Closeout checklist: Fire Station Expansion, Missouri State Fairgrounds (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 121 items across 16 trade divisions and the contract conditions, including 58 warranties, 20 tests and certificates and 17 O&M manual items. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project F2405-01
- Location
- Sedalia, MO
- Bid date
- 2025-10-21
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 455 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 121 items, by trade
Division 02 Existing conditions 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsProject Record DocumentsDemolition02 41 00 1.03.D · PDF p. 97Spec wording“D. Project Record Documents: Accurately record actual locations of capped and active utilities and subsurface construction. 02 4100 /1” | 02 41 00 1.03.D | 97 | – |
Division 04 Masonry 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Mix DesignsUnit Masonry04 20 00 1.04.J · PDF p. 106Spec wording“J. Mix Designs: For each type of mortar and grout, include description of type and proportions of ingredients. 1. Include test reports per ASTM C780 for mortar mixes required to comply with property specification. 2. Include test reports per ASTM C1019 for grout mixes required to comply with compressive strength requirement. 3. Statement of Compressive Strength of Masonry: For each combination of masonry unit type ...” | 04 20 00 1.04.J | 106 | – |
| Spare parts | Spare partsMaintenance MaterialsUnit Masonry04 20 00 1.04.K · PDF p. 106Spec wording“K. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. See Division One for additional provisions. 2. Extra Clay Facing Brick Units: 50 of each type, size, texture, and color combination.” | 04 20 00 1.04.K | 106 | – |
Division 07 Roofing, insulation and waterproofing 26 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyWarranty DocumentationAsphalt Shingles07 31 13 1.03.G · PDF p. 149Spec wording“G. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.” | 07 31 13 1.03.G | 149 | – |
| Spare parts | Spare partsMaintenance MaterialsAsphalt Shingles07 31 13 1.03.H · PDF p. 149-150Spec wording“H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 07 3113 /1 1. Extra Shingles: 25 sq ft of each type and color.” | 07 31 13 1.03.H | 149-150 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsAsphalt Shingles07 31 13 1.06.A · PDF p. 150Spec wording“A. See Division 1 for additional warranty requirements.” | 07 31 13 1.06.A | 150 | – |
| Warranty | WarrantyCorrect defective Work within a five year period after Date ...Asphalt Shingles07 31 13 1.06.B · PDF p. 150Spec wording“B. Correct defective Work within a five year period after Date of Substantial Completion.” | 07 31 13 1.06.B | 150 | – |
| Warranty | WarrantyProvide lifetime manufacturer's warranty for coverage against black streaks caused ...Asphalt Shingles07 31 13 1.06.C · PDF p. 150Spec wording“C. Provide lifetime manufacturer's warranty for coverage against black streaks caused by algae.” | 07 31 13 1.06.C | 150 | – |
| Warranty | WarrantyProvide five year manufacturer's warranty for wind damageAsphalt Shingles07 31 13 1.06.D · PDF p. 150Spec wording“D. Provide five year manufacturer's warranty for wind damage.” | 07 31 13 1.06.D | 150 | – |
| Warranty | WarrantyWarrantyMetal Soffit Panels07 41 12 1.02.E · PDF p. 154Spec wording“E. Warranty: Submit specified manufacturer's warranty and ensure that forms have been completed in Owner's name and are registered with manufacturer.” | 07 41 12 1.02.E | 154 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsMetal Soffit Panels07 41 12 1.04.A · PDF p. 154Spec wording“A. See Division 1 for additional warranty requirements.” | 07 41 12 1.04.A | 154 | – |
| Warranty | WarrantyFinish WarrantyMetal Soffit Panels07 41 12 1.04.B · PDF p. 154Spec wording“B. Finish Warranty: Provide manufacturer's special warranty covering failure of factory-applied exterior finish on metal roof panels and agreeing to repair or replace panels that show evidence of finish degradation, including significant fading, chalking, cracking, or peeling within specified warranty period of five years from Date of Substantial Completion.” | 07 41 12 1.04.B | 154 | – |
| Warranty | WarrantyWarrantyMetal Roof Panels07 41 14 1.02.E · PDF p. 157Spec wording“E. Warranty: Submit specified manufacturer's warranty and ensure that forms have been completed in Owner's name and are registered with manufacturer.” | 07 41 14 1.02.E | 157 | – |
| Warranty | WarrantyFinish WarrantyMetal Roof Panels07 41 14 1.05.A · PDF p. 157Spec wording“A. Finish Warranty: Provide manufacturer's special warranty covering failure of factory-applied exterior finish on metal roof panels and agreeing to repair or replace panels that show evidence of finish degradation, including significant fading, chalking, cracking, or peeling within specified warranty period of twenty years from Date of Substantial Completion.” | 07 41 14 1.05.A | 157 | – |
| Warranty | WarrantyWarranty Documentation for Installation of Building Rainscreen AssemblyMetal Wall Panels07 42 13 1.03.D · PDF p. 161Spec wording“D. Warranty Documentation for Installation of Building Rainscreen Assembly: Submit installer warranty and ensure that forms have been completed in Owner's name and registered with installer.” | 07 42 13 1.03.D | 161 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirements. F2405-01 MSF- Fire ...Metal Wall Panels07 42 13 1.06.A · PDF p. 161Spec wording“A. See Division 1 for additional warranty requirements. F2405-01 MSF- Fire Station Expansion 07 4213/1” | 07 42 13 1.06.A | 161 | – |
| Warranty | WarrantyCorrect defective work within a five year period after Date ...Metal Wall Panels07 42 13 1.06.B · PDF p. 162Spec wording“B. Correct defective work within a five year period after Date of Substantial Completion for degradation of panel finish, including color fading caused by exposure to weather.” | 07 42 13 1.06.B | 162 | – |
| Warranty | WarrantyWarrantyFiber-Cement Siding (Alternate #2)07 46 46 1.04.D · PDF p. 164Spec wording“D. Warranty: Submit copy of manufacturer's warranty, made out in Owner's name, showing that it has been registered with manufacturer.” | 07 46 46 1.04.D | 164 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsFiber-Cement Siding (Alternate #2)07 46 46 1.07.A · PDF p. 164Spec wording“A. See Division 1 for additional warranty requirements.” | 07 46 46 1.07.A | 164 | – |
| Warranty | WarrantyCorrect defective work within a five year period after Date ...Fiber-Cement Siding (Alternate #2)07 46 46 1.07.B · PDF p. 164Spec wording“B. Correct defective work within a five year period after Date of Substantial Completion. 07 4646 /1” | 07 46 46 1.07.B | 164 | – |
| Warranty | WarrantyWarrantyElastomeric Membrane Roofing07 53 00 1.04.G · PDF p. 168Spec wording“G. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer. Provide upon completion.” | 07 53 00 1.04.G | 168 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsElastomeric Membrane Roofing07 53 00 1.08.A · PDF p. 168Spec wording“A. See Division 1 for additional warranty requirements.” | 07 53 00 1.08.A | 168 | – |
| Warranty | WarrantyProvide written certification, submitted with shop drawings, thatElastomeric Membrane Roofing07 53 00 1.08.B · PDF p. 168Spec wording“B. Provide written certification, submitted with shop drawings, that: "All roofing components exclusive of the deck, contained in the system proposed are approved, and compatible with the warranty requirements of the roof system as specified, and that the warranty specified will be issued at completion of project if system is installed as designed." 07 5300 /2” | 07 53 00 1.08.B | 168 | – |
| Warranty | WarrantyProvide 20-year, non-prorated, no dollar limit (NDL) manufacturer's material and ...Elastomeric Membrane Roofing07 53 00 1.08.C · PDF p. 169Spec wording“C. Provide 20-year, non-prorated, no dollar limit (NDL) manufacturer's material and labor warranty to cover failure to prevent penetration of water. Include all insulation, flashings and penetrations in the warranty.” | 07 53 00 1.08.C | 169 | – |
| Warranty | WarrantyWarranty shall be executed by both the system manufacturer and ...Elastomeric Membrane Roofing07 53 00 1.08.D · PDF p. 169Spec wording“D. Warranty shall be executed by both the system manufacturer and the roofing contractor.” | 07 53 00 1.08.D | 169 | – |
| Warranty | WarrantyRoofing Contractor WarrantyElastomeric Membrane Roofing07 53 00 1.08.E · PDF p. 169Spec wording“E. Roofing Contractor Warranty: Provide 5 year, non-prorated, no dollar limit (NDL) contractors warranty, covering complete installation and any area of work not covered by the roof system warranty.” | 07 53 00 1.08.E | 169 | – |
| Warranty | WarrantySee Division One for University of Missouri Roof System Manufacturers ...Sheet Metal Flashing And Trim07 62 00 1.05.A · PDF p. 176Spec wording“A. See Division One for University of Missouri Roof System Manufacturers Certification and University of Missouri Contractors Roofing/Flashing/Sheet Metal Guarantee.” | 07 62 00 1.05.A | 176 | – |
| Warranty | WarrantyCorrect defective work within a two year period after Date ...(Untitled)07 90 05 1.07.A · PDF p. 184Spec wording“A. Correct defective work within a two year period after Date of Substantial Completion. 07 9005 /1” | 07 90 05 1.07.A | 184 | – |
| Warranty | WarrantyWarranty(Untitled)07 90 05 1.07.B · PDF p. 185Spec wording“B. Warranty: Include coverage for installed sealants and accessories which fail to achieve airtight seal and watertight seal, exhibit loss of adhesion or cohesion, or do not cure.” | 07 90 05 1.07.B | 185 | – |
Division 08 Doors, windows and hardware 17 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantySpecimen warrantyFlush Wood Doors08 14 16 1.02.D · PDF p. 195Spec wording“D. Specimen warranty.” | 08 14 16 1.02.D | 195 | – |
| Warranty | WarrantyWarranty, executed in Owner's name at completion of workFlush Wood Doors08 14 16 1.02.G · PDF p. 195Spec wording“G. Warranty, executed in Owner's name at completion of work.” | 08 14 16 1.02.G | 195 | – |
| Warranty | WarrantyInterior DoorsFlush Wood Doors08 14 16 1.05.A · PDF p. 195Spec wording“A. Interior Doors: Provide manufacturer's warranty for the life of the installation. 08 1416 /1” | 08 14 16 1.05.A | 195 | – |
| Warranty | WarrantyInclude coverage for delamination of veneer, warping beyond specified installation ...Flush Wood Doors08 14 16 1.05.B · PDF p. 196Spec wording“B. Include coverage for delamination of veneer, warping beyond specified installation tolerances, defective materials, and telegraphing core construction.” | 08 14 16 1.05.B | 196 | – |
| Record docs | Record docsProject Record DocumentsAccess Doors And Panels08 31 00 1.02.E · PDF p. 198Spec wording“E. Project Record Documents: Record actual locations of all access units.” | 08 31 00 1.02.E | 198 | – |
| O&M | O&MMaintenance DataExterior Overhead Coiling Doors08 33 23 1.03.F · PDF p. 201Spec wording“F. Maintenance Data: Indicate lubrication requirements and frequency and periodic adjustments required.” | 08 33 23 1.03.F | 201 | – |
| Test / cert. | Test / cert.Field Quality Control SubmittalsWood Windows08 52 00 1.03.E · PDF p. 205Spec wording“E. Field Quality Control Submittals: Report of field testing for water penetration and air leakage.” | 08 52 00 1.03.E | 205 | – |
| Warranty | WarrantyWarranty DocumentationWood Windows08 52 00 1.03.H · PDF p. 205Spec wording“H. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer. 08 5200 /1” | 08 52 00 1.03.H | 205 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsWood Windows08 52 00 1.07.A · PDF p. 206Spec wording“A. See Division 1 for additional warranty requirements.” | 08 52 00 1.07.A | 206 | – |
| Warranty | WarrantyCorrect defective Work within a five year period after Date ...Wood Windows08 52 00 1.07.B · PDF p. 206Spec wording“B. Correct defective Work within a five year period after Date of Substantial Completion.” | 08 52 00 1.07.B | 206 | – |
| Warranty | WarrantyProvide five year manufacturer warranty for insulated glass units from ...Wood Windows08 52 00 1.07.C · PDF p. 206Spec wording“C. Provide five year manufacturer warranty for insulated glass units from seal failure, interpane dusting or misting, and replacement of same.” | 08 52 00 1.07.C | 206 | – |
| Warranty | WarrantyWarrantyWood Windows08 52 00 1.07.D · PDF p. 206Spec wording“D. Warranty: Include coverage for the following: 1. Degradation of color finish. 2. Delamination or separation of finish cladding from window member.” | 08 52 00 1.07.D | 206 | – |
| O&M | O&MMaintenance DataDoor Hardware08 71 00 1.03.E · PDF p. 210Spec wording“E. Maintenance Data: Include data on operating hardware, lubrication requirements, and inspection procedures related to preventative maintenance.” | 08 71 00 1.03.E | 210 | – |
| Spare parts | Spare partsMaintenance Materials and ToolsDoor Hardware08 71 00 1.03.G · PDF p. 210Spec wording“G. Maintenance Materials and Tools: Furnish the following for Owner's use in maintenance of project. 1. Tools: One set of each special wrench or tool applicable for each different or special hardware component, whether supplied by hardware component manufacturer or not.” | 08 71 00 1.03.G | 210 | One set |
| Warranty | WarrantyWarranty DocumentationGlazing08 80 00 1.05.E · PDF p. 216Spec wording“E. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.” | 08 80 00 1.05.E | 216 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsGlazing08 80 00 1.08.A · PDF p. 216Spec wording“A. See Division 1 for additional warranty requirements.” | 08 80 00 1.08.A | 216 | – |
| Warranty | WarrantyInsulating Glass UnitsGlazing08 80 00 1.08.B · PDF p. 216Spec wording“B. Insulating Glass Units: Provide a five (5) year manufacturer warranty to include coverage for seal failure, interpane dusting or misting, including providing products to replace failed units.” | 08 80 00 1.08.B | 216 | – |
Division 09 Finishes 7 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Concrete Subfloor Test ReportResilient Flooring09 65 00 1.03.E · PDF p. 228Spec wording“E. Concrete Subfloor Test Report: Submit a copy of the moisture and alkalinity (pH) test reports.” | 09 65 00 1.03.E | 228 | – |
| O&M | O&MMaintenance DataResilient Flooring09 65 00 1.03.H · PDF p. 228Spec wording“H. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning, stripping, and re-waxing.” | 09 65 00 1.03.H | 228 | – |
| Spare parts | Spare partsMaintenance MaterialsResilient Flooring09 65 00 1.03.I · PDF p. 228Spec wording“I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. See Division 1 for additional provisions. 2. Extra Flooring Material: 100 square feet of each type and color. 3. Extra Wall Base: 100 linear feet of each type and color. 09 6500 /1” | 09 65 00 1.03.I | 228 | – |
| O&M | O&MMaintenance DataTile Carpeting09 68 13 1.02.F · PDF p. 233Spec wording“F. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning.” | 09 68 13 1.02.F | 233 | – |
| Spare parts | Spare partsMaintenance MaterialsTile Carpeting09 68 13 1.02.G · PDF p. 233Spec wording“G. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Carpet Tiles: Quantity equal to 5 percent of total installed of each color and pattern installed.” | 09 68 13 1.02.G | 233 | – |
| O&M | O&MMaintenance DataSection 09 900009 90 00 1.03.I · PDF p. 237Spec wording“I. Maintenance Data: Submit data on cleaning, touch-up, and repair of painted and coated surfaces.” | 09 90 00 1.03.I | 237 | – |
| Spare parts | Spare partsMaintenance MaterialsSection 09 900009 90 00 1.03.J · PDF p. 237Spec wording“J. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Paint and Coatings: 1 gallon of each color; store where directed. 2. Label each container with color in addition to the manufacturer's label.” | 09 90 00 1.03.J | 237 | – |
Division 10 Specialties 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsMaintenance MaterialsSignage10 14 00 1.02.H · PDF p. 243Spec wording“H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.” | 10 14 00 1.02.H | 243 | – |
| O&M | O&MMaintenance DataFire Protection Specialties10 44 00 1.02.E · PDF p. 251Spec wording“E. Maintenance Data: Include test, refill or recharge schedules and re-certification requirements.” | 10 44 00 1.02.E | 251 | – |
Division 12 Furnishings 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsProject Record Documents(Untitled)12 24 00 1.03.G · PDF p. 256Spec wording“G. Project Record Documents: Record actual locations of control systems and show interconnecting wiring.” | 12 24 00 1.03.G | 256 | – |
| O&M | O&MOperation and Maintenance Data(Untitled)12 24 00 1.03.H · PDF p. 256Spec wording“H. Operation and Maintenance Data: List of all components with part numbers, sources of supply, and operation and maintenance instructions; include copy of shop drawings.” | 12 24 00 1.03.H | 256 | – |
| Warranty | WarrantyWarranty(Untitled)12 24 00 1.03.I · PDF p. 256Spec wording“I. Warranty: Submit sample of manufacturer's warranty and documentation of final executed warranty completed in Owner's name and registered with manufacturer. 12 2400 /1” | 12 24 00 1.03.I | 256 | – |
| Warranty | WarrantyProvide manufacturer's warranty from the Date of Substantial Completion, covering ...(Untitled)12 24 00 1.07.A · PDF p. 257Spec wording“A. Provide manufacturer's warranty from the Date of Substantial Completion, covering the following: 1. Shade Hardware: 2 years. 2. Fabric: 2 years.” | 12 24 00 1.07.A | 257 | – |
| O&M | O&MDemonstration(Untitled)12 24 00 3.05.A · PDF p. 259Spec wording“A. Demonstration: Demonstrate operation and maintenance of window shade system to Owner's personnel. 12 2400 /4” | 12 24 00 3.05.A | 259 | – |
| O&M | O&MTraining(Untitled)12 24 00 3.05.B · PDF p. 260Spec wording“B. Training: Train Owner's personnel on operation and maintenance of system. 1. Use operation and maintenance manual as training reference, supplemented with additional training materials as required. 2. Provide minimum of two hours training by manufacturer's authorized personnel at location designated by the Owner.” | 12 24 00 3.05.B | 260 | – |
Division 13 Special construction 6 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyWarrantySection 13 212613 21 26 1.04.J · PDF p. 262Spec wording“J. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.” | 13 21 26 1.04.J | 262 | – |
| Warranty | WarrantySee Division 1 for additional warranty requirementsSection 13 212613 21 26 1.05.A · PDF p. 262Spec wording“A. See Division 1 for additional warranty requirements.” | 13 21 26 1.05.A | 262 | – |
| Warranty | WarrantyCorrect defective Work within a five-year period after Date of ...Section 13 212613 21 26 1.05.B · PDF p. 262Spec wording“B. Correct defective Work within a five-year period after Date of Substantial Completion.” | 13 21 26 1.05.B | 262 | – |
| Warranty | WarrantyProvide five-year manufacturer warranty for remote refrigeration compressor unit ...Section 13 212613 21 26 1.05.C · PDF p. 262Spec wording“C. Provide five-year manufacturer warranty for remote refrigeration compressor unit.” | 13 21 26 1.05.C | 262 | – |
| Test / cert. | Test / cert.Provide three copies of a written quality control test reportSection 13 212613 21 26 3.03.E · PDF p. 265Spec wording“E. Provide three copies of a written quality control test report.” | 13 21 26 3.03.E | 265 | three copies |
| Training | TrainingDemonstrate, in the presence of Owner, the operation, function, and ...Section 13 212613 21 26 3.05.A · PDF p. 266Spec wording“A. Demonstrate, in the presence of Owner, the operation, function, and maintenance of each room and its associated equipment.” | 13 21 26 3.05.A | 266 | – |
Division 21 Fire suppression (sprinklers) 1 item
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsMaintenance MaterialsFire-Suppression Sprinkler Systems21 13 00 1.5.B · PDF p. 271Spec wording“B. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. See Section 01 60 00 - Product Requirements, for additional provisions. 2. Extra Sprinklers: Type and size matching those installed, in quantity required by referenced NFPA design and installation standard. 3. Sprinkler Wrenches: For each sprinkler type. 21 13 00 /1” | 21 13 00 1.5.B | 271 | – |
Division 22 Plumbing 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Warranty | WarrantyCorrect defective Work within a 1 year period after Date ...Sleeves And Sleeve Seals For Plumbing Piping22 05 17 1.5.A · PDF p. 274Spec wording“A. Correct defective Work within a 1 year period after Date of Substantial Completion.” | 22 05 17 1.5.A | 274 | – |
| Spare parts | Spare partsMaintenance MaterialsPlumbing Piping Specialties22 10 06 1.4.B · PDF p. 289Spec wording“B. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. See Section 01 60 00 - Product Requirements, for additional provisions. 2. Extra Loose Keys for Outside Hose Bibbs: One. 22 10 06 /1” | 22 10 06 1.4.B | 289 | – |
| Warranty | WarrantyWarrantyPlumbing Fixtures22 40 00 1.3.C · PDF p. 292Spec wording“C. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.” | 22 40 00 1.3.C | 292 | – |
Division 23 HVAC 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.TAB PlanTesting, Adjusting, And Balancing For Hvac23 05 93 1.3.A · PDF p. 301Spec wording“A. TAB Plan: Submit a written plan indicating the testing, adjusting, and balancing standard to be followed and the specific approach for each system and component. 1. Submit to the Engineer . 2. Include at least the following in the plan: a. List of all air flow & system capacity and efficiency measurements to be performed and a description of specific test procedures, parameters, formulas to be used. b. Copy of ...” | 23 05 93 1.3.A | 301 | – |
| O&M | O&MFinal ReportTesting, Adjusting, And Balancing For Hvac23 05 93 1.3.B · PDF p. 301Spec wording“B. Final Report: Indicate deficiencies in systems that would prevent proper testing, adjusting, and balancing of systems and equipment to achieve specified performance. 1. Revise TAB plan to reflect actual procedures and submit as part of final report. 2. Submit draft copies of report for review prior to final acceptance of Project. Provide final copies for Architect and for inclusion in operating and maintenance ...” | 23 05 93 1.3.B | 301 | – |
| Record docs | Record docsProject Record DocumentsTesting, Adjusting, And Balancing For Hvac23 05 93 1.3.C · PDF p. 302Spec wording“C. Project Record Documents: Record actual locations of flow measuring stations and balancing valves and rough setting.” | 23 05 93 1.3.C | 302 | – |
| Closeout step | Closeout stepMark on drawings the locations where traverse and other critical ...Testing, Adjusting, And Balancing For Hvac23 05 93 3.5.D · PDF p. 303Spec wording“D. Mark on drawings the locations where traverse and other critical measurements were taken and cross reference the location in the final report.” | 23 05 93 3.5.D | 303 | – |
| Warranty | WarrantyWarrantyPackaged Rooftop Air-Conditioning Units23 74 16 1.3.B · PDF p. 320Spec wording“B. Warranty: Submit manufacturer's warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.” | 23 74 16 1.3.B | 320 | – |
| Warranty | WarrantyProvide a five year warranty to include coverage for refrigeration ...Packaged Rooftop Air-Conditioning Units23 74 16 1.4.A · PDF p. 320Spec wording“A. Provide a five year warranty to include coverage for refrigeration compressors.” | 23 74 16 1.4.A | 320 | – |
| Test / cert. | Test / cert.Prepare and start equipment. Adjust for proper operationPackaged Rooftop Air-Conditioning Units23 74 16 3.3.A · PDF p. 322Spec wording“A. Prepare and start equipment. Adjust for proper operation.” | 23 74 16 3.3.A | 322 | – |
| Warranty | WarrantyWarrantySelf-Contained Air-Conditioners23 81 19 1.2.B · PDF p. 323Spec wording“B. Warranty: Submit manufacturer's warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.” | 23 81 19 1.2.B | 323 | – |
| Warranty | WarrantyProvide a five year warranty to include coverage for refrigeration ...Self-Contained Air-Conditioners23 81 19 1.3.A · PDF p. 323Spec wording“A. Provide a five year warranty to include coverage for refrigeration compressors.” | 23 81 19 1.3.A | 323 | – |
| Warranty | WarrantyWarrantySmall-Capacity Split-System Air Conditioners23 81 26.13 1.3.B · PDF p. 325Spec wording“B. Warranty: Submit manufacturers warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.” | 23 81 26.13 1.3.B | 325 | – |
| Warranty | WarrantyProvide five year manufacturers warranty for heat exchangers and compressors. ...Small-Capacity Split-System Air Conditioners23 81 26.13 1.4.A · PDF p. 325Spec wording“A. Provide five year manufacturers warranty for heat exchangers and compressors. 23 81 26.13 /1” | 23 81 26.13 1.4.A | 325 | – |
Division 26 Electrical 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsMaintenance MaterialsPanelboards26 24 16 1.5.C · PDF p. 363Spec wording“C. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Panelboard Keys: Two of each different key.” | 26 24 16 1.5.C | 363 | – |
| Warranty | WarrantyProvide five year manufacturer warranty for LED luminaires, including drivers ...Interior Lighting26 51 00 1.8.A · PDF p. 377Spec wording“A. Provide five year manufacturer warranty for LED luminaires, including drivers.” | 26 51 00 1.8.A | 377 | – |
| Warranty | WarrantyProvide five year manufacturer warranty for all LED luminaires, including ...Exterior Lighting26 56 00 1.7.A · PDF p. 382Spec wording“A. Provide five year manufacturer warranty for all LED luminaires, including drivers.” | 26 56 00 1.7.A | 382 | – |
Division 28 Fire alarm and security 8 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Spare parts | Spare partsDesign DocumentsFire Detection And Alarm28 46 00 1.3.B · PDF p. 385-386Spec wording“B. Design Documents: Submit all information required for plan review and permitting by authorities having jurisdiction, including but not limited to floor plans, riser diagrams sealed by a professional engineering of the state of missouri. 1. Copy (if any) of list of data required by authority having jurisdiction. 2. NFPA 72 "Record of Completion", filled out to the extent known at the time. 3. Clear and concise ...” | 28 46 00 1.3.B | 385-386 | – |
| Training | TrainingInspection and Test Reports:Fire Detection And Alarm28 46 00 1.3.E · PDF p. 386Spec wording“E. Inspection and Test Reports: 1. Submit inspection and test plan prior to closeout demonstration. 2. Submit documentation of satisfactory inspections and tests. 3. Submit NFPA 72 "Inspection and Test Form," filled out.” | 28 46 00 1.3.E | 386 | – |
| Record docs | Record docsProject Record Documents:Fire Detection And Alarm28 46 00 1.3.F · PDF p. 386Spec wording“F. Project Record Documents: 1. Complete set of floor plans showing actual installed locations of components, conduit, and zones. 2. "As installed" wiring and schematic diagrams, with final terminal identifications. 3. "As programmed" operating sequences, including control events by device, updated input/output chart, and voice messages by event.” | 28 46 00 1.3.F | 386 | – |
| Test / cert. | Test / cert.Closeout Documents:Fire Detection And Alarm28 46 00 1.3.G · PDF p. 386Spec wording“G. Closeout Documents: 1. Certification by manufacturer that the system has been installed in compliance with manufacturer's installation requirements, is complete, and is in satisfactory operating condition. 2. NFPA 72 "Record of Completion", filled out completely and signed by installer and authorized representative of authority having jurisdiction. 3. Certificate of Occupancy. 4. Maintenance contract.” | 28 46 00 1.3.G | 386 | – |
| Warranty | WarrantyProvide control panel manufacturer's warranty that system components other than ...Fire Detection And Alarm28 46 00 1.5.A · PDF p. 387Spec wording“A. Provide control panel manufacturer's warranty that system components other than wire and conduit are free from defects and will remain so for 1 year after date of Substantial Completion.” | 28 46 00 1.5.A | 387 | – |
| Warranty | WarrantyProvide installer's warranty that the installation is free from defects ...Fire Detection And Alarm28 46 00 1.5.B · PDF p. 387Spec wording“B. Provide installer's warranty that the installation is free from defects and will remain so for 1 year after date of Substantial Completion.” | 28 46 00 1.5.B | 387 | – |
| O&M | O&MCloseout DemonstrationFire Detection And Alarm28 46 00 3.3.A · PDF p. 389Spec wording“A. Closeout Demonstration: Demonstrate proper operation of all functions to Owner. 1. Be prepared to conduct any of the required tests. 2. Have at least one copy of operation and maintenance data, copy of project record drawings, input/output matrix, and operator instruction chart(s) available during demonstration. 3. Have authorized technical representative of control unit manufacturer present during ...” | 28 46 00 3.3.A | 389 | one copy |
| O&M | O&MSubstantial Completion of the project cannot be achieved until inspection ...Fire Detection And Alarm28 46 00 3.3.B · PDF p. 389Spec wording“B. Substantial Completion of the project cannot be achieved until inspection and testing is successful and: 1. Approved operating and maintenance data has been delivered. 2. All aspects of operation have been demonstrated to Owner. 3. Final acceptance of the fire alarm system has been given by authorities having jurisdiction. 4. Occupancy permit has been granted.” | 28 46 00 3.3.B | 389 | – |
Division 31 Earthwork 3 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Record docs | Record docsRecord DrawingsSite Clearing31 10 00 1.6.B · PDF p. 392Spec wording“B. Record Drawings: Identify and accurately showing location of capped utilities and other subsurface structural, electrical, and mechanical conditions.” | 31 10 00 1.6.B | 392 | – |
| Test / cert. | Test / cert.Material Test ReportsEarth Moving31 20 00 1.6.B · PDF p. 398Spec wording“B. Material Test Reports: For each on-site and borrow soil material for proposed fill and backfill as follows: a. Classification according to ASTM D 2487 b. Laboratory compaction curve according to ASTM D 698.” | 31 20 00 1.6.B | 398 | – |
| Test / cert. | Test / cert.When testing agency reports that subgrades, fills, or backfills have ...Earth Moving31 20 00 2.19.E · PDF p. 404Spec wording“E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.” | 31 20 00 2.19.E | 404 | – |
Division 32 Paving and site improvements 10 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Material Test ReportsAsphalt Paving32 12 16 1.4.D · PDF p. 412Spec wording“D. Material Test Reports: For each paving material.” | 32 12 16 1.4.D | 412 | – |
| Warranty | WarrantyOther Action Submittals:Concrete Paving32 13 13 1.4.B · PDF p. 418Spec wording“B. Other Action Submittals: a. Design Mixtures: For each concrete paving mixture. Include alternate design mixtures when characteristics of materials, project conditions, weather, test results, or other circumstances warrant adjustments.” | 32 13 13 1.4.B | 418 | – |
| Test / cert. | Test / cert.Material Test ReportsConcrete Paving32 13 13 1.4.E · PDF p. 418Spec wording“E. Material Test Reports: For each of the following: a. Aggregates” | 32 13 13 1.4.E | 418 | – |
| Test / cert. | Test / cert.Field quality-control reportsConcrete Paving32 13 13 1.4.F · PDF p. 419Spec wording“F. Field quality-control reports.” | 32 13 13 1.4.F | 419 | – |
| Test / cert. | Test / cert.Test results shall be reported in writing to the Owner, ...Concrete Paving32 13 13 3.10.D · PDF p. 427Spec wording“D. Test results shall be reported in writing to the Owner, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project Identification name and number, date of concrete placement, name of concrete testing an inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, ...” | 32 13 13 3.10.D | 427 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsConcrete Paving32 13 13 3.10.I · PDF p. 427Spec wording“I. Prepare test and inspection reports.” | 32 13 13 3.10.I | 427 | – |
| Test / cert. | Test / cert.Product Test ReportsConcrete Paving Joint Sealants32 13 73 1.3.E · PDF p. 428Spec wording“E. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for joint sealants.” | 32 13 73 1.3.E | 428 | – |
| Test / cert. | Test / cert.Preconstruction Compatibility and Adhesion Test ReportsConcrete Paving Joint Sealants32 13 73 1.3.F · PDF p. 428Spec wording“F. Preconstruction Compatibility and Adhesion Test Reports: From joint-sealant manufacturer, indicating the following: a. Materials forming joint substrates and joint-sealant backings have been tested for compatibility with and adhesion to joint sealants. b. Interpretation of test results and written recommendations for primers and substrate preparation needed for adhesion.” | 32 13 73 1.3.F | 428 | – |
| O&M | O&MMaintenance DataTurf And Grasses32 92 00 1.5.A · PDF p. 433Spec wording“A. Maintenance Data: Recommended procedures to be established by Owner for maintenance of turf during calendar year.” | 32 92 00 1.5.A | 433 | – |
| Closeout step | Closeout stepTurf Maintenance ServiceTurf And Grasses32 92 00 3.10.A · PDF p. 437Spec wording“A. Turf Maintenance Service: Provide full maintenance by skilled employees of landscape installer. Begin maintenance immediately after each area is planted and continue until acceptable turf is established, but not for less than the following periods: a. Seeded Turf: As long as required until satisfactory turf is established and approved by Owner. b. Sodded Turf: As long as required and until satisfactory turf is ...” | 32 92 00 3.10.A | 437 | – |
Division 33 Utilities 4 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Test / cert. | Test / cert.Field quality-control test reportsFacility Water Distribution Piping33 11 13 1.4.B · PDF p. 438Spec wording“B. Field quality-control test reports.” | 33 11 13 1.4.B | 438 | – |
| O&M | O&MOperation and Maintenance DataFacility Water Distribution Piping33 11 13 1.4.C · PDF p. 438Spec wording“C. Operation and Maintenance Data: For water valves and specialties to include emergency, operation, and maintenance manuals.” | 33 11 13 1.4.C | 438 | – |
| Test / cert. | Test / cert.Prepare reports of testing activities as neededFacility Water Distribution Piping33 11 13 3.12.C · PDF p. 443Spec wording“C. Prepare reports of testing activities as needed.” | 33 11 13 3.12.C | 443 | – |
| Test / cert. | Test / cert.Field quality control reportsStorm Utility Drainage Piping33 41 00 1.3.C · PDF p. 451Spec wording“C. Field quality control reports.” | 33 41 00 1.3.C | 451 | – |
Front end Contract conditions (final payment, releases, retainage) 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 25Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 25 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 36Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 36 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 37Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 37 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 43Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 43 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 44Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 44 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 36Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 36 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 36Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 36 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 36-37Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 36-37 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 37Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 37 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 41-42Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 41-42 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 42Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 42 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.