Closeout checklist: Replace Windows, Siding, Flooring and Interior Lights, MSHP Troop E Service Center (Missouri FMDC, MO)

Every closeout item we found in the public spec book for this job: 93 items across Division 01, 10 trade divisions and the contract conditions, including 37 warranties, 20 O&M manual items and 17 tests and certificates. Each one is tied to its spec section and the PDF page it sits on.

Owner
State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
Number
FMDC project R2321-01
Location
Missouri
Bid date
2025-06-26
Public spec book
Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing
Spec book size
218 PDF pages
Checklist built
2026-10-21

Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.

What this job asks for at closeout

37Warranties
20O&M manuals
17Tests and certificates
6Training
3Record documents
5Spare parts
5Payment release

All 93 items, by trade

Division 01 General requirements 6 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.01.A · PDF p. 63
Spec wording
“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...”
01 32 00 3.01.A63–
WarrantyWarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...(Untitled)01 33 00 1.08.A · PDF p. 69
Spec wording
“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.”
01 33 00 1.08.A69–
WarrantyWarrantyContractor shall submit the information for materials and equipment to ...(Untitled)01 33 00 3.01.A · PDF p. 69-72
Spec wording
“A. Contractor shall submit the information for materials and equipment to be provided under this contract, as noted on the following page: SPEC TITLE CATEGORY SECTION 013200 Schedules Construction Schedule 013200 Schedules Schedule of Values 013200 Schedules List of Subcontractors 013200 Schedules Major Material Suppliers 024100 Demolition - Site Plan Shop Drawings 024100 Demolition - Utility Plan Shop Drawings ...”
01 33 00 3.01.A69-72–
TrainingTrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.01.A · PDF p. 85
Spec wording
“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".”
01 79 00 3.01.A85–
TrainingTrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.02.A · PDF p. 85
Spec wording
“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Owner will furnish Contractor with names and positions of participants.”
01 79 00 3.02.A85–
TrainingTrainingSchedulingDemonstration And Training01 79 00 3.02.B · PDF p. 85
Spec wording
“B. Scheduling: Provide instruction at mutually agreed on times. 1. Schedule training with Owner with at least seven days' advance notice.”
01 79 00 3.02.B85–

Division 02 Existing conditions 2 items

TypeItemSpec sectionPDF pageCopies / format
Record docsRecord docsProject Closeout Submittals:(Untitled)02 41 19 1.06.E · PDF p. 87
Spec wording
“E. Project Closeout Submittals: 1. Inventory: Submit a list of items that have been removed and salvaged 2. Record drawings at Project closeout indication as-built conditions. 3. Identify and accurately locate capped utilities and other subsurface structural, electrical, or mechanical conditions.”
02 41 19 1.06.E87–
WarrantyWarrantyExisting Warranties(Untitled)02 41 19 1.10.A · PDF p. 87
Spec wording
“A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.”
02 41 19 1.10.A87–

Division 03 Concrete 3 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Test ReportsCast-In-Place Concrete03 30 00 1.04.E · PDF p. 92
Spec wording
“E. Test Reports: Submit report for each test or series of tests specified.”
03 30 00 1.04.E92–
Record docsRecord docsProject Record DocumentsCast-In-Place Concrete03 30 00 1.04.F · PDF p. 92
Spec wording
“F. Project Record Documents: Accurately record actual locations of embedded utilities and components that will be concealed from view upon completion of concrete work.”
03 30 00 1.04.F92–
WarrantyWarrantyWarrantyCast-In-Place Concrete03 30 00 1.04.G · PDF p. 92
Spec wording
“G. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner's name and registered with manufacturer.”
03 30 00 1.04.G92–

Division 06 Wood and plastics 2 items

TypeItemSpec sectionPDF pageCopies / format
WarrantyWarrantySpecimen warrantySheathing06 16 00 1.04.B · PDF p. 96
Spec wording
“B. Specimen warranty.”
06 16 00 1.04.B96–
WarrantyWarrantyManufacturer WarrantySheathing06 16 00 1.07.A · PDF p. 96
Spec wording
“A. Manufacturer Warranty: Provide warranty for material defects and fabrication as noted in manufacturer's documentation. Complete forms in Owner's name and register with manufacturer.”
06 16 00 1.07.A96–

Division 07 Roofing, insulation and waterproofing 12 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Product Test ReportsInsulated Glazing Infill Panels07 42 00 1.04.B · PDF p. 100
Spec wording
“B. Product Test Reports: For each product, tests performed by a qualified testing agency.”
07 42 00 1.04.B100–
Test / cert.Test / cert.Field quality-control reportsInsulated Glazing Infill Panels07 42 00 1.04.C · PDF p. 100
Spec wording
“C. Field quality-control reports.”
07 42 00 1.04.C100–
O&MO&MMaintenance DataInsulated Glazing Infill Panels07 42 00 1.05.A · PDF p. 100
Spec wording
“A. Maintenance Data: For infill panels to include in maintenance manuals.”
07 42 00 1.05.A100–
WarrantyWarrantySpecial WarrantyInsulated Glazing Infill Panels07 42 00 1.10.A · PDF p. 101
Spec wording
“A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of panel systems that fail in materials or workmanship within specified warranty period. 1. Failures include, but are not limited to, the following: a. Structural failures including rupturing, cracking, or puncturing. b. Deterioration of materials beyond normal weathering. 2. Warranty Period: Two years ...”
07 42 00 1.10.A101–
Test / cert.Test / cert.Prepare test and inspection reportsInsulated Glazing Infill Panels07 42 00 3.04.F · PDF p. 103
Spec wording
“F. Prepare test and inspection reports.”
07 42 00 3.04.F103–
Test / cert.Test / cert.Test ReportsMetal Wall Panels07 42 13 1.04.D · PDF p. 104
Spec wording
“D. Test Reports: Submit test report verifying compliance with NFPA 285 for previously-tested exterior wall assembly.”
07 42 13 1.04.D104–
WarrantyWarrantyWarranty Documentation for Installation of Building Rainscreen AssemblyMetal Wall Panels07 42 13 1.04.G · PDF p. 104
Spec wording
“G. Warranty Documentation for Installation of Building Rainscreen Assembly: Submit installer warranty and ensure that forms have been completed in Owner's name and registered with installer.”
07 42 13 1.04.G104–
WarrantyWarrantyFinish WarrantyMetal Wall Panels07 42 13 1.08.A · PDF p. 105
Spec wording
“A. Finish Warranty: Provide 15-year manufacturer warranty against excessive degradation of exterior finish. Include provision for replacement of units with excessive fading, chalking, or flaking. Complete forms in Owner's name and register with warrantor.”
07 42 13 1.08.A105–
WarrantyWarrantySpecial WarrantyMetal Wall Panels07 42 13 1.08.B · PDF p. 105
Spec wording
“B. Special Warranty: Provide 2-year warranty covering water tightness and integrity of seals of metal wall panels. Complete forms in Owner's name and register with warrantor.”
07 42 13 1.08.B105–
Test / cert.Test / cert.Preconstruction Laboratory Test ReportsJoint Sealants07 92 00 1.03.B · PDF p. 108
Spec wording
“B. Preconstruction Laboratory Test Reports: Submit at least four weeks prior to start of installation.”
07 92 00 1.03.B108–
WarrantyWarrantyExecuted warrantyJoint Sealants07 92 00 1.03.C · PDF p. 108
Spec wording
“C. Executed warranty.”
07 92 00 1.03.C108–
WarrantyWarrantyManufacturer WarrantyJoint Sealants07 92 00 1.05.A · PDF p. 108
Spec wording
“A. Manufacturer Warranty: Provide 2-year manufacturer warranty for installed sealants and accessories that fail to achieve a watertight seal, exhibit loss of adhesion or cohesion, or do not cure. Complete forms in Owner's name and register with manufacturer.”
07 92 00 1.05.A108–

Division 08 Doors, windows and hardware 27 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MMaintenance DataSectional Doors08 36 13 1.03.G · PDF p. 115
Spec wording
“G. Maintenance Data: Include data for motor and transmission, shaft and gearing, lubrication frequency, spare part sources.”
08 36 13 1.03.G115–
WarrantyWarrantySpecimen warrantySectional Doors08 36 13 1.03.H · PDF p. 115
Spec wording
“H. Specimen warranty.”
08 36 13 1.03.H115–
WarrantyWarrantyExtended Correction PeriodSectional Doors08 36 13 1.05.A · PDF p. 116
Spec wording
“A. Extended Correction Period: Correct defective work within a 2-year period commencing on Date of Substantial Completion.”
08 36 13 1.05.A116–
WarrantyWarrantyManufacturer WarrantySectional Doors08 36 13 1.05.B · PDF p. 116
Spec wording
“B. Manufacturer Warranty: Provide 5-year manufacturer warranty for electric operating equipment. Complete forms in Owner's name and register with manufacturer.”
08 36 13 1.05.B116–
Test / cert.Test / cert.Field Quality Control SubmittalsAluminum-Framed Storefronts08 43 13 1.04.F · PDF p. 120
Spec wording
“F. Field Quality Control Submittals: Report of field testing for water penetration and air leakage.”
08 43 13 1.04.F120–
WarrantyWarrantySpecimen warrantyAluminum-Framed Storefronts08 43 13 1.04.J · PDF p. 120
Spec wording
“J. Specimen warranty.”
08 43 13 1.04.J120–
WarrantyWarrantyProvide five year manufacturer warranty against failure of glass seal ...Aluminum-Framed Storefronts08 43 13 1.08.A · PDF p. 120
Spec wording
“A. Provide five year manufacturer warranty against failure of glass seal on insulating glass units, including interpane dusting or misting. Include provision for replacement of failed units.”
08 43 13 1.08.A120–
WarrantyWarrantyProvide five year manufacturer warranty against excessive degradation of exterior ...Aluminum-Framed Storefronts08 43 13 1.08.B · PDF p. 120
Spec wording
“B. Provide five year manufacturer warranty against excessive degradation of exterior finish. Include provision for replacement of units with excessive fading, chalking, or flaking.”
08 43 13 1.08.B120–
Test / cert.Test / cert.Provide services of storefront manufacturer's field representative to observe for ...Aluminum-Framed Storefronts08 43 13 3.04.A · PDF p. 123
Spec wording
“A. Provide services of storefront manufacturer's field representative to observe for proper installation of system and submit report.”
08 43 13 3.04.A123–
Test / cert.Test / cert.Grade SubstantiationAluminum Windows08 51 13 1.05.D · PDF p. 125
Spec wording
“D. Grade Substantiation: Prior to submitting shop drawings or starting fabrication, submit one of the following showing compliance with specified grade: 1. Evidence of AAMA Certification. 2. Evidence of WDMA Certification. 3. Evidence of CSA Certification. 4. Test report(s) by independent testing agency itemizing compliance and acceptable to authorities having jurisdiction.”
08 51 13 1.05.D125–
Test / cert.Test / cert.Test ReportsAluminum Windows08 51 13 1.05.E · PDF p. 125
Spec wording
“E. Test Reports: Prior to submitting shop drawings or starting fabrication, submit test report(s) by independent testing agency showing compliance with performance requirements in excess of those prescribed by specified grade.”
08 51 13 1.05.E125–
Test / cert.Test / cert.Field Quality Control SubmittalsAluminum Windows08 51 13 1.05.F · PDF p. 125
Spec wording
“F. Field Quality Control Submittals: Report of field testing for water penetration and air leakage.”
08 51 13 1.05.F125–
WarrantyWarrantySpecimen warrantyAluminum Windows08 51 13 1.05.I · PDF p. 125
Spec wording
“I. Specimen warranty.”
08 51 13 1.05.I125–
WarrantyWarrantyManufacturer WarrantyAluminum Windows08 51 13 1.09.A · PDF p. 125
Spec wording
“A. Manufacturer Warranty: Provide 5-year manufacturer warranty against failure of glass seal on insulating glass units, including interpane dusting or misting. Include provision for replacement of failed units. Complete forms in Owner's name and register with manufacturer.”
08 51 13 1.09.A125–
WarrantyWarrantyManufacturer WarrantyAluminum Windows08 51 13 1.09.B · PDF p. 125
Spec wording
“B. Manufacturer Warranty: Provide 20-year manufacturer warranty against excessive degradation of exterior finish. Include provision for replacement of units with excessive fading, chalking, or flaking. Complete forms in Owner's name and register with manufacturer.”
08 51 13 1.09.B125–
O&MO&MMaintenance DataDoor Hardware08 71 00 1.05.D · PDF p. 130
Spec wording
“D. Maintenance Data: Include data on operating hardware, lubrication requirements, and inspection procedures related to preventative maintenance. 1. Submit manufacturer's parts lists and templates.”
08 71 00 1.05.D130–
WarrantyWarrantySpecimen warrantyDoor Hardware08 71 00 1.05.H · PDF p. 130
Spec wording
“H. Specimen warranty.”
08 71 00 1.05.H130–
Record docsRecord docsProject Record DocumentsDoor Hardware08 71 00 1.05.I · PDF p. 130
Spec wording
“I. Project Record Documents: Record actual locations of concealed equipment, services, and conduit.”
08 71 00 1.05.I130–
Spare partsSpare partsMaintenance Materials and ToolsDoor Hardware08 71 00 1.05.J · PDF p. 130
Spec wording
“J. Maintenance Materials and Tools: Furnish the following for Owner's use in maintenance of project. 1. Lock Cylinders: ​One​ for each ​master​ keyed group. 2. Tools: One set of each special wrench or tool applicable for each different or special hardware component, whether supplied by hardware component manufacturer or not.”
08 71 00 1.05.J130One set
WarrantyWarrantyManufacturer's WarrantyDoor Hardware08 71 00 1.08.A · PDF p. 131
Spec wording
“A. Manufacturer's Warranty: Provide warranty against defects in material and workmanship for period indicated. Complete forms in Owner's name and register with manufacturer. 1. Closers: Five years, minimum. 2. Locksets and Cylinders: Three years, minimum. 3. Other Hardware: Two years, minimum.”
08 71 00 1.08.A131–
O&MO&MMaintenance DataPower Door Operators08 71 13 1.04.E · PDF p. 136
Spec wording
“E. Maintenance Data: Include manufacturer's parts list and maintenance instructions for each type of hardware and operating component.”
08 71 13 1.04.E136–
WarrantyWarrantySpecimen warrantyPower Door Operators08 71 13 1.04.F · PDF p. 136
Spec wording
“F. Specimen warranty.”
08 71 13 1.04.F136–
WarrantyWarrantyManufacturer WarrantyPower Door Operators08 71 13 1.06.A · PDF p. 136
Spec wording
“A. Manufacturer Warranty: Provide 2-year manufacturer warranty for components of power door operators. Complete forms in Owner's name and register with manufacturer.”
08 71 13 1.06.A136–
TrainingTrainingDemonstrate to Owner's representative equipment operation, operating components, adjustment features, ...Power Door Operators08 71 13 3.05.A · PDF p. 138
Spec wording
“A. Demonstrate to Owner's representative equipment operation, operating components, adjustment features, and lubrication requirements.”
08 71 13 3.05.A138–
WarrantyWarrantyWarranty DocumentationGlazing08 80 00 1.04.F · PDF p. 139
Spec wording
“F. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.”
08 80 00 1.04.F139–
WarrantyWarrantyInsulating Glass UnitsGlazing08 80 00 1.07.A · PDF p. 140
Spec wording
“A. Insulating Glass Units: Provide a five (5) year manufacturer warranty to include coverage for seal failure, interpane dusting or misting, including providing products to replace failed units.”
08 80 00 1.07.A140–
Test / cert.Test / cert.Monitor and report installation procedures and unacceptable conditionsGlazing08 80 00 3.05.B · PDF p. 142
Spec wording
“B. Monitor and report installation procedures and unacceptable conditions.”
08 80 00 3.05.B142–

Division 09 Finishes 8 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MMaintenance DataResilient Flooring09 65 00 1.03.F · PDF p. 146
Spec wording
“F. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning, stripping, and re-waxing.”
09 65 00 1.03.F146–
Spare partsSpare partsMaintenance MaterialsResilient Flooring09 65 00 1.03.G · PDF p. 146
Spec wording
“G. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Flooring Material: ​30 square feet​ of each type and color. 2. Extra Wall Base: ​40 linear feet​ of each type and color.”
09 65 00 1.03.G146–
O&MO&MOperation and Maintenance DataTile Carpeting09 68 13 1.03.E · PDF p. 149
Spec wording
“E. Operation and Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for cleaning.”
09 68 13 1.03.E149–
Spare partsSpare partsMaintenance MaterialsTile Carpeting09 68 13 1.03.F · PDF p. 149
Spec wording
“F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Carpet Tiles: Quantity equal to 5 percent of total installed of each color and pattern installed.”
09 68 13 1.03.F149–
O&MO&MMaintenance DataExterior Painting09 91 13 1.03.C · PDF p. 151
Spec wording
“C. Maintenance Data: Submit data including finish schedule showing where each product/color/finish was used, product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.”
09 91 13 1.03.C151–
Spare partsSpare partsMaintenance MaterialsExterior Painting09 91 13 1.03.D · PDF p. 151
Spec wording
“D. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Paint and Finish Materials: ​1 gallon​ of each ​color and type​;​ from the same product run,​ store where directed. 2. Label each container with ​color and type​ in addition to the manufacturer's label.”
09 91 13 1.03.D151–
O&MO&MMaintenance DataInterior Painting09 91 23 1.03.D · PDF p. 154
Spec wording
“D. Maintenance Data: Submit data including finish schedule showing where each product/color/finish was used, product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and finished surfaces, and color samples of each color and finish used.”
09 91 23 1.03.D154–
Spare partsSpare partsMaintenance MaterialsInterior Painting09 91 23 1.03.E · PDF p. 154
Spec wording
“E. Maintenance Materials: Furnish the following for Owner's use in maintenance of project. 1. Extra Paint and Finish Materials: ​1 gal​ of each ​color and type​;​ from the same product run,​ store where directed. 2. Label each container with ​color and type​ in addition to the manufacturer's label.”
09 91 23 1.03.E154–

Division 12 Furnishings 5 items

TypeItemSpec sectionPDF pageCopies / format
O&MO&MOperation and Maintenance DataManual Cordless Roller Shades12 24 13 1.04.A · PDF p. 158
Spec wording
“A. Operation and Maintenance Data: For single roller shades.”
12 24 13 1.04.A158–
WarrantyWarrantyLimited WarrantyManual Cordless Roller Shades12 24 13 1.09.A · PDF p. 159
Spec wording
“A. Limited Warranty: Manufacturer agrees to repair or replace cordless roller shade springs and shade fabrics that fail in materials or workmanship within the specified warranty period. 1. Warranty Period: 10 years from date of Substantial Completion.”
12 24 13 1.09.A159–
O&MO&MMaintenance DataManufactured Wood Casework12 32 00 1.06.D · PDF p. 161
Spec wording
“D. Maintenance Data: Manufacturer's recommendations for care and cleaning.”
12 32 00 1.06.D161–
WarrantyWarrantyCorrect defective Work within a five year period after Date ...Manufactured Wood Casework12 32 00 1.09.A · PDF p. 162
Spec wording
“A. Correct defective Work within a five year period after Date of Substantial Completion, at no additional cost to Owner. Defects include, but are not limited to: 1. Ruptured, cracked, or stained finish coating. 2. Discoloration or lack of finish integrity. 3. Cracking or peeling of finish. 4. Failure of hardware.”
12 32 00 1.09.A162–
O&MO&MMaintenance DataCountertops12 36 00 1.04.F · PDF p. 165
Spec wording
“F. Maintenance Data: Manufacturer's instructions and recommendations for maintenance and repair of countertop surfaces.”
12 36 00 1.04.F165–

Division 22 Plumbing 1 item

TypeItemSpec sectionPDF pageCopies / format
O&MO&MMaintenance DataPlumbing Fixtures22 40 00 1.03.D · PDF p. 168
Spec wording
“D. Maintenance Data: Include fixture trim exploded view and replacement parts lists.”
22 40 00 1.03.D168–

Division 23 HVAC 7 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Provide manufacturer representative or authorized technician services to execute inspection ...Vibration And Seismic Controls For Hvac23 05 48 3.03.B · PDF p. 175
Spec wording
“B. Provide manufacturer representative or authorized technician services to execute inspection and testing of seismic controls. Submit a detailed copy of manufacturer recommended inspection, testing, and field report procedurces.”
23 05 48 3.03.B175–
O&MO&MOperation and Maintenance DataSmall-Capacity Split-System Air Conditioners23 81 26.13 1.03.D · PDF p. 176
Spec wording
“D. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listing.”
23 81 26.13 1.03.D176–
WarrantyWarrantyWarrantySmall-Capacity Split-System Air Conditioners23 81 26.13 1.03.E · PDF p. 176
Spec wording
“E. Warranty: Submit manufacturers warranty and ensure forms have been filled out in Owner's name and registered with manufacturer.”
23 81 26.13 1.03.E176–
WarrantyWarrantyProvide 10 year manufacturers warranty for heat pumpsSmall-Capacity Split-System Air Conditioners23 81 26.13 1.05.A · PDF p. 176
Spec wording
“A. Provide 10 year manufacturers warranty for heat pumps.”
23 81 26.13 1.05.A176–
O&MO&MOperation and Maintenance DataConvection Heating And Cooling Units23 82 00 1.02.E · PDF p. 178
Spec wording
“E. Operation and Maintenance Data: Include manufacturer's descriptive literature, operating instructions, installation instructions, maintenance and repair data, and parts listings.”
23 82 00 1.02.E178–
WarrantyWarrantyWarrantyConvection Heating And Cooling Units23 82 00 1.02.F · PDF p. 178
Spec wording
“F. Warranty: Submit manufacturer's warranty and ensure forms have been completed in Owner's name and registered with manufacturer.”
23 82 00 1.02.F178–
WarrantyWarrantyProvide manufacturer's standard warranty for all equipmentConvection Heating And Cooling Units23 82 00 1.04.A · PDF p. 178
Spec wording
“A. Provide manufacturer's standard warranty for all equipment.”
23 82 00 1.04.A178–

Division 26 Electrical 9 items

TypeItemSpec sectionPDF pageCopies / format
Test / cert.Test / cert.Provide services of a manufacturer's authorized representative for seismic controls ...Vibration And Seismic Controls For Electrical Systems26 05 48 3.03.B · PDF p. 204
Spec wording
“B. Provide services of a manufacturer's authorized representative for seismic controls to perform inspection and testing. Include manufacturer's detailed testing and inspection procedures and field reports with submittals.”
26 05 48 3.03.B204–
O&MO&MOperation and Maintenance DataInterior Lighting26 51 00 1.05.D · PDF p. 210
Spec wording
“D. Operation and Maintenance Data: Instructions for each product including information on replacement parts.”
26 51 00 1.05.D210–
WarrantyWarrantyProvide ​5-year​ manufacturer warranty for LED luminaires, including drivers ...Interior Lighting26 51 00 1.09.A · PDF p. 210
Spec wording
“A. Provide ​5-year​ manufacturer warranty for LED luminaires, including drivers.”
26 51 00 1.09.A210–
TrainingTrainingSee Section 017900 - Demonstration and Training, for additional requirements ...Interior Lighting26 51 00 3.06.A · PDF p. 213
Spec wording
“A. See Section 017900 - Demonstration and Training, for additional requirements.”
26 51 00 3.06.A213–
Test / cert.Test / cert.Field Quality Control ReportsExterior Lighting26 56 00 1.05.E · PDF p. 215
Spec wording
“E. Field Quality Control Reports. 1. Include test report indicating measured illumination levels.”
26 56 00 1.05.E215–
O&MO&MOperation and Maintenance DataExterior Lighting26 56 00 1.05.G · PDF p. 215
Spec wording
“G. Operation and Maintenance Data: Instructions for each product including information on replacement parts.”
26 56 00 1.05.G215–
WarrantyWarrantyProvide ​5-year​ manufacturer warranty for all LED luminaires, including drivers ...Exterior Lighting26 56 00 1.08.A · PDF p. 215
Spec wording
“A. Provide ​5-year​ manufacturer warranty for all LED luminaires, including drivers.”
26 56 00 1.08.A215–
Test / cert.Test / cert.Measure illumination levels at night with calibrated meters to verify ...Exterior Lighting26 56 00 3.04.D · PDF p. 218
Spec wording
“D. Measure illumination levels at night with calibrated meters to verify compliance with performance requirements. Record test results in written report to be included with submittals.”
26 56 00 3.04.D218–
TrainingTrainingSee Section 017900 - Demonstration and Training, for additional requirements ...Exterior Lighting26 56 00 3.07.A · PDF p. 218
Spec wording
“A. See Section 017900 - Demonstration and Training, for additional requirements.”
26 56 00 3.07.A218–

Front end Contract conditions (final payment, releases, retainage) 11 items

TypeItemSpec sectionPDF pageCopies / format
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 22
Spec wording
“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...”
Conditions Of The Contract (Find Heading On The Cited Page)22–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 33
Spec wording
“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.”
Conditions Of The Contract (Find Heading On The Cited Page)33–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 34
Spec wording
“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.”
Conditions Of The Contract (Find Heading On The Cited Page)34three (4) copies
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 40
Spec wording
“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.”
Conditions Of The Contract (Find Heading On The Cited Page)40–
Payment releasePayment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 41
Spec wording
“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...”
Conditions Of The Contract (Find Heading On The Cited Page)41–
WarrantyWarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 33
Spec wording
“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...”
Conditions Of The Contract ARTICLE.A33–
WarrantyWarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 33
Spec wording
“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.”
Conditions Of The Contract ARTICLE.B33–
O&MO&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 33-34
Spec wording
“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...”
Conditions Of The Contract ARTICLE.A33-34three (3) copies; three (4) copies
O&MO&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 34
Spec wording
“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...”
Conditions Of The Contract ARTICLE.B34binders; binder
O&MO&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 38-39
Spec wording
“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...”
Conditions Of The Contract ARTICLE.A38-39–
Test / cert.Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 39
Spec wording
“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...”
Conditions Of The Contract ARTICLE.C39–

Don't want to chase all of this yourself?

Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.

Email [email protected]

Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.