Free closeout checklist · University job · Missouri

Closeout checklist: Judith Enyeart Reynolds Complex, Project Manual Volume 3 (Missouri State University, MO)

Every closeout item we found in the public spec book for this job: 232 items across 12 trade divisions, including 91 O&M manual items, 66 tests and certificates and 16 warranties. Each one is tied to its spec section and the PDF page it sits on.

Owner
Board of Governors of Missouri State University
Number
MSU project 23-043
Location
Springfield, MO
Issued for bid
2024-10-07
Public spec book
Project manual Volume 3 on the Missouri State University design website
Spec book size
736 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Volume 3 holds the mechanical, plumbing and electrical sections only. Division 01 and the contract conditions are in another volume, so the general closeout rules are not in this list.

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

16Warranties
91O&M manuals
66Tests and certificates
15Training
14Record documents
5Spare parts
0Payment release
17Closeout steps

All 232 items, by trade

Division 20 Mechanical, common work 21 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1 and each section of Division 20Basic Mechanical, Plumbing, And Fire Protection20 00 00 1.5.A · PDF p. 12
Spec wording
“A. Refer to Division 1 and each section of Division 20.”
20 00 00 1.5.A12–
O&MO&MOperation and Maintenance DataSeismic Controls20 05 48 1.5.A · PDF p. 16
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 05 48 1.5.A16–
O&MO&MParts ListSeismic Controls20 05 48 1.5.B · PDF p. 16
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 05 48 1.5.B16–
Record docsRecord docsAs-built seismic drawings with sealed letter from Seismic engineer stating ...Seismic Controls20 05 48 1.5.C · PDF p. 16
Spec wording
“C. As-built seismic drawings with sealed letter from Seismic engineer stating that the completed installation meets the design.”
20 05 48 1.5.C16–
O&MO&MOperation and Maintenance DataVibration Controls20 05 49 1.4.A · PDF p. 22
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 05 49 1.4.A22–
O&MO&MParts ListVibration Controls20 05 49 1.4.B · PDF p. 22
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 05 49 1.4.B22–
Test / cert.Test / cert.Prepare written report of testingBasic Mechanical Materials And Methods20 10 00 3.6.G · PDF p. 31
Spec wording
“G. Prepare written report of testing.”
20 10 00 3.6.G31–
O&MO&MOperation and Maintenance DataBasic Piping Materials20 10 10 1.4.A · PDF p. 32
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 10 10 1.4.A32–
O&MO&MParts ListBasic Piping Materials20 10 10 1.4.B · PDF p. 32
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 10 10 1.4.B32–
WarrantyWarrantyGrooved fittings and couplings Manufacturer's WarrantyBasic Piping Materials20 10 10 1.6.A · PDF p. 33
Spec wording
“A. Grooved fittings and couplings Manufacturer's Warranty: Manufacturer agrees to repair or replace couplings and fittings that fail in materials or workmanship within 20 years from date of Substantial Completion. 1. Warranty is to cover labor and material costs of repairing and/or replacing defective materials and repairing any incidental damage caused by failure of the piping system due to defects in materials or ...”
20 10 10 1.6.A33–
O&MO&MOperation and Maintenance DataValves And Strainers20 10 20 1.4.A · PDF p. 44
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 10 20 1.4.A44–
O&MO&MParts ListValves And Strainers20 10 20 1.4.B · PDF p. 44
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 10 20 1.4.B44–
Test / cert.Test / cert.Field quality-control reportsSleeves And Seals20 10 40 1.3.B · PDF p. 58
Spec wording
“B. Field quality-control reports.”
20 10 40 1.3.B58–
Record docsRecord docsValve tag information is required on "as-built" drawing submittalsIdentification20 10 70 1.3.A · PDF p. 82
Spec wording
“A. Valve tag information is required on "as-built" drawing submittals.”
20 10 70 1.3.A82–
O&MO&MList tagged valves in a valve schedule in the operating ...Identification20 10 70 1.3.B · PDF p. 82
Spec wording
“B. List tagged valves in a valve schedule in the operating and maintenance manual.”
20 10 70 1.3.B82–
O&MO&MOperation and Maintenance DataElectrical Requirements20 20 10 1.6.A · PDF p. 91
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 20 10 1.6.A91–
O&MO&MParts ListElectrical Requirements20 20 10 1.6.B · PDF p. 91
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 20 10 1.6.B91–
O&MO&MOperation and Maintenance DataDrives And Guards20 20 20 1.4.A · PDF p. 95
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
20 20 20 1.4.A95–
O&MO&MParts ListDrives And Guards20 20 20 1.4.B · PDF p. 95
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
20 20 20 1.4.B95–
WarrantyWarrantySelf-Adhesive Outdoor Jacket warranty information and copy of sales receipt ...Insulation20 20 25 1.6.A · PDF p. 100
Spec wording
“A. Self-Adhesive Outdoor Jacket warranty information and copy of sales receipt and other information required for warranty claim.”
20 20 25 1.6.A100–
WarrantyWarrantySelf-Adhesive Outdoor Jacket shall have a 10 year manufacturer warranty ...Insulation20 20 25 1.9.A · PDF p. 100
Spec wording
“A. Self-Adhesive Outdoor Jacket shall have a 10 year manufacturer warranty.”
20 20 25 1.9.A100–

Division 21 Fire suppression (sprinklers) 11 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1, Division 20, and each section of Division 21Fire Protection System21 00 00 1.6.A · PDF p. 118
Spec wording
“A. Refer to Division 1, Division 20, and each section of Division 21.”
21 00 00 1.6.A118–
Closeout stepCloseout stepAt the completion of the project, submit a letter stating ...Fire Protection System21 00 00 1.6.B · PDF p. 118
Spec wording
“B. At the completion of the project, submit a letter stating all materials are asbestos free, and meet the specified ASTM E-84 flame/smoke rating of 25/50, and that all piping and duct penetrations are smoke or fire stopped as required by the Code.”
21 00 00 1.6.B118–
O&MO&MOperation and Maintenance DataFire Protection Design21 00 10 1.5.A · PDF p. 120
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
21 00 10 1.5.A120–
O&MO&MParts ListFire Protection Design21 00 10 1.5.B · PDF p. 120
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
21 00 10 1.5.B120–
O&MO&MOperation and Maintenance DataPiping And Accessories21 00 20 1.4.A · PDF p. 124
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
21 00 20 1.4.A124–
O&MO&MParts ListPiping And Accessories21 00 20 1.4.B · PDF p. 124
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
21 00 20 1.4.B124–
Spare partsSpare partsFurnish extra materials that match products installed and that are ...Piping And Accessories21 00 20 1.5.A · PDF p. 124
Spec wording
“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Sprinkler Cabinets: Finished, wall-mounted, steel cabinet with hinged cover, and with space for minimum of two (2) heads of each sprinkler head plus sprinkler wrench(es). Where this quantity is less than what is required by NFPA 13, provide additional ...”
21 00 20 1.5.A124–
O&MO&MOperation and Maintenance DataWet Pipe Sprinkler System21 00 30 1.4.A · PDF p. 133
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
21 00 30 1.4.A133–
O&MO&MParts ListWet Pipe Sprinkler System21 00 30 1.4.B · PDF p. 133
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
21 00 30 1.4.B133–
O&MO&MOperation and Maintenance DataDry-Pipe Sprinkler System21 00 40 1.4.A · PDF p. 138
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
21 00 40 1.4.A138–
O&MO&MParts ListDry-Pipe Sprinkler System21 00 40 1.4.B · PDF p. 138
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
21 00 40 1.4.B138–

Division 22 Plumbing 21 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1, Division 20, and each section of Division 22Plumbing Work22 00 00 1.7.A · PDF p. 148
Spec wording
“A. Refer to Division 1, Division 20, and each section of Division 22.”
22 00 00 1.7.A148–
Record docsRecord docsAs-built drawings of underground plumbing shall include dimensions from walls/columns ...Plumbing Work22 00 00 1.7.B · PDF p. 148
Spec wording
“B. As-built drawings of underground plumbing shall include dimensions from walls/columns and invert elevations.”
22 00 00 1.7.B148–
Closeout stepCloseout stepAt the completion of the project, submit a letter stating ...Plumbing Work22 00 00 1.7.C · PDF p. 148
Spec wording
“C. At the completion of the project, submit a letter stating all materials are asbestos free, and meet the specified ASTM E-84 flame/smoke rating of 25/50, and that all piping and duct penetrations are smoke or fire stopped as required by the Code.”
22 00 00 1.7.C148–
Test / cert.Test / cert.Refer to Section 01 91 13 for commissioning team membersCommissioning Of Plumbing Systems22 08 00 1.6.A · PDF p. 150
Spec wording
“A. Refer to Section 01 91 13 for commissioning team members.”
22 08 00 1.6.A150–
Test / cert.Test / cert.Refer to Section 01 91 13 for additional required commissioning ...Commissioning Of Plumbing Systems22 08 00 1.7.A · PDF p. 150
Spec wording
“A. Refer to Section 01 91 13 for additional required commissioning submittals.”
22 08 00 1.7.A150–
Test / cert.Test / cert.Refer to Section 01 91 13 for an overview of the commissioning processCommissioning Of Plumbing Systems22 08 00 3.1.A · PDF p. 150
Spec wording
“A. Refer to Section 01 91 13 for an overview of the commissioning process.”
22 08 00 3.1.A150–
Test / cert.Test / cert.Refer to Section 01 91 13 for Start-Up and Checkout requirementsCommissioning Of Plumbing Systems22 08 00 3.5.A · PDF p. 150
Spec wording
“A. Refer to Section 01 91 13 for Start-Up and Checkout requirements.”
22 08 00 3.5.A150–
Test / cert.Test / cert.Refer to Section 01 91 13 for information regarding Non-Conformance ...Commissioning Of Plumbing Systems22 08 00 3.7.A · PDF p. 151
Spec wording
“A. Refer to Section 01 91 13 for information regarding Non-Conformance and Cx Issues.”
22 08 00 3.7.A151–
TrainingTrainingThe GC/CM is responsible for execution of Owner Training as ...Commissioning Of Plumbing Systems22 08 00 3.8.A · PDF p. 151
Spec wording
“A. The GC/CM is responsible for execution of Owner Training as outlined in section 01 79 00.”
22 08 00 3.8.A151–
Test / cert.Test / cert.Pressure test reportsPlumbing Piping Systems22 10 00 1.3.B · PDF p. 152
Spec wording
“B. Pressure test reports.”
22 10 00 1.3.B152–
Test / cert.Test / cert.Field quality-control reportsPlumbing Piping Systems22 10 00 1.3.C · PDF p. 152
Spec wording
“C. Field quality-control reports.”
22 10 00 1.3.C152–
O&MO&MOperation and Maintenance DataPlumbing Fixtures22 40 00 1.4.A · PDF p. 166
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
22 40 00 1.4.A166–
O&MO&MParts ListPlumbing Fixtures22 40 00 1.4.B · PDF p. 166
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
22 40 00 1.4.B166–
Test / cert.Test / cert.Prepare test and inspection reportsPlumbing Fixtures22 40 00 3.3.D · PDF p. 176
Spec wording
“D. Prepare test and inspection reports.”
22 40 00 3.3.D176–
O&MO&MOperation and Maintenance DataPlumbing Equipment22 50 00 1.4.A · PDF p. 178
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
22 50 00 1.4.A178–
O&MO&MParts ListPlumbing Equipment22 50 00 1.4.B · PDF p. 178
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
22 50 00 1.4.B178–
Test / cert.Test / cert.Prepare test and inspection reportsPlumbing Equipment22 50 00 3.4.E · PDF p. 181
Spec wording
“E. Prepare test and inspection reports.”
22 50 00 3.4.E181–
TrainingTrainingEngage a factory-authorized service representative to train Train Owner's maintenance ...Plumbing Equipment22 50 00 3.5.A · PDF p. 181
Spec wording
“A. Engage a factory-authorized service representative to train Train Owner's maintenance personnel to adjust, operate, and maintain domestic-water heaters, circulators, pumps.”
22 50 00 3.5.A181–
O&MO&MOperation and Maintenance DataPlumbing Specialties22 80 00 1.4.A · PDF p. 182
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
22 80 00 1.4.A182–
O&MO&MParts ListPlumbing Specialties22 80 00 1.4.B · PDF p. 182
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
22 80 00 1.4.B182–
Test / cert.Test / cert.Prepare test and inspection reportsPlumbing Specialties22 80 00 3.3.D · PDF p. 188
Spec wording
“D. Prepare test and inspection reports.”
22 80 00 3.3.D188–

Division 23 HVAC 36 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1, Division 20, and each section of Division 23Hvac Piping And Equipment23 00 00 1.6.A · PDF p. 192
Spec wording
“A. Refer to Division 1, Division 20, and each section of Division 23.”
23 00 00 1.6.A192–
Record docsRecord docsAs-built drawings of underground piping or equipment shall include dimensions ...Hvac Piping And Equipment23 00 00 1.6.B · PDF p. 192
Spec wording
“B. As-built drawings of underground piping or equipment shall include dimensions from building walls/columns and elevations.”
23 00 00 1.6.B192–
Closeout stepCloseout stepAt the completion of the project, submit a letter stating ...Hvac Piping And Equipment23 00 00 1.6.C · PDF p. 192
Spec wording
“C. At the completion of the project, submit a letter stating all materials are asbestos free, and meet the specified ASTM E-84 flame/smoke rating of 25/50, and that all piping and duct penetrations are smoke or fire stopped as required by the Code.”
23 00 00 1.6.C192–
Test / cert.Test / cert.Refer to Section 01 91 13 for commissioning team membersCommissioning Of Hvac Systems23 08 00 1.6.A · PDF p. 194
Spec wording
“A. Refer to Section 01 91 13 for commissioning team members.”
23 08 00 1.6.A194–
Test / cert.Test / cert.Refer to Section 01 91 13 for additional required commissioning ...Commissioning Of Hvac Systems23 08 00 1.7.A · PDF p. 194
Spec wording
“A. Refer to Section 01 91 13 for additional required commissioning submittals.”
23 08 00 1.7.A194–
Test / cert.Test / cert.TAB Plan:Commissioning Of Hvac Systems23 08 00 1.7.B · PDF p. 194
Spec wording
“B. TAB Plan: 1. The GC/CM, with assistance from the TABC, shall develop a TAB Plan and execute TAB utilizing the following procedure. 2. Compile detailed TAB forms according to the TABC's certifying agency standard. TAB documentation shall include specific boxes or lines for recording and documenting data of each piece of equipment. 3. Submit the TAB Plan to the CxA for review and include the following at a ...”
23 08 00 1.7.B194–
Test / cert.Test / cert.Refer to Section 01 91 13 for an overview of the commissioning processCommissioning Of Hvac Systems23 08 00 3.1.A · PDF p. 195
Spec wording
“A. Refer to Section 01 91 13 for an overview of the commissioning process.”
23 08 00 3.1.A195–
Test / cert.Test / cert.Refer to Section 01 91 13 for Start-Up and Checkout requirementsCommissioning Of Hvac Systems23 08 00 3.5.A · PDF p. 196
Spec wording
“A. Refer to Section 01 91 13 for Start-Up and Checkout requirements.”
23 08 00 3.5.A196–
Test / cert.Test / cert.Refer to Section 01 91 13 for information regarding Non-Conformance ...Commissioning Of Hvac Systems23 08 00 3.8.A · PDF p. 197
Spec wording
“A. Refer to Section 01 91 13 for information regarding Non-Conformance and Cx Issues.”
23 08 00 3.8.A197–
TrainingTrainingThe GC/CM is responsible for execution of Owner Training as ...Commissioning Of Hvac Systems23 08 00 3.9.A · PDF p. 197
Spec wording
“A. The GC/CM is responsible for execution of Owner Training as outlined in section 01 79 00.”
23 08 00 3.9.A197–
O&MO&MOperation and Maintenance DataHydronic Piping And Equipment23 21 00 1.4.A · PDF p. 199
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 21 00 1.4.A199–
O&MO&MParts ListHydronic Piping And Equipment23 21 00 1.4.B · PDF p. 199
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 21 00 1.4.B199–
TrainingTrainingSubmit product data for the following:Underground Hydronic Piping23 21 15 1.5.A · PDF p. 208
Spec wording
“A. Submit product data for the following: 1. Pipe, valves and fittings. 2. Restraining devices. 3. Valve boxes and vent boxes.”
23 21 15 1.5.A208–
Test / cert.Test / cert.Field quality-control test reportsUnderground Hydronic Piping23 21 15 1.5.B · PDF p. 208
Spec wording
“B. Field quality-control test reports.”
23 21 15 1.5.B208–
O&MO&MOperation and Maintenance DataUnderground Hydronic Piping23 21 15 1.5.C · PDF p. 208
Spec wording
“C. Operation and Maintenance Data: For valves and specialties to include in emergency, operation, and maintenance manuals.”
23 21 15 1.5.C208–
O&MO&MOperation and Maintenance DataHydronic Pumps And Accessories23 21 20 1.4.A · PDF p. 217
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 21 20 1.4.A217–
O&MO&MParts ListHydronic Pumps And Accessories23 21 20 1.4.B · PDF p. 217
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 21 20 1.4.B217–
Test / cert.Test / cert.Where existing systems are modified, provide start-up strainers at all ...Hydronic Pumps And Accessories23 21 20 3.4.A · PDF p. 220
Spec wording
“A. Where existing systems are modified, provide start-up strainers at all existing pumps. Strainers shall be removed after 72 hours of operation.”
23 21 20 3.4.A220–
O&MO&MOperation and Maintenance DataSteam And Condensate Piping And Equipment23 22 00 1.4.A · PDF p. 221
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 22 00 1.4.A221–
O&MO&MParts ListSteam And Condensate Piping And Equipment23 22 00 1.4.B · PDF p. 221
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 22 00 1.4.B221–
O&MO&MOperation and Maintenance DataHvac Water Treatment23 25 00 1.5.A · PDF p. 227
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 25 00 1.5.A227–
O&MO&MParts ListHvac Water Treatment23 25 00 1.5.B · PDF p. 227
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 25 00 1.5.B227–
Test / cert.Test / cert.Prepare test and inspection reportsHvac Water Treatment23 25 00 3.5.D · PDF p. 230
Spec wording
“D. Prepare test and inspection reports.”
23 25 00 3.5.D230–
Test / cert.Test / cert.Scope of Maintenance ServiceHvac Water Treatment23 25 00 3.6.A · PDF p. 231
Spec wording
“A. Scope of Maintenance Service: Provide chemicals and service program to maintain water conditions required above, to inhibit corrosion, scale formation, and biological growth for heating, steam and condensate piping and equipment. Services and chemicals shall be provided for a period of one year from date of Substantial Completion and shall include the following: 1. Initial water analysis and HVAC water-treatment ...”
23 25 00 3.6.A231–
TrainingTrainingTrain Owner's maintenance personnel to adjust, operate, and maintain HVAC ...Hvac Water Treatment23 25 00 3.7.A · PDF p. 231
Spec wording
“A. Train Owner's maintenance personnel to adjust, operate, and maintain HVAC water-treatment systems and equipment.”
23 25 00 3.7.A231–
O&MO&MOperation and Maintenance DataHeat Exchangers23 57 00 1.4.A · PDF p. 232
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 57 00 1.4.A232–
O&MO&MParts ListHeat Exchangers23 57 00 1.4.B · PDF p. 232
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 57 00 1.4.B232–
O&MO&MOperation and Maintenance DataCentral Station Air Handling Units23 73 00 1.4.A · PDF p. 235
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 73 00 1.4.A235–
O&MO&MParts ListCentral Station Air Handling Units23 73 00 1.4.B · PDF p. 235
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 73 00 1.4.B235–
Test / cert.Test / cert.Engage a factory-authorized service representative to perform startup service ...Central Station Air Handling Units23 73 00 3.6.A · PDF p. 239
Spec wording
“A. Engage a factory-authorized service representative to perform startup service. 1. Complete installation and startup checks according to manufacturer's written instructions. 2. Verify that shipping, blocking, and bracing are removed. 3. Verify that unit is secure on mountings and supporting devices and that connections to piping, ducts, and electrical systems are complete. Verify that proper thermal-overload ...”
23 73 00 3.6.A239–
Test / cert.Test / cert.Starting procedures for air-handling units include the following:Central Station Air Handling Units23 73 00 3.6.B · PDF p. 239
Spec wording
“B. Starting procedures for air-handling units include the following: 1. Energize motor; verify proper operation of motor, drive system, and fan wheel. Adjust fan to indicated rpm. 2. Measure and record motor electrical values for voltage and amperage. 3. Manually operate dampers from fully closed to fully open position and record fan performance.”
23 73 00 3.6.B239–
TrainingTrainingTrain Owner's maintenance personnel to adjust, operate, and maintain air-handling ...Central Station Air Handling Units23 73 00 3.8.A · PDF p. 239
Spec wording
“A. Train Owner's maintenance personnel to adjust, operate, and maintain air-handling units.”
23 73 00 3.8.A239–
O&MO&MOperation and Maintenance DataConvection Heating And Cooling Units23 82 00 1.4.A · PDF p. 240
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 82 00 1.4.A240–
O&MO&MParts ListConvection Heating And Cooling Units23 82 00 1.4.B · PDF p. 240
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 82 00 1.4.B240–
O&MO&MOperation and Maintenance DataAir Compressor23 83 00 1.4.A · PDF p. 248
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
23 83 00 1.4.A248–
O&MO&MParts ListAir Compressor23 83 00 1.4.B · PDF p. 248
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
23 83 00 1.4.B248–

Division 24 Division 24 16 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1, Division 20, and each section of Division 24Air Distribution24 00 00 1.8.A · PDF p. 252
Spec wording
“A. Refer to Division 1, Division 20, and each section of Division 24.”
24 00 00 1.8.A252–
Closeout stepCloseout stepAt the completion of the project, submit a letter stating ...Air Distribution24 00 00 1.8.B · PDF p. 252
Spec wording
“B. At the completion of the project, submit a letter stating all materials are asbestos free, and meet the specified ASTM E-84 flame/smoke rating of 25/50, and that all piping and duct penetrations are smoke or fire stopped as required by the Code.”
24 00 00 1.8.B252–
O&MO&MOperation and Maintenance DataSheetmetal Ductwork24 31 00 1.4.A · PDF p. 253
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 31 00 1.4.A253–
O&MO&MParts ListSheetmetal Ductwork24 31 00 1.4.B · PDF p. 253
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 31 00 1.4.B253–
O&MO&MOperation and Maintenance DataDuctwork Accessories24 33 00 1.4.A · PDF p. 264
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 33 00 1.4.A264–
O&MO&MParts ListDuctwork Accessories24 33 00 1.4.B · PDF p. 264
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 33 00 1.4.B264–
O&MO&MOperation and Maintenance DataFans24 34 00 1.4.A · PDF p. 275
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 34 00 1.4.A275–
O&MO&MParts ListFans24 34 00 1.4.B · PDF p. 275
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 34 00 1.4.B275–
O&MO&MOperation and Maintenance DataDust Collection System24 36 00 1.4.A · PDF p. 278
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 36 00 1.4.A278–
O&MO&MParts ListDust Collection System24 36 00 1.4.B · PDF p. 278
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 36 00 1.4.B278–
O&MO&MOperation and Maintenance DataAir Devices24 37 00 1.4.A · PDF p. 282
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 37 00 1.4.A282–
O&MO&MParts ListAir Devices24 37 00 1.4.B · PDF p. 282
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 37 00 1.4.B282–
O&MO&MOperation and Maintenance DataType Ii Hoods24 38 10 1.5.A · PDF p. 286
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 38 10 1.5.A286–
O&MO&MParts ListType Ii Hoods24 38 10 1.5.B · PDF p. 286
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 38 10 1.5.B286–
O&MO&MOperation and Maintenance DataFilter Assemblies24 41 00 1.4.A · PDF p. 289
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
24 41 00 1.4.A289–
O&MO&MParts ListFilter Assemblies24 41 00 1.4.B · PDF p. 289
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
24 41 00 1.4.B289–

Division 25 Building automation and controls 14 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepRefer to Division 1, Division 20, and each section of Division 25Temperature Control System25 00 00 1.8.A · PDF p. 299
Spec wording
“A. Refer to Division 1, Division 20, and each section of Division 25.”
25 00 00 1.8.A299–
Record docsRecord docsAs-built drawings of electrical circuit numbers, power panels, remote sensors, ...Temperature Control System25 00 00 1.8.B · PDF p. 299
Spec wording
“B. As-built drawings of electrical circuit numbers, power panels, remote sensors, outdoor air sensor building differential pressure sensor and reference probes.”
25 00 00 1.8.B299–
Test / cert.Test / cert.Field quality-control reportsControl System Requirements25 10 00 1.3.B · PDF p. 300
Spec wording
“B. Field quality-control reports.”
25 10 00 1.3.B300–
O&MO&MOperation and Maintenance DataControl System Requirements25 10 00 1.4.A · PDF p. 300
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
25 10 00 1.4.A300–
O&MO&MParts ListControl System Requirements25 10 00 1.4.B · PDF p. 300
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
25 10 00 1.4.B300–
TrainingTrainingThe contractor shall provide a representative from the company used ...Control System Requirements25 10 00 3.5.A · PDF p. 319
Spec wording
“A. The contractor shall provide a representative from the company used as the source for the electronic controllers used in the systems installed under this contract. The representative shall conduct the training class on the project site at a time scheduled in advance with the Owner and shall occur during or immediately following system start up. These instructions are to be conducted during normal working hours. ...”
25 10 00 3.5.A319–
O&MO&MOperation and Maintenance DataAir Side Control Equipment25 20 00 1.4.A · PDF p. 320
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
25 20 00 1.4.A320–
O&MO&MParts ListAir Side Control Equipment25 20 00 1.4.B · PDF p. 320
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
25 20 00 1.4.B320–
O&MO&MOperation and Maintenance DataHydronic Control Equipment25 30 00 1.4.A · PDF p. 335
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
25 30 00 1.4.A335–
O&MO&MParts ListHydronic Control Equipment25 30 00 1.4.B · PDF p. 335
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
25 30 00 1.4.B335–
O&MO&MOperation and Maintenance DataAuxiliary Equipment25 40 00 1.4.A · PDF p. 344
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
25 40 00 1.4.A344–
O&MO&MParts ListAuxiliary Equipment25 40 00 1.4.B · PDF p. 344
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
25 40 00 1.4.B344–
O&MO&MManufacturer's Operation and Maintenance instructionWiring Materials And Methods25 50 00 1.4.A · PDF p. 351
Spec wording
“A. Manufacturer's Operation and Maintenance instruction: For each type of product.”
25 50 00 1.4.A351–
O&MO&MParts ListWiring Materials And Methods25 50 00 1.4.B · PDF p. 351
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
25 50 00 1.4.B351–

Division 26 Electrical 58 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Post-installation Hi-pot test results– Medium Voltage Cable, Terminations, And Splices26 05 13 1.4.A · PDF p. 394
Spec wording
“A. Post-installation Hi-pot test results”
26 05 13 1.4.A394–
Test / cert.Test / cert.Prepare test and inspection reports– Medium Voltage Cable, Terminations, And Splices26 05 13 3.2.C · PDF p. 397
Spec wording
“C. Prepare test and inspection reports.”
26 05 13 3.2.C397–
Not requiredNot requiredNot required– Low-Voltage Electrical Power Conductors And Cables26 05 19 1.4.A · PDF p. 398
Spec wording
“A. Not required.”
26 05 19 1.4.A398–
Test / cert.Test / cert.Perform tests and inspections and prepare test reports– Low-Voltage Electrical Power Conductors And Cables26 05 19 3.5.A · PDF p. 401
Spec wording
“A. Perform tests and inspections and prepare test reports.”
26 05 19 3.5.A401–
Test / cert.Test / cert.Test Reports– Low-Voltage Electrical Power Conductors And Cables26 05 19 3.5.C · PDF p. 402
Spec wording
“C. Test Reports: Prepare a written report to record the following: 1. Test procedures used. 2. Test results that comply with requirements. 3. Test results that do not comply with requirements and corrective action taken to achieve compliance with requirements.”
26 05 19 3.5.C402–
Test / cert.Test / cert.Field quality-control reportsGrounding And Bonding For Electrical Systems26 05 26 1.2.C · PDF p. 403
Spec wording
“C. Field quality-control reports.”
26 05 26 1.2.C403–
O&MO&MOperation and Maintenance Data:Grounding And Bonding For Electrical Systems26 05 26 1.3.A · PDF p. 404
Spec wording
“A. Operation and Maintenance Data: 1. In addition to items specified in Section 260010 "Supplemental Requirements for Electrical," include the following: a. Photographs of transformer grounding.”
26 05 26 1.3.A404–
Test / cert.Test / cert.Collect, assemble, and submit test and inspection reportsGrounding And Bonding For Electrical Systems26 05 26 3.5.D · PDF p. 410
Spec wording
“D. Collect, assemble, and submit test and inspection reports. 1. Report measured ground resistances that exceed the following values: a. Power and Lighting Equipment or System with Capacity of 500 kVA and Less: 10 Ω b. Substations and Pad-Mounted Equipment: 5 Ω. c. Manhole Grounds: 10 Ω.”
26 05 26 3.5.D410–
Not requiredNot requiredNot required– Raceway For Electrical Systems26 05 33 1.4.A · PDF p. 411
Spec wording
“A. Not required”
26 05 33 1.4.A411–
Not requiredNot requiredNot required– Boxes For Electrical Systems26 05 34 1.4.A · PDF p. 417
Spec wording
“A. Not required”
26 05 34 1.4.A417–
Not requiredNot requiredNot required– Cable Trays For Electrical Systems26 05 36 1.4.A · PDF p. 421
Spec wording
“A. Not required”
26 05 36 1.4.A421–
Record docsRecord docsAs-built and field modifications shall be submitted– Seismic Restraint26 05 48 1.4.A · PDF p. 424
Spec wording
“A. As-built and field modifications shall be submitted.”
26 05 48 1.4.A424–
Not requiredNot requiredNot required– Arc Flash Hazard Analysis, Short Circuit Analysis, And26 05 73 1.5.A · PDF p. 427
Spec wording
“A. Not required.”
26 05 73 1.5.A427–
Test / cert.Test / cert.Refer to Section 01 91 13 for commissioning team membersCommissioning Of Electrical Systems26 08 00 1.6.A · PDF p. 431
Spec wording
“A. Refer to Section 01 91 13 for commissioning team members.”
26 08 00 1.6.A431–
Test / cert.Test / cert.Refer to Section 01 91 13 for additional required commissioning ...Commissioning Of Electrical Systems26 08 00 1.7.A · PDF p. 431
Spec wording
“A. Refer to Section 01 91 13 for additional required commissioning submittals.”
26 08 00 1.7.A431–
Test / cert.Test / cert.Refer to Section 01 91 13 for an overview of the commissioning processCommissioning Of Electrical Systems26 08 00 3.1.A · PDF p. 432
Spec wording
“A. Refer to Section 01 91 13 for an overview of the commissioning process.”
26 08 00 3.1.A432–
Test / cert.Test / cert.Refer to Section 01 91 13 for Start-Up and Checkout requirementsCommissioning Of Electrical Systems26 08 00 3.5.A · PDF p. 432
Spec wording
“A. Refer to Section 01 91 13 for Start-Up and Checkout requirements.”
26 08 00 3.5.A432–
Test / cert.Test / cert.Refer to Section 01 91 13 for information regarding Non-Conformance ...Commissioning Of Electrical Systems26 08 00 3.7.A · PDF p. 433
Spec wording
“A. Refer to Section 01 91 13 for information regarding Non-Conformance and Cx Issues.”
26 08 00 3.7.A433–
TrainingTrainingThe GC/CM is responsible for execution of Owner TrainingCommissioning Of Electrical Systems26 08 00 3.8.A · PDF p. 433
Spec wording
“A. The GC/CM is responsible for execution of Owner Training.”
26 08 00 3.8.A433–
O&MO&MOperating Instructions– Lighting Control Devices26 09 23 1.4.A · PDF p. 434
Spec wording
“A. Operating Instructions: For each type of product.”
26 09 23 1.4.A434–
Test / cert.Test / cert.Prepare test and inspection reports– Lighting Control Devices26 09 23 3.6.D · PDF p. 437
Spec wording
“D. Prepare test and inspection reports.”
26 09 23 3.6.D437–
O&MO&MOperating Instructions:– Network/Addressable Lighting Controls26 09 43 1.4.A · PDF p. 438
Spec wording
“A. Operating Instructions: 1. Installation and programming instructions for all system components. 2. Operating instructions for all system components. 3. Relay schedule documentation. 4. Switch schedule documentation. 5. Time Clock schedule documentation.”
26 09 43 1.4.A438–
Test / cert.Test / cert.Field Test Reports:– Network/Addressable Lighting Controls26 09 43 3.5.D · PDF p. 441
Spec wording
“D. Field Test Reports: 1. Prepare test and inspection reports. Include notation of deficiencies detected, remedial action taken, and observations made after remedial action.”
26 09 43 3.5.D441–
Test / cert.Test / cert.The Contractor shall provide a representative from the company to ...– Network/Addressable Lighting Controls26 09 43 3.6.A · PDF p. 441
Spec wording
“A. The Contractor shall provide a representative from the company to conduct a 2-hour training class at a time scheduled in advance with the Owner and shall occur during or immediately following system startup. These instructions are to be conducted during normal working hours. All pertinent costs shall be included in this contract.”
26 09 43 3.6.A441–
Test / cert.Test / cert.Engage a factory-authorized service representative to perform startup service ...– Network/Addressable Lighting Controls26 09 43 3.6.B · PDF p. 441
Spec wording
“B. Engage a factory-authorized service representative to perform startup service. 1. Complete installation and startup checks according to manufacturer's written instructions. 2. Activate luminaires and verify that all lamps are operating. 3. Confirm correct communications wiring, initiate communications between DLM devices and controller/gateways, and program the lighting control system according to approved ...”
26 09 43 3.6.B441–
TrainingTrainingManufacturer shall provide six (6) sets of full system submittals. ...Theatrical Lighting Controls26 09 61 1.3.A · PDF p. 442
Spec wording
“A. Manufacturer shall provide six (6) sets of full system submittals. Submittals shall include: 1. Full system riser diagram(s) illustrating interconnection of system components, wiring requirements, back box sizes and any special installation considerations. 2. Full set of printed technical data sheets. 3. Detailed set of dimmer schedules 4. Detailed set of circuit and control schedules, including a complete list ...”
26 09 61 1.3.A442six (6) sets
WarrantyWarrantyManufacturer shall warrant products under normal use and service to ...Theatrical Lighting Controls26 09 61 1.14.A · PDF p. 466
Spec wording
“A. Manufacturer shall warrant products under normal use and service to be free from defects in materials and workmanship for a period of two years from date of delivery.”
26 09 61 1.14.A466–
WarrantyWarrantyWarranty shall cover repair or replacement of such parts determined ...Theatrical Lighting Controls26 09 61 1.14.B · PDF p. 466
Spec wording
“B. Warranty shall cover repair or replacement of such parts determined defective upon inspection.”
26 09 61 1.14.B466–
WarrantyWarrantyWarranty does not cover any product or part of a ...Theatrical Lighting Controls26 09 61 1.14.C · PDF p. 466
Spec wording
“C. Warranty does not cover any product or part of a product subject to accident, negligence, alteration, abuse or misuse. Warranty does not cover any accessories or parts not supplied by the manufacturer.”
26 09 61 1.14.C466–
WarrantyWarrantyWarranty shall not cover any labor expended or materials used ...Theatrical Lighting Controls26 09 61 1.14.D · PDF p. 466
Spec wording
“D. Warranty shall not cover any labor expended or materials used to repair any equipment without manufacturers prior written authorization.”
26 09 61 1.14.D466–
Test / cert.Test / cert.Prepare test and inspection reports. Record as-left set points of ...Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers26 12 19 3.5.D · PDF p. 472
Spec wording
“D. Prepare test and inspection reports. Record as-left set points of adjustable devices.”
26 12 19 3.5.D472–
Not requiredNot requiredNone required– Medium-Voltage Switchgear26 13 00 1.4.A · PDF p. 474
Spec wording
“A. None required.”
26 13 00 1.4.A474–
O&MO&MOperation and Maintenance Data– Low-Voltage Dry-Type Transformers26 22 13 1.4.A · PDF p. 480
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
26 22 13 1.4.A480–
O&MO&MOperation and Maintenance Data– Switchboards26 24 13 1.4.A · PDF p. 483
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
26 24 13 1.4.A483–
O&MO&MParts List– Switchboards26 24 13 1.4.B · PDF p. 483
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
26 24 13 1.4.B483–
Spare partsSpare partsTwo (2) keys for each type of panelboard– Panelboards26 24 16 1.4.A · PDF p. 487
Spec wording
“A. Two (2) keys for each type of panelboard.”
26 24 16 1.4.A487–
Spare partsSpare partsOne (1) spare breaker for each type of breaker (GFCI, standard, etc.)– Panelboards26 24 16 1.4.B · PDF p. 487
Spec wording
“B. One (1) spare breaker for each type of breaker (GFCI, standard, etc.).”
26 24 16 1.4.B487–
O&MO&MOperation and Maintenance Data– Panelboards26 24 16 1.5.A · PDF p. 487
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
26 24 16 1.5.A487–
O&MO&MParts List– Panelboards26 24 16 1.5.B · PDF p. 487
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
26 24 16 1.5.B487–
Test / cert.Test / cert.Perform startup service– Panelboards26 24 16 3.3.A · PDF p. 491
Spec wording
“A. Perform startup service. 1. Complete installation and startup checks according to manufacturer's instructions. 2. Confirm correct communication wiring, initiate communications between panels, and program control system according to approved time-of-day schedules and input override assignments.”
26 24 16 3.3.A491–
O&MO&MOperation Manual– Metering26 27 13 1.4.A · PDF p. 493
Spec wording
“A. Operation Manual”
26 27 13 1.4.A493–
Test / cert.Test / cert.Collect, assemble, and submit test and inspection reports– Metering26 27 13 3.2.D · PDF p. 494
Spec wording
“D. Collect, assemble, and submit test and inspection reports.”
26 27 13 3.2.D494–
O&MO&MOperating InstructionsWiring Devices26 27 26 1.4.A · PDF p. 496
Spec wording
“A. Operating Instructions: For each type of product.”
26 27 26 1.4.A496–
Test / cert.Test / cert.Assemble and submit test and inspection reportsWiring Devices26 27 26 3.5.C · PDF p. 502
Spec wording
“C. Assemble and submit test and inspection reports.”
26 27 26 3.5.C502–
Test / cert.Test / cert.Assemble and submit test and inspection reportsWiring Devices26 27 26 3.6.C · PDF p. 502
Spec wording
“C. Assemble and submit test and inspection reports.”
26 27 26 3.6.C502–
Test / cert.Test / cert.Assemble and submit test and inspection reportsWiring Devices26 27 26 3.8.C · PDF p. 503
Spec wording
“C. Assemble and submit test and inspection reports.”
26 27 26 3.8.C503–
Not requiredNot requiredNot required– Fuses26 28 13 1.4.A · PDF p. 505
Spec wording
“A. Not required”
26 28 13 1.4.A505–
Not requiredNot requiredNot required– Disconnect Switches26 28 16 1.4.A · PDF p. 507
Spec wording
“A. Not required”
26 28 16 1.4.A507–
O&MO&MOperation manual– Elevator Power Module Switch26 28 19 1.4.A · PDF p. 510
Spec wording
“A. Operation manual”
26 28 19 1.4.A510–
O&MO&MOperation and Maintenance Data– Motor And Appliance Control26 29 13 1.4.A · PDF p. 512
Spec wording
“A. Operation and Maintenance Data: For each type of product.”
26 29 13 1.4.A512–
O&MO&MParts List– Motor And Appliance Control26 29 13 1.4.B · PDF p. 512
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
26 29 13 1.4.B512–
Test / cert.Test / cert.Prepare test and inspection reports– Motor And Appliance Control26 29 13 3.2.D · PDF p. 516
Spec wording
“D. Prepare test and inspection reports.”
26 29 13 3.2.D516–
O&MO&MOperation Manual:– Variable Frequency Drives26 29 23 1.4.A · PDF p. 517
Spec wording
“A. Operation Manual:”
26 29 23 1.4.A517–
O&MO&MParts List– Variable Frequency Drives26 29 23 1.4.B · PDF p. 517
Spec wording
“B. Parts List: For each type of product that has replaceable parts.”
26 29 23 1.4.B517–
O&MO&MOperations Manual– Surge Protective Devices (Spd)26 43 13 1.4.A · PDF p. 522
Spec wording
“A. Operations Manual”
26 43 13 1.4.A522–
O&MO&MOperation and Maintenance Data– Led Lighting26 51 00 1.5.A · PDF p. 525
Spec wording
“A. Operation and Maintenance Data: For luminaires and lighting systems to include in operation and maintenance manuals. 1. Provide a list of all Lamps/LED Light Bars & Drivers/Transformers used on Project; use ANSI and manufacturers' codes.”
26 51 00 1.5.A525–
Spare partsSpare partsFurnish extra materials that match products installed and that are ...– Led Lighting26 51 00 1.6.A · PDF p. 525
Spec wording
“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Lamps/LED Light Bars: One for every 100 of each type and rating installed. Furnish at least one of each type. 2. Diffusers and Lenses: One for every 100 of each type and rating installed. Furnish at least one of each type. 3. Drivers/Transformers: One ...”
26 51 00 1.6.A525–
O&MO&MOperation and Maintenance Data– Emergency Lighting Transfer Devices26 52 13 1.4.A · PDF p. 531
Spec wording
“A. Operation and Maintenance Data”
26 52 13 1.4.A531–

Division 27 Communications 21 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepNot required 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONSPathways For Communications Systems27 05 28 1.4.A · PDF p. 533
Spec wording
“A. Not required 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS”
27 05 28 1.4.A533–
Closeout stepCloseout stepRequirements of the following Sections of the Specifications apply to ...Pathways For Communications Systems27 05 28 1.4.A · PDF p. 533
Spec wording
“A. Requirements of the following Sections of the Specifications apply to Work for this Section: 1. Division 26 – Electrical 2. Division 28 – Electronic Safety and Security”
27 05 28 1.4.A533–
Record docsRecord docsAs-built drawings providing identification and routing of all fiber cabling. ...Communications Optical Fiber Backbone Cabling27 13 23 1.4.A · PDF p. 536
Spec wording
“A. As-built drawings providing identification and routing of all fiber cabling. 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS”
27 13 23 1.4.A536–
Closeout stepCloseout stepRequirements of the following Sections of the Specifications apply to ...Communications Optical Fiber Backbone Cabling27 13 23 1.4.A · PDF p. 536
Spec wording
“A. Requirements of the following Sections of the Specifications apply to Work for this Section: 1. Division 26 – Electrical 2. Division 28 – Electronic Safety and Security”
27 13 23 1.4.A536–
Test / cert.Test / cert.Test reports may be submitted in hardcopy and/or electronic format. ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.F · PDF p. 538
Spec wording
“F. Test reports may be submitted in hardcopy and/or electronic format. Hand-written test reports are not acceptable.”
27 13 23 3.2.F538hardcopy; electronic format
Test / cert.Test / cert.Hardcopy reports are to be submitted in labeled 3 ring ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.G · PDF p. 538
Spec wording
“G. Hardcopy reports are to be submitted in labeled 3 ring binders with a witness signature verifying passing execution of all tests.”
27 13 23 3.2.G538Hardcopy; binders
Test / cert.Test / cert.Electronic reports are to be submitted on 3.5 inch diskettes ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.H · PDF p. 538
Spec wording
“H. Electronic reports are to be submitted on 3.5 inch diskettes or CD format. Disk or CD shall contain the software required to view test results. Electronic reports must be accompanied by a Certificate signed by an authorized representative of the Contractor warranting the truth and accuracy of the electronic report. Certificate must reference traceable circuit numbers that match the electronic record.”
27 13 23 3.2.H538CD
Test / cert.Test / cert.Test reports shall include the following information for each cabling ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.I · PDF p. 538
Spec wording
“I. Test reports shall include the following information for each cabling element tested: 1. Actual measured and maximum allowable attenuation (loss) at the specified wavelengths and the margin. An individual test that fails the link criteria shall be marked as FAIL. 2. Reference method. 3. Number of mated connectors and number of splices (if any). 4. Actual length and maximum allowable length per Part 2 Section 3. ...”
27 13 23 3.2.I538–
Test / cert.Test / cert.Test reports shall be submitted within 7 business days of ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.J · PDF p. 538
Spec wording
“J. Test reports shall be submitted within 7 business days of completion of testing.”
27 13 23 3.2.J538–
Test / cert.Test / cert.Test equipment used under this contract shall be from manufacturers ...Communications Optical Fiber Backbone Cabling27 13 23 3.2.K · PDF p. 539
Spec wording
“K. Test equipment used under this contract shall be from manufacturers that have a minimum of 5 years experience in producing field test equipment. Manufacturers must be ISO 9001 certified. All test tools of a given type shall be from the same manufacturer, and have compatible electronic results output.”
27 13 23 3.2.K539–
Record docsRecord docsProvide as-built drawings indicating cable routing and cable/jack/patch panel identification. ...Communications Copper Horizontal Cabling Systems27 15 13 1.4.A · PDF p. 540
Spec wording
“A. Provide as-built drawings indicating cable routing and cable/jack/patch panel identification. 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS”
27 15 13 1.4.A540–
Closeout stepCloseout stepRequirements of the following Sections of the Specifications apply to ...Communications Copper Horizontal Cabling Systems27 15 13 1.4.A · PDF p. 540
Spec wording
“A. Requirements of the following Sections of the Specifications apply to Work for this Section: 1. Division 26 – Electrical 2. Division 28 – Electronic Safety and Security”
27 15 13 1.4.A540–
Record docsRecord docsAs-built drawings 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS ...Communications Coaxial Horizontal Cabling Systems27 15 33 1.4.A · PDF p. 544
Spec wording
“A. As-built drawings 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS”
27 15 33 1.4.A544–
Closeout stepCloseout stepRequirements of the following Sections of the Specifications apply to ...Communications Coaxial Horizontal Cabling Systems27 15 33 1.4.A · PDF p. 544
Spec wording
“A. Requirements of the following Sections of the Specifications apply to Work for this Section: 1. Division 26 – Electrical 2. Division 28 – Electronic Safety and Security”
27 15 33 1.4.A544–
O&MO&MOperation and Maintenance DataAudio-Video Systems27 41 00 1.4.E · PDF p. 550
Spec wording
“E. Operation and Maintenance Data”
27 41 00 1.4.E550–
TrainingTrainingOwner's operating personnel in the proper set up, operating and ...Audio-Video Systems27 41 00 3.7.A · PDF p. 554
Spec wording
“A. Owner's operating personnel in the proper set up, operating and maintenance procedures, installed under this contract, and shall include at least three (3) service calls of 4 hours minimum during the warranty period for service or instructions as required by the Owner, at a time mutually agreeable to the Owner and Contractor.”
27 41 00 3.7.A554–
TrainingTrainingProvide minimum of two four-hour training sessions for system operation ...Audio-Video Systems27 41 00 3.7.B · PDF p. 555
Spec wording
“B. Provide minimum of two four-hour training sessions for system operation of the Blackbox Theater and two one-hour sessions for all other Audio-Visual systems.”
27 41 00 3.7.B555–
TrainingTrainingGeneralClock And Time Tone System27 53 13 1.4.A · PDF p. 556
Spec wording
“A. General: Submit the following in accordance with Conditions of Contract Sections: 1. Submit equipment prints, full electronic wiring diagrams and specifications sheets for each item specified herein. Provide a tabulation of the specification clearly comparing the submitted item with the specified item, being able to refer to all written expressed functions and capabilities. Specification sheets shall be ...”
27 53 13 1.4.A556–
TrainingTrainingThe contractor shall provide training with this system. These sessions ...Clock And Time Tone System27 53 13 1.7.A · PDF p. 557
Spec wording
“A. The contractor shall provide training with this system. These sessions shall be broken into segments that will facilitate the training of individuals in the operation of this system. Operators Manuals and Users Guides shall be provided at the time of this training.”
27 53 13 1.7.A557–
Test / cert.Test / cert.Train Owner's maintenance personnel in the procedures and schedules involved ...Clock And Time Tone System27 53 13 3.3.A · PDF p. 560
Spec wording
“A. Train Owner's maintenance personnel in the procedures and schedules involved in operating, troubleshooting, servicing, and preventative maintenance of the system. Operators Manuals and Users Guides shall be provided at the time of this training.”
27 53 13 3.3.A560–
Test / cert.Test / cert.Schedule training with Owner through the Architect, with at least ...Clock And Time Tone System27 53 13 3.3.B · PDF p. 560
Spec wording
“B. Schedule training with Owner through the Architect, with at least seven (7) days advance notice.”
27 53 13 3.3.B560–

Division 28 Fire alarm and security 8 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepNot required 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONSPathways For Electronic And Safety Systems28 05 28 1.4.A · PDF p. 562
Spec wording
“A. Not required 1.5 REFERENCES, RELATED SECTIONS of the SPECIFICATIONS”
28 05 28 1.4.A562–
Closeout stepCloseout stepRequirements of the following Sections of the Specifications apply to ...Pathways For Electronic And Safety Systems28 05 28 1.4.A · PDF p. 562
Spec wording
“A. Requirements of the following Sections of the Specifications apply to Work for this Section: 1. Division 26 – Electrical 2. Division 28 – Electronic Safety and Security”
28 05 28 1.4.A562–
Test / cert.Test / cert.Field quality-control reportsVideo Surveillance Systems28 23 00 1.4.B · PDF p. 566
Spec wording
“B. Field quality-control reports.”
28 23 00 1.4.B566–
O&MO&MOperation and Maintenance DataVideo Surveillance Systems28 23 00 1.5.A · PDF p. 566
Spec wording
“A. Operation and Maintenance Data: For cameras, power supplies, infrared illuminators, monitors, videotape recorders, digital video recorders, video switches, and control-station components to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. Lists of spare parts and replacement components ...”
28 23 00 1.5.A566–
WarrantyWarrantySpecial WarrantyVideo Surveillance Systems28 23 00 1.8.A · PDF p. 567
Spec wording
“A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of cameras, equipment related to camera operation, and control-station equipment that fall in materials or workmanship within specified period. 1. Warranty Period: One year from date of Substantial Completion.”
28 23 00 1.8.A567–
Test / cert.Test / cert.Prepare test and inspection reportsVideo Surveillance Systems28 23 00 3.4.E · PDF p. 569
Spec wording
“E. Prepare test and inspection reports.”
28 23 00 3.4.E569–
TrainingTrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Video Surveillance Systems28 23 00 3.7.A · PDF p. 570
Spec wording
“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain video-surveillance equipment.”
28 23 00 3.7.A570–
O&MO&MProvide shop drawings in accordance with the appropriate paragraphs the ...Fire Detection And Alarm System28 30 00 1.2.A · PDF p. 571-572
Spec wording
“A. Provide shop drawings in accordance with the appropriate paragraphs the applicable version of NFPA 72 for the following items: 1. Written narrative providing intent and system description. 2. Floorplan layout showing location of all devices, including isolation components to comply with the applicable NFPA 72 chapter on the Performance of Signaling Line Circuits (SLCs) referencing fault tolerances and ...”
28 30 00 1.2.A571-572Hard copy; thumb drive

Division 31 Earthwork 5 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyDesign MixturesDrilled Concrete Piers And Shafts31 63 29 1.5.B · PDF p. 594-595
Spec wording
“B. Design Mixtures: For each concrete mixture. Submit alternative design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments. 1. Indicate amounts of mixing water to be withheld for later addition at Project site.”
31 63 29 1.5.B594-595–
Test / cert.Test / cert.Material Test ReportsDrilled Concrete Piers And Shafts31 63 29 1.6.D · PDF p. 595
Spec wording
“D. Material Test Reports: For each material below, by a qualified testing agency: 1. Aggregates”
31 63 29 1.6.D595–
Test / cert.Test / cert.Field quality-control reportsDrilled Concrete Piers And Shafts31 63 29 1.6.E · PDF p. 595
Spec wording
“E. Field quality-control reports.”
31 63 29 1.6.E595–
Record docsRecord docsRecord drawingsDrilled Concrete Piers And Shafts31 63 29 1.7.A · PDF p. 595
Spec wording
“A. Record drawings.”
31 63 29 1.7.A595–
Test / cert.Test / cert.Prepare test and inspection reports for each drilled pier as follows:Drilled Concrete Piers And Shafts31 63 29 3.6.F · PDF p. 602-603
Spec wording
“F. Prepare test and inspection reports for each drilled pier as follows: 1. Actual top and bottom elevations. 2. Actual drilled-pier diameter at top, bottom, and bell. 3. Top of rock elevation. 4. Description of soil materials. 5. Description, location, and dimensions of obstructions. 6. Final top centerline location and deviations from requirements. 7. Variation of shaft from plumb. 8. Shaft excavating method. 9. ...”
31 63 29 3.6.F602-603–

Division 32 Paving and site improvements 19 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test Reports and Design Mixes:Concrete Paving32 13 13 1.3.E · PDF p. 625
Spec wording
“E. Test Reports and Design Mixes: 1. Submit 3 copies of design mixes and material test reports to OWNER.”
32 13 13 1.3.E6253 copies
Test / cert.Test / cert.The testing laboratory shall report all test and inspection results ...Concrete Paving32 13 13 3.11.E · PDF p. 630
Spec wording
“E. The testing laboratory shall report all test and inspection results to OWNER, OWNER'S Engineer, and Contractor immediately after they are performed. All concrete test reports shall include name of job, date of placement, date of test, batch mix design, slump and the exact location in the Work at which the batch represented by the test was deposited.”
32 13 13 3.11.E630–
Test / cert.Test / cert.All costs necessary to prepare concrete test cylinders, make tests ...Concrete Paving32 13 13 3.11.F · PDF p. 630
Spec wording
“F. All costs necessary to prepare concrete test cylinders, make tests and furnishing of written reports shall be borne by the Contractor.”
32 13 13 3.11.F630–
Record docsRecord docsRecord Drawings:Landscape Irrigation Preformance Specification32 84 00 1.05.A · PDF p. 666
Spec wording
“A. Record Drawings: 1. Record accurately on one set of drawings all changes in the work constituting departures from the original approved Shop Drawings and the actual final installed locations of all required components as shown below. 2. Record Drawings shall be prepared to the satisfaction of the Architect. Prior to final inspection of work, submit Record Drawings to the Architect. 3. Show locations and depths ...”
32 84 00 1.05.A666one set
Test / cert.Test / cert.Acquire certificate of compliance from local authority indicating approval of ...Landscape Irrigation Preformance Specification32 84 00 1.06.F · PDF p. 667
Spec wording
“F. Acquire certificate of compliance from local authority indicating approval of backflow preventer installation.”
32 84 00 1.06.F667–
Spare partsSpare partsFurnish to Owner the following extra components:Landscape Irrigation Preformance Specification32 84 00 3.7.A · PDF p. 672
Spec wording
“A. Furnish to Owner the following extra components: 1. Two sprinkler heads of each type and size. 2. Two nozzle inserts for each type and size. 3. Two drip emitters of each type and size 4. Two drip line basket filters of each type and size. 5. Two keys each for valve boxes and controller (if locked boxes are used). 6. Two of any required special tools for adjustment or replacement of each type of outlet, nozzle, ...”
32 84 00 3.7.A672–
TrainingTrainingProvide system demonstration to Owner and Architect/Engineer for review and ...Landscape Irrigation Preformance Specification32 84 00 3.8.A · PDF p. 672
Spec wording
“A. Provide system demonstration to Owner and Architect/Engineer for review and final acceptance of work. Coordinate demonstration of procedures for winterizing (draining system lines, backflow preventer, etc.) and spring start-up with Owner. Review system operation and components during service visit.”
32 84 00 3.8.A672–
O&MO&MInstruct Owner or representative in operation and maintenance of system, ...Landscape Irrigation Preformance Specification32 84 00 3.8.B · PDF p. 672
Spec wording
“B. Instruct Owner or representative in operation and maintenance of system, including adjusting of sprinkler heads. Use operation and maintenance material as basis for demonstration.”
32 84 00 3.8.B672–
O&MO&MDeliver record drawing of system, required operation and maintenance information, ...Landscape Irrigation Preformance Specification32 84 00 3.8.C · PDF p. 672
Spec wording
“C. Deliver record drawing of system, required operation and maintenance information, extra materials and backflow preventer certificate to Owner at the instruction meeting.”
32 84 00 3.8.C672–
WarrantyWarrantyProvide one-year materials and workmanship warranty on all system components ...Landscape Irrigation Preformance Specification32 84 00 3.9.A · PDF p. 673
Spec wording
“A. Provide one-year materials and workmanship warranty on all system components and installation beginning on date of acceptance of the work.”
32 84 00 3.9.A673–
WarrantyWarrantyReplace failed components immediately upon notification by Owner or Architect/Engineer ...Landscape Irrigation Preformance Specification32 84 00 3.9.B · PDF p. 673
Spec wording
“B. Replace failed components immediately upon notification by Owner or Architect/Engineer.”
32 84 00 3.9.B673–
Test / cert.Test / cert.Submit materials test reportTurf Grasses32 92 00 1.03.C · PDF p. 674
Spec wording
“C. Submit materials test report.”
32 92 00 1.03.C674–
WarrantyWarrantyProvide a uniform stand of grass by watering, mowing, and ...Turf Grasses32 92 00 1.06.A · PDF p. 675
Spec wording
“A. Provide a uniform stand of grass by watering, mowing, and maintaining lawn areas until final acceptance. Re sod areas, with specified materials, which fail to provide a uniform stand of grass until all affected areas are accepted by the Landscape Architect.”
32 92 00 1.06.A675–
Record docsRecord docsProvide plant material record drawings:Exterior Plants32 93 00 1.03.D · PDF p. 682
Spec wording
“D. Provide plant material record drawings: 1. Legibly mark drawings to record actual construction. 2. Indicate horizontal and vertical locations, referenced to permanent surface improvements. 3. Identify field changes of dimension and detail and changes made by Change Order.”
32 93 00 1.03.D682–
WarrantyWarrantyWarrant plant material to remain alive and be in healthy, ...Exterior Plants32 93 00 1.06.A · PDF p. 684
Spec wording
“A. Warrant plant material to remain alive and be in healthy, vigorous condition for a period of 1 year after completion and acceptance of entire project. 1. A review of plants will be made by the Architect at Substantial Completion and Final Completion.”
32 93 00 1.06.A684–
WarrantyWarrantyReplace, in accordance with the drawings and specifications, all plants ...Exterior Plants32 93 00 1.06.B · PDF p. 684
Spec wording
“B. Replace, in accordance with the drawings and specifications, all plants that are dead or, as determined by the Architect, are in an unhealthy or unsightly condition, and have lost their natural shape due to dead branches, or other causes such as bark abrasions and misuse of chemicals, due to the Landscape Contractor's negligence. The cost of such replacement(s) is at Landscape Contractor's expense. Warrant all ...”
32 93 00 1.06.B684–
WarrantyWarrantyWarranty shall not include damage or loss of trees, plants, ...Exterior Plants32 93 00 1.06.C · PDF p. 684
Spec wording
“C. Warranty shall not include damage or loss of trees, plants, or ground covers caused by fires, floods, freezing rains, lightning storms, or winds over 75 miles per hour, winter kill caused by extreme cold and severe winter conditions not typical of planting area, acts of vandalism or negligence on the part of the owner.”
32 93 00 1.06.C684–
WarrantyWarrantyRemove and immediately replace all plants, as determined by the ...Exterior Plants32 93 00 1.06.D · PDF p. 684
Spec wording
“D. Remove and immediately replace all plants, as determined by the Architect, to be unsatisfactory during the initial planting installation.”
32 93 00 1.06.D684–
Test / cert.Test / cert.An inspection of the trees, shrubs, groundcovers, perennials and native ...Exterior Plants32 93 00 3.07.A · PDF p. 696
Spec wording
“A. An inspection of the trees, shrubs, groundcovers, perennials and native grasses will be made by the Landscape Architect upon request for Application of Substantial Completion by the Landscape Contractor. Provide notification of at least five (5) working days before requested inspection date.”
32 93 00 3.07.A696–

Division 33 Utilities 2 items

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsProject Record Documents:Sewer Manholes, Frames, And Covers33 05 13 1.4.D · PDF p. 719
Spec wording
“D. Project Record Documents: 1. Disinfection report: Record the following: a. Type and form of disinfectant used. b. Date and time disinfectant injection start and time of completion. c. Test locations. d. Initial and 24 hour disinfectant residuals (quantity in treated water) in ppm for each outlet tested. e. Date and time of flushing start and completion. f. Disinfectant residual after flushing in ppm for each ...”
33 05 13 1.4.D719–
Record docsRecord docsProject Record Documents:Sanitary Sewage Systems33 31 11 1.3.A · PDF p. 725
Spec wording
“A. Project Record Documents: 1. Accurately record actual locations of pipe runs, connections, cleanouts, and invert elevations. 2. Identify and describe unexpected variations to subsoil conditions and location of uncharted utilities.”
33 31 11 1.3.A725–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.