Closeout checklist: Renovate B200 Ground for Bronchoscopy, James H. Quillen VA Medical Center (U.S. Department of Veterans Affairs, TN)

Every closeout item we found in the public spec book for this job: 372 items across Division 01, 14 trade divisions, including 147 tests and certificates, 65 O&M manual items and 55 warranties. Each one is tied to its spec section and the PDF page it sits on.

Owner
U.S. Department of Veterans Affairs, Network Contracting Office 9
Number
Solicitation 36C24925R0040, VA project 621-24-101
Location
Mountain Home, TN
Contract signed
2025-08-15
Public spec book
Solicitation notice on SAM.gov (spec book attached, marked public)
Spec book size
1,322 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Built from the specifications as revised by amendment 0002.

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

55Warranties
65O&M manuals
147Tests and certificates
40Training
49Record documents
10Spare parts
0Payment release
6Closeout steps

All 372 items, by trade

Division 01 General requirements 107 items

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsThe contractor shall maintain two full size sets of as-built ...General Requirements01 00 00 1.10.A · PDF p. 116
Spec wording
“A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.”
01 00 00 1.10.A116two full size sets
Record docsRecord docsAll variations shall be shown in the same general detail ...General Requirements01 00 00 1.10.B · PDF p. 116
Spec wording
“B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.”
01 00 00 1.10.B116–
Record docsRecord docsContractor shall deliver two approved completed sets of as-built drawings ...General Requirements01 00 00 1.10.C · PDF p. 116
Spec wording
“C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.”
01 00 00 1.10.C116electronic version; PDF
Record docsRecord docsParagraphs A, B, & C shall also apply to all shop drawingsGeneral Requirements01 00 00 1.10.D · PDF p. 116
Spec wording
“D. Paragraphs A, B, & C shall also apply to all shop drawings.”
01 00 00 1.10.D116–
WarrantyWarrantyWarranty Management PlanGeneral Requirements01 00 00 1.11.A · PDF p. 116-118
Spec wording
“A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The ...”
01 00 00 1.11.A116-118four sets; binder
WarrantyWarrantyPerformance & Payment BondsGeneral Requirements01 00 00 1.11.B · PDF p. 118
Spec wording
“B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period. 1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the ...”
01 00 00 1.11.B118–
WarrantyWarrantyPre-Warranty ConferenceGeneral Requirements01 00 00 1.11.C · PDF p. 118-119
Spec wording
“C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for ...”
01 00 00 1.11.C118-119–
WarrantyWarrantyContractor's Response to Construction Warranty Service Requirements:General Requirements01 00 00 1.11.D · PDF p. 119
Spec wording
“D. Contractor's Response to Construction Warranty Service Requirements:”
01 00 00 1.11.D119–
WarrantyWarrantyFollowing oral or written notification by the Contracting Officer, the ...General Requirements01 00 00 1.11.E · PDF p. 119-121
Spec wording
“E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date ...”
01 00 00 1.11.E119-121–
WarrantyWarrantyWarranty TagsGeneral Requirements01 00 00 1.11.F · PDF p. 121
Spec wording
“F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for ...”
01 00 00 1.11.F121–
O&MO&MContractor shall furnish Maintenance and Operating manuals (hard copies and ...General Requirements01 00 00 1.18.A · PDF p. 126
Spec wording
“A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.”
01 00 00 1.18.A126–
O&MO&MManualsGeneral Requirements01 00 00 1.18.B · PDF p. 126-127
Spec wording
“B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, ...”
01 00 00 1.18.B126-127four hard copies; one electronic copy
TrainingTrainingInstructionsGeneral Requirements01 00 00 1.18.C · PDF p. 127-128
Spec wording
“C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment, i.e. the AHU. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different ...”
01 00 00 1.18.C127-128–
WarrantyWarrantyThe contractor shall make every effort to compile a comprehensive ...Shop Drawings, Product Data, And Samples01 33 23 1.5.G · PDF p. 154-155
Spec wording
“G. The contractor shall make every effort to compile a comprehensive submittal package that includes all required components such as product data, samples, test reports, certificates, and other items as specified in the contract documents. If the contractor is unable to provide a complete package, GC must clearly communicate any missing components to the AE and the VA within the submittal package. At a minimum, a ...”
01 33 23 1.5.G154-155–
TrainingTrainingThe Contractor shall provide an online construction document management platform ...Shop Drawings, Product Data, And Samples01 33 23 1.6.D · PDF p. 157-158
Spec wording
“D. The Contractor shall provide an online construction document management platform for use by all parties at the Contractor's expense. The purpose of this platform is to facilitate efficient communication, collaboration, and document sharing among project stakeholders throughout the construction process. The platform shall meet the following performance requirements: 1. Accessibility: The platform shall be ...”
01 33 23 1.6.D157-158–
O&MO&MSubmit data specified for a given item within 30 calendar ...Shop Drawings, Product Data, And Samples01 33 23 1.8.A · PDF p. 158
Spec wording
“A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.”
01 33 23 1.8.A158–
O&MO&MIn the event the Contractor fails to deliver O&M Data ...Shop Drawings, Product Data, And Samples01 33 23 1.8.B · PDF p. 159
Spec wording
“B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the COR may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.”
01 33 23 1.8.B159–
TrainingTrainingThe designated Prime Contractor SSHO must meet the requirements of ...Safety Requirements01 35 26 1.10.A · PDF p. 177
Spec wording
“A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project.”
01 35 26 1.10.A177–
TrainingTrainingAs a minimum the SSHO must have completed the OSHA ...Safety Requirements01 35 26 1.10.B · PDF p. 177
Spec wording
“B. As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety Outreach class within the past five (5) years and: 1. Seven (7) years of construction industry safety related experience. 2. OR have a safety and health degree from an accredited university or college and five (5) years of construction industry safety related experience 3. OR hold as current, a Certified Safety Professional (CSP) or a ...”
01 35 26 1.10.B177–
TrainingTrainingThe Alternate Safety Officer shall meet, at a minimum, the ...Safety Requirements01 35 26 1.10.C · PDF p. 178
Spec wording
“C. The Alternate Safety Officer shall meet, at a minimum, the requirements of EM 385-1-1 Section 1 and have five (5) years of construction industry safety experience If the SSHO does not have a current certification, certification must be obtained within 90 days, maximum, of contract award.”
01 35 26 1.10.C178–
TrainingTrainingAll designated CPs shall have completed the OSHA 30-hour Construction ...Safety Requirements01 35 26 1.10.D · PDF p. 178
Spec wording
“D. All designated CPs shall have completed the OSHA 30-hour Construction Safety course and/or EM 385-1-1 40-hour training within the past 5 years. In addition, all CPs with high hazard work operations (such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations) shall have a specialized formal ...”
01 35 26 1.10.D178–
TrainingTrainingAll other construction workers shall have the OSHA 10-hour Construction ...Safety Requirements01 35 26 1.10.E · PDF p. 178
Spec wording
“E. All other construction workers shall have the OSHA 10-hour Construction Safety Outreach course within the past 5 years and any necessary safety training to be able to identify hazards within their work environment.”
01 35 26 1.10.E178–
TrainingTrainingSubmit training records associated with the above training requirements to ...Safety Requirements01 35 26 1.10.F · PDF p. 178
Spec wording
“F. Submit training records associated with the above training requirements to COR for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance.”
01 35 26 1.10.F178–
TrainingTrainingPrior to any worker for the contractor or subcontractors beginning ...Safety Requirements01 35 26 1.10.G · PDF p. 178
Spec wording
“G. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, this briefing shall include information on the site-specific hazards, construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, emergency procedures, ...”
01 35 26 1.10.G178–
TrainingTrainingOngoing safety training will be accomplished in the form of ...Safety Requirements01 35 26 1.10.H · PDF p. 178
Spec wording
“H. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.”
01 35 26 1.10.H178–
Test / cert.Test / cert.Government approval is required for all submittals. CQC inspection reports ...Quality Control01 45 00 1.3 · PDF p. 203
Spec wording
“Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Initial, or Follow-Up)]: [Applicable Specification section] naming convention. 1. Preconstruction Submittals a. Interim CQC Plan b. CQC Plan c. Additional Requirements for Design Quality Control (DQC) Plan 2. Design Data a. ...”
01 45 00 1.3203–
Test / cert.Test / cert.Personnel RequirementsQuality Control01 45 00 3.4.A · PDF p. 207-208
Spec wording
“A. Personnel Requirements: The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager (if applicable), and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager shall satisfy the requirements of Specification 01 35 26 Safety Requirements and reports directly to a senior project (or ...”
01 45 00 3.4.A207-208–
Test / cert.Test / cert.CQC PersonnelQuality Control01 45 00 3.4.C · PDF p. 208-209
Spec wording
“C. CQC Personnel: In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist in the CQC System Manager for the following areas, as applicable: electrical, mechanical, civil, structural, environmental, architectural, materials technician submittals clerk, Commissioning Agent/LEED specialist, and low voltage systems. These individuals or ...”
01 45 00 3.4.C208-209–
Test / cert.Test / cert.Organizational ChangesQuality Control01 45 00 3.4.E · PDF p. 210
Spec wording
“E. Organizational Changes: Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer or Authorized designee for acceptance. 3.5 SUBMITTALS AND DELIVERABLES: Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Product Data, and Samples. The CQC ...”
01 45 00 3.4.E210–
Closeout stepCloseout stepCloseout SubmittalsSustainable Construction Requirements01 81 13 1.5.G · PDF p. 230
Spec wording
“G. Closeout Submittals: Within 14 days after Substantial Completion provide the following: 1. Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet. 2. Manufacturer's cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction if permanently installed air handling units are used during construction. ...”
01 81 13 1.5.G230–
Test / cert.Test / cert.This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form ...General Commissioning Requirements01 91 00 1.1.A · PDF p. 241
Spec wording
“A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form the basis of the construction phase commissioning process and procedures. The Commissioning Agent shall add, modify, and refine the commissioning procedures, as approved by the Department of Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed ...”
01 91 00 1.1.A241–
Test / cert.Test / cert.Various sections of the project specifications require equipment startup, testing, ...General Commissioning Requirements01 91 00 1.1.B · PDF p. 241
Spec wording
“B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the D Division 22, Division 23, and Division 26 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not intended to duplicate services. The Contractor shall ...”
01 91 00 1.1.B241–
Test / cert.Test / cert.Where individual testing, adjusting, or related services are required in ...General Commissioning Requirements01 91 00 1.1.C · PDF p. 241
Spec wording
“C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services shall be provided and copies of documentation, as required by those specifications shall be submitted to the VA and the Commissioning Agent to be indexed for future reference.”
01 91 00 1.1.C241–
Test / cert.Test / cert.Where training or educational services for VA are required and ...General Commissioning Requirements01 91 00 1.1.D · PDF p. 241
Spec wording
“D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 22, Division 23, and Division 26series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.”
01 91 00 1.1.D241–
Test / cert.Test / cert.Commissioning is a systematic process of verifying that the building ...General Commissioning Requirements01 91 00 1.1.E · PDF p. 241-242
Spec wording
“E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA's operational needs. The commissioning process shall encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy ...”
01 91 00 1.1.E241-242–
Test / cert.Test / cert.The commissioning process does not take away from or reduce ...General Commissioning Requirements01 91 00 1.1.F · PDF p. 242
Spec wording
“F. The commissioning process does not take away from or reduce the responsibility of the Contractor to provide a finished and fully functioning product.”
01 91 00 1.1.F242–
Test / cert.Test / cert.The commissioning team shall consist of, but not be limited ...General Commissioning Requirements01 91 00 1.8.A · PDF p. 255
Spec wording
“A. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning Agent.”
01 91 00 1.8.A255–
Test / cert.Test / cert.Members Appointed by Contractor:General Commissioning Requirements01 91 00 1.8.B · PDF p. 255
Spec wording
“B. Members Appointed by Contractor: 1. Contractor' Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team. 2. Contractor's Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through ...”
01 91 00 1.8.B255–
Test / cert.Test / cert.Members Appointed by VA:General Commissioning Requirements01 91 00 1.8.C · PDF p. 255-256
Spec wording
“C. Members Appointed by VA: 1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA will engage the CxA under a separate contract. 2. User: Representatives of the facility user and operation and maintenance personnel. 3. A/E: Representative of the Architect and engineering design professionals.”
01 91 00 1.8.C255-256–
Test / cert.Test / cert.Appoint an individual, company or firm to act as the ...General Commissioning Requirements01 91 00 1.9.A · PDF p. 256
Spec wording
“A. Appoint an individual, company or firm to act as the Commissioning Agent”
01 91 00 1.9.A256–
Test / cert.Test / cert.Assign operation and maintenance personnel and schedule them to participate ...General Commissioning Requirements01 91 00 1.9.B · PDF p. 256
Spec wording
“B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following: 1. Coordination meetings. 2. Training in operation and maintenance of systems, subsystems, and equipment. 3. Testing meetings. 4. Witness and assist in Systems Functional Performance Testing. 5. Demonstration of operation of systems, subsystems, and equipment.”
01 91 00 1.9.B256–
Test / cert.Test / cert.Provide the Construction Documents, prepared by Architect and approved by ...General Commissioning Requirements01 91 00 1.9.C · PDF p. 256
Spec wording
“C. Provide the Construction Documents, prepared by Architect and approved by VA, to the Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.”
01 91 00 1.9.C256–
Test / cert.Test / cert.The Contractor shall assign a Commissioning Manager to manage commissioning ...General Commissioning Requirements01 91 00 1.10.A · PDF p. 256
Spec wording
“A. The Contractor shall assign a Commissioning Manager to manage commissioning activities of the Contractor, and subcontractors.”
01 91 00 1.10.A256–
Test / cert.Test / cert.The Contractor shall ensure that the commissioning responsibilities outlined in ...General Commissioning Requirements01 91 00 1.10.B · PDF p. 256
Spec wording
“B. The Contractor shall ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.”
01 91 00 1.10.B256–
Test / cert.Test / cert.The Contractor shall ensure that each installing subcontractor shall assign ...General Commissioning Requirements01 91 00 1.10.C · PDF p. 256-257
Spec wording
“C. The Contractor shall ensure that each installing subcontractor shall assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the following: 1. Participate in commissioning coordination meetings. 2. Conduct operation and maintenance training sessions in accordance with ...”
01 91 00 1.10.C256-257–
Test / cert.Test / cert.Organize and lead the commissioning teamGeneral Commissioning Requirements01 91 00 1.11.A · PDF p. 257
Spec wording
“A. Organize and lead the commissioning team.”
01 91 00 1.11.A257–
Test / cert.Test / cert.Prepare the commissioning plan. See Paragraph 1.11-A of this specification ...General Commissioning Requirements01 91 00 1.11.B · PDF p. 257
Spec wording
“B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.”
01 91 00 1.11.B257–
Test / cert.Test / cert.Review and comment on selected submittals from the Contractor for ...General Commissioning Requirements01 91 00 1.11.C · PDF p. 257
Spec wording
“C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems ...”
01 91 00 1.11.C257–
Test / cert.Test / cert.At the beginning of the construction phase, conduct an initial ...General Commissioning Requirements01 91 00 1.11.D · PDF p. 257-258
Spec wording
“D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre-Functional Checklists, Systems Functional Performance Testing; and project completion.”
01 91 00 1.11.D257-258–
Test / cert.Test / cert.Convene commissioning team meetings for the purpose of coordination, communication, ...General Commissioning Requirements01 91 00 1.11.E · PDF p. 258
Spec wording
“E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The Commissioning Agent shall prepare and distribute minutes to commissioning team members and attendees within five workdays of the ...”
01 91 00 1.11.E258–
Test / cert.Test / cert.Observe construction and report progress, observations and issues. Observe systems ...General Commissioning Requirements01 91 00 1.11.F · PDF p. 258
Spec wording
“F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.”
01 91 00 1.11.F258–
Test / cert.Test / cert.Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test ...General Commissioning Requirements01 91 00 1.11.G · PDF p. 258
Spec wording
“G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.”
01 91 00 1.11.G258–
Test / cert.Test / cert.Coordinate Systems Functional Performance Testing schedule with the Contractor ...General Commissioning Requirements01 91 00 1.11.H · PDF p. 258
Spec wording
“H. Coordinate Systems Functional Performance Testing schedule with the Contractor.”
01 91 00 1.11.H258–
Test / cert.Test / cert.Witness selected systems startupsGeneral Commissioning Requirements01 91 00 1.11.I · PDF p. 258
Spec wording
“I. Witness selected systems startups.”
01 91 00 1.11.I258–
Test / cert.Test / cert.Verify selected Pre-Functional Checklists completed and submitted by the Contractor ...General Commissioning Requirements01 91 00 1.11.J · PDF p. 258
Spec wording
“J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.”
01 91 00 1.11.J258–
Test / cert.Test / cert.Witness and document Systems Functional Performance TestingGeneral Commissioning Requirements01 91 00 1.11.K · PDF p. 258
Spec wording
“K. Witness and document Systems Functional Performance Testing.”
01 91 00 1.11.K258–
Test / cert.Test / cert.Compile test data, inspection reports, and certificates and include them ...General Commissioning Requirements01 91 00 1.11.L · PDF p. 258
Spec wording
“L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.”
01 91 00 1.11.L258–
Test / cert.Test / cert.Review and comment on operation and maintenance (O&M) documentation and ...General Commissioning Requirements01 91 00 1.11.M · PDF p. 258
Spec wording
“M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.”
01 91 00 1.11.M258–
Test / cert.Test / cert.Review operation and maintenance training program developed by the Contractor. ...General Commissioning Requirements01 91 00 1.11.N · PDF p. 258
Spec wording
“N. Review operation and maintenance training program developed by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.”
01 91 00 1.11.N258–
Test / cert.Test / cert.Prepare commissioning Field Observation ReportsGeneral Commissioning Requirements01 91 00 1.11.O · PDF p. 258
Spec wording
“O. Prepare commissioning Field Observation Reports.”
01 91 00 1.11.O258–
Test / cert.Test / cert.Prepare the Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.11.P · PDF p. 258
Spec wording
“P. Prepare the Final Commissioning Report.”
01 91 00 1.11.P258–
Test / cert.Test / cert.Return to the site at 10 months into the 12 ...General Commissioning Requirements01 91 00 1.11.Q · PDF p. 258-259
Spec wording
“Q. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Systems Functional Performance Testing. Also interview facility staff and identify problems or concerns they have operating the building as originally intended. Make suggestions for improvements and for ...”
01 91 00 1.11.Q258-259–
Test / cert.Test / cert.Assemble the final commissioning documentation, including the Final Commissioning Report ...General Commissioning Requirements01 91 00 1.11.R · PDF p. 259
Spec wording
“R. Assemble the final commissioning documentation, including the Final Commissioning Report and Addendum to the Final Commissioning Report.”
01 91 00 1.11.R259–
Test / cert.Test / cert.Commissioning PlanGeneral Commissioning Requirements01 91 00 1.12.A · PDF p. 259-260
Spec wording
“A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited, to the following: 1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a ...”
01 91 00 1.12.A259-260–
Test / cert.Test / cert.Systems Functional Performance Test ProceduresGeneral Commissioning Requirements01 91 00 1.12.B · PDF p. 260
Spec wording
“B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested. Preliminary Systems Functional ...”
01 91 00 1.12.B260–
Test / cert.Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.12.C · PDF p. 260
Spec wording
“C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre-Functional Checklists. Pre-Functional Checklists shall be completed and signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing. Inaccurate or incomplete Pre-Functional ...”
01 91 00 1.12.C260–
Test / cert.Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.12.D · PDF p. 260-261
Spec wording
“D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application shall be included with data. Commissioning Agent Will compile test and inspection reports and test and ...”
01 91 00 1.12.D260-261–
Test / cert.Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.12.E · PDF p. 261
Spec wording
“E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results.”
01 91 00 1.12.E261–
Test / cert.Test / cert.Commissioning Issues LogGeneral Commissioning Requirements01 91 00 1.12.F · PDF p. 261-262
Spec wording
“F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues Log will identify and track issues as they are ...”
01 91 00 1.12.F261-262–
Test / cert.Test / cert.Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.G · PDF p. 262
Spec wording
“G. Final Commissioning Report: The Commissioning Agent will document results of the commissioning process, including unresolved issues, and performance of systems, subsystems, and equipment. The Commissioning Report will indicate whether systems, subsystems, and equipment have been properly installed and are performing according to the Contract Documents. This report will be used by the Department of Veterans ...”
01 91 00 1.12.G262–
Test / cert.Test / cert.Addendum to Final Commissioning ReportGeneral Commissioning Requirements01 91 00 1.12.H · PDF p. 263
Spec wording
“H. Addendum to Final Commissioning Report: The Commissioning Agent will prepare an Addendum to the Final Commissioning Report near the end of the Warranty Period. The Addendum will indicate whether systems, subsystems, and equipment are complete and continue to perform according to the Contract Documents. The Addendum to the Final Commissioning Report shall include, but is not limited to, the following: 1. ...”
01 91 00 1.12.H263–
Test / cert.Test / cert.Systems ManualGeneral Commissioning Requirements01 91 00 1.12.I · PDF p. 263
Spec wording
“I. Systems Manual: The Commissioning Agent will gather required information and compile the Systems Manual. The Systems Manual will include, but is not limited to, the following: 1. Design Narrative, including system narratives, schematics, single-line diagrams, flow diagrams, equipment schedules, and changes made throughout the Project. 2. Reference to Final Commissioning Plan. 3. Reference to Final Commissioning ...”
01 91 00 1.12.I263–
Test / cert.Test / cert.Preliminary Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.A · PDF p. 263-264
Spec wording
“A. Preliminary Commissioning Plan Submittal: The Commissioning Agent has prepared a Preliminary Commissioning Plan based on the final Construction Documents. The Preliminary Commissioning Plan is included as an Appendix to this specification section. The Preliminary Commissioning Plan is provided for information only. It contains preliminary information about the following commissioning activities: 1. The ...”
01 91 00 1.13.A263-264–
Test / cert.Test / cert.Final Commissioning Plan SubmittalGeneral Commissioning Requirements01 91 00 1.13.B · PDF p. 264
Spec wording
“B. Final Commissioning Plan Submittal: Based on the Final Construction Documents and the Contractor's project team, the Commissioning Agent will prepare the Final Commissioning Plan as described in this section. The Commissioning Agent will submit three hard copies and three sets of electronic files of Final Commissioning Plan. The Contractor shall review the Commissioning Plan and provide any comments to the VA. ...”
01 91 00 1.13.B264three hard copies; three sets; electronic files
Test / cert.Test / cert.Systems Functional Performance Test ProcedureGeneral Commissioning Requirements01 91 00 1.13.C · PDF p. 264-265
Spec wording
“C. Systems Functional Performance Test Procedure: The Commissioning Agent will submit preliminary Systems Functional Performance Test Procedures to the Contractor, and the VA for review and comment. The Contractor shall return review comments to the VA and the Commissioning Agent. The VA will also return review comments to the Commissioning Agent. The Commissioning Agent will incorporate review comments into the ...”
01 91 00 1.13.C264-265–
Test / cert.Test / cert.Pre-Functional ChecklistsGeneral Commissioning Requirements01 91 00 1.13.D · PDF p. 265
Spec wording
“D. Pre-Functional Checklists: The Commissioning Agent will submit Pre-Functional Checklists to be completed by the Contractor.”
01 91 00 1.13.D265–
Test / cert.Test / cert.Test and Inspection ReportsGeneral Commissioning Requirements01 91 00 1.13.E · PDF p. 265
Spec wording
“E. Test and Inspection Reports: The Commissioning Agent will submit test and inspection reports to the VA with copies to the Contractor and the Architect/Engineer.”
01 91 00 1.13.E265–
Test / cert.Test / cert.Corrective Action DocumentsGeneral Commissioning Requirements01 91 00 1.13.F · PDF p. 265
Spec wording
“F. Corrective Action Documents: The Commissioning Agent will submit corrective action documents to the VA Resident Engineer with copies to the Contractor and Architect.”
01 91 00 1.13.F265–
Test / cert.Test / cert.Preliminary Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.G · PDF p. 265
Spec wording
“G. Preliminary Commissioning Report Submittal: The Commissioning Agent will submit three electronic copies of the preliminary commissioning report. One electronic copy, with review comments, will be returned to the Commissioning Agent for preparation of the final submittal.”
01 91 00 1.13.G265three electronic copies; One electronic copy
Test / cert.Test / cert.Final Commissioning Report SubmittalGeneral Commissioning Requirements01 91 00 1.13.H · PDF p. 265
Spec wording
“H. Final Commissioning Report Submittal: The Commissioning Agent will submit four sets of electronically formatted information of the final commissioning report to the VA. The final submittal will incorporate comments as directed by the VA.”
01 91 00 1.13.H265four sets; electronically
Test / cert.Test / cert.Data for Commissioning:General Commissioning Requirements01 91 00 1.13.I · PDF p. 265
Spec wording
“I. Data for Commissioning: 1. The Commissioning Agent will request in writing from the Contractor specific information needed about each piece of commissioned equipment or system to fulfill requirements of the Commissioning Plan. 2. The Commissioning Agent may request further documentation as is necessary for the commissioning process or to support other VA data collection requirements, including Construction ...”
01 91 00 1.13.I265–
Test / cert.Test / cert.The Commissioning Agent will be responsible for the overall management ...General Commissioning Requirements01 91 00 1.14.A · PDF p. 265-266
Spec wording
“A. The Commissioning Agent will be responsible for the overall management of the commissioning process as well as coordinating scheduling of commissioning tasks with the VA and the Contractor. As directed by the VA, the Contractor shall incorporate Commissioning tasks, including, but not limited to, Systems Functional Performance Testing (including predecessors) with the Master Construction Schedule.”
01 91 00 1.14.A265-266–
Test / cert.Test / cert.Within 14 days of contract award, the Contractor shall designate ...General Commissioning Requirements01 91 00 1.14.B · PDF p. 266
Spec wording
“B. Within 14 days of contract award, the Contractor shall designate a specific individual as the Commissioning Manager (CxM) to manage and lead the commissioning effort on behalf of the Contractor. The Commissioning Manager shall be the single point of contact and communications for all commissioning related services by the Contractor.”
01 91 00 1.14.B266–
Test / cert.Test / cert.Within 21 days of contract award, the Contractor shall ensure ...General Commissioning Requirements01 91 00 1.14.C · PDF p. 266
Spec wording
“C. Within 21 days of contract award, the Contractor shall ensure that each subcontractor designates specific individuals as Commissioning Representatives (CXR) to be responsible for commissioning related tasks. The Contractor shall ensure the designated Commissioning Representatives participate in the commissioning process as team members providing commissioning testing services, equipment operation, adjustments, ...”
01 91 00 1.14.C266–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.A · PDF p. 269
Spec wording
“A. The following table outlines the roles and responsibilities for the Commissioning Team members during the Construction Phase: Construction Phase CxA = Commissioning Agent L = Lead RE = Resident Engineer P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M ...”
01 91 00 3.1.A269–
Test / cert.Test / cert.H. Quillen VAMC Renovate B200 Ground Floor Bronch Procedure Room ...General Commissioning Requirements01 91 00 3.1.J · PDF p. 270
Spec wording
“J. H. Quillen VAMC Renovate B200 Ground Floor Bronch Procedure Room Mt. Home, TN 37604 Construction Phase Commissioning Roles & Responsibilities Category Task Description Document TAB Plan Review Reviews Submittal and Shop Drawing Review Review Contractor Equipment Startup Checklists Review Change Orders, ASI, and RFI Site Witness Factory Testing Observations Construction Observation Site Visits Functional Final ...”
01 91 00 3.1.J270–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.B · PDF p. 271-272
Spec wording
“B. The following table outlines the roles and responsibilities for the Commissioning Team members during the Acceptance Phase: Acceptance Phase CxA = Commissioning Agent L = Lead RE = Resident Engineer P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M Notes ...”
01 91 00 3.1.B271-272–
Test / cert.Test / cert.The following table outlines the roles and responsibilities for the ...General Commissioning Requirements01 91 00 3.1.C · PDF p. 273
Spec wording
“C. The following table outlines the roles and responsibilities for the Commissioning Team members during the Warranty Phase: Warranty Phase CxA = Commissioning Agent L = Lead RE = Resident Engineer P = Participate A/E = Design Arch/Engineer A = Approve Commissioning Roles & Responsibilities PC = Prime Contractor R = Review O&M = Gov't Facility O&M O = Optional Category Task Description CxA RE A/E PC O&M Notes ...”
01 91 00 3.1.C273–
Test / cert.Test / cert.The following procedures shall apply to all equipment and systems ...General Commissioning Requirements01 91 00 3.2.A · PDF p. 274-275
Spec wording
“A. The following procedures shall apply to all equipment and systems to be commissioned, according to Part 1, Systems to Be Commissioned. 1. Pre-Functional Checklists are important to ensure that the equipment and systems are hooked up and operational. These ensure that Systems Functional Performance Testing may proceed without unnecessary delays. Each system to be commissioned shall have a full Pre-Functional ...”
01 91 00 3.2.A274-275–
Test / cert.Test / cert.The Contractor shall clearly list any outstanding items of the ...General Commissioning Requirements01 91 00 3.3.A · PDF p. 275
Spec wording
“A. The Contractor shall clearly list any outstanding items of the initial startup and Pre-Functional Checklist procedures that were not completed successfully, at the bottom of the procedures form or on an attached sheet. The procedures form and any outstanding deficiencies shall be provided to the VA and the Commissioning Agent within two days of completion.”
01 91 00 3.3.A275–
Test / cert.Test / cert.The Commissioning Agent will review the report and submit comments ...General Commissioning Requirements01 91 00 3.3.B · PDF p. 276
Spec wording
“B. The Commissioning Agent will review the report and submit comments to the VA. The Commissioning Agent will work with the Contractor to correct and verify deficiencies or uncompleted items. The Commissioning Agent will involve the VA and others as necessary. The Contractor shall correct all areas that are noncompliant or incomplete in the checklists in a timely manner, and shall notify the VA and Commissioning ...”
01 91 00 3.3.B276–
Test / cert.Test / cert.The Contractor shall be responsible for resolution of deficiencies as ...General Commissioning Requirements01 91 00 3.3.C · PDF p. 276
Spec wording
“C. The Contractor shall be responsible for resolution of deficiencies as directed the VA.”
01 91 00 3.3.C276–
Test / cert.Test / cert.The project may require startup and initial checkout to be ...General Commissioning Requirements01 91 00 3.4.A · PDF p. 276
Spec wording
“A. The project may require startup and initial checkout to be executed in phases. This phasing shall be planned and scheduled in a coordination meeting of the VA, Commissioning Agent, and the Contractor. Results will be added to the master construction schedule and the commissioning schedule.”
01 91 00 3.4.A276–
Test / cert.Test / cert.Trending is a method of testing as a standalone method ...General Commissioning Requirements01 91 00 3.5.A · PDF p. 276
Spec wording
“A. Trending is a method of testing as a standalone method or to augment manual testing. The Contractor shall trend any and all points of the system or systems at intervals specified below.”
01 91 00 3.5.A276–
Test / cert.Test / cert.Alarms are a means to notify the system operator that ...General Commissioning Requirements01 91 00 3.5.B · PDF p. 276-277
Spec wording
“B. Alarms are a means to notify the system operator that abnormal conditions are present in the system. Alarms shall be structured into three tiers – Critical, Priority, and Maintenance. 1. Critical alarms are intended to be alarms that require the immediate attention of and action by the Operator. These alarms shall be displayed on the Operator Workstation in a popup style window that is graphically linked to the ...”
01 91 00 3.5.B276-277–
Test / cert.Test / cert.The Contractor shall provide a wireless internet network in the ...General Commissioning Requirements01 91 00 3.5.C · PDF p. 277
Spec wording
“C. The Contractor shall provide a wireless internet network in the building for use during controls programming, checkout, and commissioning. This network will allow project team members to more effectively program, view, manipulate and test control devices while being in the same room as the controlled device.”
01 91 00 3.5.C277–
Test / cert.Test / cert.The Contractor shall provide graphical trending through the DDC control ...General Commissioning Requirements01 91 00 3.5.D · PDF p. 277-282
Spec wording
“D. The Contractor shall provide graphical trending through the DDC control system of systems being commissioned. Trending requirements are indicated below and included with the Systems Functional Performance Test Procedures. Trending shall occur before, during and after Systems Functional Performance Testing. The Contractor shall be responsible for producing graphical representations of the trended DDC points that ...”
01 91 00 3.5.D277-282–
Test / cert.Test / cert.The Contractor shall provide the following information prior to Systems ...General Commissioning Requirements01 91 00 3.5.E · PDF p. 282-283
Spec wording
“E. The Contractor shall provide the following information prior to Systems Functional Performance Testing. Any documentation that is modified after submission shall be recorded and resubmitted to the Resident Engineer and Commissioning Agent. 1. Point-to-Point checkout documentation; 2. Sensor field calibration documentation including system name, sensor/point name, measured value, DDC value, and Correction Factor. ...”
01 91 00 3.5.E282-283–
O&MO&MTraining Preparation ConferenceGeneral Commissioning Requirements01 91 00 3.9.A · PDF p. 291
Spec wording
“A. Training Preparation Conference: Before operation and maintenance training, the Commissioning Agent will convene a training preparation conference to include VA's Resident Engineer, VA's Operations and Maintenance personnel, and the Contractor. The purpose of this conference will be to discuss and plan for Training and Demonstration of VA Operations and Maintenance personnel.”
01 91 00 3.9.A291–
O&MO&MThe Contractor shall provide training and demonstration as required by ...General Commissioning Requirements01 91 00 3.9.B · PDF p. 291
Spec wording
“B. The Contractor shall provide training and demonstration as required by other Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 sections. The Training and Demonstration shall include, but is not limited to, the following: 1. Review the Contract Documents. 2. Review installed systems, subsystems, and equipment. 3. Review instructor qualifications. 4. Review instructional ...”
01 91 00 3.9.B291–
O&MO&MTraining Module SubmittalsGeneral Commissioning Requirements01 91 00 3.9.C · PDF p. 291-292
Spec wording
“C. Training Module Submittals: The Contractor shall submit the following information to the VA and the Commissioning Agent: 1. Instruction Program: Submit two copies of outline of instructional program for demonstration and training, including a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training ...”
01 91 00 3.9.C291-292two copies; DVD; 3-ring; binders; binder
O&MO&MQuality Assurance:General Commissioning Requirements01 91 00 3.9.D · PDF p. 292-293
Spec wording
“D. Quality Assurance: 1. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. 2. Instructor Qualifications: A factory authorized service representative, complying with ...”
01 91 00 3.9.D292-293–
O&MO&MTraining Coordination:General Commissioning Requirements01 91 00 3.9.E · PDF p. 293
Spec wording
“E. Training Coordination: 1. Coordinate instruction schedule with VA's operations. Adjust schedule as required to minimize disrupting VA's operations. 2. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. 3. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction ...”
01 91 00 3.9.E293–
O&MO&MInstruction Program:General Commissioning Requirements01 91 00 3.9.F · PDF p. 293
Spec wording
“F. Instruction Program: 1. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections, and as follows: a. Fire protection systems, including fire alarm, fire pumps, and fire suppression systems. b. Intrusion detection systems. c. Conveying systems, including elevators, wheelchair ...”
01 91 00 3.9.F293–
O&MO&MTraining ModulesGeneral Commissioning Requirements01 91 00 3.9.G · PDF p. 294-296
Spec wording
“G. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participants are expected to master. For each module, include instruction for the following: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment descriptions. b. Performance and design criteria if ...”
01 91 00 3.9.G294-296–
O&MO&MTraining Execution:General Commissioning Requirements01 91 00 3.9.H · PDF p. 296-297
Spec wording
“H. Training Execution: 1. Preparation: Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a combined training manual. Set up instructional equipment at instruction location. 2. Instruction: a. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate ...”
01 91 00 3.9.H296-297–
O&MO&MDemonstration and Training Recording:General Commissioning Requirements01 91 00 3.9.I · PDF p. 297-298
Spec wording
“I. Demonstration and Training Recording: 1. General: Engage a qualified commercial photographer to record demonstration and training. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. At beginning of each training module, record each chart containing learning objective and lesson outline. 2. Video Format: ...”
01 91 00 3.9.I297-298DVD

Division 02 Existing conditions 2 items

TypeItemSpec sectionPDF pageCopies / format
Closeout stepCloseout stepInventory of items that have been removed and salvagedSelective Demolition02 41 19 1.5.A · PDF p. 299
Spec wording
“A. Inventory of items that have been removed and salvaged.”
02 41 19 1.5.A299–
WarrantyWarrantyExisting WarrantiesSelective Demolition02 41 19 1.7.A · PDF p. 300
Spec wording
“A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.”
02 41 19 1.7.A300–

Division 07 Roofing, insulation and waterproofing 7 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyConstruction WarrantyThermal Insulation07 21 13 1.7.A · PDF p. 306
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
07 21 13 1.7.A306–
Test / cert.Test / cert.Certified laboratory test reports for ASTM E814 tests for systems ...Firestopping07 84 00 1.3.F · PDF p. 311
Spec wording
“F. Certified laboratory test reports for ASTM E814 tests for systems not listed by FM, UL, or WH proposed for use.”
07 84 00 1.3.F311–
Test / cert.Test / cert.Furnish service of approved inspector to inspect firestopping in accordance ...Firestopping07 84 00 3.5.B · PDF p. 316
Spec wording
“B. Furnish service of approved inspector to inspect firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results. Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers.”
07 84 00 3.5.B316–
WarrantyWarrantyManufacturer warrantyJoint Sealants07 92 00 1.5.G · PDF p. 318
Spec wording
“G. Manufacturer warranty.”
07 92 00 1.5.G318–
WarrantyWarrantyConstruction WarrantyJoint Sealants07 92 00 1.9.A · PDF p. 319
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
07 92 00 1.9.A319–
WarrantyWarrantyManufacturer WarrantyJoint Sealants07 92 00 1.9.B · PDF p. 319
Spec wording
“B. Manufacturer Warranty: Manufacturer shall warranty their sealant for a minimum of five (5) years from the date of installation and final acceptance by the Government. Submit manufacturer warranty.”
07 92 00 1.9.B319–
Test / cert.Test / cert.Inspect tested joints and report on following:Joint Sealants07 92 00 3.6.C · PDF p. 326
Spec wording
“C. Inspect tested joints and report on following: 1. Whether sealants in joints connected to pulled-out portion failed to adhere to joint substrates or tore cohesively. Include data on pull distance used to test each type of product and joint substrate. 2. Compare these results to determine if adhesion passes sealant manufacturer's field-adhesion hand-pull test criteria. 3. Whether sealants filled joint cavities ...”
07 92 00 3.6.C326–

Division 08 Doors, windows and hardware 15 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test reportsHollow Metal Doors And Frames08 11 13 1.4.E · PDF p. 330
Spec wording
“E. Test reports: Certify each product complies with specifications. 1. Sound rated door.”
08 11 13 1.4.E330–
WarrantyWarrantyConstruction WarrantyHollow Metal Doors And Frames08 11 13 1.8.A · PDF p. 331
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 11 13 1.8.A331–
Test / cert.Test / cert.Test ReportsInterior Wood Doors08 14 00 1.4.F · PDF p. 340
Spec wording
“F. Test Reports: Indicate each product complies with specifications. 1. Screw Holding Capacity Test. 2. Cycle-Slam Test. 3. Hinge-Loading Test.”
08 14 00 1.4.F340–
O&MO&MOperation and Maintenance Data:Interior Wood Doors08 14 00 1.4.G · PDF p. 340
Spec wording
“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
08 14 00 1.4.G340–
WarrantyWarrantyConstruction WarrantyInterior Wood Doors08 14 00 1.9.A · PDF p. 341
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 14 00 1.9.A341–
WarrantyWarrantyManufacturer's WarrantyInterior Wood Doors08 14 00 1.9.B · PDF p. 341
Spec wording
“B. Manufacturer's Warranty: Warrant interior factory finished flush wood doors against material and manufacturing defects. 1. Warranty Period: Lifetime of original installation.”
08 14 00 1.9.B341–
WarrantyWarrantyConstruction WarrantyAccess Doors And Frames08 31 13 1.8.A · PDF p. 348
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
08 31 13 1.8.A348–
WarrantyWarrantyWarranty DocumentationSpecial Function Doors08 34 00 1.3.F · PDF p. 354
Spec wording
“F. Warranty Documentation: Submit manufacturer's standard warranty.”
08 34 00 1.3.F354–
Test / cert.Test / cert.Test ReportsSpecial Function Doors08 34 00 1.3.G · PDF p. 354
Spec wording
“G. Test Reports: Submit acoustical reports or UL1784 as applicable.”
08 34 00 1.3.G354–
WarrantyWarrantyAutomatic door operators shall be subject to the terms of ...Door Hardware08 71 00 1.4.A · PDF p. 358
Spec wording
“A. Automatic door operators shall be subject to the terms of FAR Clause 52.246-21, except that the Warranty period shall be two years in lieu of one year for all items except as noted below: 1. Locks, latchsets, and panic hardware: 5 years. 2. Door closers and continuous hinges: 10 years.”
08 71 00 1.4.A358–
O&MO&MIn accordance with Section 01 00 00, GENERAL REQUIREMENTS Article ...Door Hardware08 71 00 1.5.A · PDF p. 358
Spec wording
“A. In accordance with Section 01 00 00, GENERAL REQUIREMENTS Article titled "INSTRUCTIONS", furnish maintenance manuals and instructions on all door hardware. Provide installation instructions with the submittal documentation.”
08 71 00 1.5.A358–
Test / cert.Test / cert.Certificate of Compliance and Test ReportsDoor Hardware08 71 00 1.6.D · PDF p. 359
Spec wording
“D. Certificate of Compliance and Test Reports: Submit certificates that hardware conforms to the requirements specified herein. Certificates shall be accompanied by copies of reports as referenced. The testing shall have been conducted either in the manufacturer's plant and certified by an independent testing laboratory or conducted in an independent laboratory, within four years of submittal of reports for approval.”
08 71 00 1.6.D359–
Closeout stepCloseout stepHardware Set Symbols on DrawingsDoor Hardware08 71 00 1.9.A · PDF p. 359-360
Spec wording
“A. Hardware Set Symbols on Drawings: Except for protective plates, door stops, mutes, thresholds and the like specified herein, hardware requirements for each door are indicated on drawings by symbols. Symbols for hardware sets consist of letters (e.g., "HW") followed by a number. Each number designates a set of hardware items applicable to a door type.”
08 71 00 1.9.A359-360–
Spare partsSpare partsKeyingDoor Hardware08 71 00 1.9.B · PDF p. 360
Spec wording
“B. Keying: A new Great Grandmaster key shall be established for this project. The key system shall be small format (Best size and profile) removable core type as previously described. The key blanks shall be protected by a utility patent with a minimum seven years remaining on the patent from the start of construction, and protected by contract-controlled distribution. The manufacturer shall furnish code pattern ...”
08 71 00 1.9.B360electronic format
TrainingTrainingDemonstrate efficacy of mechanical hardware and electrical, and electronic hardware ...Door Hardware08 71 00 3.4.A · PDF p. 376
Spec wording
“A. Demonstrate efficacy of mechanical hardware and electrical, and electronic hardware systems, including adjustment and maintenance procedures, to satisfaction of Resident/Project Engineer and VA Locksmith.”
08 71 00 3.4.A376–

Division 09 Finishes 9 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyTest Data:Subsurface Preparation For Floor Finishes09 05 16 1.3.D · PDF p. 381
Spec wording
“D. Test Data: 1. Moisture test and pH results performed by a qualified independent testing agency or warranty holding manufacturer's technical representative.”
09 05 16 1.3.D381–
WarrantyWarrantyManufacturer's Literature and Data:Acoustical Ceilings09 51 00 1.5.C · PDF p. 414
Spec wording
“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Ceiling suspension system indicating manufacturer recommendation for each application. 3. Installation instructions. 4. Warranty.”
09 51 00 1.5.C414–
O&MO&MOperation and Maintenance Data:Acoustical Ceilings09 51 00 1.5.H · PDF p. 415
Spec wording
“H. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
09 51 00 1.5.H415–
WarrantyWarrantyConstruction WarrantyAcoustical Ceilings09 51 00 1.10.A · PDF p. 416
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
09 51 00 1.10.A416–
O&MO&MOperation and Maintenance Data:Resilient Base And Accessories09 65 13 1.4.E · PDF p. 423
Spec wording
“E. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
09 65 13 1.4.E423–
WarrantyWarrantyConstruction WarrantyResilient Base And Accessories09 65 13 1.8.A · PDF p. 424
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
09 65 13 1.8.A424–
WarrantyWarrantyConstruction WarrantyResilient Tile Flooring09 65 19 1.7.A · PDF p. 428
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".”
09 65 19 1.7.A428–
WarrantyWarrantySubmit in accordance with Section 01 33 23, SHOP DRAWINGS, ...Resinous Poured In Place Resilient Flooring (Res-4)09 67 23.40 1.3 · PDF p. 435-436
Spec wording
“Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Manufacturer's Literature and Data: 1. Description of each product to be provided. 2. Application and installation instructions. 3. Maintenance Instructions: Submit manufacturer's written instructions for recommended maintenance practices. Qualification Data: For Installer. Sustainable Submittal: 1. Product data for products ...”
09 67 23.40 1.3435-436–
WarrantyWarrantyWork subject to the terms of the Article "Warranty of ...Resinous Poured In Place Resilient Flooring (Res-4)09 67 23.40 1.7 · PDF p. 440
Spec wording
“Work subject to the terms of the Article "Warranty of Construction" FAR clause 52.246-21. Warranty: Manufacture shall furnish a single, written warranty covering the full assembly (including substrata) for both material and workmanship for a extended period of three (3) full years from date of installation, or provide a joint and several warranty signed on a single document by manufacturer and applicator jointly ...”
09 67 23.40 1.7440–

Division 10 Specialties 8 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyConstruction WarrantySignage10 14 00 1.6.A · PDF p. 474
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21, "Warranty of Construction".”
10 14 00 1.6.A474–
WarrantyWarrantyConstruction WarrantyCubicle Curtain Tracks10 21 23 1.4.A · PDF p. 485
Spec wording
“A. Construction Warranty: Cubicle curtain tracks are subject to the terms of the Article "Warranty of Construction," FAR clause 52.246-21.”
10 21 23 1.4.A485–
Test / cert.Test / cert.Test ReportWall And Door Protection10 26 00 1.4.E · PDF p. 489
Spec wording
“E. Test Report: Showing that resilient material complies with specified fire and safety code requirements.”
10 26 00 1.4.E489–
WarrantyWarrantyManufacturer's warrantyWall And Door Protection10 26 00 1.4.H · PDF p. 489
Spec wording
“H. Manufacturer's warranty.”
10 26 00 1.4.H489–
WarrantyWarrantyConstruction WarrantyWall And Door Protection10 26 00 1.6.A · PDF p. 490
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
10 26 00 1.6.A490–
WarrantyWarrantyManufacturer WarrantyWall And Door Protection10 26 00 1.6.B · PDF p. 490
Spec wording
“B. Manufacturer Warranty: Manufacturer shall warranty their wall and door protection for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer warranty.”
10 26 00 1.6.B490–
O&MO&MOperation and Maintenance Data:Toilet, Bath, And Laundry Accessories10 28 00 1.4.G · PDF p. 496
Spec wording
“G. Operation and Maintenance Data: 1. Care instructions for each exposed finish product.”
10 28 00 1.4.G496–
WarrantyWarrantyConstruction WarrantyToilet, Bath, And Laundry Accessories10 28 00 1.8.A · PDF p. 497
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
10 28 00 1.8.A497–

Division 11 Equipment 8 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyManufacturer's standard limited warranty unless indicated otherwiseHealthcare Equipment – Lead Apron Racks11 70 00 1.7.A · PDF p. 501
Spec wording
“A. Manufacturer's standard limited warranty unless indicated otherwise.”
11 70 00 1.7.A501–
O&MO&MOperation and Maintenance Data:Medical Gas Booms11 76 00 1.6.A · PDF p. 505
Spec wording
“A. Operation and Maintenance Data: 1. Submit to Owner complete maintenance and operating instructions for inclusion in the building Operation and Maintenance Manual specified in Section 01 00 02 - Standard General Requirements and 01 00 01 - Project Specific General Requirements. 2. As a minimum, include wiring diagrams, technical data sheets, and information for ordering replacement parts.”
11 76 00 1.6.A505–
Record docsRecord docsSubmit complete "As built" diagrams indicating all items of equipment, ...Medical Gas Booms11 76 00 1.6.B · PDF p. 505
Spec wording
“B. Submit complete "As built" diagrams indicating all items of equipment, their interconnecting wiring and interconnecting piping.”
11 76 00 1.6.B505–
WarrantyWarrantySubmit a five (5) year written warranty (1 year for ...Medical Gas Booms11 76 00 1.11.A · PDF p. 507
Spec wording
“A. Submit a five (5) year written warranty (1 year for parts and labour, 4 years for parts only), beginning from date of Substantial Performance of the Work, and executed by the Contractor, booms manufacturer and the installer agreeing to repair or replace components of booms systems that develop defects in materials or workmanship within the specified warranty period.”
11 76 00 1.11.A507–
Test / cert.Test / cert.Inspect installation for proper performance in accordance with CSA and ...Medical Gas Booms11 76 00 3.5.A · PDF p. 513
Spec wording
“A. Inspect installation for proper performance in accordance with CSA and NFPA requirements. Submit 2 written test results and certification of medical gas piping systems and outlets in accordance with CSA Z7396.1 and NFPA 99c.”
11 76 00 3.5.A513–
Test / cert.Test / cert.Submit two (2) written reports on the results of the ...Medical Gas Booms11 76 00 3.5.B · PDF p. 513
Spec wording
“B. Submit two (2) written reports on the results of the electrical safety testing and the installation inspection authored by equipment manufacturer's technician conforming to UL and CSA requirements.”
11 76 00 3.5.B513–
Test / cert.Test / cert.Obtain field reports within three days of review and submit ...Medical Gas Booms11 76 00 3.6.C · PDF p. 513
Spec wording
“C. Obtain field reports within three days of review and submit immediately to Engineer - Architect.”
11 76 00 3.6.C513–
TrainingTrainingAn authorized representative from the manufacturer shall train Owner's maintenance ...Medical Gas Booms11 76 00 3.7.A · PDF p. 514
Spec wording
“A. An authorized representative from the manufacturer shall train Owner's maintenance personnel to adjust, operate, and maintain patient bed service panels as specified.”
11 76 00 3.7.A514–

Division 12 Furnishings 9 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyManufacturer's warrantyManufactured Metal Casework12 31 00 1.4.F · PDF p. 516
Spec wording
“F. Manufacturer's warranty.”
12 31 00 1.4.F516–
WarrantyWarrantyConstruction WarrantyManufactured Metal Casework12 31 00 1.5.A · PDF p. 516
Spec wording
“A. Construction Warranty: Comply with FAR clause 52.246-21 "Warranty of Construction".”
12 31 00 1.5.A516–
WarrantyWarrantyManufacturer WarrantyManufactured Metal Casework12 31 00 1.5.B · PDF p. 517
Spec wording
“B. Manufacturer Warranty: Manufacturer shall warranty their wood casework for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer warranty. 1. Defects include, but are not limited to: a. Ruptured, cracked, or stained coating b. Discoloration or lack of finish integrity c. Cracking or peeling of finish d. Slippage, shift, or failure of attachment to wall, ...”
12 31 00 1.5.B517–
Closeout stepCloseout stepProvide operational and cleaning manuals and verbal instructions in accordance ...Manufactured Metal Casework12 31 00 3.7.A · PDF p. 529
Spec wording
“A. Provide operational and cleaning manuals and verbal instructions in accordance with Article INSTRUCTIONS, SECTION 01 00 00, GENERAL REQUIREMENTS.”
12 31 00 3.7.A529–
TrainingTrainingProvide in service training both prior to and after facility ...Manufactured Metal Casework12 31 00 3.7.B · PDF p. 529
Spec wording
“B. Provide in service training both prior to and after facility opening. Coordinate in service activities with COR.”
12 31 00 3.7.B529–
Closeout stepCloseout stepCommencing at least seven (7) days prior to opening of ...Manufactured Metal Casework12 31 00 3.7.C · PDF p. 529
Spec wording
“C. Commencing at least seven (7) days prior to opening of facility, provide one (1) 4-hour day of on-site orientation and technical instruction on use and cleaning procedures application of products and systems specified herein.”
12 31 00 3.7.C529–
O&MO&MOperations and Maintenance DataHealthcare Casework12 56 70 1.3.D · PDF p. 536
Spec wording
“D. Operations and Maintenance Data: Submit manufacturer's recommendations for cleaning and maintenance, including a list of spare parts and information for ordering.”
12 56 70 1.3.D536–
WarrantyWarrantyWarrantyHealthcare Casework12 56 70 1.3.E · PDF p. 536
Spec wording
“E. Warranty: Submit executed copy of manufacturer's standard limited warranty.”
12 56 70 1.3.E536–
WarrantyWarrantyModular Casework Limited WarrantyHealthcare Casework12 56 70 1.6.A · PDF p. 536
Spec wording
“A. Modular Casework Limited Warranty: Provide manufacturer's standard limited warranty for the items listed below, with additional exclusions as included in manufacturer's standard warranty. Furnish copies of warranties for components not manufactured by modular casework manufacturer but incorporated into the casework as applicable. 1. Door and drawer fronts, casters, 5 years. 2. accessories, 1 year.”
12 56 70 1.6.A536–

Division 13 Special construction 5 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantyManufacturer's Literature and Data:Radiation Protection13 49 00 1.5.C · PDF p. 540
Spec wording
“C. Manufacturer's Literature and Data: 1. Description of each product. 2. Installation instructions. 3. Warranty.”
13 49 00 1.5.C540–
Test / cert.Test / cert.Test ReportsRadiation Protection13 49 00 1.5.F · PDF p. 540-541
Spec wording
“F. Test Reports: Certify each product complies with specifications. 1. Lead control windows. 2. Cassette transfer cabinets. 3. Lead lined wood doors. 4. Hardware. 5. Lead lined door frames. 6. Thresholds. 7. Lead ray proof louvers.”
13 49 00 1.5.F540-541–
O&MO&MOperation and Maintenance Data:Radiation Protection13 49 00 1.5.I · PDF p. 541
Spec wording
“I. Operation and Maintenance Data: 1. Care instructions for each exposed finish product. 2. Start-up, maintenance, troubleshooting, emergency, and shut-down instructions for each operational product.”
13 49 00 1.5.I541–
WarrantyWarrantyConstruction WarrantyRadiation Protection13 49 00 1.7.A · PDF p. 541
Spec wording
“A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."”
13 49 00 1.7.A541–
WarrantyWarrantyManufacturer's WarrantyRadiation Protection13 49 00 1.7.B · PDF p. 541
Spec wording
“B. Manufacturer's Warranty: Warrant lead lined doors against material and manufacturing defects. 1. Defects Include: Warp or twist exceeding 6 mm (1/4 inch) in any face dimension of door (including full diagonal), measured minimum six months after doors have been hung and finished. 2. Warranty Period: Two years.”
13 49 00 1.7.B541–

Division 21 Fire suppression (sprinklers) 2 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MSubmit as one package in accordance with Section 01 33 ...Wet-Pipe Sprinkler Systems21 13 13 1.4.A · PDF p. 550-551
Spec wording
“A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting ...”
21 13 13 1.4.A550-551binders; electronically; pdf; full size; One complete set; AutoCAD
O&MO&MFurnish the services of a competent instructor for not less ...Wet-Pipe Sprinkler Systems21 13 13 3.3.A · PDF p. 558
Spec wording
“A. Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR. ---END---”
21 13 13 3.3.A558–

Division 22 Plumbing 39 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MPlumbing Maintenance Data and Operating Instructions:Common Work Results For Plumbing22 05 11 1.4.J · PDF p. 568-569
Spec wording
“J. Plumbing Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all ...”
22 05 11 1.4.J568-569–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.A · PDF p. 573
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 05 11 1.7.A573–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Plumbing22 05 11 1.7.B · PDF p. 573
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
22 05 11 1.7.B573electronic version; CD; DVD; binder
Record docsRecord docsThe installing Contractor shall maintain as-built drawings of each completed ...Common Work Results For Plumbing22 05 11 1.7.C · PDF p. 573-574
Spec wording
“C. The installing Contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
22 05 11 1.7.C573-574one paper copy; PDF; CD; DVD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Common Work Results For Plumbing22 05 11 1.7.D · PDF p. 574
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
22 05 11 1.7.D574–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Common Work Results For Plumbing22 05 11 1.7.E · PDF p. 574
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
22 05 11 1.7.E574–
Test / cert.Test / cert.Startup of equipment shall be performed as described in the ...Common Work Results For Plumbing22 05 11 3.9.A · PDF p. 591
Spec wording
“A. Startup of equipment shall be performed as described in the equipment specifications. Vibration within specified tolerance shall be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.”
22 05 11 3.9.A591–
O&MO&MAll new and temporary equipment and all elements of each ...Common Work Results For Plumbing22 05 11 3.11.A · PDF p. 591
Spec wording
“A. All new and temporary equipment and all elements of each assembly shall be included.”
22 05 11 3.11.A591–
O&MO&MData sheet on each device listing model, size, capacity, pressure, ...Common Work Results For Plumbing22 05 11 3.11.B · PDF p. 591
Spec wording
“B. Data sheet on each device listing model, size, capacity, pressure, speed, horsepower, impeller size, and other information shall be included.”
22 05 11 3.11.B591–
O&MO&MManufacturer's installation, maintenance, repair, and operation instructions for each device ...Common Work Results For Plumbing22 05 11 3.11.C · PDF p. 591
Spec wording
“C. Manufacturer's installation, maintenance, repair, and operation instructions for each device shall be included. Assembly drawings and parts lists shall also be included. A summary of operating precautions and reasons for precautions shall be included in the Operations and Maintenance Manual.”
22 05 11 3.11.C591–
O&MO&MLubrication instructions, type and quantity of lubricant shall be included ...Common Work Results For Plumbing22 05 11 3.11.D · PDF p. 592
Spec wording
“D. Lubrication instructions, type and quantity of lubricant shall be included.”
22 05 11 3.11.D592–
O&MO&MSchematic diagrams and wiring diagrams of all control systems corrected ...Common Work Results For Plumbing22 05 11 3.11.E · PDF p. 592
Spec wording
“E. Schematic diagrams and wiring diagrams of all control systems corrected to include all field modifications shall be included.”
22 05 11 3.11.E592–
O&MO&MSet points of all interlock devices shall be listedCommon Work Results For Plumbing22 05 11 3.11.F · PDF p. 592
Spec wording
“F. Set points of all interlock devices shall be listed.”
22 05 11 3.11.F592–
O&MO&MTrouble-shooting guide for the control system troubleshooting shall be inserted ...Common Work Results For Plumbing22 05 11 3.11.G · PDF p. 592
Spec wording
“G. Trouble-shooting guide for the control system troubleshooting shall be inserted into the Operations and Maintenance Manual.”
22 05 11 3.11.G592–
O&MO&MThe control system sequence of operation corrected with submittal review ...Common Work Results For Plumbing22 05 11 3.11.H · PDF p. 592
Spec wording
“H. The control system sequence of operation corrected with submittal review comments shall be inserted into the Operations and Maintenance Manual.”
22 05 11 3.11.H592–
O&MO&MEmergency procedures for shutdown and startup of equipment and systemsCommon Work Results For Plumbing22 05 11 3.11.I · PDF p. 592
Spec wording
“I. Emergency procedures for shutdown and startup of equipment and systems.”
22 05 11 3.11.I592–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Plumbing22 05 11 3.12.A · PDF p. 592
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 05 11 3.12.A592–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General-Duty Valves For Plumbing Piping22 05 23 1.4.E · PDF p. 596
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance. ...”
22 05 23 1.4.E596–
Test / cert.Test / cert.Testing and adjusting of balancing valves shall be performed by ...General-Duty Valves For Plumbing Piping22 05 23 3.4.D · PDF p. 608
Spec wording
“D. Testing and adjusting of balancing valves shall be performed by an independent NEBB Accredited Test and Balance Contractor. A final settings and flow report shall be submitted to the VA Contracting Officer's Representative (COR).”
22 05 23 3.4.D608–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General-Duty Valves For Plumbing Piping22 05 23 3.5.A · PDF p. 608
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
22 05 23 3.5.A608–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...General-Duty Valves For Plumbing Piping22 05 23 3.5.B · PDF p. 608
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
22 05 23 3.5.B608–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...General-Duty Valves For Plumbing Piping22 05 23 3.6.A · PDF p. 608
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system. ---END---”
22 05 23 3.6.A608–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.A · PDF p. 615
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 07 11 1.6.A615–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Plumbing Insulation22 07 11 1.6.B · PDF p. 615
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 07 11 1.6.B615electronic version; DVD; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Plumbing Insulation22 07 11 1.6.C · PDF p. 615
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version 2018 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall ...”
22 07 11 1.6.C615CAD; DVD
Record docsRecord docsCertification documentation shall be provided prior to submitting the request ...Plumbing Insulation22 07 11 1.6.D · PDF p. 615
Spec wording
“D. Certification documentation shall be provided prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.”
22 07 11 1.6.D615–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Water Distribution22 11 00 1.4.D · PDF p. 637
Spec wording
“D. Complete operating and maintenance manuals including wiring diagrams, technical data sheets and information for ordering replacement parts: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 11 00 1.4.D637–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Facility Water Distribution22 11 00 1.7.A · PDF p. 637
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
22 11 00 1.7.A637–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Facility Water Distribution22 11 00 1.7.B · PDF p. 637-638
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 11 00 1.7.B637-638electronic version; DVD; three-ring; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Facility Water Distribution22 11 00 1.7.C · PDF p. 638
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in Auto-CAD version 2018 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it ...”
22 11 00 1.7.C638CAD; DVD
Record docsRecord docsCertification documentation shall be provided to COR 10 working days ...Facility Water Distribution22 11 00 1.7.D · PDF p. 638
Spec wording
“D. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certificate if applicable that all results of tests were within limits specified. If a certificate is not ...”
22 11 00 1.7.D638–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Facility Water Distribution22 11 00 3.4.A · PDF p. 645
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.”
22 11 00 3.4.A645–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Facility Sanitary And Vent Piping22 13 00 1.4.E · PDF p. 651
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
22 13 00 1.4.E651–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 ...Facility Sanitary And Vent Piping22 13 00 1.6.A · PDF p. 651
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" of Section 22 05 11, COMMON WORK RESULTS FOR PLUMBING.”
22 13 00 1.6.A651–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Facility Sanitary And Vent Piping22 13 00 3.6.A · PDF p. 662
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
22 13 00 3.6.A662–
O&MO&MSubmit operation and maintenance data updated to include submittal review ...Plumbing Fixtures22 40 00 1.4.F · PDF p. 664-665
Spec wording
“F. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction revisions shall be in electronic version on compact disc or DVD inserted into a three ring binder. All aspects of system operation and maintenance procedures, including piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of ...”
22 40 00 1.4.F664-665electronic version; DVD; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Plumbing Fixtures22 40 00 1.4.G · PDF p. 665
Spec wording
“G. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them in AutoCAD version 2018 provided on compact disk or DVD. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall ...”
22 40 00 1.4.G665AutoCAD; DVD
Test / cert.Test / cert.Certification documentation shall be provided to COR 10 working days ...Plumbing Fixtures22 40 00 1.4.H · PDF p. 665
Spec wording
“H. Certification documentation shall be provided to COR 10 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and certification that all results of tests were within limits specified.”
22 40 00 1.4.H665–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Plumbing Fixtures22 40 00 3.3.A · PDF p. 668
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA Personnel in operation and maintenance of the system.”
22 40 00 3.3.A668–

Division 23 HVAC 85 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MHVAC Maintenance Data and Operating Instructions:Common Work Results For Hvac23 05 11 1.4.J · PDF p. 677-678
Spec wording
“J. HVAC Maintenance Data and Operating Instructions: 1. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment. 2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: a. Include complete list indicating all components ...”
23 05 11 1.4.J677-678–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.A · PDF p. 682
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
23 05 11 1.7.A682–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Common Work Results For Hvac23 05 11 1.7.B · PDF p. 682
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
23 05 11 1.7.B682electronic version; CD; DVD; three-ring; binder
Record docsRecord docsThe installing Contractor shall maintain as-built drawings of each completed ...Common Work Results For Hvac23 05 11 1.7.C · PDF p. 682-683
Spec wording
“C. The installing Contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing Contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
23 05 11 1.7.C682-683one paper copy; PDF; CD; DVD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Common Work Results For Hvac23 05 11 1.7.D · PDF p. 683
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
23 05 11 1.7.D683–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Common Work Results For Hvac23 05 11 1.7.E · PDF p. 683
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
23 05 11 1.7.E683–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Common Work Results For Hvac23 05 11 3.11.A · PDF p. 703
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 05 11 3.11.A703–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Common Work Results For Hvac23 05 11 3.11.B · PDF p. 703
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 05 11 3.11.B703–
Test / cert.Test / cert.Startup of equipment shall be performed as described in equipment ...Common Work Results For Hvac23 05 11 3.11.C · PDF p. 703
Spec wording
“C. Startup of equipment shall be performed as described in equipment specifications. Vibration within specified tolerance shall be verified prior to extended operation. Temporary use of equipment is specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT.”
23 05 11 3.11.C703–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Hvac23 05 11 3.13.A · PDF p. 704
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 05 11 3.13.A704–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.F · PDF p. 706-707
Spec wording
“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
23 05 12 1.4.F706-707–
Test / cert.Test / cert.CertificationGeneral Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.4.G · PDF p. 707
Spec wording
“G. Certification: Two weeks prior to final inspection, unless otherwise noted, certification shall be submitted to the COR stating that the motors have been properly applied, installed, adjusted, lubricated, and tested.”
23 05 12 1.4.G707–
Record docsRecord docsComply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 1.5.A · PDF p. 707
Spec wording
“A. Comply with requirements in Paragraph "AS-BUILT DOCUMENTATION" in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 05 12 1.5.A707–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.A · PDF p. 713
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 05 12 3.3.A713–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.3.B · PDF p. 713
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 05 12 3.3.B713–
TrainingTrainingProvide services of manufacturer's technical representative for one hour to ...General Motor Requirements For Hvac And Steam Generation Equipment23 05 12 3.4.A · PDF p. 713
Spec wording
“A. Provide services of manufacturer's technical representative for one hour to instruct each VA personnel responsible in operation and maintenance of the system.”
23 05 12 3.4.A713–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Noise And Vibration Control For Hvac Piping And Equipment23 05 41 1.6.A · PDF p. 718
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 05 41 1.6.A718–
TrainingTrainingCertification, training, and project experience resume of field shaft alignment ...Noise And Vibration Control For Boiler Plant23 05 51 1.4.D · PDF p. 724
Spec wording
“D. Certification, training, and project experience resume of field shaft alignment and or dynamic machine balancing technicians.”
23 05 51 1.4.D724–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Noise And Vibration Control For Boiler Plant23 05 51 1.4.F · PDF p. 725
Spec wording
“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
23 05 51 1.4.F725–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Noise And Vibration Control For Boiler Plant23 05 51 1.6.A · PDF p. 726
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
23 05 51 1.6.A726–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Noise And Vibration Control For Boiler Plant23 05 51 1.6.B · PDF p. 726
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
23 05 51 1.6.B726electronic version; CD; DVD; three-ring; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Noise And Vibration Control For Boiler Plant23 05 51 1.6.C · PDF p. 726-727
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
23 05 51 1.6.C726-727one paper copy; PDF; CD; DVD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Noise And Vibration Control For Boiler Plant23 05 51 1.6.D · PDF p. 727
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
23 05 51 1.6.D727–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Noise And Vibration Control For Boiler Plant23 05 51 1.6.E · PDF p. 727
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
23 05 51 1.6.E727–
WarrantyWarrantyLabor and materials for control systems shall be warranted for ...Direct-Digital Control System For Hvac23 09 23 1.6 · PDF p. 782-783
Spec wording
“Labor and materials for control systems shall be warranted for a period as specified under Warranty in FAR clause 52.246-21. Control system failures during the warranty period shall be adjusted, repaired, or replaced at no cost or reduction in service to the owner. The system includes all computer equipment, transmission equipment, and all sensors and control devices. The on-line support service shall allow the ...”
23 09 23 1.6782-783–
WarrantyWarrantySubmit shop drawings in accordance with Section 01 33 23, ...Direct-Digital Control System For Hvac23 09 23 1.7 · PDF p. 783-785
Spec wording
“Submit shop drawings in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Information and material submitted under this section shall be marked "SUBMITTED UNDER SECTION 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC", with applicable paragraph identification. Manufacturer's Literature and Data Including: 1. A wiring diagram for each type of input device and output device including DDC ...”
23 09 23 1.7783-785three (3) copies; one (1) set; CD-ROM; CAD; One copy
TrainingTrainingInstructions to VA operations personnelDirect-Digital Control System For Hvac23 09 23 1.8 · PDF p. 786-787
Spec wording
“Instructions to VA operations personnel: Perform in accordance with Article, INSTRUCTIONS, in Specification Section 01 00 00, GENERAL REQUIREMENTS, and as noted below. 1. First Phase: Formal instructions to the VA facilities personnel for a total of 16 hours, given in multiple training sessions (each no longer than four hours in length), conducted sometime between the completed installation and prior to the ...”
23 09 23 1.8786-787–
TrainingTrainingAs part of final system acceptance, a system demonstration is ...Direct-Digital Control System For Hvac23 09 23 3.2 · PDF p. 828-829
Spec wording
“As part of final system acceptance, a system demonstration is required (see below). Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the controls and instrumentation system. Validation 1. Prepare and submit for approval a validation test plan including test procedures for the performance verification tests. Test Plan shall be submitted for review with the ...”
23 09 23 3.2828-829–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Direct-Digital Control System For Hvac23 09 23 3.3 · PDF p. 830
Spec wording
“Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part. When any defects are detected, correct defects and repeat test at no additional cost or time to ...”
23 09 23 3.3830–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Direct-Digital Control System For Hvac23 09 23 3.4 · PDF p. 830
Spec wording
“Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in the operation and maintenance of the system.”
23 09 23 3.4830–
Record docsRecord docsAs-Built Piping DiagramsHydronic Piping23 21 13 1.4.G · PDF p. 836-837
Spec wording
“G. As-Built Piping Diagrams: Provide drawings as follows for chilled water, condenser water, and heating hot water system and other piping systems and equipment. 1. 1wall-mounted stick file with complete set of prints. Mount stick file in the chiller plant or control room along with control diagram stick file. 2. 1 complete set of reproducible drawings. 3. 1 complete set of drawings in electronic AutoCAD and pdf ...”
23 21 13 1.4.G836-8371 complete set; AutoCAD; pdf
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hydronic Piping23 21 13 1.4.H · PDF p. 837
Spec wording
“H. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
23 21 13 1.4.H837–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hydronic Piping23 21 13 1.6.A · PDF p. 837
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 21 13 1.6.A837–
Spare partsSpare partsFor mechanical pressed sealed fittings provide tools required for each ...Hydronic Piping23 21 13 1.7.A · PDF p. 837
Spec wording
“A. For mechanical pressed sealed fittings provide tools required for each pipe size used at the facility.”
23 21 13 1.7.A837–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hydronic Piping23 21 13 3.6.A · PDF p. 854
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 21 13 3.6.A854–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Hydronic Piping23 21 13 3.6.B · PDF p. 854
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 21 13 3.6.B854–
Test / cert.Test / cert.Adjust red set hand on pressure gauges to normal working pressureHydronic Piping23 21 13 3.6.C · PDF p. 854
Spec wording
“C. Adjust red set hand on pressure gauges to normal working pressure.”
23 21 13 3.6.C854–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Hydronic Piping23 21 13 3.7.A · PDF p. 854
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 21 13 3.7.A854–
Record docsRecord docsAs-Built Piping DiagramsSteam And Condensate Heating Piping23 22 13 1.4.F · PDF p. 858
Spec wording
“F. As-Built Piping Diagrams: Provide drawing as follows for steam and steam condensate piping and other central plant equipment. 1. One wall-mounted stick file for prints. Mount stick file in the chiller plant or adjacent control room along with control diagram stick file. 2. One set of reproducible drawings.”
23 22 13 1.4.F858One set
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Steam And Condensate Heating Piping23 22 13 1.4.G · PDF p. 858
Spec wording
“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.”
23 22 13 1.4.G858–
Record docsRecord docsSubmit manufacturer's literature and data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.A · PDF p. 859
Spec wording
“A. Submit manufacturer's literature and data updated to include submittal review comments and any equipment substitutions.”
23 22 13 1.6.A859–
Record docsRecord docsSubmit operation and maintenance data updated to include submittal review ...Steam And Condensate Heating Piping23 22 13 1.6.B · PDF p. 859
Spec wording
“B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and ...”
23 22 13 1.6.B859electronic version; CD; DVD; three-ring; binder
Record docsRecord docsThe installing contractor shall maintain as-built drawings of each completed ...Steam And Condensate Heating Piping23 22 13 1.6.C · PDF p. 859
Spec wording
“C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company' requirement. Provide record ...”
23 22 13 1.6.C859one paper copy; PDF; CD; DVD
Record docsRecord docsThe as-built drawings shall indicate the location and type of ...Steam And Condensate Heating Piping23 22 13 1.6.D · PDF p. 860
Spec wording
“D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.”
23 22 13 1.6.D860–
Record docsRecord docsCertification documentation shall be provided to COR 21 working days ...Steam And Condensate Heating Piping23 22 13 1.6.E · PDF p. 860
Spec wording
“E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall ...”
23 22 13 1.6.E860–
Test / cert.Test / cert.Prepare and submit test and inspection reports to the COR ...Steam And Condensate Heating Piping23 22 13 3.6.D · PDF p. 884
Spec wording
“D. Prepare and submit test and inspection reports to the COR within 5 working days of test completion and prior to covering the pipe.”
23 22 13 3.6.D884–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Steam And Condensate Heating Piping23 22 13 3.8.A · PDF p. 884
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 22 13 3.8.A884–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Steam And Condensate Heating Piping23 22 13 3.8.B · PDF p. 884
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 22 13 3.8.B884–
Test / cert.Test / cert.Adjust red set hand on pressure gauges to normal working pressureSteam And Condensate Heating Piping23 22 13 3.8.C · PDF p. 884
Spec wording
“C. Adjust red set hand on pressure gauges to normal working pressure.”
23 22 13 3.8.C884–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Steam And Condensate Heating Piping23 22 13 3.9.A · PDF p. 884
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 22 13 3.9.A884–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Ducts And Casings23 31 00 1.4.E · PDF p. 888
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 31 00 1.4.E888–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Ducts And Casings23 31 00 1.6.A · PDF p. 888
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 31 00 1.6.A888–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Fans23 34 00 1.4.G · PDF p. 901
Spec wording
“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 34 00 1.4.G901–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Fans23 34 00 1.6.A · PDF p. 902
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 34 00 1.6.A902–
Spare partsSpare partsProvide one additional set of belts for all belt-driven fansHvac Fans23 34 00 1.7.A · PDF p. 902
Spec wording
“A. Provide one additional set of belts for all belt-driven fans.”
23 34 00 1.7.A902one additional set
Test / cert.Test / cert.Verify operation of motor, drive system and fan wheel according ...Hvac Fans23 34 00 3.3.A · PDF p. 907
Spec wording
“A. Verify operation of motor, drive system and fan wheel according to the contract documents.”
23 34 00 3.3.A907–
Test / cert.Test / cert.Check vibration and correct as necessary for air balance workHvac Fans23 34 00 3.3.B · PDF p. 907
Spec wording
“B. Check vibration and correct as necessary for air balance work.”
23 34 00 3.3.B907–
Test / cert.Test / cert.After air balancing is complete and permanent sheaves are in ...Hvac Fans23 34 00 3.3.C · PDF p. 907
Spec wording
“C. After air balancing is complete and permanent sheaves are in place perform necessary field mechanical balancing to meet vibration tolerance in Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and EQUIPMENT.”
23 34 00 3.3.C907–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Fans23 34 00 3.3.D · PDF p. 908
Spec wording
“D. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 34 00 3.3.D908–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Fans23 34 00 3.3.E · PDF p. 908
Spec wording
“E. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 34 00 3.3.E908–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Hvac Fans23 34 00 3.4.A · PDF p. 908
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system. ---END---”
23 34 00 3.4.A908–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Terminal Units23 36 00 1.4.E · PDF p. 910
Spec wording
“E. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 36 00 1.4.E910–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Terminal Units23 36 00 1.6.A · PDF p. 910
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 36 00 1.6.A910–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Terminal Units23 36 00 3.2.A · PDF p. 914
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 36 00 3.2.A914–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Air Terminal Units23 36 00 3.2.B · PDF p. 914
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 36 00 3.2.B914–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Air Terminal Units23 36 00 3.3.A · PDF p. 914
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct each VA personnel responsible in operation and maintenance of the system.”
23 36 00 3.3.A914–
WarrantyWarrantySuppliers warrantyHvac Air Cleaning Devices23 40 00 1.4.E · PDF p. 916
Spec wording
“E. Suppliers warranty.”
23 40 00 1.4.E916–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Hvac Air Cleaning Devices23 40 00 1.4.F · PDF p. 916
Spec wording
“F. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 40 00 1.4.F916–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Hvac Air Cleaning Devices23 40 00 1.6.A · PDF p. 918
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 40 00 1.6.A918–
Test / cert.Test / cert.Clean and vacuum air handling units and plenums prior to ...Hvac Air Cleaning Devices23 40 00 3.2.A · PDF p. 928
Spec wording
“A. Clean and vacuum air handling units and plenums prior to starting air handling systems.”
23 40 00 3.2.A928–
Test / cert.Test / cert.Replace pre-filters and install clean filter units prior to final ...Hvac Air Cleaning Devices23 40 00 3.2.B · PDF p. 928
Spec wording
“B. Replace pre-filters and install clean filter units prior to final inspection as directed by the COR.”
23 40 00 3.2.B928–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Hvac Air Cleaning Devices23 40 00 3.2.C · PDF p. 928
Spec wording
“C. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 40 00 3.2.C928–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Hvac Air Cleaning Devices23 40 00 3.2.D · PDF p. 928
Spec wording
“D. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government. ---END---”
23 40 00 3.2.D928–
O&MO&MMaintenance and operating manuals in accordance with Section 01 00 ...Indoor Central-Station Air-Handling Units23 73 00 1.4.C · PDF p. 931
Spec wording
“C. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL REQUIREMENTS. Include instructions for lubrication, filter replacement, motor and drive replacement, spare part lists, and wiring diagrams.”
23 73 00 1.4.C931–
Test / cert.Test / cert.The air handling unit shall not be operated for any ...Indoor Central-Station Air-Handling Units23 73 00 3.2.A · PDF p. 942
Spec wording
“A. The air handling unit shall not be operated for any purpose, temporary or permanent, until ductwork is clean, filters are in place, bearings are lubricated and fan has been test run under observation.”
23 73 00 3.2.A942–
Test / cert.Test / cert.After the air handling unit is installed and tested, provide ...Indoor Central-Station Air-Handling Units23 73 00 3.2.B · PDF p. 942
Spec wording
“B. After the air handling unit is installed and tested, provide startup and operating instructions to VA personnel.”
23 73 00 3.2.B942–
Test / cert.Test / cert.An authorized factory representative should start up, test and certify ...Indoor Central-Station Air-Handling Units23 73 00 3.2.C · PDF p. 942-943
Spec wording
“C. An authorized factory representative should start up, test and certify the final installation and application specific calibration of control components. Items to be verified include fan performance over entire operating range, noise and vibration testing, verification of proper alignment, overall inspection of the installation, Owner/Operator training, etc.”
23 73 00 3.2.C942-943–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Indoor Central-Station Air-Handling Units23 73 00 3.3.A · PDF p. 943
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.”
23 73 00 3.3.A943–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Indoor Central-Station Air-Handling Units23 73 00 3.3.B · PDF p. 943
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.”
23 73 00 3.3.B943–
O&MO&MProvide installation, operating and maintenance instructionsAir Coils23 82 16 1.4.D · PDF p. 946
Spec wording
“D. Provide installation, operating and maintenance instructions.”
23 82 16 1.4.D946–
O&MO&MComplete operating and maintenance manuals including wiring diagrams, technical data ...Air Coils23 82 16 1.4.G · PDF p. 946
Spec wording
“G. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replaceable parts, and troubleshooting guide: 1. Include complete list indicating all components of the systems. 2. Include complete diagrams of the internal wiring for each item of equipment. 3. Diagrams shall have their terminals identified to facilitate installation, operation, and maintenance.”
23 82 16 1.4.G946–
Record docsRecord docsComply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 ...Air Coils23 82 16 1.6.A · PDF p. 947
Spec wording
“A. Comply with requirements in paragraph AS-BUILT DOCUMENTATION of Section 23 05 11, COMMON WORK RESULTS FOR HVAC.”
23 82 16 1.6.A947–
Test / cert.Test / cert.Perform tests as recommended by product manufacturer and listed standards ...Air Coils23 82 16 3.2.A · PDF p. 948
Spec wording
“A. Perform tests as recommended by product manufacturer and listed standards and under actual or simulated operating conditions and prove full compliance with design and specified requirements. Tests of the various items of equipment shall be performed simultaneously with the system of which each item is an integral part.”
23 82 16 3.2.A948–
Test / cert.Test / cert.When any defects are detected, correct defects and repeat test ...Air Coils23 82 16 3.2.B · PDF p. 948
Spec wording
“B. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.”
23 82 16 3.2.B948–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Air Coils23 82 16 3.3.A · PDF p. 948
Spec wording
“A. Provide services of manufacturer's technical representative for 4 hours to instruct VA personnel responsible in operation and maintenance of the system.”
23 82 16 3.3.A948–

Division 26 Electrical 17 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.All submittals shall include six copies of adequate descriptive literature, ...Requirements For Electrical Installations26 05 11 1.12.C · PDF p. 955-956
Spec wording
“C. All submittals shall include six copies of adequate descriptive literature, catalog cuts, shop drawings, test reports, certifications, samples, and other data necessary for the Government to ascertain that the proposed materials and equipment comply with drawing and specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify specific materials and equipment being ...”
26 05 11 1.12.C955-956six copies
O&MO&MThe submittals shall include the following:Requirements For Electrical Installations26 05 11 1.12.E · PDF p. 956
Spec wording
“E. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, manuals, pictures, nameplate data, and test reports as required. 2. Elementary and interconnection wiring diagrams for communication and signal systems, control systems, and equipment ...”
26 05 11 1.12.E956–
O&MO&MMaintenance and Operation Manuals:Requirements For Electrical Installations26 05 11 1.12.F · PDF p. 956
Spec wording
“F. Maintenance and Operation Manuals: 1. Submit as required for systems and equipment specified in the technical sections. Furnish in hardcover binders or an approved equivalent. 2. Inscribe the following identification on the cover: the words "MAINTENANCE AND OPERATION MANUAL," the name and location of the system, material, equipment, building, name of Contractor, and contract name and number. Include in the ...”
26 05 11 1.12.F956binders
Test / cert.Test / cert.Approvals will be based on complete submission of shop drawings, ...Requirements For Electrical Installations26 05 11 1.12.G · PDF p. 957
Spec wording
“G. Approvals will be based on complete submission of shop drawings, manuals, test reports, certifications, and samples as applicable.”
26 05 11 1.12.G957–
WarrantyWarrantyAll work performed and all equipment and material furnished under ...Requirements For Electrical Installations26 05 11 1.15.A · PDF p. 958
Spec wording
“A. All work performed and all equipment and material furnished under this Division shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the COR for the Government.”
26 05 11 1.15.A958–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Low-Voltage Electrical Power Conductors And Cables26 05 19 1.4.A · PDF p. 959
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings and insulation type for each conductor and cable. 2) Splicing materials and pulling lubricant. ...”
26 05 19 1.4.A959–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Grounding And Bonding For Electrical Systems26 05 26 1.4.A · PDF p. 967-968
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit plans showing the location of system grounding electrodes and connections, and the routing of aboveground and underground grounding electrode ...”
26 05 26 1.4.A967-968–
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Raceway And Boxes For Electrical Systems26 05 33 1.4.A · PDF p. 975-976
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Size and location of main feeders. b. Size and location of panels and pull-boxes. c. Layout of required conduit penetrations through structural elements. d. Submit the following data for approval: 1) Raceway types and sizes. 2) Conduit bodies, ...”
26 05 33 1.4.A975-976–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Lighting Controls26 09 23 1.4.A · PDF p. 987-988
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting controls. b. Material and construction details. c. Physical dimensions and description. d. Wiring schematic and connection diagram. e. Installation details. 2. Manuals: a. Submit, ...”
26 09 23 1.4.A987-988–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Panelboards26 24 16 1.4.A · PDF p. 993-994
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, circuit breakers, wiring and connection ...”
26 24 16 1.4.A993-994–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Wiring Devices26 27 26 1.4.A · PDF p. 999-1000
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, mounting details, construction materials, grade, and termination information. 2. Manuals: a. Submit, simultaneously ...”
26 27 26 1.4.A999-1000–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Motor Controllers26 29 11 1.4.A · PDF p. 1005-1006
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Include electrical ratings, dimensions, weights, mounting details, materials, overcurrent protection devices, overload relays, sizes of enclosures, wiring ...”
26 29 11 1.4.A1005-1006–
Spare partsSpare partsTwo weeks prior to the final inspection, provide one complete ...Motor Controllers26 29 11 3.4.A · PDF p. 1013-1014
Spec wording
“A. Two weeks prior to the final inspection, provide one complete set of spare fuses for each motor controller.”
26 29 11 3.4.A1013-1014one complete set
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Enclosed Switches And Circuit Breakers26 29 21 1.4.A · PDF p. 1015-1016
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Submit the following data for approval: 1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, ...”
26 29 21 1.4.A1015-1016–
Spare partsSpare partsTwo weeks prior to the final inspection, furnish one complete ...Enclosed Switches And Circuit Breakers26 29 21 3.3.A · PDF p. 1018
Spec wording
“A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the COR. ---END---”
26 29 21 3.3.A1018one complete set
Test / cert.Test / cert.Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Facility Lightning Protection26 41 00 1.4.A · PDF p. 1019
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit sufficient information to demonstrate compliance with drawings and specifications. b. Show locations of air terminals, connections to required metal surfaces, down conductors, and grounding means. c. Show the mounting hardware and materials ...”
26 41 00 1.4.A1019–
O&MO&MSubmit in accordance with Paragraph, SUBMITTALS in Section 26 05 ...Interior Lighting26 51 00 1.4.A · PDF p. 1023-1024
Spec wording
“A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements: 1. Shop Drawings: a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation. b. Material and construction details, include information on housing and optics system. ...”
26 51 00 1.4.A1023-1024–

Division 27 Communications 15 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MProvide parts list including quantity of spare partsRequirements For Communications Installations27 05 11 1.7.B · PDF p. 1054
Spec wording
“B. Provide parts list including quantity of spare parts.”
27 05 11 1.7.B1054–
Test / cert.Test / cert.Furnish electronic certified test reports to COR prior to final ...Requirements For Communications Installations27 05 11 1.7.K · PDF p. 1056
Spec wording
“K. Furnish electronic certified test reports to COR prior to final inspection and not more than 90 days after completion of tests.”
27 05 11 1.7.K1056–
WarrantyWarrantyProvide following closeout submittals prior to project closeout date:Requirements For Communications Installations27 05 11 1.8.A · PDF p. 1056
Spec wording
“A. Provide following closeout submittals prior to project closeout date: 1. Warranty certificate. 2. Evidence of compliance with requirements such as low voltage certificate of inspection. 3. Project record documents. 4. Instruction manuals and software that are a part of system.”
27 05 11 1.8.A1056–
WarrantyWarrantyMaintenance and Operation ManualsRequirements For Communications Installations27 05 11 1.8.B · PDF p. 1056
Spec wording
“B. Maintenance and Operation Manuals: Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS. 1. Prepare a manual for each system and equipment specified. 2. Furnish on portable storage drive in PDF format or equivalent accepted by COR. 3. Furnish complete manual as specified in specification section, fifteen days prior to performance of systems or equipment test. 4. Furnish remaining manuals prior to ...”
27 05 11 1.8.B1056PDF
Test / cert.Test / cert.Record Wiring Diagrams:Requirements For Communications Installations27 05 11 1.8.C · PDF p. 1057-1058
Spec wording
“C. Record Wiring Diagrams: 1. Red Line Drawings: Keep one E size 91.44 cm x 121.92 cm (36 inches x 48 inches) set of floor plans, on site during work hours, showing installation progress marked and backbone cable labels noted. Make these drawings available for examination during construction meetings or field inspections. 2. General Drawing Specifications: Detail and elevation drawings to be D size 61 cm x 91.44 cm ...”
27 05 11 1.8.C1057-1058CAD; four complete sets
Closeout stepCloseout stepService QualificationsRequirements For Communications Installations27 05 11 1.8.D · PDF p. 1058
Spec wording
“D. Service Qualifications: Submit name and contact information of service organizations providing service to this installation within eight hours of receipt of notification service is needed.”
27 05 11 1.8.D1058–
Spare partsSpare partsAfter approval and prior to installation, furnish COR with the ...Requirements For Communications Installations27 05 11 1.9.A · PDF p. 1058
Spec wording
“A. After approval and prior to installation, furnish COR with the following: 1. A 300 mm (12 inch) length of each type and size of wire and cable along with tag from coils of reels from which samples were taken. 2. One coupling, bushing and termination fitting for each type of conduit. 3. Samples of each hanger, clamp and supports for conduit and pathways. 4. Duct sealing compound.”
27 05 11 1.9.A1058–
WarrantyWarrantyComply with FAR clause 52.246-21, except as follows:Requirements For Communications Installations27 05 11 1.13.A · PDF p. 1061
Spec wording
“A. Comply with FAR clause 52.246-21, except as follows: 1. Warranty material and equipment to be free from defects, workmanship, and remain so for a period of one year for Emergency Systems from date of final acceptance of system by Government; provide OEM's equipment warranty document to COR. 2. Government maintenance personnel shall have ability to contact OEM for emergency maintenance and logistic assistance, ...”
27 05 11 1.13.A1061–
Test / cert.Test / cert.Proof of Performance Certification:Requirements For Communications Installations27 05 11 3.6.L · PDF p. 1071
Spec wording
“L. Proof of Performance Certification: 1. If system is declared acceptable, AHJ (SMCS 005OP2H3) provides COR notice stating system processes to required operating standards and functions and is Government accepted for use by facility. 2. Validate items with COR needing to be provided to complete project contract (i.e. charts & diagrams, manuals, spare parts, system warranty documents executed. Once items have been ...”
27 05 11 3.6.L1071–
TrainingTrainingProvide training in accordance with subsection, INSTRUCTIONS, of Section 01 ...Requirements For Communications Installations27 05 11 3.8.A · PDF p. 1072
Spec wording
“A. Provide training in accordance with subsection, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.”
27 05 11 3.8.A1072–
TrainingTrainingProvide training for equipment or system as required in each ...Requirements For Communications Installations27 05 11 3.8.B · PDF p. 1072
Spec wording
“B. Provide training for equipment or system as required in each associated specification.”
27 05 11 3.8.B1072–
TrainingTrainingDevelop and submit training schedule for approval by COR, at ...Requirements For Communications Installations27 05 11 3.8.C · PDF p. 1072
Spec wording
“C. Develop and submit training schedule for approval by COR, at least 30 days prior to planned training.”
27 05 11 3.8.C1072–
Test / cert.Test / cert.Closeout SubmittalsGrounding And Bonding For Communications Systems27 05 26 1.3.C · PDF p. 1075
Spec wording
“C. Closeout Submittals: In addition to Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS provide the following: 1. Certified test reports of ground resistance. 2. Certifications: Two weeks prior to final inspection, submit following to COR: a. Certification materials and installation is in accordance with construction documents. b. Certification complete installation has been installed and tested.”
27 05 26 1.3.C1075–
Test / cert.Test / cert.CertificationRaceways And Boxes For Communications Systems27 05 33 1.3.B · PDF p. 1083
Spec wording
“B. Certification: Provide letter prior to final inspection, certifying material is in accordance with construction documents and properly installed.”
27 05 33 1.3.B1083–
WarrantyWarrantyCloseout Submittals:Control, Communication And Signal Wiring27 10 00 1.3.E · PDF p. 1097-1098
Spec wording
“E. Closeout Submittals: 1. Provide contact information for maintenance personnel to contact contractor for emergency maintenance and logistic assistance, and assistance in resolving technical problems at any time during warranty period. 2. Provide certified OEM sweep test tags from each cable reel to COR. 3. Furnish spare or unused wire and cable with appropriate connectors (female types) for installation in ...”
27 10 00 1.3.E1097-1098–

Division 28 Fire alarm and security 44 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MThe submittals shall include the following:Common Work Results For Electronic Safety And Security28 05 00 1.6.D · PDF p. 1112
Spec wording
“D. The submittals shall include the following: 1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required. 2. Parts list which shall include those replacement parts recommended by the equipment manufacturer, quantity of parts, current ...”
28 05 00 1.6.D1112–
WarrantyWarrantySubmittals shall be in full compliance of the Contract Documents. ...Common Work Results For Electronic Safety And Security28 05 00 1.6.E · PDF p. 1112-1118
Spec wording
“E. Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. All submittals ...”
28 05 00 1.6.E1112-1118AutoCAD; CAD; Binders; binder; four copies
Record docsRecord docsGroup 1 Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.F · PDF p. 1118-1123
Spec wording
“F. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA CAD Standards Guide. All text associated with security details shall be 1/8" ...”
28 05 00 1.6.F1118-1123CAD; AutoCAD
O&MO&MGroup IV Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.H · PDF p. 1124-1127
Spec wording
“H. Group IV Technical Data Package 1. Performance Verification Test a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to the ...”
28 05 00 1.6.H1124-1127DVD; four copies; CAD; hard copy
O&MO&MGroup V Technical Data PackageCommon Work Results For Electronic Safety And Security28 05 00 1.6.I · PDF p. 1127-1131
Spec wording
“I. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or ...”
28 05 00 1.6.I1127-1131CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD
WarrantyWarrantyThe Contractor shall, as a condition precedent to the final ...Common Work Results For Electronic Safety And Security28 05 00 1.20.A · PDF p. 1152
Spec wording
“A. The Contractor shall, as a condition precedent to the final payment, execute a written guarantee (warranty) to the COR certifying all contract requirements have been completed according to the final specifications. Contract drawings and the warranty of all materials and equipment furnished under this contract are to remain in satisfactory operating condition (ordinary wear and tear, abuse and causes beyond his ...”
28 05 00 1.20.A1152–
TrainingTrainingTraining shall be provided in accordance with Article, INSTRUCTIONS, of ...Common Work Results For Electronic Safety And Security28 05 00 3.3.A · PDF p. 1158
Spec wording
“A. Training shall be provided in accordance with Article, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.”
28 05 00 3.3.A1158–
TrainingTrainingTraining shall be provided for the particular equipment or system ...Common Work Results For Electronic Safety And Security28 05 00 3.3.B · PDF p. 1158
Spec wording
“B. Training shall be provided for the particular equipment or system as required in each associated specification.”
28 05 00 3.3.B1158–
TrainingTrainingA training schedule shall be developed and submitted by the ...Common Work Results For Electronic Safety And Security28 05 00 3.3.C · PDF p. 1159
Spec wording
“C. A training schedule shall be developed and submitted by the contractor and approved by the COR at least 30 days prior to the planned training.”
28 05 00 3.3.C1159–
TrainingTrainingProvide services of manufacturer's technical representative for 4 hours to ...Common Work Results For Electronic Safety And Security28 05 00 3.3.D · PDF p. 1159
Spec wording
“D. Provide services of manufacturer's technical representative for 4 hours to instruct VA personnel in operation and maintenance of units.”
28 05 00 3.3.D1159–
Test / cert.Test / cert.The inspection and test will be conducted by a factory-certified ...Common Work Results For Electronic Safety And Security28 05 00 3.6.C · PDF p. 1161
Spec wording
“C. The inspection and test will be conducted by a factory-certified contractor representative and witnessed by a Government Representative. The results of the inspection will be officially recorded by a designated Government Representative and maintained on file by the COR (RE), until completion of the entire project. The results will be compared to the Acceptance Test results.”
28 05 00 3.6.C1161–
O&MO&MIn accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT ...Conductors And Cables For Electronic Safety And Security28 05 13 1.5.A · PDF p. 1168
Spec wording
“A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following: 1. Manufacturer's Literature and Data: Showing each cable type and rating. 2. Certificates: Two weeks prior to final inspection, deliver to the Contracting Officer's Representative (COR) four copies of the certification that the material is in accordance with the drawings and specifications and diagrams for ...”
28 05 13 1.5.A1168four copies; electronic copy
Test / cert.Test / cert.Document data for each measurement. Print data for submittals in ...Conductors And Cables For Electronic Safety And Security28 05 13 3.8.D · PDF p. 1182
Spec wording
“D. Document data for each measurement. Print data for submittals in a summary report that is formatted using Table 10.1 in BICSI TDMM as a guide, or transfer the data from the instrument to the computer, save as text files, print, and submit.”
28 05 13 3.8.D1182–
Test / cert.Test / cert.Prepare test and inspection reportsConductors And Cables For Electronic Safety And Security28 05 13 3.8.F · PDF p. 1182
Spec wording
“F. Prepare test and inspection reports.”
28 05 13 3.8.F1182–
Test / cert.Test / cert.Test ReportsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.C · PDF p. 1183
Spec wording
“C. Test Reports: Provide certified test reports of ground resistance.”
28 05 26 1.3.C1183–
Test / cert.Test / cert.CertificationsGrounding And Bonding For Electronic Safety And Security28 05 26 1.3.D · PDF p. 1183
Spec wording
“D. Certifications: Two weeks prior to final inspection, submit four copies of the following to the COR: 1. Certification that the materials and installation are in accordance with the drawings and specifications. 2. Certification by the contractor that the complete installation has been properly installed and tested.”
28 05 26 1.3.D1183four copies
Test / cert.Test / cert.Prepare test and inspection reportsGrounding And Bonding For Electronic Safety And Security28 05 26 3.7.D · PDF p. 1188
Spec wording
“D. Prepare test and inspection reports.”
28 05 26 3.7.D1188–
Test / cert.Test / cert.Report measured ground resistances that exceed the following values:Grounding And Bonding For Electronic Safety And Security28 05 26 3.7.E · PDF p. 1188
Spec wording
“E. Report measured ground resistances that exceed the following values: 1. Power Distribution Units or Panel boards Serving Electronic Equipment: 3 ohm(s).”
28 05 26 3.7.E1188–
Test / cert.Test / cert.CertificationConduits And Backboxes For Electronic Safety And Security28 05 28.33 1.5.C · PDF p. 1190
Spec wording
“C. Certification: Prior to final inspection, deliver to the Contracting Officer's Representative (COR) four copies of the certification that the material is in accordance with the drawings and specifications and has been properly installed.”
28 05 28.33 1.5.C1190four copies
Record docsRecord docsProvide a complete and thorough pre-installation and as-built design package ...Physical Access Control System28 13 00 1.4.D · PDF p. 1210
Spec wording
“D. Provide a complete and thorough pre-installation and as-built design package in both electronic format and on paper, minimum size 48 x 48 inches (1220 x 1220 millimeters); drawing submittals shall be per the established project schedule.”
28 13 00 1.4.D1210electronic format
Test / cert.Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.I · PDF p. 1212
Spec wording
“I. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 1.4.I1212–
WarrantyWarrantyGeneralPhysical Access Control System28 13 00 1.4.J · PDF p. 1212-1217
Spec wording
“J. General: Submittals shall be in full compliance of the Contract Documents. All submittals shall be provided in accordance with this section. Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. Additional ...”
28 13 00 1.4.J1212-1217AutoCAD; CAD; Binders; binder
Record docsRecord docsGroup 1 Technical Data PackagePhysical Access Control System28 13 00 1.4.K · PDF p. 1217-1223
Spec wording
“K. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following: 1. Section I - Drawings: a. General – Drawings shall conform to VA Special Conditions and CAD Standards Documents. All text associated with ...”
28 13 00 1.4.K1217-1223CAD; AutoCAD
O&MO&MGroup IV Technical Data PackagePhysical Access Control System28 13 00 1.4.N · PDF p. 1224-1227
Spec wording
“N. Group IV Technical Data Package 1. Performance Verification Test a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The Contractor shall deliver the PVT and endurance test procedures to the ...”
28 13 00 1.4.N1224-1227DVD; four copies; CAD; hard copy
O&MO&MGroup V Technical Data PackagePhysical Access Control System28 13 00 1.4.O · PDF p. 1227-1231
Spec wording
“O. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or ...”
28 13 00 1.4.O1227-1231CD; two (2) complete sets; binder; one (1) copy; AutoCAD; DVD
Test / cert.Test / cert.Completed System Readiness Checklists provided by the Commissioning Agent and ...Physical Access Control System28 13 00 1.4.R · PDF p. 1232
Spec wording
“R. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician, and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 1.4.R1232–
WarrantyWarrantyWarrant PACS work subject to the Article "Warranty of Construction" ...Physical Access Control System28 13 00 1.11.A · PDF p. 1244
Spec wording
“A. Warrant PACS work subject to the Article "Warranty of Construction" of FAR clause 52.246-21.”
28 13 00 1.11.A1244–
WarrantyWarrantyDemonstration and training shall be performed prior to system acceptance ...Physical Access Control System28 13 00 1.11.B · PDF p. 1244
Spec wording
“B. Demonstration and training shall be performed prior to system acceptance.”
28 13 00 1.11.B1244–
Spare partsSpare partsProvide 2-door door controllerPhysical Access Control System28 13 00 2.20.A · PDF p. 1297
Spec wording
“A. Provide 2-door door controller.”
28 13 00 2.20.A1297–
Spare partsSpare partsProvide 4-card readersPhysical Access Control System28 13 00 2.20.B · PDF p. 1297
Spec wording
“B. Provide 4-card readers.”
28 13 00 2.20.B1297–
Spare partsSpare partsProvide 4-request for exitPhysical Access Control System28 13 00 2.20.C · PDF p. 1297
Spec wording
“C. Provide 4-request for exit.”
28 13 00 2.20.C1297–
Spare partsSpare partsProvide 1-keypadPhysical Access Control System28 13 00 2.20.D · PDF p. 1297
Spec wording
“D. Provide 1-keypad.”
28 13 00 2.20.D1297–
Test / cert.Test / cert.Manufacturer's Field ServicePhysical Access Control System28 13 00 3.10.A · PDF p. 1306
Spec wording
“A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing.”
28 13 00 3.10.A1306–
Test / cert.Test / cert.Testing AgencyPhysical Access Control System28 13 00 3.10.B · PDF p. 1306
Spec wording
“B. Testing Agency: Engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports:”
28 13 00 3.10.B1306–
Test / cert.Test / cert.Perform the following field tests and inspections and prepare test ...Physical Access Control System28 13 00 3.10.C · PDF p. 1306-1307
Spec wording
“C. Perform the following field tests and inspections and prepare test reports: 1. LAN Cable Procedures: Inspect for physical damage and test each conductor signal path for continuity and shorts. Use Class 2, bidirectional, Category 5 tester. Test for faulty connectors, splices, and terminations. Test according to TIA/EIA-568-1, "Commercial Building Telecommunications Cabling Standards - Part 1 General ...”
28 13 00 3.10.C1306-1307–
Test / cert.Test / cert.Provide commissioning documentation in accordance with the requirements of Section ...Physical Access Control System28 13 00 3.12.A · PDF p. 1307
Spec wording
“A. Provide commissioning documentation in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.”
28 13 00 3.12.A1307–
Test / cert.Test / cert.Components provided under this section of the specification will be ...Physical Access Control System28 13 00 3.12.B · PDF p. 1307
Spec wording
“B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS and related sections for contractor responsibilities for system commissioning.”
28 13 00 3.12.B1307–
TrainingTrainingProvide services of manufacturer's technical representative for four hours to ...Physical Access Control System28 13 00 3.13.A · PDF p. 1307
Spec wording
“A. Provide services of manufacturer's technical representative for four hours to instruct VA personnel in operation and maintenance of units.”
28 13 00 3.13.A1307–
TrainingTrainingSubmit training plans and instructor qualifications in accordance with the ...Physical Access Control System28 13 00 3.13.B · PDF p. 1307
Spec wording
“B. Submit training plans and instructor qualifications in accordance with the requirements of Section 28 08 00 – COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.”
28 13 00 3.13.B1307–
TrainingTrainingDevelop separate training modules for the following:Physical Access Control System28 13 00 3.13.C · PDF p. 1307-1308
Spec wording
“C. Develop separate training modules for the following: 1. Computer system administration personnel to manage and repair the LAN and databases and to update and maintain software. 2. Operators who prepare and input credentials to man the control station and workstations and to enroll personnel. 3. Security personnel. 4. Hardware maintenance personnel. 5. Corporate management.”
28 13 00 3.13.C1307-1308–
TrainingTrainingAll testing and training shall be compliant with the VA ...Physical Access Control System28 13 00 3.13.D · PDF p. 1308
Spec wording
“D. All testing and training shall be compliant with the VA General Requirements, Section 01 00 00, GENERAL REQUIREMENTS. ---END---”
28 13 00 3.13.D1308–
Record docsRecord docsDrawings:Fire Detection And Alarm28 31 00 1.4.B · PDF p. 1310-1311
Spec wording
“B. Drawings: 1. Prepare drawings using AutoCAD latest Release software and include all contractors information. Layering shall be by VA criteria as provided by the Contracting Officer Representative (COR). Bid drawing files on AutoCAD shall be provided to the Contractor at the pre-construction meeting. The contractor shall be responsible for verifying all critical dimensions shown on the drawings provided by VA. 2. ...”
28 31 00 1.4.B1310-1311AutoCAD; 3 sets; one set
O&MO&MManuals:Fire Detection And Alarm28 31 00 1.4.C · PDF p. 1311-1312
Spec wording
“C. Manuals: 1. Submit simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets for all items used in the system, power requirements, device wiring diagrams, dimensions, and information for ordering replacement parts. a. Wiring diagrams shall have their terminals identified to facilitate installation, operation, expansion and maintenance. ...”
28 31 00 1.4.C1311-1312binder; 4 copies
WarrantyWarrantyAll work performed and all material and equipment furnished under ...Fire Detection And Alarm28 31 00 1.5.A · PDF p. 1313
Spec wording
“A. All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the Contracting Officer.”
28 31 00 1.5.A1313–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.