commissioning Agent within two days of completion.” | 01 91 00 3.3.A | 225 | – |
| Test / cert. | Test / cert.The Commissioning Agent will review the report and submit comments ...General Commissioning Requirements01 91 00 3.3.B · PDF p. 226Spec wording“B. The Commissioning Agent will review the report and submit comments to the VA. The Commissioning Agent will work with the Contractor to correct and verify deficiencies or uncompleted items. The Commissioning Agent will involve the VA and others as necessary. The Contractor shall correct all areas that are noncompliant or incomplete in the checklists in a timely manner, and shall notify the VA and Commissioning ...” | 01 91 00 3.3.B | 226 | – |
| Test / cert. | Test / cert.The Contractor shall be responsible for resolution of deficiencies as ...General Commissioning Requirements01 91 00 3.3.C · PDF p. 226Spec wording“C. The Contractor shall be responsible for resolution of deficiencies as directed the VA.” | 01 91 00 3.3.C | 226 | – |
| Test / cert. | Test / cert.The project may require startup and initial checkout to be ...General Commissioning Requirements01 91 00 3.4.A · PDF p. 226Spec wording“A. The project may require startup and initial checkout to be executed in phases. This phasing shall be planned and scheduled in a coordination meeting of the VA, Commissioning Agent, and the Contractor. Results will be added to the master construction schedule and the commissioning schedule.” | 01 91 00 3.4.A | 226 | – |
| Test / cert. | Test / cert.Trending is a method of testing as a standalone method ...General Commissioning Requirements01 91 00 3.5.A · PDF p. 226Spec wording“A. Trending is a method of testing as a standalone method or to augment manual testing. The Contractor shall trend any and all points of the system or systems at intervals specified below.” | 01 91 00 3.5.A | 226 | – |
| Test / cert. | Test / cert.Alarms are a means to notify the system operator that ...General Commissioning Requirements01 91 00 3.5.B · PDF p. 226-227Spec wording“B. Alarms are a means to notify the system operator that abnormal conditions are present in the system. Alarms shall be structured into three tiers – Critical, Priority, and Maintenance. 1. Critical alarms are intended to be alarms that require the immediate attention of and action by the Operator. These alarms shall be displayed on the Operator Workstation in a popup style window that is graphically linked to the ...” | 01 91 00 3.5.B | 226-227 | – |
| Test / cert. | Test / cert.The Contractor shall provide a wireless internet network in the ...General Commissioning Requirements01 91 00 3.5.C · PDF p. 227Spec wording“C. The Contractor shall provide a wireless internet network in the building for use during controls programming, checkout, and commissioning. This network will allow project team members to more effectively program, view, manipulate and test control devices while being in the same room as the controlled device.” | 01 91 00 3.5.C | 227 | – |
| Test / cert. | Test / cert.The Contractor shall provide graphical trending through the DDC control ...General Commissioning Requirements01 91 00 3.5.D · PDF p. 227-244Spec wording“D. The Contractor shall provide graphical trending through the DDC control system of systems being commissioned. Trending requirements are indicated below and included with the Systems Functional Performance Test Procedures. Trending shall occur before, during and after Systems Functional Performance Testing. The Contractor shall be responsible for producing graphical representations of the trended DDC points that ...” | 01 91 00 3.5.D | 227-244 | – |
| Test / cert. | Test / cert.The Contractor shall provide the following information prior to Systems ...General Commissioning Requirements01 91 00 3.5.E · PDF p. 244-245Spec wording“E. The Contractor shall provide the following information prior to Systems Functional Performance Testing. Any documentation that is modified after submission shall be recorded and resubmitted to the COR and Commissioning Agent. 1. Point-to-Point checkout documentation; 2. Sensor field calibration documentation including system name, sensor/point name, measured value, DDC value, and Correction Factor. 3. A sensor ...” | 01 91 00 3.5.E | 244-245 | – |
| O&M | O&MTraining Preparation ConferenceGeneral Commissioning Requirements01 91 00 3.9.A · PDF p. 253Spec wording“A. Training Preparation Conference: Before operation and maintenance training, the Commissioning Agent will convene a training preparation conference to include VA's COR, VA's Operations and Maintenance personnel, and the Contractor. The purpose of this conference will be to discuss and plan for Training and Demonstration of VA Operations and Maintenance personnel.” | 01 91 00 3.9.A | 253 | – |
| O&M | O&MThe Contractor shall provide training and demonstration as required by ...General Commissioning Requirements01 91 00 3.9.B · PDF p. 253-254Spec wording“B. The Contractor shall provide training and demonstration as required by other Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 sections. The Training and Demonstration shall include, but is not limited to, the following: 1. Review the Contract Documents. 2. Review installed systems, subsystems, and equipment. 3. Review instructor qualifications. 4. Review instructional ...” | 01 91 00 3.9.B | 253-254 | – |
| O&M | O&MTraining Module SubmittalsGeneral Commissioning Requirements01 91 00 3.9.C · PDF p. 254-255Spec wording“C. Training Module Submittals: The Contractor shall submit the following information to the VA and the Commissioning Agent: 1. Instruction Program: Submit two copies of outline of instructional program for demonstration and training, including a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training ...” | 01 91 00 3.9.C | 254-255 | two copies; DVD; 3-ring; binders; binder |
| O&M | O&MQuality Assurance:General Commissioning Requirements01 91 00 3.9.D · PDF p. 255Spec wording“D. Quality Assurance: 1. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. 2. Instructor Qualifications: A factory authorized service representative, complying with ...” | 01 91 00 3.9.D | 255 | – |
| O&M | O&MTraining Coordination:General Commissioning Requirements01 91 00 3.9.E · PDF p. 255Spec wording“E. Training Coordination: 1. Coordinate instruction schedule with VA's operations. Adjust schedule as required to minimize disrupting VA's operations. 2. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. 3. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction ...” | 01 91 00 3.9.E | 255 | – |
| O&M | O&MInstruction Program:General Commissioning Requirements01 91 00 3.9.F · PDF p. 255Spec wording“F. Instruction Program: 1. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections, and as follows: a. Fire protection systems, including fire alarm, fire pumps, and fire suppression systems. b. Intrusion detection systems. c. Conveying systems, including elevators, wheelchair ...” | 01 91 00 3.9.F | 255 | – |
| O&M | O&MTraining ModulesGeneral Commissioning Requirements01 91 00 3.9.G · PDF p. 256-258Spec wording“G. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participants are expected to master. For each module, include instruction for the following: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment descriptions. b. Performance and design criteria if ...” | 01 91 00 3.9.G | 256-258 | – |
| O&M | O&MTraining Execution:General Commissioning Requirements01 91 00 3.9.H · PDF p. 258-259Spec wording“H. Training Execution: 1. Preparation: Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a combined training manual. Set up instructional equipment at instruction location. 2. Instruction: a. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate ...” | 01 91 00 3.9.H | 258-259 | – |
| O&M | O&MDemonstration and Training Recording:General Commissioning Requirements01 91 00 3.9.I · PDF p. 259Spec wording“I. Demonstration and Training Recording: 1. General: Engage a qualified commercial photographer to record demonstration and training. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. At beginning of each training module, record each chart containing learning objective and lesson outline. 2. Video Format: ...” | 01 91 00 3.9.I | 259 | DVD |
Division 02 Existing conditions 14 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Monitoring, Inspection and Testing by Contractor CPIH/CIHTraditional Asbestos Abatement02 82 11 2.2.C · PDF p. 299-300Spec wording“C. Monitoring, Inspection and Testing by Contractor CPIH/CIH: The Contractor's CPIH/CIH is responsible for managing all monitoring, inspections, and testing required by these specifications, as well as any and all regulatory requirements adopted by these specifications. The CPIH/CIH is responsible for the continuous monitoring of all subsystems and procedures which could affect the health and safety of the ...” | 02 82 11 2.2.C | 299-300 | |
| Training | TrainingPre-Start Meeting Submittals:Traditional Asbestos Abatement02 82 11 2.4.A · PDF p. 301Spec wording“A. Pre-Start Meeting Submittals: 1. Submit to the VA a minimum of 14 days prior to the pre-start meeting the following for review and approval. Meeting this requirement is a prerequisite for the pre-start meeting for this project: a. Submit a detailed work schedule for the entire project reflecting contract documents and the phasing/schedule requirements from the CPM chart. b. Submit a staff organization chart ...” | 02 82 11 2.4.A | 301 | – |
| Test / cert. | Test / cert.Submittals at Completion of AbatementTraditional Asbestos Abatement02 82 11 2.4.C · PDF p. 305Spec wording“C. Submittals at Completion of Abatement: The CPIH/CIH shall submit a project report consisting of the daily log book requirements and documentation of events during the abatement project including Waste Shipment Records signed by the landfill's agent. It will also include information on the containment and transportation of waste from the containment with applicable Chain of Custody forms. The report shall include ...” | 02 82 11 2.4.C | 305 | – |
| Test / cert. | Test / cert.Laboratory Testing of PCM Clearance SamplesTraditional Asbestos Abatement02 82 11 3.6.G · PDF p. 330-331Spec wording“G. Laboratory Testing of PCM Clearance Samples: The services of an AIHA accredited laboratory will be employed by the VA to perform analysis for the PCM air samples. The accredited laboratory shall be successfully participating in the AIHA Proficiency Analytical Testing (PAT) program. Samples will be sent daily by the VPIH/CIH so that verbal/faxed reports can be received within 24-36 hours. A complete record, ...” | 02 82 11 3.6.G | 330-331 | – |
| Test / cert. | Test / cert.Laboratory Testing of TEM SamplesTraditional Asbestos Abatement02 82 11 3.6.H · PDF p. 331Spec wording“H. Laboratory Testing of TEM Samples: Samples shall be sent by the VPIH/CIH to a NIST NVLAP accredited laboratory for analysis by TEM. The laboratory shall be successfully participating in the NIST Airborne Asbestos Analysis (TEM) program. Verbal/faxed results from the laboratory shall be available within 24-36 hours after receipt of the samples. A complete record, certified by the laboratory, of all TEM results ...” | 02 82 11 3.6.H | 331 | – |
| Test / cert. | Test / cert.Laboratory Testing of Bulk SamplesTraditional Asbestos Abatement02 82 11 3.6.I · PDF p. 331Spec wording“I. Laboratory Testing of Bulk Samples: Samples shall be sent by the VPIH/CIH or CPIH/CIH to a NIST NVLAP accredited laboratory for analysis by PLM. The laboratory shall successfully participate in the NIST NVLAP Bulk Asbestos Analysis (PLM) program. Verbal/faxed results from the laboratory shall be available within 24-36 hours after receipt of the samples. A complete record, certified by the laboratory, of all PLM ...” | 02 82 11 3.6.I | 331 | – |
| Test / cert. | Test / cert.Completion of Abatement Work:Traditional Asbestos Abatement02 82 11 3.7.A · PDF p. 331Spec wording“A. Completion of Abatement Work: 1. After thorough decontamination, seal negative air machines with 2 layers of 6-mil poly and duct tape to form a tight seal at the intake/outlet ends before removal from the regulated area. Complete asbestos abatement work upon meeting the regulated area visual and air clearance criteria and fulfilling the following: a. Remove all equipment and materials from the project area. b. ...” | 02 82 11 3.7.A | 331 | – |
| Test / cert. | Test / cert.Certificate of Completion By ContractorTraditional Asbestos Abatement02 82 11 3.7.B · PDF p. 332Spec wording“B. Certificate of Completion By Contractor: The CPIH/CIH shall complete and sign the "Certificate of Completion" in accordance with Attachment 1 at the completion of the abatement and decontamination of the regulated area.” | 02 82 11 3.7.B | 332 | – |
| Test / cert. | Test / cert.Work ShiftsTraditional Asbestos Abatement02 82 11 3.7.C · PDF p. 332Spec wording“C. Work Shifts: All work shall generally be done during administrative hours (8:00 AM to 4:30 PM) Monday - Friday excluding Federal Holidays. Any change in the work schedule must be approved in writing by the VA Representative.” | 02 82 11 3.7.C | 332 | – |
| Test / cert. | Test / cert.Re-InsulationTraditional Asbestos Abatement02 82 11 3.7.D · PDF p. 332-336Spec wording“D. Re-Insulation: If required as part of the contract, replace all asbestos containing insulation/fire-proofing with suitable non-asbestos material. Provide SDS's for all replacement materials in advance of installation for VA approval. Refer to Section 23 07 11, HVAC, PLUMBING, AND BOILER PLANT INSULATION. ATTACHMENT #1 CERTIFICATE OF COMPLETION DATE: VA Project #: PROJECT NAME: Abatement Contractor: VAMC/ADDRESS: ...” | 02 82 11 3.7.D | 332-336 | – |
| Test / cert. | Test / cert.Test ReportsLead-Based Paint Removal And Disposal02 83 33.13 1.6.C · PDF p. 341Spec wording“C. Test Reports: Submit testing laboratory reports. 1. Submit air monitoring results within three working days, signed by testing laboratory employee performing air monitoring, employee analyzing sample, and CIH.” | 02 83 33.13 1.6.C | 341 | – |
| Training | TrainingCertificatesLead-Based Paint Removal And Disposal02 83 33.13 1.6.D · PDF p. 341Spec wording“D. Certificates: Certify completed lead training. 1. Submit certificate for each employee signed and dated by CIH and employee stating employee was trained.” | 02 83 33.13 1.6.D | 341 | – |
| Record docs | Record docsRecord Documents:Lead-Based Paint Removal And Disposal02 83 33.13 1.6.F · PDF p. 342Spec wording“F. Record Documents: 1. Completed and signed hazardous waste manifest from waste transporter. 2. Toxicity Characteristic Leaching Procedure (TCLP) test results to determine if waste is hazardous. 3. Paint disposal facility receipts and disposition reports. 4. Certification of medical examinations. 5. Medical Opinion that employee is qualified to wear a respirator, that employees has been trained and fit tested for ...” | 02 83 33.13 1.6.F | 342 | – |
| Warranty | WarrantyConstruction WarrantyLead-Based Paint Removal And Disposal02 83 33.13 1.8.A · PDF p. 344Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 02 83 33.13 1.8.A | 344 | – |
Division 03 Concrete 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Mill Test Reports:Cast-In-Place Concrete03 30 00 1.6.C · PDF p. 351Spec wording“C. Mill Test Reports: 1. Reinforcing Steel. 2. Cement.” | 03 30 00 1.6.C | 351 | – |
| Training | TrainingManufacturer's Certificates:Cast-In-Place Concrete03 30 00 1.6.D · PDF p. 351Spec wording“D. Manufacturer's Certificates: 1. Abrasive aggregate. 2. Lightweight aggregate for structural concrete. 3. Air-entraining admixture. 4. Chemical admixtures, including chloride ion content. 5. Waterproof paper for curing concrete. 6. Liquid membrane-forming compounds for curing concrete. 7. Non-shrinking grout. 8. Liquid hardener. 9. Waterstops. 10. Expansion joint filler. 11. Adhesive binder.” | 03 30 00 1.6.D | 351 | binder |
| Test / cert. | Test / cert.Test Report for Concrete Mix DesignsCast-In-Place Concrete03 30 00 1.6.F · PDF p. 352Spec wording“F. Test Report for Concrete Mix Designs: Trial mixes including water-cement, fly ash, ratio curves, concrete mix ingredients, and admixtures.” | 03 30 00 1.6.F | 352 | – |
Division 05 Metals 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test ReportsStructural Steel Framing05 12 00 1.4.D · PDF p. 383Spec wording“D. Test Reports: Certify products comply with specifications. 1. Welders' qualifying tests.” | 05 12 00 1.4.D | 383 | – |
| Warranty | WarrantyConstruction WarrantyStructural Steel Framing05 12 00 1.6.A · PDF p. 384Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 05 12 00 1.6.A | 384 | – |
Division 06 Wood and plastics 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantyFinish Carpentry06 20 00 1.9.A · PDF p. 421Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 06 20 00 1.9.A | 421 | – |
| O&M | O&MMaintenance dataSolid Polymer Fabrications06650 1.03.D · PDF p. 430Spec wording“D. Maintenance data: Submit manufacturer's care and maintenance data, including repair and cleaning instructions. Include in project close-out documents.” | 06650 1.03.D | 430 | – |
| Warranty | WarrantyProvide manufacturer's 10 year warranty against defects in materials. Warranty ...Solid Polymer Fabrications06650 1.06.A · PDF p. 431Spec wording“A. Provide manufacturer's 10 year warranty against defects in materials. Warranty shall provide material and labor to repair or replace defective materials. Damage caused by physical or chemical abuse or damage from excessive heat will not be warranted.” | 06650 1.06.A | 431 | – |
Division 07 Roofing, insulation and waterproofing 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyManufacturer's Literature and Data:Preparation For Re-Roofing07 01 50.19 1.5.C · PDF p. 438Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Description of temporary roof system and components. 3. List of patching materials. 4. Recover board fastening requirements. 5. Temporary roofing installation instructions and preparation instructions to receive new roofing. Existing roofing warrantor's instructions if under warranty.” | 07 01 50.19 1.5.C | 438 | – |
| Warranty | WarrantyField Inspection Reports:Preparation For Re-Roofing07 01 50.19 1.5.E · PDF p. 438Spec wording“E. Field Inspection Reports: 1. Certify warrantor inspected completed roofing and existing warranty remains in effect.” | 07 01 50.19 1.5.E | 438 | – |
| Warranty | WarrantyConstruction WarrantyPreparation For Re-Roofing07 01 50.19 1.8.A · PDF p. 438Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 01 50.19 1.8.A | 438 | – |
| Warranty | WarrantyExisting WarrantiesPreparation For Re-Roofing07 01 50.19 1.8.B · PDF p. 439Spec wording“B. Existing Warranties: Perform work to maintain existing roofing warranty in effect. 1. Notify warrantor before beginning, and upon completion of reroofing. 2. Obtain warrantor's instructions for maintaining existing warranty.” | 07 01 50.19 1.8.B | 439 | – |
| Warranty | WarrantyConstruction WarrantyThermal Insulation07 21 13 1.7.A · PDF p. 443Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 21 13 1.7.A | 443 | – |
| Test / cert. | Test / cert.Furnish service of approved inspector to inspect firestopping in accordance ...Firestopping07 84 00 3.5.B · PDF p. 467Spec wording“B. Furnish service of approved inspector to inspect firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results. Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers.” | 07 84 00 3.5.B | 467 | – |
| Warranty | WarrantyConstruction WarrantyJoint Sealants07 92 00 1.9.A · PDF p. 471Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".” | 07 92 00 1.9.A | 471 | – |
| Warranty | WarrantyManufacturer WarrantyJoint Sealants07 92 00 1.9.B · PDF p. 471Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their sealant for a minimum of five (5) years from the date of installation and final acceptance by the Government. Submit manufacturer warranty.” | 07 92 00 1.9.B | 471 | – |
| Test / cert. | Test / cert.Inspect tested joints and report on following:Joint Sealants07 92 00 3.6.C · PDF p. 478Spec wording“C. Inspect tested joints and report on following: 1. Whether sealants in joints connected to pulled-out portion failed to adhere to joint substrates or tore cohesively. Include data on pull distance used to test each type of product and joint substrate. 2. Compare these results to determine if adhesion passes sealant manufacturer's field-adhesion hand-pull test criteria. 3. Whether sealants filled joint cavities ...” | 07 92 00 3.6.C | 478 | – |
| O&M | O&MOperation and Maintenance Data:Expansion Joint Cover Assemblies07 95 13 1.4.G · PDF p. 482Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 07 95 13 1.4.G | 482 | – |
| Warranty | WarrantyConstruction WarrantyExpansion Joint Cover Assemblies07 95 13 1.9.A · PDF p. 482Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 07 95 13 1.9.A | 482 | – |
Division 08 Doors, windows and hardware 27 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Test reportsHollow Metal Doors And Frames08 11 13 1.4.E · PDF p. 493Spec wording“E. Test reports: Certify each product complies with specifications.” | 08 11 13 1.4.E | 493 | – |
| Warranty | WarrantyConstruction WarrantyHollow Metal Doors And Frames08 11 13 1.8.A · PDF p. 494Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 11 13 1.8.A | 494 | – |
| Test / cert. | Test / cert.Test ReportsInterior Wood Doors08 14 00 1.4.F · PDF p. 503Spec wording“F. Test Reports: Indicate each product complies with specifications. 1. Screw Holding Capacity Test. 2. Cycle-Slam Test. 3. Hinge-Loading Test.” | 08 14 00 1.4.F | 503 | – |
| O&M | O&MOperation and Maintenance Data:Interior Wood Doors08 14 00 1.4.G · PDF p. 503Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 08 14 00 1.4.G | 503 | – |
| Warranty | WarrantyConstruction WarrantyInterior Wood Doors08 14 00 1.9.A · PDF p. 504Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 14 00 1.9.A | 504 | – |
| Warranty | WarrantyManufacturer's WarrantyInterior Wood Doors08 14 00 1.9.B · PDF p. 504Spec wording“B. Manufacturer's Warranty: Warrant interior factory finished flush wood doors against material and manufacturing defects. 1. Warranty Period: Lifetime of original installation.” | 08 14 00 1.9.B | 504 | – |
| O&M | O&MOperation and Maintenance Data:Integrated Door Assemblies08 17 10 1.5.G · PDF p. 512Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product. 2. Maintenance and adjustment instructions for integrated door assemblies.” | 08 17 10 1.5.G | 512 | – |
| Warranty | WarrantyConstruction WarrantyIntegrated Door Assemblies08 17 10 1.10.A · PDF p. 513Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 17 10 1.10.A | 513 | – |
| Warranty | WarrantyManufacturer's WarrantyIntegrated Door Assemblies08 17 10 1.10.B · PDF p. 513Spec wording“B. Manufacturer's Warranty: Warrant door closers and hinges against material and manufacturing defects. 1. Warranty Periods: a. Door Closers: 10 years. b. Steel Pinned Continuous Hinges: 10 years.” | 08 17 10 1.10.B | 513 | – |
| Warranty | WarrantyConstruction WarrantyAccess Doors And Frames08 31 13 1.8.A · PDF p. 517Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 31 13 1.8.A | 517 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Icu Sliding Glass Doors08 32 13 1.6.C · PDF p. 523-524Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Doors, each type. 3. Entrance and Storefront construction. 4. Installation instructions. 5. Warranty.” | 08 32 13 1.6.C | 523-524 | – |
| Test / cert. | Test / cert.Test reportsIcu Sliding Glass Doors08 32 13 1.6.F · PDF p. 524Spec wording“F. Test reports: Certify products comply with specifications.” | 08 32 13 1.6.F | 524 | – |
| O&M | O&MOperation and Maintenance Data:Icu Sliding Glass Doors08 32 13 1.6.J · PDF p. 524Spec wording“J. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 08 32 13 1.6.J | 524 | – |
| Warranty | WarrantyConstruction WarrantyIcu Sliding Glass Doors08 32 13 1.9.A · PDF p. 525Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction." Warranty Period for /One years for but not limited to, the following: Structural failure including excessive deflection 1. Faulty operation of hardware 2. Excessive deterioration/failure of metals, metal finishes, glass and other materials.” | 08 32 13 1.9.A | 525 | – |
| Warranty | WarrantyManufacturer's WarrantyIcu Sliding Glass Doors08 32 13 1.9.B · PDF p. 525Spec wording“B. Manufacturer's Warranty: Warrant painted finish against material and manufacturing defects. 1. Warranty Period: 20 years.” | 08 32 13 1.9.B | 525 | – |
| Training | TrainingEngage a factory-authorized representative to train Owner's maintenance personnel to ...Icu Sliding Glass Doors08 32 13 3.5.A · PDF p. 531Spec wording“A. Engage a factory-authorized representative to train Owner's maintenance personnel to adjust, operate, and maintain safe operation of the door.” | 08 32 13 3.5.A | 531 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Automatic Door Operators08 71 13 1.4.C · PDF p. 562Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.” | 08 71 13 1.4.C | 562 | – |
| Test / cert. | Test / cert.Test reportsAutomatic Door Operators08 71 13 1.4.E · PDF p. 562Spec wording“E. Test reports: Certify each product complies with specifications.” | 08 71 13 1.4.E | 562 | – |
| O&M | O&MOperation and Maintenance Data:Automatic Door Operators08 71 13 1.4.G · PDF p. 563Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product. 2. Start-up, maintenance, troubleshooting, emergency, and shut-down instructions for each operational product.” | 08 71 13 1.4.G | 563 | – |
| Warranty | WarrantyConstruction WarrantyAutomatic Door Operators08 71 13 1.6.A · PDF p. 563Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 08 71 13 1.6.A | 563 | – |
| Warranty | WarrantyManufacturer's WarrantyAutomatic Door Operators08 71 13 1.6.B · PDF p. 563Spec wording“B. Manufacturer's Warranty: Warrant automatic door operators against material and manufacturing defects. 1. Warranty Period: Two years.” | 08 71 13 1.6.B | 563 | – |
| Training | TrainingInstruct VA personnel in proper automatic door operator operation and ...Automatic Door Operators08 71 13 3.3.A · PDF p. 568Spec wording“A. Instruct VA personnel in proper automatic door operator operation and maintenance. 1. Trainer: Manufacturer approved instructor. 2. Training Time: / 2 hours minimum.” | 08 71 13 3.3.A | 568 | – |
| Training | TrainingCoordinate instruction to VA personnel with VA Contracting Officer's Representative ...Automatic Door Operators08 71 13 3.3.B · PDF p. 569Spec wording“B. Coordinate instruction to VA personnel with VA Contracting Officer's Representative.” | 08 71 13 3.3.B | 569 | – |
| Warranty | WarrantyConstruction WarrantyGlazing08 80 00 1.8.A · PDF p. 572Spec wording“A. Construction Warranty: Comply with the FAR clause 52.246-21 "Warranty of Construction".” | 08 80 00 1.8.A | 572 | – |
| Warranty | WarrantyManufacturer WarrantyGlazing08 80 00 1.8.B · PDF p. 572Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their glazing from the date of installation and final acceptance by the Government as follows. Submit manufacturer warranty. 1. Warrant electrochromic laminated products against lamination defects, such as edge separation or delamination, that materially obstruct vision through the glass for a period of five (5) years. 2. Warrant electrochromic controls against ...” | 08 80 00 1.8.B | 572 | – |
| Test / cert. | Test / cert.Before start-up of electrochromic glass control system, conduct visual inspection ...Glazing08 80 00 3.6.A · PDF p. 580Spec wording“A. Before start-up of electrochromic glass control system, conduct visual inspection to verify system is installed per code and in working order. Verify proper wire connections to and from equipment and insulating glass units.” | 08 80 00 3.6.A | 580 | – |
| Test / cert. | Test / cert.When system is in start-up, conduct an overall system test ...Glazing08 80 00 3.6.B · PDF p. 580Spec wording“B. When system is in start-up, conduct an overall system test and verify system is operating per electrochromic IGU manufacturer's operating instructions.” | 08 80 00 3.6.B | 580 | – |
Division 09 Finishes 15 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyTest Data:Subsurface Preparation For Floor Finishes09 05 16 1.3.D · PDF p. 582Spec wording“D. Test Data: 1. Moisture test and pH results performed by a qualified independent testing agency or warranty holding manufacturer's technical representative.” | 09 05 16 1.3.D | 582 | – |
| Warranty | WarrantyConstruction WarrantyCeramic/Porcelain Tiling09 30 13 1.6.A · PDF p. 608Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 09 30 13 1.6.A | 608 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Acoustical Ceilings09 51 00 1.5.C · PDF p. 627Spec wording“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Ceiling suspension system indicating manufacturer recommendation for each application. 3. Installation instructions. 4. Warranty.” | 09 51 00 1.5.C | 627 | – |
| O&M | O&MOperation and Maintenance Data:Acoustical Ceilings09 51 00 1.5.H · PDF p. 628Spec wording“H. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 09 51 00 1.5.H | 628 | – |
| Warranty | WarrantyConstruction WarrantyAcoustical Ceilings09 51 00 1.10.A · PDF p. 629Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 09 51 00 1.10.A | 629 | – |
| O&M | O&MOperation and Maintenance Data:Resilient Base And Accessories09 65 13 1.4.E · PDF p. 637Spec wording“E. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 09 65 13 1.4.E | 637 | – |
| Warranty | WarrantyConstruction WarrantyResilient Base And Accessories09 65 13 1.8.A · PDF p. 637Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 09 65 13 1.8.A | 637 | – |
| Warranty | WarrantyManufacturer's Literature and Data:Resilient Sheet Flooring09 65 16 1.4.B · PDF p. 640-641Spec wording“B. Manufacturer's Literature and Data: 1. Description of each product. 2. Application, Installation, and instructions. 3. Warranty.” | 09 65 16 1.4.B | 640-641 | – |
| Warranty | WarrantyConstruction WarrantyResilient Sheet Flooring09 65 16 1.9.A · PDF p. 642Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 09 65 16 1.9.A | 642 | – |
| Warranty | WarrantyManufacturer's WarrantyResilient Sheet Flooring09 65 16 1.9.B · PDF p. 642Spec wording“B. Manufacturer's Warranty: Warrant resilient sheet flooring against material and manufacturing defects. 1. Warranty Period: 2 years.” | 09 65 16 1.9.B | 642 | – |
| Test / cert. | Test / cert.Test Reports:Resilient Tile Flooring09 65 19 1.3.F · PDF p. 648Spec wording“F. Test Reports: 1. Abrasion resistance: Depth of wear for each tile type and color and volume loss of tile, certified by independent laboratory. Tested per ASTM F510/F510M. 2. Moisture and pH test results as per Section 09 05 16, SUBSURFACE PREPARATION FOR FLOOR FINISHES.” | 09 65 19 1.3.F | 648 | – |
| Warranty | WarrantyConstruction WarrantyResilient Tile Flooring09 65 19 1.7.A · PDF p. 649Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 09 65 19 1.7.A | 649 | – |
| Warranty | WarrantyWarrantyResinous (Epoxy Base) With Vinyl Chip Broadcast (Res-2)09 67 23.20 1.3.H · PDF p. 657Spec wording“H. Warranty: As specified in this section.” | 09 67 23.20 1.3.H | 657 | – |
| Warranty | WarrantyWork subject to the terms of the Article "Warranty of ...Resinous (Epoxy Base) With Vinyl Chip Broadcast (Res-2)09 67 23.20 1.7.A · PDF p. 661Spec wording“A. Work subject to the terms of the Article "Warranty of Construction" FAR clause 52.246-21.” | 09 67 23.20 1.7.A | 661 | – |
| Warranty | WarrantyWarrantyResinous (Epoxy Base) With Vinyl Chip Broadcast (Res-2)09 67 23.20 1.7.B · PDF p. 661Spec wording“B. Warranty: Manufacture shall furnish a single, written warranty covering the full assembly (including substrata) for both material and workmanship for a extended period of three (3) full years from date of installation, or provide a joint and several warranty signed on a single document by manufacturer and applicator jointly and severally warranting the materials and workmanship for a period of three (3) full ...” | 09 67 23.20 1.7.B | 661 | – |
Division 10 Specialties 10 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyConstruction WarrantySignage10 14 00 1.6.A · PDF p. 699Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 10 14 00 1.6.A | 699 | – |
| Warranty | WarrantyConstruction WarrantyCubicle Curtain Tracks10 21 23 1.5.A · PDF p. 710Spec wording“A. Construction Warranty: Cubicle curtain tracks are subject to the terms of the Article "Warranty of Construction," FAR clause 52.246-21.” | 10 21 23 1.5.A | 710 | – |
| O&M | O&MIn accordance with Section 26 05 11, REQUIREMENTS FOR ELECTRICAL ...Patient Bed Service Walls10 25 13 1.3.C · PDF p. 715-716Spec wording“C. In accordance with Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS and Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, submit the following: 1. Shop Drawings: a. Include sufficient information, clearly presented, to determine compliance with construction documents. b. Include electrical ratings, dimensions, mounting details, front view, side view, equipment and device arrangement, wiring ...” | 10 25 13 1.3.C | 715-716 | four (4) copies |
| Warranty | WarrantyConstruction WarrantyPatient Bed Service Walls10 25 13 1.4.A · PDF p. 716Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".” | 10 25 13 1.4.A | 716 | – |
| Test / cert. | Test / cert.Test ReportWall And Door Protection10 26 00 1.4.E · PDF p. 722Spec wording“E. Test Report: Showing that resilient material complies with specified fire and safety code requirements.” | 10 26 00 1.4.E | 722 | – |
| Warranty | WarrantyManufacturer's warrantyWall And Door Protection10 26 00 1.4.H · PDF p. 723Spec wording“H. Manufacturer's warranty.” | 10 26 00 1.4.H | 723 | – |
| Warranty | WarrantyConstruction WarrantyWall And Door Protection10 26 00 1.6.A · PDF p. 723Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".” | 10 26 00 1.6.A | 723 | – |
| Warranty | WarrantyManufacturer WarrantyWall And Door Protection10 26 00 1.6.B · PDF p. 723Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their wall and door protection for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer warranty.” | 10 26 00 1.6.B | 723 | – |
| O&M | O&MOperation and Maintenance Data:Toilet, Bath, And Laundry Accessories10 28 00 1.4.G · PDF p. 732Spec wording“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.” | 10 28 00 1.4.G | 732 | – |
| Warranty | WarrantyConstruction WarrantyToilet, Bath, And Laundry Accessories10 28 00 1.8.A · PDF p. 732Spec wording“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."” | 10 28 00 1.8.A | 732 | – |
Division 11 Equipment 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.NSF ComplianceCustom Fabricated Foodservice Equipment11 40 11 1.3.C · PDF p. 744Spec wording“C. NSF Compliance: Equipment bears NSF Certification Mark or UL Classification Mark indicating compliance with NSF/ANSI 2.” | 11 40 11 1.3.C | 744 | – |
| Warranty | WarrantyWarrant food service equipment to be free from defects in ...Custom Fabricated Foodservice Equipment11 40 11 1.5.A · PDF p. 745Spec wording“A. Warrant food service equipment to be free from defects in materials and workmanship in accordance with requirements of "Warranty of Construction", FAR clause 52.246-21.” | 11 40 11 1.5.A | 745 | – |
| O&M | O&MInstruct personnel and transmit operating instructions in accordance with requirements ...Custom Fabricated Foodservice Equipment11 40 11 3.3.A · PDF p. 747Spec wording“A. Instruct personnel and transmit operating instructions in accordance with requirements in Section 01 00 00, GENERAL REQUIREMENTS.” | 11 40 11 3.3.A | 747 | – |
| Training | TrainingTraining shall be provided for the required personnel to educate ...Ceiling Mounted Patient Lift System11 73 00 3.2 · PDF p. 751Spec wording“Training shall be provided for the required personnel to educate them on proper operation and maintenance for the lift system equipment.” | 11 73 00 3.2 | 751 | – |
Division 12 Furnishings 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyManufacturer's warrantyWindow Shades12 24 00 1.4.F · PDF p. 755Spec wording“F. Manufacturer's warranty.” | 12 24 00 1.4.F | 755 | – |
| Warranty | WarrantyConstruction WarrantyWindow Shades12 24 00 1.5.A · PDF p. 755Spec wording“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".” | 12 24 00 1.5.A | 755 | – |
| Warranty | WarrantyManufacturer WarrantyWindow Shades12 24 00 1.5.B · PDF p. 755Spec wording“B. Manufacturer Warranty: Manufacturer shall warranty their window shades for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer's warranty.” | 12 24 00 1.5.B | 755 | – |
| O&M | O&MOperations and Maintenance DataHealthcare Casework12 35 70 1.3.F · PDF p. 761Spec wording“F. Operations and Maintenance Data: Submit manufacturer's recommendations for cleaning and maintenance, including a list of spare parts and information for ordering.” | 12 35 70 1.3.F | 761 | – |
| Warranty | WarrantyWarrantyHealthcare Casework12 35 70 1.3.G · PDF p. 761Spec wording“G. Warranty: Submit executed copy of manufacturer's standard limited warranty.” | 12 35 70 1.3.G | 761 | – |
| Warranty | WarrantyModular Casework Limited WarrantyHealthcare Casework12 35 70 1.6.A · PDF p. 761Spec wording“A. Modular Casework Limited Warranty: Provide manufacturer's standard limited warranty for the items listed below, with additional exclusions as included in manufacturer's standard warranty. Furnish copies of warranties for components not manufactured by Midmark Corporation but incorporated into the casework as applicable. 1. Door and drawer fronts, casters, 5 years. 2. Task lights, 3 years. 3. Laminate top ...” | 12 35 70 1.6.A | 761 | – |
Division 13 Special construction 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Seismic CertificationSeismic Restraint Requirements For Non-Structural Components13 05 41 1.3.C · PDF p. 782Spec wording“C. Seismic Certification: In structures assigned to Seismic Design Category C, D, E, or F, permanent equipment and components are to have Special Seismic Certification in accordance with requirements of section 13.2.2 of ASCE 7, including those required in existing buildings within Section 13.7.1.3.3, 13.7.7.3.3 and 13.7.8.3.3 of ASCE 41, except for equipment and components that are considered inherently rugged as ...” | 13 05 41 1.3.C | 782 | – |
| Test / cert. | Test / cert.Submit a complete and coordinated set of bracing and signed ...Seismic Restraint Requirements For Non-Structural Components13 05 41 1.4.A · PDF p. 782-783Spec wording“A. Submit a complete and coordinated set of bracing and signed and sealed anchorage drawings and calculations for all non-structural elements requiring seismic restraint by the delegated professional structural engineer mentioned in Section 1.3.A.1 for review prior to installation including: 1. Description, layout, and location of all items to be anchored or braced with anchorage or brace points noted and ...” | 13 05 41 1.4.A | 782-783 | – |
Division 21 Fire suppression (sprinklers) 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MSubmit as one package in accordance with Section 01 33 ...Wet-Pipe Sprinkler Systems21 13 13 1.4.A · PDF p. 795-797Spec wording“A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting ...” | 21 13 13 1.4.A | 795-797 | binders; electronically; pdf; full size; One complete set; AutoCAD |
| O&M | O&MFurnish the services of a competent instructor for not less ...Wet-Pipe Sprinkler Systems21 13 13 3.3.A · PDF p. 804Spec wording“A. Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.” | 21 13 13 3.3.A | 804 | – |
Division 22 Plumbing 122 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MPlumbing Maintenance Data and Operating Instructions:Common Work Results For Plumbing22 05 11 1.4.K · PDF p. 816Spec wording“K. Plumbing Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all ...” | 22 05 11 1.4.K | 816 | – |
| Test / cert. | Test / cert.Provide copies of approved plumbing equipment submittals to the TAB ...Common Work Results For Plumbing22 05 11 1.4.L · PDF p. 816Spec wording“L. Provide copies of approved plumbing equipment submittals to the TAB and Commissioning Subcontractor.” | 22 05 11 1.4.L | 816 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Common Work Results For Plumbing22 05 11 1.4.M · PDF p. 816Spec wording“M. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 11 1.4.M | 816 | – |
| Test / cert. | Test / cert.Submit training plans, trainer qualifications and instructor qualifications in accordance ...Common Work Results For Plumbing22 05 11 1.4.N · PDF p. 816Spec wording“N. Submit training plans, trainer qualifications and instructor qualifications in accordance with the requirements of Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 11 1.4.N | 816 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.A · PDF p. 821Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 05 11 1.7.A | 821 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.B · PDF p. 821Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions will be in electronic version on CD or DVD inserted into a three─ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence ...” | 22 05 11 1.7.B | 821 | electronic version; CD; DVD; binder |
| Record docs | Record docsThe installing Contractor will maintain as-built drawings of each completed ...Common Work Results For Plumbing22 05 11 1.7.C · PDF p. 821Spec wording“C. The installing Contractor will maintain as-built drawings of each completed phase for verification; and, will provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 22 05 11 1.7.C | 821 | one paper copy; PDF; CD; DVD; AutoCAD; CAD |
| Record docs | Record docsThe as-built drawings will indicate the location and type of ...Common Work Results For Plumbing22 05 11 1.7.D · PDF p. 821-822Spec wording“D. The as-built drawings will indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 22 05 11 1.7.D | 821-822 | – |
| Record docs | Record docsCertification documentation will be provided to COR 21 working days ...Common Work Results For Plumbing22 05 11 1.7.E · PDF p. 822Spec wording“E. Certification documentation will be provided to COR 21 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results will ...” | 22 05 11 1.7.E | 822 | – |
| Test / cert. | Test / cert.Startup of equipment will be performed as described in the ...Common Work Results For Plumbing22 05 11 3.9.A · PDF p. 840Spec wording“A. Startup of equipment will be performed as described in the equipment specifications. Vibration within specified tolerance will be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.” | 22 05 11 3.9.A | 840 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Common Work Results For Plumbing22 05 11 3.9.B · PDF p. 841Spec wording“B. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the Contracting Officer's Representative and CxA. Provide a minimum of 2 weeks prior notice.” | 22 05 11 3.9.B | 841 | – |
| O&M | O&MAll new and temporary equipment and all elements of each ...Common Work Results For Plumbing22 05 11 3.11.A · PDF p. 841Spec wording“A. All new and temporary equipment and all elements of each assembly will be included.” | 22 05 11 3.11.A | 841 | – |
| O&M | O&MData sheet on each device listing model, size, capacity, pressure, ...Common Work Results For Plumbing22 05 11 3.11.B · PDF p. 841Spec wording“B. Data sheet on each device listing model, size, capacity, pressure, speed, horsepower, impeller size, and other information will be included.” | 22 05 11 3.11.B | 841 | – |
| O&M | O&MManufacturer's installation, maintenance, repair, and operation instructions for each device ...Common Work Results For Plumbing22 05 11 3.11.C · PDF p. 841Spec wording“C. Manufacturer's installation, maintenance, repair, and operation instructions for each device will be included. Assembly drawings and parts lists will also be included. A summary of operating precautions and reasons for precautions will be included in the Operations and Maintenance Manual.” | 22 05 11 3.11.C | 841 | – |
| O&M | O&MLubrication instructions, type and quantity of lubricant will be included ...Common Work Results For Plumbing22 05 11 3.11.D · PDF p. 841Spec wording“D. Lubrication instructions, type and quantity of lubricant will be included.” | 22 05 11 3.11.D | 841 | – |
| O&M | O&MSchematic diagrams and wiring diagrams of all control systems corrected ...Common Work Results For Plumbing22 05 11 3.11.E · PDF p. 841Spec wording“E. Schematic diagrams and wiring diagrams of all control systems corrected to include all field modifications will be included.” | 22 05 11 3.11.E | 841 | – |
| O&M | O&MSet points of all interlock devices will be listedCommon Work Results For Plumbing22 05 11 3.11.F · PDF p. 841Spec wording“F. Set points of all interlock devices will be listed.” | 22 05 11 3.11.F | 841 | – |
| O&M | O&MTrouble-shooting guide for the control system troubleshooting will be inserted ...Common Work Results For Plumbing22 05 11 3.11.G · PDF p. 842Spec wording“G. Trouble-shooting guide for the control system troubleshooting will be inserted into the Operations and Maintenance Manual.” | 22 05 11 3.11.G | 842 | – |
| O&M | O&MThe control system sequence of operation corrected with submittal review ...Common Work Results For Plumbing22 05 11 3.11.H · PDF p. 842Spec wording“H. The control system sequence of operation corrected with submittal review comments will be inserted into the Operations and Maintenance Manual.” | 22 05 11 3.11.H | 842 | – |
| O&M | O&MEmergency procedures for shutdown and startup of equipment and systemsCommon Work Results For Plumbing22 05 11 3.11.I · PDF p. 842Spec wording“I. Emergency procedures for shutdown and startup of equipment and systems.” | 22 05 11 3.11.I | 842 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Plumbing22 05 11 3.12.A · PDF p. 842Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 11 3.12.A | 842 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Common Work Results For Plumbing22 05 11 3.12.B · PDF p. 842Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 05 11 3.12.B | 842 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Plumbing22 05 11 3.13.A · PDF p. 842Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 22 05 11 3.13.A | 842 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Plumbing22 05 11 3.13.B · PDF p. 842Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 11 3.13.B | 842 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.F · PDF p. 846Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 05 12 1.4.F | 846 | – |
| Test / cert. | Test / cert.CertificationGeneral Motor Requirements For Plumbing Equipment22 05 12 1.4.G · PDF p. 846Spec wording“G. Certification: Two weeks prior to final inspection, unless otherwise noted, the following certification shall be submitted to the Contracting Officer's Representative (COR). 1. Certification shall be submitted stating that the motors have been properly applied, installed, adjusted, lubricated, and tested.” | 22 05 12 1.4.G | 846 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.H · PDF p. 846Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 12 1.4.H | 846 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Plumbing Equipment22 05 12 1.4.I · PDF p. 846Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 12 1.4.I | 846 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...General Motor Requirements For Plumbing Equipment22 05 12 1.6.A · PDF p. 846Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 05 12 1.6.A | 846 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.A · PDF p. 853Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 05 12 3.3.A | 853 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.B · PDF p. 853Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 05 12 3.3.B | 853 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...General Motor Requirements For Plumbing Equipment22 05 12 3.3.C · PDF p. 853Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 22 05 12 3.3.C | 853 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General Motor Requirements For Plumbing Equipment22 05 12 3.4.A · PDF p. 853Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 12 3.4.A | 853 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification shall be ...General Motor Requirements For Plumbing Equipment22 05 12 3.4.B · PDF p. 853Spec wording“B. Components provided under this section of the specification shall be tested as part of a larger system.” | 22 05 12 3.4.B | 853 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4hours to instruct ...General Motor Requirements For Plumbing Equipment22 05 12 3.5.A · PDF p. 853Spec wording“A. Provide services of manufacturer's technical representative for 4hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 22 05 12 3.5.A | 853 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Plumbing Equipment22 05 12 3.5.B · PDF p. 853Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 12 3.5.B | 853 | – |
| O&M | O&MComplete operating and maintenance manual shall including wiring diagrams, technical ...Meters And Gauges For Plumbing Piping22 05 19 1.4.D · PDF p. 855Spec wording“D. Complete operating and maintenance manual shall including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the system. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and ...” | 22 05 19 1.4.D | 855 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Meters And Gauges For Plumbing Piping22 05 19 1.4.E · PDF p. 855-856Spec wording“E. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 19 1.4.E | 855-856 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Meters And Gauges For Plumbing Piping22 05 19 1.4.F · PDF p. 856Spec wording“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 19 1.4.F | 856 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Meters And Gauges For Plumbing Piping22 05 19 1.5.A · PDF p. 856Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 05 19 1.5.A | 856 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Meters And Gauges For Plumbing Piping22 05 19 3.3.A · PDF p. 857Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 05 19 3.3.A | 857 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Meters And Gauges For Plumbing Piping22 05 19 3.3.B · PDF p. 857Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 05 19 3.3.B | 857 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Meters And Gauges For Plumbing Piping22 05 19 3.3.C · PDF p. 857Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 22 05 19 3.3.C | 857 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Meters And Gauges For Plumbing Piping22 05 19 3.4.A · PDF p. 857Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 19 3.4.A | 857 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Meters And Gauges For Plumbing Piping22 05 19 3.4.B · PDF p. 858Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 05 19 3.4.B | 858 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Meters And Gauges For Plumbing Piping22 05 19 3.5.A · PDF p. 858Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 22 05 19 3.5.A | 858 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Meters And Gauges For Plumbing Piping22 05 19 3.5.B · PDF p. 858Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 19 3.5.B | 858 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General-Duty Valves For Plumbing Piping22 05 23 1.4.E · PDF p. 863Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance. ...” | 22 05 23 1.4.E | 863 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General-Duty Valves For Plumbing Piping22 05 23 1.4.F · PDF p. 863Spec wording“F. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 23 1.4.F | 863 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...General-Duty Valves For Plumbing Piping22 05 23 1.4.G · PDF p. 863Spec wording“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 23 1.4.G | 863 | – |
| Test / cert. | Test / cert.Testing and adjusting of balancing valves shall be performed by ...General-Duty Valves For Plumbing Piping22 05 23 3.4.D · PDF p. 872Spec wording“D. Testing and adjusting of balancing valves shall be performed by an independent NEBB Accredited Test and Balance Contractor. A final settings and flow report shall be submitted to the VA Contracting Officer's Representative (COR).” | 22 05 23 3.4.D | 872 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General-Duty Valves For Plumbing Piping22 05 23 3.5.A · PDF p. 872Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 22 05 23 3.5.A | 872 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...General-Duty Valves For Plumbing Piping22 05 23 3.5.B · PDF p. 872Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 22 05 23 3.5.B | 872 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...General-Duty Valves For Plumbing Piping22 05 23 3.5.C · PDF p. 872Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 22 05 23 3.5.C | 872 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General-Duty Valves For Plumbing Piping22 05 23 3.6.A · PDF p. 873Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 23 3.6.A | 873 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...General-Duty Valves For Plumbing Piping22 05 23 3.6.B · PDF p. 873Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 05 23 3.6.B | 873 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...General-Duty Valves For Plumbing Piping22 05 23 3.7.A · PDF p. 873Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 22 05 23 3.7.A | 873 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...General-Duty Valves For Plumbing Piping22 05 23 3.7.B · PDF p. 873Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 05 23 3.7.B | 873 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Plumbing Insulation22 07 11 1.4.F · PDF p. 879Spec wording“F. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 07 11 1.4.F | 879 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.A · PDF p. 880Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 07 11 1.6.A | 880 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.B · PDF p. 880-881Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...” | 22 07 11 1.6.B | 880-881 | electronic version; DVD; binder |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Plumbing Insulation22 07 11 1.6.C · PDF p. 881Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not ...” | 22 07 11 1.6.C | 881 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided prior to submitting the request ...Plumbing Insulation22 07 11 1.6.D · PDF p. 881Spec wording“D. Certification documentation shall be provided prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 07 11 1.6.D | 881 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Plumbing Insulation22 07 11 3.3.A · PDF p. 893Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 07 11 3.3.A | 893 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Plumbing Insulation22 07 11 3.3.B · PDF p. 893Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 07 11 3.3.B | 893 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals. The Commissioning ...Commissioning Of Plumbing Systems22 08 00 1.6.A · PDF p. 897Spec wording“A. The commissioning process requires review of selected Submittals. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 22 08 00 1.6.A | 897 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Plumbing Systems22 08 00 1.6.B · PDF p. 897Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 22 08 00 1.6.B | 897 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Plumbing Systems22 08 00 3.4.A · PDF p. 898Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Engineer of Record ...” | 22 08 00 3.4.A | 898 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Plumbing Systems22 08 00 3.5.A · PDF p. 898-899Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the VA and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...” | 22 08 00 3.5.A | 898-899 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Water Distribution22 11 00 1.4.D · PDF p. 904Spec wording“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets and information for ordering replacement parts: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 11 00 1.4.D | 904 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Facility Water Distribution22 11 00 1.4.E · PDF p. 904Spec wording“E. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 11 00 1.4.E | 904 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Facility Water Distribution22 11 00 1.4.F · PDF p. 904Spec wording“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 11 00 1.4.F | 904 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Facility Water Distribution22 11 00 1.6.A · PDF p. 905Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 11 00 1.6.A | 905 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Facility Water Distribution22 11 00 1.6.B · PDF p. 905Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...” | 22 11 00 1.6.B | 905 | electronic version; DVD; three-ring; binder |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Facility Water Distribution22 11 00 1.6.C · PDF p. 905Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 11 00 1.6.C | 905 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided to COR 10 working days ...Facility Water Distribution22 11 00 1.6.D · PDF p. 905Spec wording“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certificate if applicable that all results of tests were within limits specified. If a certificate is not ...” | 22 11 00 1.6.D | 905 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Facility Water Distribution22 11 00 3.4.A · PDF p. 910Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 11 00 3.4.A | 910 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Facility Water Distribution22 11 00 3.4.B · PDF p. 911Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 11 00 3.4.B | 911 | – |
| Training | TrainingProvide services of manufacturer's technical representative for four hours to ...Facility Water Distribution22 11 00 3.5.A · PDF p. 911Spec wording“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.” | 22 11 00 3.5.A | 911 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Facility Water Distribution22 11 00 3.5.B · PDF p. 911Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 11 00 3.5.B | 911 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Sanitary And Vent Piping22 13 00 1.4.E · PDF p. 916Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 22 13 00 1.4.E | 916 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CXA and completed ...Facility Sanitary And Vent Piping22 13 00 1.4.F · PDF p. 916Spec wording“F. Completed System Readiness Checklist provided by the CXA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 13 00 1.4.F | 916 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Facility Sanitary And Vent Piping22 13 00 1.4.G · PDF p. 916Spec wording“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 13 00 1.4.G | 916 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Facility Sanitary And Vent Piping22 13 00 1.6.A · PDF p. 917Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.” | 22 13 00 1.6.A | 917 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Facility Sanitary And Vent Piping22 13 00 3.6.A · PDF p. 925Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 13 00 3.6.A | 925 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification shall be ...Facility Sanitary And Vent Piping22 13 00 3.6.B · PDF p. 925Spec wording“B. Components provided under this section of the specification shall be tested as part of a larger system.” | 22 13 00 3.6.B | 925 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Facility Sanitary And Vent Piping22 13 00 3.7.A · PDF p. 925Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 22 13 00 3.7.A | 925 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Facility Sanitary And Vent Piping22 13 00 3.7.B · PDF p. 925Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 13 00 3.7.B | 925 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Plumbing Fixtures22 40 00 1.4.E · PDF p. 927Spec wording“E. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 40 00 1.4.E | 927 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Plumbing Fixtures22 40 00 1.4.F · PDF p. 928Spec wording“F. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 40 00 1.4.F | 928 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.A · PDF p. 928Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 40 00 1.6.A | 928 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Fixtures22 40 00 1.6.B · PDF p. 928Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions will be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation ...” | 22 40 00 1.6.B | 928 | electronic version; DVD; binder |
| Record docs | Record docsThe installing contractor will maintain as-built drawings of each completed ...Plumbing Fixtures22 40 00 1.6.C · PDF p. 928Spec wording“C. The installing contractor will maintain as-built drawings of each completed phase for verification; and will provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in AutoCAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it will not be deemed a ...” | 22 40 00 1.6.C | 928 | AutoCAD; DVD |
| Record docs | Record docsCertification documentation will be provided to COR 10 working days ...Plumbing Fixtures22 40 00 1.6.D · PDF p. 928-929Spec wording“D. Certification documentation will be provided to COR 10 working days prior to submitting the request for final inspection. The documentation will include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 40 00 1.6.D | 928-929 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Plumbing Fixtures22 40 00 3.4.A · PDF p. 933Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 40 00 3.4.A | 933 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Plumbing Fixtures22 40 00 3.4.B · PDF p. 933Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 40 00 3.4.B | 933 | – |
| Training | TrainingProvide services of manufacturer's technical representative for four hours to ...Plumbing Fixtures22 40 00 3.5.A · PDF p. 933Spec wording“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.” | 22 40 00 3.5.A | 933 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Plumbing Fixtures22 40 00 3.5.B · PDF p. 933Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 40 00 3.5.B | 933 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.4.G · PDF p. 938-939Spec wording“G. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 62 00 1.4.G | 938-939 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.4.H · PDF p. 939Spec wording“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 62 00 1.4.H | 939 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.7.A · PDF p. 941Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 62 00 1.7.A | 941 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.7.B · PDF p. 941Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...” | 22 62 00 1.7.B | 941 | electronic version; DVD; three-ring; binder |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.7.C · PDF p. 941-942Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 62 00 1.7.C | 941-942 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided to COR 10 working days ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 1.7.D · PDF p. 942Spec wording“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 62 00 1.7.D | 942 | – |
| Test / cert. | Test / cert.Prior to handing over the systems to VAMC, the contractor ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 3.3.A · PDF p. 954-955Spec wording“A. Prior to handing over the systems to VAMC, the contractor shall retain a verifier acceptable to the engineer of record and VA who shall follow strictly the procedures for verification as described in NFPA 99 5.1.12.3 and provide a written report and certificate bearing the notarized signature of an officer of the verification company on company letterhead which contains at least the following: 1. A current ACORD ...” | 22 62 00 3.3.A | 954-955 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 3.5.A · PDF p. 957Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 62 00 3.5.A | 957 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 3.5.B · PDF p. 957Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 62 00 3.5.B | 957 | – |
| Training | TrainingProvide services of manufacturer's technical representative for four hours to ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 3.6.A · PDF p. 957Spec wording“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.” | 22 62 00 3.6.A | 957 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Vacuum Systems For Laboratory And Healthcare Facilities22 62 00 3.6.B · PDF p. 957Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 62 00 3.6.B | 957 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.4.R · PDF p. 962Spec wording“R. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 63 00 1.4.R | 962 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.4.S · PDF p. 962Spec wording“S. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 63 00 1.4.S | 962 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.6.A · PDF p. 964Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 22 63 00 1.6.A | 964 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.6.B · PDF p. 964Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...” | 22 63 00 1.6.B | 964 | electronic version; DVD; binder |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.6.C · PDF p. 964Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be ...” | 22 63 00 1.6.C | 964 | CAD; DVD |
| Record docs | Record docsCertification documentation shall be provided to COR 10 working days ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 1.6.D · PDF p. 964Spec wording“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.” | 22 63 00 1.6.D | 964 | – |
| Test / cert. | Test / cert.Initial TestsGas Systems For Laboratory And Healthcare Facilities22 63 00 3.2.A · PDF p. 973Spec wording“A. Initial Tests: Blow down and high and low pressure leakage tests as required by NFPA 99 with documentation.” | 22 63 00 3.2.A | 973 | – |
| Test / cert. | Test / cert.Laboratory and/or healthcare testing agency shall perform the following: ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.2.B · PDF p. 973-974Spec wording“B. Laboratory and/or healthcare testing agency shall perform the following: 1. Perform and document all cross connection tests, labeling verification, supply system operation, and valve and alarm operation tests as required by, and in accordance with NFPA 99 and the procedures set forth in pre-qualification documentation. 2. Verify that the systems, as installed, meet or exceed the requirements of NFPA 99, this ...” | 22 63 00 3.2.B | 973-974 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.2.C · PDF p. 974Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Contractor shall provide a minimum of 10 working days prior to startup and testing.” | 22 63 00 3.2.C | 974 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.4.A · PDF p. 974Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 63 00 3.4.A | 974 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.4.B · PDF p. 974Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 22 63 00 3.4.B | 974 | – |
| Training | TrainingProvide services of manufacturer's technical representative for four hours to ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.5.A · PDF p. 974Spec wording“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of units.” | 22 63 00 3.5.A | 974 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Gas Systems For Laboratory And Healthcare Facilities22 63 00 3.5.B · PDF p. 975Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.” | 22 63 00 3.5.B | 975 | – |
Division 23 HVAC 123 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MHVAC Maintenance Data and Operating Instructions:Common Work Results For Hvac23 05 11 1.4.M · PDF p. 985Spec wording“M. HVAC Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, paragraph INSTRUCTIONS for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all components ...” | 23 05 11 1.4.M | 985 | – |
| Test / cert. | Test / cert.Provide copies of approved HVAC equipment submittals to the TAB ...Common Work Results For Hvac23 05 11 1.4.N · PDF p. 985Spec wording“N. Provide copies of approved HVAC equipment submittals to the TAB and Commissioning Subcontractor.” | 23 05 11 1.4.N | 985 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Common Work Results For Hvac23 05 11 1.4.O · PDF p. 985Spec wording“O. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 1.4.O | 985 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Common Work Results For Hvac23 05 11 1.4.P · PDF p. 985Spec wording“P. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 1.4.P | 985 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.A · PDF p. 990Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 23 05 11 1.7.A | 990 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.B · PDF p. 990Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...” | 23 05 11 1.7.B | 990 | electronic version; CD; DVD; three-ring; binder |
| Record docs | Record docsThe installing Contractor shall maintain as-built drawings of each completed ...Common Work Results For Hvac23 05 11 1.7.C · PDF p. 991Spec wording“C. The installing Contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 23 05 11 1.7.C | 991 | one paper copy; PDF; CD; DVD; AutoCAD; CAD |
| Record docs | Record docsThe as-built drawings shall indicate the location and type of ...Common Work Results For Hvac23 05 11 1.7.D · PDF p. 991Spec wording“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 23 05 11 1.7.D | 991 | – |
| Record docs | Record docsCertification documentation shall be provided to COR 21 working days ...Common Work Results For Hvac23 05 11 1.7.E · PDF p. 991Spec wording“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...” | 23 05 11 1.7.E | 991 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Common Work Results For Hvac23 05 11 3.11.A · PDF p. 1012Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 05 11 3.11.A | 1012 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Common Work Results For Hvac23 05 11 3.11.B · PDF p. 1012Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 05 11 3.11.B | 1012 | – |
| Test / cert. | Test / cert.The CxA will observe startup and Contractor testing of selected ...Common Work Results For Hvac23 05 11 3.11.C · PDF p. 1012Spec wording“C. The CxA will observe startup and Contractor testing of selected equipment. Coordinate the startup and Contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 05 11 3.11.C | 1012 | – |
| Test / cert. | Test / cert.Startup of equipment shall be performed as described in equipment ...Common Work Results For Hvac23 05 11 3.11.D · PDF p. 1012Spec wording“D. Startup of equipment shall be performed as described in equipment specifications. Vibration within specified tolerance shall be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, paragraph TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.” | 23 05 11 3.11.D | 1012 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Common Work Results For Hvac23 05 11 3.13.A · PDF p. 1013Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 3.13.A | 1013 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Common Work Results For Hvac23 05 11 3.13.B · PDF p. 1013Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 05 11 3.13.B | 1013 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Hvac23 05 11 3.14.A · PDF p. 1013Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 11 3.14.A | 1013 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.F · PDF p. 1016Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 05 12 1.4.F | 1016 | – |
| Test / cert. | Test / cert.CertificationGeneral Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.G · PDF p. 1016Spec wording“G. Certification: Two weeks prior to final inspection, unless otherwise noted, certification shall be submitted to the COR stating that the motors have been properly applied, installed, adjusted, lubricated, and tested.” | 23 05 12 1.4.G | 1016 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.H · PDF p. 1016Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 1.4.H | 1016 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.I · PDF p. 1016Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS./” | 23 05 12 1.4.I | 1016 | – |
| Record docs | Record docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.5.A · PDF p. 1016Spec wording“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 05 10, COMMON WORK RESULTS FOR BOILER PLANT AND STEAM GENERATION Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 05 12 1.5.A | 1016 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.A · PDF p. 1022-1023Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 05 12 3.3.A | 1022-1023 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.B · PDF p. 1023Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 05 12 3.3.B | 1023 | – |
| Test / cert. | Test / cert.The CxA shall observe startup and contractor testing of selected ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.C · PDF p. 1023Spec wording“C. The CxA shall observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 05 12 3.3.C | 1023 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.4.A · PDF p. 1023Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 3.4.A | 1023 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification shall be ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.4.B · PDF p. 1023Spec wording“B. Components provided under this section of the specification shall be tested as part of a greater system.” | 23 05 12 3.4.B | 1023 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 1 hour to ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.5.A · PDF p. 1023Spec wording“A. Provide services of manufacturer's technical representative for 1 hour to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 05 12 3.5.A | 1023 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.5.B · PDF p. 1023Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 12 3.5.B | 1023 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Noise And Vibration Control For Hvac Piping And Equipment23 05 41 1.6.A · PDF p. 1027Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC. 23 05 41 4” | 23 05 41 1.6.A | 1027 | – |
| Test / cert. | Test / cert.Submit the following for review and approval:Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.E · PDF p. 1036Spec wording“E. Submit the following for review and approval: 1. Design Review Report within 90 days for conventional design projects within 60 days for design-build projects after the system layout on air and water side is completed by the Contractor. 2. Systems inspection report on equipment and installation for conformance with design. 3. Duct Air Leakage Test Report. 4. Systems Readiness Report. 5. Intermediate and Final ...” | 23 05 93 1.4.E | 1036 | – |
| Test / cert. | Test / cert.Prior to request for Final or Partial Final inspection, submit ...Testing, Adjusting, And Balancing For Hvac23 05 93 1.4.F · PDF p. 1036Spec wording“F. Prior to request for Final or Partial Final inspection, submit completed Test and Balance report for the area with noted critical paths.” | 23 05 93 1.4.F | 1036 | – |
| Test / cert. | Test / cert.Record initial measurements for each unit of equipment on test ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.8.B · PDF p. 1044Spec wording“B. Record initial measurements for each unit of equipment on test forms and submit a report to the COR. Where vibration readings exceed the allowable tolerance Contractor shall be directed to correct the problem. The TAB agency shall verify that the corrections are done and submit a final report to the COR.” | 23 05 93 3.8.B | 1044 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.13.A · PDF p. 1045Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 05 93 3.13.A | 1045 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.13.B · PDF p. 1045Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 05 93 3.13.B | 1045 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Hvac Systems23 08 00 1.6.A · PDF p. 1047Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 23 08 00 1.6.A | 1047 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Hvac Systems23 08 00 1.6.B · PDF p. 1047Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 23 08 00 1.6.B | 1047 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Hvac Systems23 08 00 3.4.A · PDF p. 1049Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Engineer of Record ...” | 23 08 00 3.4.A | 1049 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Hvac Systems23 08 00 3.5.A · PDF p. 1049-1050Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the VA and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...” | 23 08 00 3.5.A | 1049-1050 | – |
| Warranty | WarrantyLabor and materials for control systems shall be warranted for ...Direct-Digital Control System For Hvac23 09 23 1.6 · PDF p. 1068Spec wording“Labor and materials for control systems shall be warranted for a period as specified under Warranty in FAR clause 52.246-21. Control system failures during the warranty period shall be adjusted, repaired, or replaced at no cost or reduction in service to the owner. The system includes all computer equipment, transmission equipment, and all sensors and control devices. The on-line support service shall allow the ...” | 23 09 23 1.6 | 1068 | – |
| Warranty | WarrantySubmit shop drawings in accordance with Section 01 33 23, ...Direct-Digital Control System For Hvac23 09 23 1.7 · PDF p. 1069-1071Spec wording“Submit shop drawings in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Information and material submitted under this section shall be marked "SUBMITTED UNDER SECTION 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC", with applicable paragraph identification. Manufacturer's Literature and Data Including: 1. A wiring diagram for each type of input device and output device including DDC ...” | 23 09 23 1.7 | 1069-1071 | three (3) copies; one (1) set; CD-ROM; CAD; One copy |
| Training | TrainingInstructions to VA operations personnelDirect-Digital Control System For Hvac23 09 23 1.8 · PDF p. 1072Spec wording“Instructions to VA operations personnel: Perform in accordance with Article, INSTRUCTIONS, in Specification Section 01 00 00, GENERAL REQUIREMENTS, and as noted below. Contractor shall also video tape instruction sessions noted below. 1. First Phase: Formal instructions to the VA facilities personnel for a total of 16 hours, given in multiple training sessions (each no longer than four hours in length), conducted ...” | 23 09 23 1.8 | 1072 | – |
| Training | TrainingAs part of final system acceptance, a system demonstration is ...Direct-Digital Control System For Hvac23 09 23 3.2 · PDF p. 1112-1114Spec wording“As part of final system acceptance, a system demonstration is required (see below). Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the controls and instrumentation system. When formal commissioning is included in the project the system validation/test shall be part of the commissioning and shall be witnessed by the CxA. Validation: 1. Prepare and submit ...” | 23 09 23 3.2 | 1112-1114 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Direct-Digital Control System For Hvac23 09 23 3.3 · PDF p. 1114-1115Spec wording“Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part. When any defects are detected, correct defects and repeat test at no additional cost or time to ...” | 23 09 23 3.3 | 1114-1115 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Direct-Digital Control System For Hvac23 09 23 3.4 · PDF p. 1115Spec wording“Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS. Components provided under this section of the specification will be tested as part of a larger system.” | 23 09 23 3.4 | 1115 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Direct-Digital Control System For Hvac23 09 23 3.5 · PDF p. 1115Spec wording“Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in the operation and maintenance of the system. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 09 23 3.5 | 1115 | – |
| Record docs | Record docsAs-Built Piping DiagramsHydronic Piping23 21 13 1.4.F · PDF p. 1120Spec wording“F. As-Built Piping Diagrams: Provide drawings as follows for chilled water, condenser water, heating hot water system, and other piping systems and equipment. 1. 1wall-mounted stick file with complete set of prints. Mount stick file in the chiller plant or control room along with control diagram stick file. 2. 1 complete set of reproducible drawings. 3. 1 complete set of drawings in electronic AutoCAD and pdf format.” | 23 21 13 1.4.F | 1120 | 1 complete set; AutoCAD; pdf |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hydronic Piping23 21 13 1.4.G · PDF p. 1120Spec wording“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 21 13 1.4.G | 1120 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hydronic Piping23 21 13 1.4.H · PDF p. 1120Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 1.4.H | 1120 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Hydronic Piping23 21 13 1.4.I · PDF p. 1120Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 1.4.I | 1120 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hydronic Piping23 21 13 1.6.A · PDF p. 1121Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 21 13 1.6.A | 1121 | – |
| Spare parts | Spare partsFor mechanical pressed sealed fittings provide tools required for each ...Hydronic Piping23 21 13 1.7.A · PDF p. 1121Spec wording“A. For mechanical pressed sealed fittings provide tools required for each pipe size used at the facility.” | 23 21 13 1.7.A | 1121 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hydronic Piping23 21 13 3.8.A · PDF p. 1136Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 21 13 3.8.A | 1136 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hydronic Piping23 21 13 3.8.B · PDF p. 1136Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 21 13 3.8.B | 1136 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hydronic Piping23 21 13 3.8.C · PDF p. 1136Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 21 13 3.8.C | 1136 | – |
| Test / cert. | Test / cert.Adjust red set hand on pressure gauges to normal working pressureHydronic Piping23 21 13 3.8.D · PDF p. 1136Spec wording“D. Adjust red set hand on pressure gauges to normal working pressure.” | 23 21 13 3.8.D | 1136 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hydronic Piping23 21 13 3.9.A · PDF p. 1136Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 3.9.A | 1136 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hydronic Piping23 21 13 3.9.B · PDF p. 1136Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 21 13 3.9.B | 1136 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Hydronic Piping23 21 13 3.10.A · PDF p. 1136Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 21 13 3.10.A | 1136 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hydronic Piping23 21 13 3.10.B · PDF p. 1136Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 21 13 3.10.B | 1136 | – |
| Record docs | Record docsAs-Built Piping DiagramsSteam And Condensate Heating Piping23 22 13 1.4.E · PDF p. 1141Spec wording“E. As-Built Piping Diagrams: Provide drawing as follows for steam and steam condensate piping and other central plant equipment. 1. One wall-mounted stick file for prints. Mount stick file in the chiller plant or adjacent control room along with control diagram stick file. 2. One set of reproducible drawings.” | 23 22 13 1.4.E | 1141 | One set |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Steam And Condensate Heating Piping23 22 13 1.4.F · PDF p. 1141Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.” | 23 22 13 1.4.F | 1141 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Steam And Condensate Heating Piping23 22 13 1.4.G · PDF p. 1141Spec wording“G. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 1.4.G | 1141 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 1.4.H · PDF p. 1141Spec wording“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 1.4.H | 1141 | – |
| Record docs | Record docsSubmit manufacturer's literature and data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.A · PDF p. 1142Spec wording“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.” | 23 22 13 1.6.A | 1142 | – |
| Record docs | Record docsSubmit operation and maintenance data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.B · PDF p. 1142Spec wording“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included ...” | 23 22 13 1.6.B | 1142 | electronic version; CD; DVD |
| Record docs | Record docsThe installing contractor shall maintain as-built drawings of each completed ...Steam And Condensate Heating Piping23 22 13 1.6.C · PDF p. 1142-1143Spec wording“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...” | 23 22 13 1.6.C | 1142-1143 | one paper copy; PDF; CD; DVD; AutoCAD; CAD |
| Record docs | Record docsThe as-built drawings shall indicate the location and type of ...Steam And Condensate Heating Piping23 22 13 1.6.D · PDF p. 1143Spec wording“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.” | 23 22 13 1.6.D | 1143 | – |
| Record docs | Record docsCertification documentation shall be provided to COR 21 working days ...Steam And Condensate Heating Piping23 22 13 1.6.E · PDF p. 1143Spec wording“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...” | 23 22 13 1.6.E | 1143 | – |
| Test / cert. | Test / cert.Prepare and submit test and inspection reports to the COR ...Steam And Condensate Heating Piping23 22 13 3.7.D · PDF p. 1160Spec wording“D. Prepare and submit test and inspection reports to the COR within 5 working days of test completion and prior to covering the pipe.” | 23 22 13 3.7.D | 1160 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Steam And Condensate Heating Piping23 22 13 3.9.A · PDF p. 1160Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 22 13 3.9.A | 1160 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Steam And Condensate Heating Piping23 22 13 3.9.B · PDF p. 1160Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 22 13 3.9.B | 1160 | – |
| Test / cert. | Test / cert.The CxA shall observe startup and contractor testing of selected ...Steam And Condensate Heating Piping23 22 13 3.9.C · PDF p. 1160Spec wording“C. The CxA shall observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 22 13 3.9.C | 1160 | – |
| Test / cert. | Test / cert.Adjust red set hand on pressure gauges to normal working pressureSteam And Condensate Heating Piping23 22 13 3.9.D · PDF p. 1160Spec wording“D. Adjust red set hand on pressure gauges to normal working pressure.” | 23 22 13 3.9.D | 1160 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Steam And Condensate Heating Piping23 22 13 3.10.A · PDF p. 1160Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 3.10.A | 1160 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification shall be ...Steam And Condensate Heating Piping23 22 13 3.10.B · PDF p. 1160Spec wording“B. Components provided under this section of the specification shall be tested as part of a larger system.” | 23 22 13 3.10.B | 1160 | – |
| Training | TrainingProvide services of manufacturer's technical representative 4 hours to instruct ...Steam And Condensate Heating Piping23 22 13 3.11.A · PDF p. 1161Spec wording“A. Provide services of manufacturer's technical representative 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 22 13 3.11.A | 1161 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Steam And Condensate Heating Piping23 22 13 3.11.B · PDF p. 1161Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 22 13 3.11.B | 1161 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Ducts And Casings23 31 00 1.4.E · PDF p. 1165Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 31 00 1.4.E | 1165 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Ducts And Casings23 31 00 1.6.A · PDF p. 1166Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 31 00 1.6.A | 1166 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Fans23 34 00 1.4.G · PDF p. 1180Spec wording“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 34 00 1.4.G | 1180 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Hvac Fans23 34 00 1.4.H · PDF p. 1180Spec wording“H. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 1.4.H | 1180 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Hvac Fans23 34 00 1.4.I · PDF p. 1180Spec wording“I. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 1.4.I | 1180 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Fans23 34 00 1.6.A · PDF p. 1181Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 34 00 1.6.A | 1181 | – |
| Spare parts | Spare partsProvide one additional set of belts for all belt-driven fansHvac Fans23 34 00 1.7.A · PDF p. 1181Spec wording“A. Provide one additional set of belts for all belt-driven fans.” | 23 34 00 1.7.A | 1181 | one additional set |
| Test / cert. | Test / cert.Verify operation of motor, drive system and fan wheel according ...Hvac Fans23 34 00 3.3.A · PDF p. 1183Spec wording“A. Verify operation of motor, drive system and fan wheel according to the contract documents.” | 23 34 00 3.3.A | 1183 | – |
| Test / cert. | Test / cert.Check vibration and correct as necessary for air balance workHvac Fans23 34 00 3.3.B · PDF p. 1183Spec wording“B. Check vibration and correct as necessary for air balance work.” | 23 34 00 3.3.B | 1183 | – |
| Test / cert. | Test / cert.After air balancing is complete and permanent sheaves are in ...Hvac Fans23 34 00 3.3.C · PDF p. 1183-1184Spec wording“C. After air balancing is complete and permanent sheaves are in place perform necessary field mechanical balancing to meet vibration tolerance in Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and EQUIPMENT.” | 23 34 00 3.3.C | 1183-1184 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Fans23 34 00 3.3.D · PDF p. 1184Spec wording“D. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 34 00 3.3.D | 1184 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Fans23 34 00 3.3.E · PDF p. 1184Spec wording“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 34 00 3.3.E | 1184 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Hvac Fans23 34 00 3.3.F · PDF p. 1184Spec wording“F. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 34 00 3.3.F | 1184 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Hvac Fans23 34 00 3.4.A · PDF p. 1184Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 3.4.A | 1184 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Hvac Fans23 34 00 3.4.B · PDF p. 1184Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 34 00 3.4.B | 1184 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Hvac Fans23 34 00 3.5.A · PDF p. 1184Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 34 00 3.5.A | 1184 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Hvac Fans23 34 00 3.5.B · PDF p. 1184Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 34 00 3.5.B | 1184 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Terminal Units23 36 00 1.4.E · PDF p. 1187Spec wording“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 36 00 1.4.E | 1187 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Air Terminal Units23 36 00 1.4.F · PDF p. 1187Spec wording“F. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 1.4.F | 1187 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Air Terminal Units23 36 00 1.4.G · PDF p. 1187Spec wording“G. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 1.4.G | 1187 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Terminal Units23 36 00 1.6.A · PDF p. 1188Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 36 00 1.6.A | 1188 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Terminal Units23 36 00 3.2.A · PDF p. 1191Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 36 00 3.2.A | 1191 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Air Terminal Units23 36 00 3.2.B · PDF p. 1191Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 36 00 3.2.B | 1191 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Air Terminal Units23 36 00 3.2.C · PDF p. 1191Spec wording“C. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 36 00 3.2.C | 1191 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Air Terminal Units23 36 00 3.3.A · PDF p. 1191Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 3.3.A | 1191 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Air Terminal Units23 36 00 3.3.B · PDF p. 1191Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 36 00 3.3.B | 1191 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Air Terminal Units23 36 00 3.4.A · PDF p. 1191Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 36 00 3.4.A | 1191 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Air Terminal Units23 36 00 3.4.B · PDF p. 1191Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 36 00 3.4.B | 1191 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Outlets And Inlets23 37 00 1.4.D · PDF p. 1193Spec wording“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.” | 23 37 00 1.4.D | 1193 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Outlets And Inlets23 37 00 1.6.A · PDF p. 1193Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 37 00 1.6.A | 1193 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Outlets And Inlets23 37 00 3.4.A · PDF p. 1198Spec wording“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 37 00 3.4.A | 1198 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Air Outlets And Inlets23 37 00 3.4.B · PDF p. 1198Spec wording“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 37 00 3.4.B | 1198 | – |
| O&M | O&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Indoor Central-Station Air-Handling Units23 73 00 1.4.F · PDF p. 1203Spec wording“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include instructions for lubrication, filter replacement, motor and drive replacement, and spare parts list. 3. Include complete diagrams of the internal wiring for each item of ...” | 23 73 00 1.4.F | 1203 | – |
| Test / cert. | Test / cert.Completed System Readiness Checklist provided by the CxA and completed ...Indoor Central-Station Air-Handling Units23 73 00 1.4.G · PDF p. 1204Spec wording“G. Completed System Readiness Checklist provided by the CxA and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 1.4.G | 1204 | – |
| Test / cert. | Test / cert.Submit training plans and instructor qualifications in accordance with the ...Indoor Central-Station Air-Handling Units23 73 00 1.4.H · PDF p. 1204Spec wording“H. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 1.4.H | 1204 | – |
| Record docs | Record docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Indoor Central-Station Air-Handling Units23 73 00 1.6.A · PDF p. 1205Spec wording“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.” | 23 73 00 1.6.A | 1205 | – |
| Test / cert. | Test / cert.The air handling unit shall not be operated for any ...Indoor Central-Station Air-Handling Units23 73 00 3.2.A · PDF p. 1213Spec wording“A. The air handling unit shall not be operated for any purpose, temporary or permanent, until ductwork is clean, filters are in place, bearings are lubricated, and the fan has been test run under observation.” | 23 73 00 3.2.A | 1213 | – |
| Test / cert. | Test / cert.After the air handling unit is installed and tested, provide ...Indoor Central-Station Air-Handling Units23 73 00 3.2.B · PDF p. 1213Spec wording“B. After the air handling unit is installed and tested, provide startup and operating instructions to VA personnel.” | 23 73 00 3.2.B | 1213 | – |
| Test / cert. | Test / cert.An authorized factory representative should startup, test, and certify the ...Indoor Central-Station Air-Handling Units23 73 00 3.2.C · PDF p. 1213Spec wording“C. An authorized factory representative should startup, test, and certify the final installation and application specific calibration of control components. Items to be verified include fan performance over entire operating range, noise and vibration testing, verification of proper alignment, overall inspection of the installation, Owner/Operator training, etc.” | 23 73 00 3.2.C | 1213 | – |
| Test / cert. | Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Indoor Central-Station Air-Handling Units23 73 00 3.2.D · PDF p. 1213Spec wording“D. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.” | 23 73 00 3.2.D | 1213 | – |
| Test / cert. | Test / cert.When any defects are detected, correct defects and repeat test ...Indoor Central-Station Air-Handling Units23 73 00 3.2.E · PDF p. 1213Spec wording“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.” | 23 73 00 3.2.E | 1213 | – |
| Test / cert. | Test / cert.The CxA will observe startup and contractor testing of selected ...Indoor Central-Station Air-Handling Units23 73 00 3.2.F · PDF p. 1213Spec wording“F. The CxA will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and CxA. Provide a minimum notice of 10 working days prior to startup and testing.” | 23 73 00 3.2.F | 1213 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Indoor Central-Station Air-Handling Units23 73 00 3.3.A · PDF p. 1213Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 3.3.A | 1213 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Indoor Central-Station Air-Handling Units23 73 00 3.3.B · PDF p. 1213Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system.” | 23 73 00 3.3.B | 1213 | – |
| Training | TrainingProvide services of manufacturer's technical representative for 4 hours to ...Indoor Central-Station Air-Handling Units23 73 00 3.4.A · PDF p. 1213Spec wording“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.” | 23 73 00 3.4.A | 1213 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Indoor Central-Station Air-Handling Units23 73 00 3.4.B · PDF p. 1213Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.” | 23 73 00 3.4.B | 1213 | – |
Division 26 Electrical 24 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.All submittals shall include six copies of adequate descriptive literature, ...Requirements For Electrical Installations26 05 11 1.12.C · PDF p. 1221Spec wording“C. All submittals shall include six copies of adequate descriptive literature, catalog cuts, shop drawings, test reports, certifications, samples, and other data necessary for the Government to ascertain that the proposed materials and equipment comply with drawing and specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify specific materials and equipment being ...” | 26 05 11 1.12.C | 1221 | six copies |
| O&M | O&MThe submittals shall include the following:Requirements For Electrical Installations26 05 11 1.12.E · PDF p. 1221Spec wording“E. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, manuals, pictures, nameplate data, and test reports as required. 2. Submittals are required for all equipment anchors and supports. Submittals shall include weights, dimensions, center ...” | 26 05 11 1.12.E | 1221 | – |
| O&M | O&MMaintenance and Operation Manuals:Requirements For Electrical Installations26 05 11 1.12.F · PDF p. 1222Spec wording“F. Maintenance and Operation Manuals: 1. Submit as required for systems and equipment specified in the technical sections. Furnish in hardcover binders or an approved equivalent. 2. Inscribe the following identification on the cover: the words "MAINTENANCE AND OPERATION MANUAL," the name and location of the system, material, equipment, building, name of Contractor, and contract name and number. Include in the ...” | 26 05 11 1.12.F | 1222 | binders |
| Test / cert. | Test / cert.Approvals will be based on complete submission of shop drawings, ...Requirements For Electrical Installations26 05 11 1.12.G · PDF p. 1222Spec wording“G. Approvals will be based on complete submission of shop drawings, manuals, test reports, certifications, and samples as applicable.” | 26 05 11 1.12.G | 1222 | – |
| Warranty | WarrantyAll work performed and all equipment and material furnished under ...Requirements For Electrical Installations26 05 11 1.15.A · PDF p. 1223Spec wording“A. All work performed and all equipment and material furnished under this Division shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer for the Government.” | 26 05 11 1.15.A | 1223 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Low-Voltage Electrical Power Conductors And Cables26 05 19 1.4.A · PDF p. 1226Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings and insulation type for each conductor and cable. 2) Splicing materials and pulling lubricant. ...” | 26 05 19 1.4.A | 1226 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Grounding And Bonding For Electrical Systems26 05 26 1.4.A · PDF p. 1234-1235Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit plans showing the location of system grounding electrodes and connections, and the routing of aboveground and underground grounding electrode ...” | 26 05 26 1.4.A | 1234-1235 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Raceway And Boxes For Electrical Systems26 05 33 1.4.A · PDF p. 1243Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Size and location of main feeders. b. Size and location of panels and pull-boxes. c. Layout of required conduit penetrations through structural elements. d. Submit the following data for approval: 1) Raceway types and sizes. 2) Conduit bodies, ...” | 26 05 33 1.4.A | 1243 | – |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Overcurrent Protective Device Coordination Study26 05 73 1.4.A · PDF p. 1254-1255Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Product data on the software program to be used for the study. Software shall be in mainstream use in the industry, shall provide device settings and ratings, and shall show selective coordination by time-current drawings. 2. Complete study as described in paragraph ...” | 26 05 73 1.4.A | 1254-1255 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Electrical Systems26 08 00 1.6.A · PDF p. 1259Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 26 08 00 1.6.A | 1259 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Electrical Systems26 08 00 1.6.B · PDF p. 1259Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 26 08 00 1.6.B | 1259 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Electrical Systems26 08 00 3.4.A · PDF p. 1260Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Contractor shall review and comment on the tests prior to approval by the COR. The Contractor shall provide the required labor, materials, ...” | 26 08 00 3.4.A | 1260 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Electrical Systems26 08 00 3.5.A · PDF p. 1260-1261Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...” | 26 08 00 3.5.A | 1260-1261 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Lighting Controls26 09 23 1.4.A · PDF p. 1262-1263Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting controls. b. Material and construction details. c. Physical dimensions and description. d. Wiring schematic and connection diagram. e. Installation details. 2. Manuals: a. Submit, ...” | 26 09 23 1.4.A | 1262-1263 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Low-Voltage Transformers26 22 00 1.4.A · PDF p. 1268-1269Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, temperature rise, wiring and connection ...” | 26 22 00 1.4.A | 1268-1269 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Panelboards26 24 16 1.4.A · PDF p. 1274-1275Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, circuit breakers, wiring and connection ...” | 26 24 16 1.4.A | 1274-1275 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Wiring Devices26 27 26 1.4.A · PDF p. 1282-1283Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, construction materials, grade, and termination information. 2. Manuals: a. Submit, simultaneously ...” | 26 27 26 1.4.A | 1282-1283 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Motor Controllers26 29 11 1.4.A · PDF p. 1290-1291Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, weights, mounting details, materials, overcurrent protection devices, overload relays, sizes of enclosures, wiring ...” | 26 29 11 1.4.A | 1290-1291 | – |
| Spare parts | Spare partsTwo weeks prior to the final inspection, provide one complete ...Motor Controllers26 29 11 3.4.A · PDF p. 1300Spec wording“A. Two weeks prior to the final inspection, provide one complete set of spare fuses for each motor controller.” | 26 29 11 3.4.A | 1300 | one complete set |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Enclosed Switches And Circuit Breakers26 29 21 1.4.A · PDF p. 1302-1303Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, ...” | 26 29 21 1.4.A | 1302-1303 | – |
| Spare parts | Spare partsTwo weeks prior to the final inspection, furnish one complete ...Enclosed Switches And Circuit Breakers26 29 21 3.3.A · PDF p. 1305Spec wording“A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the COR. ---END---” | 26 29 21 3.3.A | 1305 | one complete set |
| Test / cert. | Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Facility Lightning Protection26 41 00 1.4.A · PDF p. 1306Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Show locations of air terminals, connections to required metal surfaces, down conductors, and grounding means. c. Show the mounting hardware and materials ...” | 26 41 00 1.4.A | 1306 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Surge Protective Devices26 43 13 1.4.A · PDF p. 1312Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings and device nameplate data. 2. Manuals: a. Submit, simultaneously with the shop drawings, companion copies of complete maintenance ...” | 26 43 13 1.4.A | 1312 | – |
| O&M | O&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Interior Lighting26 51 00 1.4.A · PDF p. 1316-1317Spec wording“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...” | 26 51 00 1.4.A | 1316-1317 | – |
Division 27 Communications 33 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MProvide parts list including quantity of spare partsRequirements For Communications Installations27 05 11 1.7.B · PDF p. 1351Spec wording“B. Provide parts list including quantity of spare parts.” | 27 05 11 1.7.B | 1351 | – |
| Test / cert. | Test / cert.Furnish electronic certified test reports to COR prior to final ...Requirements For Communications Installations27 05 11 1.7.K · PDF p. 1353Spec wording“K. Furnish electronic certified test reports to COR prior to final inspection and not more than 90 days after completion of tests.” | 27 05 11 1.7.K | 1353 | – |
| Warranty | WarrantyProvide following closeout submittals prior to project closeout date:Requirements For Communications Installations27 05 11 1.8.A · PDF p. 1353Spec wording“A. Provide following closeout submittals prior to project closeout date: 1. Warranty certificate. 2. Evidence of compliance with requirements such as low voltage certificate of inspection. 3. Project record documents. 4. Instruction manuals and software that are a part of system.” | 27 05 11 1.8.A | 1353 | – |
| Warranty | WarrantyMaintenance and Operation ManualsRequirements For Communications Installations27 05 11 1.8.B · PDF p. 1353Spec wording“B. Maintenance and Operation Manuals: Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS. 1. Prepare a manual for each system and equipment specified. 2. Furnish on portable storage drive in PDF format or equivalent accepted by COR. 3. Furnish complete manual as specified in specification section, fifteen days prior to performance of systems or equipment test. 4. Furnish remaining manuals prior to ...” | 27 05 11 1.8.B | 1353 | |
| Test / cert. | Test / cert.Record Wiring Diagrams:Requirements For Communications Installations27 05 11 1.8.C · PDF p. 1354-1355Spec wording“C. Record Wiring Diagrams: 1. Red Line Drawings: Keep one E size 91.44 cm x 121.92 cm (36 inches x 48 inches) set of floor plans, on site during work hours, showing installation progress marked and backbone cable labels noted. Make these drawings available for examination during construction meetings or field inspections. 2. General Drawing Specifications: Detail and elevation drawings to be D size 61 cm x 91.44 cm ...” | 27 05 11 1.8.C | 1354-1355 | CAD; four complete sets |
| Closeout step | Closeout stepService QualificationsRequirements For Communications Installations27 05 11 1.8.D · PDF p. 1355Spec wording“D. Service Qualifications: Submit name and contact information of service organizations providing service to this installation within eight hours of receipt of notification service is needed.” | 27 05 11 1.8.D | 1355 | – |
| Spare parts | Spare partsAfter approval and prior to installation, furnish COR with the ...Requirements For Communications Installations27 05 11 1.9.A · PDF p. 1355Spec wording“A. After approval and prior to installation, furnish COR with the following: 1. A 300 mm (12 inch) length of each type and size of wire and cable along with tag from coils of reels from which samples were taken. 2. One coupling, bushing and termination fitting for each type of conduit. 3. Samples of each hanger, clamp and supports for conduit and pathways. 4. Duct sealing compound.” | 27 05 11 1.9.A | 1355 | – |
| Warranty | WarrantyComply with FAR clause 52.246-21, except as follows:Requirements For Communications Installations27 05 11 1.13.A · PDF p. 1357Spec wording“A. Comply with FAR clause 52.246-21, except as follows: 1. Warranty material and equipment to be free from defects, workmanship, and remain so for a period of one year for Emergency Systems from date of final acceptance of system by Government; provide OEM's equipment warranty document to COR. 2. Government maintenance personnel must have ability to contact OEM for emergency maintenance and logistic assistance, ...” | 27 05 11 1.13.A | 1357 | – |
| Test / cert. | Test / cert.Proof of Performance Certification:Requirements For Communications Installations27 05 11 3.6.M · PDF p. 1368Spec wording“M. Proof of Performance Certification: 1. If system is declared acceptable, AHJ (SMCS 005OP2H3) provides COR notice stating system processes to required operating standards and functions and is Government accepted for use by facility. 2. Validate items with COR needing to be provided to complete project contract (i.e. charts & diagrams, manuals, spare parts, system warranty documents executed, etc.). Once items ...” | 27 05 11 3.6.M | 1368 | – |
| Training | TrainingProvide training in accordance with subsection, INSTRUCTIONS, of Section 01 ...Requirements For Communications Installations27 05 11 3.8.A · PDF p. 1369Spec wording“A. Provide training in accordance with subsection, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.” | 27 05 11 3.8.A | 1369 | – |
| Training | TrainingProvide training for equipment or system as required in each ...Requirements For Communications Installations27 05 11 3.8.B · PDF p. 1369Spec wording“B. Provide training for equipment or system as required in each associated specification.” | 27 05 11 3.8.B | 1369 | – |
| Training | TrainingDevelop and submit training schedule for approval by COR, at ...Requirements For Communications Installations27 05 11 3.8.C · PDF p. 1369Spec wording“C. Develop and submit training schedule for approval by COR, at least 30 days prior to planned training.” | 27 05 11 3.8.C | 1369 | – |
| Test / cert. | Test / cert.Closeout SubmittalsGrounding And Bonding For Communications Systems27 05 26 1.3.C · PDF p. 1370Spec wording“C. Closeout Submittals: In addition to Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS provide the following: 1. Certified test reports of ground resistance. 2. Certifications: Two weeks prior to final inspection, submit following to COR: a. Certification materials and installation is in accordance with construction documents. b. Certification complete installation has been installed and tested.” | 27 05 26 1.3.C | 1370 | – |
| Test / cert. | Test / cert.CertificationRaceways And Boxes For Communications Systems27 05 33 1.3.B · PDF p. 1376Spec wording“B. Certification: Provide letter prior to final inspection, certifying material is in accordance with construction documents and properly installed.” | 27 05 33 1.3.B | 1376 | – |
| Test / cert. | Test / cert.Refer to Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS for ...Commissioning Of Communications Systems27 08 00 1.4.A · PDF p. 1393Spec wording“A. Refer to Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for pre-functional checklists, equipment startup reports, and other commissioning documents.” | 27 08 00 1.4.A | 1393 | – |
| Test / cert. | Test / cert.Pre-Functional Checklists:Commissioning Of Communications Systems27 08 00 1.4.B · PDF p. 1393Spec wording“B. Pre-Functional Checklists: 1. Complete pre-functional checklists provided by commissioning agent to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. 2. Submit completed checklists to COR and to Commissioning Agent. Commissioning Agent can spot check a sample of completed checklists. If Commissioning Agent determines that ...” | 27 08 00 1.4.B | 1393 | – |
| Test / cert. | Test / cert.Submit training agendas and trainer resumes in accordance with requirements ...Commissioning Of Communications Systems27 08 00 1.4.C · PDF p. 1393Spec wording“C. Submit training agendas and trainer resumes in accordance with requirements of Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.” | 27 08 00 1.4.C | 1393 | – |
| Training | TrainingTraining of Government's operation and maintenance personnel is required in ...Commissioning Of Communications Systems27 08 00 3.2.A · PDF p. 1394Spec wording“A. Training of Government's operation and maintenance personnel is required in cooperation with COR and Commissioning Agent.” | 27 08 00 3.2.A | 1394 | – |
| Training | TrainingProvide competent, factory authorized personnel to provide instruction to operation ...Commissioning Of Communications Systems27 08 00 3.2.B · PDF p. 1394Spec wording“B. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning location, operation, and troubleshooting of installed systems.” | 27 08 00 3.2.B | 1394 | – |
| Training | TrainingSchedule instruction in coordination with COR after submission and approval ...Commissioning Of Communications Systems27 08 00 3.2.C · PDF p. 1394Spec wording“C. Schedule instruction in coordination with COR after submission and approval of formal training plans.” | 27 08 00 3.2.C | 1394 | – |
| Spare parts | Spare partsWhere multiple products are listed on a single cut-sheet, circle ...Nurse Call And Code Blue Systems27 52 23 1.8.C · PDF p. 1405Spec wording“C. Where multiple products are listed on a single cut-sheet, circle or highlight the one that you propose to use. Provide a complete and through equipment list of equipment expected to be installed in the system, with spares, as a part of the submittal. Special Communications (TVE-005OP3B) will not review any submittal that does not have this list.” | 27 52 23 1.8.C | 1405 | – |
| Record docs | Record docsThroughout progress of the Work, maintain an accurate record of ...Nurse Call And Code Blue Systems27 52 23 1.9.A · PDF p. 1408Spec wording“A. Throughout progress of the Work, maintain an accurate record of changes in Contract Documents. Upon completion of Work, transfer recorded changes to a set of Project Record Documents.” | 27 52 23 1.9.A | 1408 | – |
| Record docs | Record docsThe floorplans shall be marked in pen to include the following:Nurse Call And Code Blue Systems27 52 23 1.9.B · PDF p. 1408Spec wording“B. The floorplans shall be marked in pen to include the following: 1. Each device specific locations with UL labels affixed. 2. Conduit locations. 3. Each interface and equipment specific location. 4. Head-end equipment and specific location. 5. Wiring diagram. 6. Labeling and administration documentation. 7. Warranty certificate. 8. System test results.” | 27 52 23 1.9.B | 1408 | – |
| Warranty | WarrantyThe Contractor shall warrant the installation to be free from ...Nurse Call And Code Blue Systems27 52 23 1.10.A · PDF p. 1409Spec wording“A. The Contractor shall warrant the installation to be free from defect in material and workmanship for a period of two (2) years from the date of acceptance of the project by the owner. The Contractor shall agree to remedy covered defects within four (4) hours of notification of major failures or within twenty-four (24) hours of notification for individual station related problems.” | 27 52 23 1.10.A | 1409 | – |
| Warranty | WarrantyThe Contractor shall agree to grantee the system according to ...Nurse Call And Code Blue Systems27 52 23 1.10.B · PDF p. 1409Spec wording“B. The Contractor shall agree to grantee the system according to the guidelines outlined in Article 4 herein.” | 27 52 23 1.10.B | 1409 | – |
| Test / cert. | Test / cert.Prior to final inspection and acceptance of the work, remove ...Nurse Call And Code Blue Systems27 52 23 1.13.A · PDF p. 1409Spec wording“A. Prior to final inspection and acceptance of the work, remove all debris, rubbish, waste material, tools, construction equipment, machinery and surplus materials from the project site and thoroughly clean your work area.” | 27 52 23 1.13.A | 1409 | – |
| Warranty | WarrantyBefore the project closeout date, the Contractor shall submit:Nurse Call And Code Blue Systems27 52 23 1.13.B · PDF p. 1409Spec wording“B. Before the project closeout date, the Contractor shall submit: 1. OEM Equipment Warranty Certificates. 2. Evidence of compliance with requirements of governing authorities such as the Low Voltage Certificate of Inspection. 3. Project record documents. 4. Instruction manuals and software that is a part of the system. 5. System Guaranty Certificate.” | 27 52 23 1.13.B | 1409 | – |
| Test / cert. | Test / cert.Contractor shall submit written notice that:Nurse Call And Code Blue Systems27 52 23 1.13.C · PDF p. 1410Spec wording“C. Contractor shall submit written notice that: 1. Contract Documents have been reviewed. 2. Project has been inspected for compliance with contract. 3. Work has been completed in accordance with the contract.” | 27 52 23 1.13.C | 1410 | – |
| Warranty | WarrantyComply with FAR 52.246-21, except that warranty shall be as follows:Nurse Call And Code Blue Systems27 52 23 4.2.A · PDF p. 1449Spec wording“A. Comply with FAR 52.246-21, except that warranty shall be as follows:” | 27 52 23 4.2.A | 1449 | – |
| Warranty | WarrantyContractor's Responsibility:Nurse Call And Code Blue Systems27 52 23 4.2.B · PDF p. 1449Spec wording“B. Contractor's Responsibility: 1. The Contractor shall warranty that all provided material and equipment will be free from defects, workmanship and will remain so for a period of one year from date of final acceptance of the System by the VA. The Contractor shall provide OEM's equipment warranty documents, to the RE (or Facility Contracting Officer if the Facility has taken procession of the building), that ...” | 27 52 23 4.2.B | 1449 | two (2) copies |
| Warranty | WarrantyWork Not IncludedNurse Call And Code Blue Systems27 52 23 4.2.C · PDF p. 1452Spec wording“C. Work Not Included: Maintenance and repair service shall not include the performance of any work due to improper use; accidents; other vendor, contractor, or owner tampering or negligence, for which the Contractor is not directly responsible and does not control. The Contractor shall immediately notify the RE or Facility Contracting Officer in writing upon the discovery of these incidents. The RE or Facility ...” | 27 52 23 4.2.C | 1452 | – |
| Training | TrainingProvide thorough training of all nursing staff assigned to those ...Nurse Call And Code Blue Systems27 52 23 4.3.A · PDF p. 1452Spec wording“A. Provide thorough training of all nursing staff assigned to those nursing units receiving new networked nurse/patient communications equipment. This training shall be developed and implemented to address two different types of staff. Floor nurses/staff shall receive training from their perspective, and likewise, unit secretaries (or any person whose specific responsibilities include answering patient calls and ...” | 27 52 23 4.3.A | 1452 | – |
| Training | TrainingProvide the following minimum training times and durations:Nurse Call And Code Blue Systems27 52 23 4.3.B · PDF p. 1452Spec wording“B. Provide the following minimum training times and durations: 1. 48 hours prior to opening for nursing staff (in 8-hour increments) – split evenly over 3 weeks and day and night shifts. Coordinate schedule with Owner. 2. 32 hours during the opening week for nursing staff – both day and night shifts. 3. 24 hours for supervisors and system administrators.” | 27 52 23 4.3.B | 1452 | – |
Division 28 Fire alarm and security 49 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe submittals shall include the following:Common Work Results For Electronic Safety And Security28 05 00 1.6.D · PDF p. 1473-1474Spec wording“D. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required. 2. Submittals are required for all equipment anchors and supports. Submittals shall include weights, dimensions, center of ...” | 28 05 00 1.6.D | 1473-1474 | – |
| Warranty | WarrantySubmittals shall be in full compliance of the Contract Documents. ...Common Work Results For Electronic Safety And Security28 05 00 1.6.E · PDF p. 1474-1479Spec wording“E. Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. All submittals ...” | 28 05 00 1.6.E | 1474-1479 | AutoCAD; CAD; Binders; binder; four copies |
| Record docs | Record docsGroup 1 Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.F · PDF p. 1479-1486Spec wording“F. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA CAD Standards Guide. All text associated with security details shall be 1/8" ...” | 28 05 00 1.6.F | 1479-1486 | CAD; AutoCAD |
| O&M | O&MGroup IV Technical Data Package:Common Work Results For Electronic Safety And Security28 05 00 1.6.I · PDF p. 1487-1490Spec wording“I. Group IV Technical Data Package: 1. Performance Verification Test: a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout, and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to ...” | 28 05 00 1.6.I | 1487-1490 | DVD; four copies; CAD; hard copy |
| O&M | O&MGroup V Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.J · PDF p. 1490-1494Spec wording“J. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or ...” | 28 05 00 1.6.J | 1490-1494 | PDF; two (2) complete sets; binder; one (1) copy; AutoCAD; CD |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Common Work Results For Electronic Safety And Security28 05 00 1.6.N · PDF p. 1496Spec wording“N. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 05 00 1.6.N | 1496 | – |
| Warranty | WarrantyThe Contractor shall, as a condition precedent to the final ...Common Work Results For Electronic Safety And Security28 05 00 1.20.A · PDF p. 1515-1516Spec wording“A. The Contractor shall, as a condition precedent to the final payment, execute a written guarantee (warranty) to the COR certifying all contract requirements have been completed according to the final specifications. Contract drawings and the warranty of all materials and equipment furnished under this contract are to remain in satisfactory operating condition (ordinary wear and tear, abuse and causes beyond his ...” | 28 05 00 1.20.A | 1515-1516 | – |
| Training | TrainingTraining shall be provided in accordance with Article, INSTRUCTIONS, of ...Common Work Results For Electronic Safety And Security28 05 00 3.4.A · PDF p. 1534Spec wording“A. Training shall be provided in accordance with Article, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.” | 28 05 00 3.4.A | 1534 | – |
| Training | TrainingTraining shall be provided for the particular equipment or system ...Common Work Results For Electronic Safety And Security28 05 00 3.4.B · PDF p. 1534Spec wording“B. Training shall be provided for the particular equipment or system as required in each associated specification.” | 28 05 00 3.4.B | 1534 | – |
| Training | TrainingA training schedule shall be developed and submitted by the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.C · PDF p. 1534Spec wording“C. A training schedule shall be developed and submitted by the contractor and approved by the COR at least 30 days prior to the planned training.” | 28 05 00 3.4.C | 1534 | – |
| Training | TrainingProvide services of manufacturer's technical representative for <insert hours> hours ...Common Work Results For Electronic Safety And Security28 05 00 3.4.D · PDF p. 1534Spec wording“D. Provide services of manufacturer's technical representative for <insert hours> hours to instruct VA personnel in operation and maintenance of units.” | 28 05 00 3.4.D | 1534 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Common Work Results For Electronic Safety And Security28 05 00 3.4.E · PDF p. 1534Spec wording“E. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 05 00 3.4.E | 1534 | – |
| Test / cert. | Test / cert.The inspection and test will be conducted by a factory-certified ...Common Work Results For Electronic Safety And Security28 05 00 3.7.C · PDF p. 1542Spec wording“C. The inspection and test will be conducted by a factory-certified contractor representative and witnessed by a Government Representative. The results of the inspection will be officially recorded by a designated Government Representative and maintained on file by the COR, until completion of the entire project. The results will be compared to the Acceptance Test results.” | 28 05 00 3.7.C | 1542 | – |
| O&M | O&MIn accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT ...Conductors And Cables For Electronic Safety And Security28 05 13 1.5.A · PDF p. 1549-1550Spec wording“A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following: 1. Manufacturer's Literature and Data: Showing each cable type and rating. 2. Certificates: Two weeks prior to final inspection, deliver to the COR four copies of the certification that the material is in accordance with the drawings and specifications and diagrams for cable management system. 3. Shop Drawings: ...” | 28 05 13 1.5.A | 1549-1550 | four copies; electronic copy |
| Test / cert. | Test / cert.Document data for each measurement. Print data for submittals in ...Conductors And Cables For Electronic Safety And Security28 05 13 3.8.D · PDF p. 1565Spec wording“D. Document data for each measurement. Print data for submittals in a summary report that is formatted using Table 10.1 in BICSI TDMM as a guide, or transfer the data from the instrument to the computer, save as text files, print, and submit.” | 28 05 13 3.8.D | 1565 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsConductors And Cables For Electronic Safety And Security28 05 13 3.8.F · PDF p. 1565Spec wording“F. Prepare test and inspection reports.” | 28 05 13 3.8.F | 1565 | – |
| Test / cert. | Test / cert.Test ReportsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.C · PDF p. 1566Spec wording“C. Test Reports: Provide certified test reports of ground resistance.” | 28 05 26 1.3.C | 1566 | – |
| Test / cert. | Test / cert.CertificationsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.D · PDF p. 1566-1567Spec wording“D. Certifications: Two weeks prior to final inspection, submit four copies of the following to the COR: 1. Certification that the materials and installation are in accordance with the drawings and specifications. 2. Certification by the contractor that the complete installation has been properly installed and tested.” | 28 05 26 1.3.D | 1566-1567 | four copies |
| Test / cert. | Test / cert.Prepare test and inspection reportsGrounding And Bonding For Electronic Safety And Security28 05 26 3.9.D · PDF p. 1572Spec wording“D. Prepare test and inspection reports.” | 28 05 26 3.9.D | 1572 | – |
| Test / cert. | Test / cert.Report measured ground resistances that exceed the following values:Grounding And Bonding For Electronic Safety And Security28 05 26 3.9.E · PDF p. 1572Spec wording“E. Report measured ground resistances that exceed the following values: 1. Power Distribution Units or Panel boards Serving Electronic Equipment: 3 ohm(s). 2. Manhole Grounds: 10 ohms.” | 28 05 26 3.9.E | 1572 | – |
| Test / cert. | Test / cert.The commissioning process requires review of selected Submittals that pertain ...Commissioning Of Electronic Safety And Security Systems28 08 00 1.6.A · PDF p. 1575Spec wording“A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.” | 28 08 00 1.6.A | 1575 | – |
| Test / cert. | Test / cert.The commissioning process requires Submittal review simultaneously with engineering review. ...Commissioning Of Electronic Safety And Security Systems28 08 00 1.6.B · PDF p. 1575Spec wording“B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.” | 28 08 00 1.6.B | 1575 | – |
| Test / cert. | Test / cert.The Commissioning Process includes Systems Functional Performance Testing that is ...Commissioning Of Electronic Safety And Security Systems28 08 00 3.4.A · PDF p. 1576Spec wording“A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the COR. The Contractor ...” | 28 08 00 3.4.A | 1576 | – |
| Training | TrainingTraining of the VA operation and maintenance personnel is required ...Commissioning Of Electronic Safety And Security Systems28 08 00 3.5.A · PDF p. 1576-1577Spec wording“A. Training of the VA operation and maintenance personnel is required in cooperation with the COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of ...” | 28 08 00 3.5.A | 1576-1577 | – |
| Record docs | Record docsProvide a complete and thorough pre-installation and as-built design package ...Physical Access Control System28 13 00 1.4.C · PDF p. 1585Spec wording“C. Provide a complete and thorough pre-installation and as-built design package in both electronic format and on paper, minimum size 48 x 48 inches (1220 x 1220 millimeters); drawing submittals shall be per the established project schedule.” | 28 13 00 1.4.C | 1585 | electronic format |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.H · PDF p. 1587Spec wording“H. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 13 00 1.4.H | 1587 | – |
| Warranty | WarrantyGeneralPhysical Access Control System28 13 00 1.4.I · PDF p. 1587-1592Spec wording“I. General: Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. Additional ...” | 28 13 00 1.4.I | 1587-1592 | AutoCAD; CAD; Binders; binder |
| Record docs | Record docsGroup 1 Technical Data PackagePhysical Access Control System28 13 00 1.4.J · PDF p. 1592-1599Spec wording“J. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA Special Conditions and CAD Standards Documents. All text associated with ...” | 28 13 00 1.4.J | 1592-1599 | CAD; AutoCAD |
| O&M | O&MGroup IV Technical Data Package:Physical Access Control System28 13 00 1.4.M · PDF p. 1600-1602Spec wording“M. Group IV Technical Data Package: 1. Performance Verification Test: a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout, and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to ...” | 28 13 00 1.4.M | 1600-1602 | DVD; four copies; CAD; hard copy |
| O&M | O&MGroup V Technical Data PackagePhysical Access Control System28 13 00 1.4.N · PDF p. 1602-1607Spec wording“N. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or ...” | 28 13 00 1.4.N | 1602-1607 | CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.Q · PDF p. 1608Spec wording“Q. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 13 00 1.4.Q | 1608 | – |
| Warranty | WarrantyWarrant PACS work subject to the Article "Warranty of Construction" ...Physical Access Control System28 13 00 1.11.A · PDF p. 1623Spec wording“A. Warrant PACS work subject to the Article "Warranty of Construction" of FAR clause 52.246-21.” | 28 13 00 1.11.A | 1623 | – |
| Warranty | WarrantyDemonstration and training shall be performed prior to system acceptance ...Physical Access Control System28 13 00 1.11.B · PDF p. 1623Spec wording“B. Demonstration and training shall be performed prior to system acceptance.” | 28 13 00 1.11.B | 1623 | – |
| Test / cert. | Test / cert.Manufacturer's Field ServicePhysical Access Control System28 13 00 3.10.A · PDF p. 1680Spec wording“A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing.” | 28 13 00 3.10.A | 1680 | – |
| Test / cert. | Test / cert.Testing AgencyPhysical Access Control System28 13 00 3.10.B · PDF p. 1680Spec wording“B. Testing Agency: Engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports:” | 28 13 00 3.10.B | 1680 | – |
| Test / cert. | Test / cert.Perform the following field tests and inspections and prepare test ...Physical Access Control System28 13 00 3.10.C · PDF p. 1680-1681Spec wording“C. Perform the following field tests and inspections and prepare test reports: 1. LAN Cable Procedures: Inspect for physical damage and test each conductor signal path for continuity and shorts. Use Class 2, bidirectional, Category 6A tester. Test for faulty connectors, splices, and terminations. Test according to TIA/EIA-568-1, "Commercial Building Telecommunications Cabling Standards - Part 1 General ...” | 28 13 00 3.10.C | 1680-1681 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Physical Access Control System28 13 00 3.12.A · PDF p. 1681Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.” | 28 13 00 3.12.A | 1681 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Physical Access Control System28 13 00 3.12.B · PDF p. 1681Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS and related sections for contractor responsibilities for system commissioning.” | 28 13 00 3.12.B | 1681 | – |
| Training | TrainingProvide services of manufacturer's technical representative for four hours to ...Physical Access Control System28 13 00 3.13.A · PDF p. 1681Spec wording“A. Provide services of manufacturer's technical representative for four hours to instruct VA personnel in operation and maintenance of units.” | 28 13 00 3.13.A | 1681 | – |
| Training | TrainingSubmit training plans and instructor qualifications in accordance with the ...Physical Access Control System28 13 00 3.13.B · PDF p. 1681Spec wording“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 13 00 3.13.B | 1681 | – |
| Training | TrainingDevelop separate training modules for the following:Physical Access Control System28 13 00 3.13.C · PDF p. 1681-1682Spec wording“C. Develop separate training modules for the following: 1. Computer system administration personnel to manage and repair the LAN and databases and to update and maintain software. 2. Operators who prepare and input credentials to man the control station and workstations and to enroll personnel. 3. Security personnel. 4. Hardware maintenance personnel. 5. Corporate management.” | 28 13 00 3.13.C | 1681-1682 | – |
| Training | TrainingAll testing and training shall be compliant with the VA ...Physical Access Control System28 13 00 3.13.D · PDF p. 1682Spec wording“D. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS. -----END----” | 28 13 00 3.13.D | 1682 | – |
| Record docs | Record docsDrawings:Fire28 31 00 1.4.B · PDF p. 1687-1688Spec wording“B. Drawings: 1. Prepare drawings using AutoCAD Release 14 software and include all contractor's information. Layering shall be by VA criteria as provided by the Contracting Officer's Representative (COR). Bid drawing files on AutoCAD will be provided to the Contractor at the pre-construction meeting. The contractor shall be responsible for verifying all critical dimensions shown on the drawings provided by VA. 2. ...” | 28 31 00 1.4.B | 1687-1688 | AutoCAD; 3 sets; one set |
| O&M | O&MManuals:Fire28 31 00 1.4.C · PDF p. 1688-1689Spec wording“C. Manuals: 1. Submit simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets for all items used in the system, power requirements, device wiring diagrams, dimensions, and information for ordering replacement parts. a. Wiring diagrams shall have their terminals identified to facilitate installation, operation, expansion and maintenance. ...” | 28 31 00 1.4.C | 1688-1689 | binder; 4 copies |
| Warranty | WarrantyAll work performed and all material and equipment furnished under ...Fire28 31 00 1.5.A · PDF p. 1690Spec wording“A. All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer.” | 28 31 00 1.5.A | 1690 | – |
| Test / cert. | Test / cert.CertificationConduits And Backboxes For Electronic Safety And Security28 05 28.33 1.5.C · PDF p. 1709Spec wording“C. Certification: Prior to final inspection, deliver to the COR four copies of the certification that the material is in accordance with the drawings and specifications and has been properly installed.” | 28 05 28.33 1.5.C | 1709 | four copies |
| Test / cert. | Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Conduits And Backboxes For Electronic Safety And Security28 05 28.33 1.5.D · PDF p. 1709Spec wording“D. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.” | 28 05 28.33 1.5.D | 1709 | – |
| Test / cert. | Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Conduits And Backboxes For Electronic Safety And Security28 05 28.33 3.9.A · PDF p. 1722Spec wording“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – "COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS" for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.” | 28 05 28.33 3.9.A | 1722 | – |
| Test / cert. | Test / cert.Components provided under this section of the specification will be ...Conduits And Backboxes For Electronic Safety And Security28 05 28.33 3.9.B · PDF p. 1722Spec wording“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 28 08 00, "COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS" and related sections for contractor responsibilities for system commissioning.” | 28 05 28.33 3.9.B | 1722 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.