Closeout checklist: Install New Emergency Backup System, Transition Center of St. Louis (Missouri FMDC, MO)
Every closeout item we found in the public spec book for this job: 62 items across Division 01, 2 trade divisions and the contract conditions, including 22 tests and certificates, 12 training items and 11 warranties. Each one is tied to its spec section and the PDF page it sits on.
- Owner
- State of Missouri, Office of Administration, Division of Facilities Management, Design and Construction (FMDC)
- Number
- FMDC project C2407-01
- Location
- St. Louis, MO
- Bid date
- 2025-06-03
- Public spec book
- Spec book PDF on the Missouri FMDC bid listing
FMDC bid listing - Spec book size
- 262 PDF pages
- Checklist built
- 2026-10-21
Prints the full checklist with a tick box, spec section and page for every item. In the print window, choose "Save as PDF" to keep a copy or send it to your PM.
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Built automatically from the posted spec book; check it against your own copy and addenda. Item types are sorted automatically; the spec section and page are what count.
What this job asks for at closeout
All 62 items, by trade
Division 01 General requirements 13 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MThe Contractor shall submit to the Designer, within ten (10) ...Schedule – Bar Chart01 32 00 3.1.A · PDF p. 66Spec wording“A. The Contractor shall submit to the Designer, within ten (10) working days following the Notice to Proceed, a Progress Schedule including Schedule of Values showing the rate of progress the Contractor agrees to maintain and the order in which he proposed to carry out the various phases of Work. No payments shall be made to the Contractor until the Progress Schedule has been approved by the Owner. 1. The Schedule ...” | 01 32 00 3.1.A | 66 | – |
| Warranty | WarrantyThe Contractor shall submit all required manufacturer's operating instructions, maintenance/service ...Submittals01 33 00 1.8.A · PDF p. 75Spec wording“A. The Contractor shall submit all required manufacturer's operating instructions, maintenance/service manuals, and warranties in accordance with the General Conditions, Article 3.5, and Supplementary Conditions along with this and other Sections of the Contract Documents.” | 01 33 00 1.8.A | 75 | – |
| Test / cert. | Test / cert.If any worker has a tuberculin skin test with positive ...Site Security And Health Requirements (Doc)01 35 13.16 3.5.D · PDF p. 80Spec wording“D. If any worker has a tuberculin skin test with positive results, the worker shall be denied access to the facility until the worker produces a certification from a physician licensed to practice in the State of Missouri that the worker does not have infectious tuberculosis.” | 01 35 13.16 3.5.D | 80 | – |
| Training | TrainingInstruction ProgramDemonstration And Training01 79 00 1.3.A · PDF p. 93Spec wording“A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.” | 01 79 00 1.3.A | 93 | – |
| Training | TrainingAttendance RecordDemonstration And Training01 79 00 1.3.B · PDF p. 93Spec wording“B. Attendance Record: For each training module, submit list of participants and length of instruction time.” | 01 79 00 1.3.B | 93 | – |
| Training | TrainingEvaluationsDemonstration And Training01 79 00 1.3.C · PDF p. 93Spec wording“C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.” | 01 79 00 1.3.C | 93 | – |
| Training | TrainingDemonstration and Training Video RecordingsDemonstration And Training01 79 00 1.4.A · PDF p. 93Spec wording“A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. 1. Identification: On each copy, provide an applied label with the following information: a. Name of Project. b. Name and address of videographer. c. Name of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Date of video recording. 2. At completion of training, submit complete ...” | 01 79 00 1.4.A | 93 | two copies; PDF; electronic file |
| Training | TrainingFacilitator QualificationsDemonstration And Training01 79 00 1.5.A · PDF p. 94Spec wording“A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.” | 01 79 00 1.5.A | 94 | – |
| O&M | O&MCoordinate content of training modules with content of approved emergency, ...Demonstration And Training01 79 00 1.6.C · PDF p. 94Spec wording“C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.” | 01 79 00 1.6.C | 94 | – |
| Warranty | WarrantyTraining ModulesDemonstration And Training01 79 00 2.1.B · PDF p. 94-96Spec wording“B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: a. System, subsystem, and equipment ...” | 01 79 00 2.1.B | 94-96 | – |
| Training | TrainingAssemble educational materials necessary for instruction, including documentation and training ...Demonstration And Training01 79 00 3.1.A · PDF p. 96Spec wording“A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 007213 "General Conditions".” | 01 79 00 3.1.A | 96 | – |
| Training | TrainingEngage qualified instructors to instruct Owner's personnel to adjust, operate, ...Demonstration And Training01 79 00 3.2.A · PDF p. 96Spec wording“A. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. 1. Owner will furnish Contractor with names and positions of participants.” | 01 79 00 3.2.A | 96 | – |
| Training | TrainingSchedulingDemonstration And Training01 79 00 3.2.B · PDF p. 96Spec wording“B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. 1. Schedule training with Owner with at least seven days' advance notice.” | 01 79 00 3.2.B | 96 | – |
Division 20 Mechanical, common work 2 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MMaintenance dataSeismic Protection20 08 00 1.7.G · PDF p. 101Spec wording“G. Maintenance data: For seismic supports and restraints for inclusion in Operating and Maintenance Manual specified in Division 01, Division 26 Section "Common Work Results for Electrical."” | 20 08 00 1.7.G | 101 | – |
| Test / cert. | Test / cert.ReportSeismic Protection20 08 00 3.7.B · PDF p. 110Spec wording“B. Report: Submit a certification report of the authorized representative of the seismic restraint vendor to verify the above review and to include the following: 1. Certify that all seismic-restraint systems are installed properly and in compliance with these specifications and the submittals. 2. Identify those areas that require corrective measures or certify that no corrective measures are necessary. 3. Any ...” | 20 08 00 3.7.B | 110 | – |
Division 26 Electrical 36 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| O&M | O&MOperation and Maintenance Data:Supplemental Requirements For Electrical26 00 10 1.8.A · PDF p. 123Spec wording“A. Operation and Maintenance Data: 1. Include the following information: a. Manufacturer's operating specifications. b. User's guides for software and hardware. c. Schedule of maintenance material items recommended to be stored at the Project site. d. Detailed instructions covering operation under both normal and abnormal conditions. e. Time-current curves for overcurrent protective devices and manufacturer's ...” | 26 00 10 1.8.A | 123 | – |
| Test / cert. | Test / cert.Field quality-control reportsLow-Voltage Electrical Power Conductors And26 05 19 1.2.A · PDF p. 125Spec wording“A. Field quality-control reports.” | 26 05 19 1.2.A | 125 | – |
| Test / cert. | Test / cert.Prepare test and inspection reports to record the following:Low-Voltage Electrical Power Conductors And26 05 19 3.7.C · PDF p. 129Spec wording“C. Prepare test and inspection reports to record the following: 1. Procedures used. 2. Results that comply with requirements. 3. Results that do not comply with requirements, and corrective action taken to achieve compliance with requirements.” | 26 05 19 3.7.C | 129 | – |
| Test / cert. | Test / cert.Field quality-control reportsGrounding And Bonding For Electrical Systems26 05 26 1.2.C · PDF p. 131Spec wording“C. Field quality-control reports.” | 26 05 26 1.2.C | 131 | – |
| O&M | O&MOperation and Maintenance Data:Grounding And Bonding For Electrical Systems26 05 26 1.4.A · PDF p. 131Spec wording“A. Operation and Maintenance Data: 1. In addition to items specified in Section 26 0010 "Supplemental Requirements for Electrical," include the following: a. Plans showing locations of grounding features described in "Field Quality Control for Grounding and Bonding" Article, including the following: 1) Grounding electrode access enclosures. 2) Grounding electrodes. 3) Grounding arrangements and connections for ...” | 26 05 26 1.4.A | 131 | – |
| Test / cert. | Test / cert.Field Quality-Control ReportsConduits For Electrical Systems26 05 33.13 3.3.E · PDF p. 164Spec wording“E. Field Quality-Control Reports: Collect, assemble, and submit test and inspection reports.” | 26 05 33.13 3.3.E | 164 | – |
| Test / cert. | Test / cert.Field quality-control reportsUnderground Ducts And Raceways For Electrical26 05 43 1.4.C · PDF p. 178Spec wording“C. Field quality-control reports.” | 26 05 43 1.4.C | 178 | – |
| Test / cert. | Test / cert.Field Reports:Underground Ducts And Raceways For Electrical26 05 43 1.5.C · PDF p. 178Spec wording“C. Field Reports: 1. Factory Test Reports: For handholes and boxes. 2. Manufacturer's field reports for field quality-control support.” | 26 05 43 1.5.C | 178 | – |
| Test / cert. | Test / cert.Field Quality-Control ReportsUnderground Ducts And Raceways For Electrical26 05 43 3.8.D · PDF p. 192Spec wording“D. Field Quality-Control Reports: Collect, assemble, and submit test and inspection reports.” | 26 05 43 3.8.D | 192 | – |
| Test / cert. | Test / cert.Field quality-control reportsPanelboards26 24 16 1.3.D · PDF p. 212Spec wording“D. Field quality-control reports.” | 26 24 16 1.3.D | 212 | – |
| Warranty | WarrantyWarranty documentationPanelboards26 24 16 1.5.A · PDF p. 212Spec wording“A. Warranty documentation.” | 26 24 16 1.5.A | 212 | – |
| Warranty | WarrantySpecial Installer Extended WarrantyPanelboards26 24 16 1.6.A · PDF p. 212Spec wording“A. Special Installer Extended Warranty: Installer warrants that fabricated and installed panelboards perform in accordance with specified requirements and agrees to repair or replace components or products that fail to perform as specified within extended-warranty period. 1. Extended-Warranty Period: Two years from date of Substantial Completion; full coverage for labor, materials, and equipment.” | 26 24 16 1.6.A | 212 | – |
| Test / cert. | Test / cert.Field Quality-Control ReportsPanelboards26 24 16 3.4.F · PDF p. 216Spec wording“F. Field Quality-Control Reports: Collect, assemble, and submit test and inspection reports. 1. Include certified report that identifies panelboards included and that describes scanning results, with comparisons of two scans. Include notation of deficiencies detected, remedial action taken, and observations after remedial action.” | 26 24 16 3.4.F | 216 | – |
| Test / cert. | Test / cert.Field quality-control reportsElectrical Cabinets And Enclosures26 27 16 1.3.C · PDF p. 218Spec wording“C. Field quality-control reports.” | 26 27 16 1.3.C | 218 | – |
| Test / cert. | Test / cert.Field quality-control reportsWiring Devices26 27 26 1.3.B · PDF p. 228Spec wording“B. Field quality-control reports.” | 26 27 26 1.3.B | 228 | – |
| Warranty | WarrantyWarranty documentationWiring Devices26 27 26 1.4.A · PDF p. 228Spec wording“A. Warranty documentation.” | 26 27 26 1.4.A | 228 | – |
| Warranty | WarrantySpecial Installer Extended WarrantyWiring Devices26 27 26 1.5.A · PDF p. 228Spec wording“A. Special Installer Extended Warranty: Installer warrants that installed devices perform in accordance with specified requirements and agrees to repair or replace products that fail to perform as specified within extended-warranty period. Warranty must convey to Owner upon acceptance of the Work. 1. Extended-Warranty Period: Two years from date of Substantial Completion; full coverage for labor, materials, and ...” | 26 27 26 1.5.A | 228 | – |
| Test / cert. | Test / cert.Field Quality-Control ReportsWiring Devices26 27 26 3.4.E · PDF p. 231Spec wording“E. Field Quality-Control Reports: Collect, assemble, and submit test and inspection reports.” | 26 27 26 3.4.E | 231 | – |
| Test / cert. | Test / cert.Field quality-control reportsDiesel-Engine-Driven Generator Sets26 32 13.13 1.4.E · PDF p. 235Spec wording“E. Field quality-control reports.” | 26 32 13.13 1.4.E | 235 | – |
| Warranty | WarrantyWarrantyDiesel-Engine-Driven Generator Sets26 32 13.13 1.4.F · PDF p. 235Spec wording“F. Warranty: For special warranty.” | 26 32 13.13 1.4.F | 235 | – |
| O&M | O&MOperation and Maintenance DataDiesel-Engine-Driven Generator Sets26 32 13.13 1.5.A · PDF p. 235Spec wording“A. Operation and Maintenance Data: For packaged engine generators to include in emergency, operation, and maintenance manuals. 1. In addition to items specified in Section 013300 "Submittals" include the following: a. List of tools and replacement items recommended to be stored at Project for ready access. Include part and drawing numbers, current unit prices, and source of supply. b. Operating instructions ...” | 26 32 13.13 1.5.A | 235 | – |
| Spare parts | Spare partsFurnish extra materials that match products installed and that are ...Diesel-Engine-Driven Generator Sets26 32 13.13 1.6.A · PDF p. 235Spec wording“A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Fuses: One for every 10 of each type and rating, but no fewer than one of each. 2. Indicator Lamps: Two for every six of each type used, but no fewer than two of each. 3. Filters: One set each of lubricating oil, fuel, and combustion-air filters. 4. ...” | 26 32 13.13 1.6.A | 235 | One set |
| Warranty | WarrantyManufacturer's WarrantyDiesel-Engine-Driven Generator Sets26 32 13.13 1.8.A · PDF p. 236Spec wording“A. Manufacturer's Warranty: Manufacturer agrees to repair or replace components of packaged engine generators and associated auxiliary components that fail in materials or workmanship within specified warranty period. 1. Warranty Period: Two years from date of Substantial Completion.” | 26 32 13.13 1.8.A | 236 | – |
| Test / cert. | Test / cert.Provide control module and programming for automatic monthly test of ...Diesel-Engine-Driven Generator Sets26 32 13.13 2.12.A · PDF p. 246Spec wording“A. Provide control module and programming for automatic monthly test of generator and JCAHO report of the test. Generator shall transfer load from the ATS and carrier the load for 30 continuous minutes plus cool down time after 30 minutes of load test. Coordinate the day each month with facility the generator shall perform the monthly loads test.” | 26 32 13.13 2.12.A | 246 | – |
| Test / cert. | Test / cert.Report results of tests and inspections in writing. Record adjustable ...Diesel-Engine-Driven Generator Sets26 32 13.13 3.6.J · PDF p. 250Spec wording“J. Report results of tests and inspections in writing. Record adjustable relay settings and measured insulation resistances, time delays, and other values and observations. Attach a label or tag to each tested component indicating satisfactory completion of tests.” | 26 32 13.13 3.6.J | 250 | – |
| Closeout step | Closeout stepInitial Maintenance ServiceDiesel-Engine-Driven Generator Sets26 32 13.13 3.7.A · PDF p. 251Spec wording“A. Initial Maintenance Service: Beginning at Substantial Completion, maintenance service shall include 12 months' full maintenance by skilled employees of manufacturer's authorized service representative. Include quarterly preventive maintenance and exercising to check for proper starting, load transfer, and running under load. Include routine preventive maintenance as recommended by manufacturer and adjusting as ...” | 26 32 13.13 3.7.A | 251 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Diesel-Engine-Driven Generator Sets26 32 13.13 3.8.A · PDF p. 251Spec wording“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain packaged engine generators.” | 26 32 13.13 3.8.A | 251 | – |
| Test / cert. | Test / cert.Field quality-control reportsTransfer Switches26 36 00 1.3.C · PDF p. 253Spec wording“C. Field quality-control reports.” | 26 36 00 1.3.C | 253 | – |
| O&M | O&MOperation and Maintenance DataTransfer Switches26 36 00 1.4.A · PDF p. 253Spec wording“A. Operation and Maintenance Data: For each type of product to include in emergency, operation, and maintenance manuals. 1. In addition to items specified in Section 017823 "Operation and Maintenance Data," include the following: a. Features and operating sequences, both automatic and manual. b. List of all factory settings of relays; provide relay-setting and calibration instructions, including software, where ...” | 26 36 00 1.4.A | 253 | – |
| Warranty | WarrantyManufacturer's WarrantyTransfer Switches26 36 00 1.7.A · PDF p. 253Spec wording“A. Manufacturer's Warranty: Manufacturer agrees to repair or replace components of transfer switch or transfer switch components that fail in materials or workmanship within specified warranty period. 1. Warranty Period: Two years from date of Substantial Completion.” | 26 36 00 1.7.A | 253 | – |
| Test / cert. | Test / cert.Provide control module and programming for automatic monthly test of ...Transfer Switches26 36 00 2.3.A · PDF p. 257Spec wording“A. Provide control module and programming for automatic monthly test of generator and JCAHO report of the test. Generator shall transfer load from the ATS and carrier the load for 30 continuous minutes plus cool down time after 30 minutes of load test. Coordinate the day each month with facility the generator shall perform the monthly loads test.” | 26 36 00 2.3.A | 257 | – |
| Test / cert. | Test / cert.Report results of tests and inspections in writing. Record adjustable ...Transfer Switches26 36 00 3.3.D · PDF p. 261Spec wording“D. Report results of tests and inspections in writing. Record adjustable relay settings and measured insulation and contact resistances and time delays. Attach a label or tag to each tested component indicating satisfactory completion of tests.” | 26 36 00 3.3.D | 261 | – |
| Test / cert. | Test / cert.Prepare test and inspection reportsTransfer Switches26 36 00 3.3.G · PDF p. 261Spec wording“G. Prepare test and inspection reports.” | 26 36 00 3.3.G | 261 | – |
| Training | TrainingEngage a factory-authorized service representative to train Owner's maintenance personnel ...Transfer Switches26 36 00 3.4.A · PDF p. 262Spec wording“A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain transfer switches and related equipment.” | 26 36 00 3.4.A | 262 | – |
| Training | TrainingTraining shall include testing ground-fault protective devices and instructions to ...Transfer Switches26 36 00 3.4.B · PDF p. 262Spec wording“B. Training shall include testing ground-fault protective devices and instructions to determine when the ground-fault system shall be retested. Include instructions on where ground-fault sensors are located and how to avoid negating the ground-fault protection scheme during testing and circuit modifications.” | 26 36 00 3.4.B | 262 | – |
| Training | TrainingCoordinate this training with that for generator equipmentTransfer Switches26 36 00 3.4.C · PDF p. 262Spec wording“C. Coordinate this training with that for generator equipment.” | 26 36 00 3.4.C | 262 | – |
Front end Contract conditions (final payment, releases, retainage) 11 items
| Type | Item | Spec section | PDF page | Copies / format |
|---|---|---|---|---|
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 21Spec wording“DIVISION OF FACILITIES MANAGEMENT, DESIGN AND CONSTRUCTION FINAL RECEIPT OF PAYMENT AND RELEASE KNOW ALL MEN BY THESE PRESENT THAT: hereinafter called "Subcontractor" who heretofore entered into an agreement with hereinafter called "Contractor", for the performance of work and/or furnishing of material for the construction of the project entitled (PROJECT TITLE, PROJECT LOCATION, AND PROJECT NUMBER) at (ADDRESS OF ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 21 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 32Spec wording“The Contractor shall update a complete set of the construction drawings, shop drawings and schedules of all work monthly by marking changes, and at the completion of their work (prior to submission of request for final payment) note all changes and turn the set over to the Construction Representative.” | Conditions Of The Contract (Find Heading On The Cited Page) | 32 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 33Spec wording“Prior to the final payment, furnish to the Designer three (4) copies of parts catalogs for each piece of equipment furnished by him/her on the project with the components identified by number for replacement ordering.” | Conditions Of The Contract (Find Heading On The Cited Page) | 33 | three (4) copies |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 39Spec wording“The Contractor shall be allowed to include in the Application and Certification for Payment, one hundred (100%) of the value, subject to retainage, of major equipment and material stored off the site if all of the following conditions are met: 1.” | Conditions Of The Contract (Find Heading On The Cited Page) | 39 | – |
| Payment release | Payment releaseFinal payment / retainage conditionConditions Of The Contract (Find Heading On The Cited Page)Conditions Of The Contract (Find Heading On The Cited Page) · PDF p. 40Spec wording“The final payment shall not become due until the Contractor delivers to the Construction Representative: a) A complete file of releases, on the standard form included in the contract documents as "Final Receipt of Payment and Release Form", from subcontractors and material suppliers evidencing payment in full for services, equipment and materials, as the case may require, if the Owner approves, or a consent from ...” | Conditions Of The Contract (Find Heading On The Cited Page) | 40 | – |
| Warranty | WarrantyA. General Guaranty 1. Neither the final certificate of payment ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 32Spec wording“A. General Guaranty 1. Neither the final certificate of payment nor any provision in the contract documents nor partial use or occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with contract requirements. 2. The Contractor or surety shall remedy any defects in the work and pay for any damage to property resulting there from which shall appear within a period of one ...” | Conditions Of The Contract ARTICLE.A | 32 | – |
| Warranty | WarrantyB. Extended Warranty Manufacturer's certificates of warranty shall be obtained ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 32Spec wording“B. Extended Warranty Manufacturer's certificates of warranty shall be obtained for all major equipment. Warranty shall be obtained for at least one year. Where a longer period is offered at no additional cost or called for in the specific equipment specifications, the longer period shall govern.” | Conditions Of The Contract ARTICLE.B | 32 | – |
| O&M | O&MA. Immediately after equipment submittals are approved and no later ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 32-33Spec wording“A. Immediately after equipment submittals are approved and no later than ten (10) working days prior to the substantial completion inspection, the Contractor shall provide to the Designer three (3) copies of operating instructions and service manuals, containing the following: 1. Start-up and Shut-down Procedures: Provide a step-by-step write up of all major equipment. When manufacturer's printed start-up, trouble ...” | Conditions Of The Contract ARTICLE.A | 32-33 | three (3) copies; three (4) copies |
| O&M | O&MB. Submission of operating instructions shall be done in the ...Conditions Of The ContractConditions Of The Contract ARTICLE.B · PDF p. 33Spec wording“B. Submission of operating instructions shall be done in the following manner. 1. Manuals shall be in quadruplicate, and all materials shall be bound into volumes of standard 8½" x 11" hard binders. Large drawings too bulky to be folded into 8½" x 11" shall be separately bound or folded and in envelopes, cross referenced and indexed with the manuals. 2. The manuals shall identify project name, project number, and ...” | Conditions Of The Contract ARTICLE.B | 33 | binders; binder |
| O&M | O&MA. Substantial Completion. A Project is substantially complete when construction ...Conditions Of The ContractConditions Of The Contract ARTICLE.A · PDF p. 37-38Spec wording“A. Substantial Completion. A Project is substantially complete when construction is essentially complete and work items remaining to be completed can be done without interfering with the Owner's ability to use the Project for its intended purpose. 1. Once the Contractor has reached what they believe is Substantial Completion, the Contractor shall notify the Designer and the Construction Representative of the ...” | Conditions Of The Contract ARTICLE.A | 37-38 | – |
| Test / cert. | Test / cert.C. Final Completion. The Project is finally complete when the ...Conditions Of The ContractConditions Of The Contract ARTICLE.C · PDF p. 38Spec wording“C. Final Completion. The Project is finally complete when the Certificate of Substantial Completion has been issued and all work items identified therein as incomplete have been completed, and when all administrative items required by the contract have been completed. Final Completion entitles the Contractor to payment of the outstanding balance of the contract amount including all change orders and retainage. ...” | Conditions Of The Contract ARTICLE.C | 38 | – |
Don't want to chase all of this yourself?
Want us to collect all of this and hand you one binder to sign? $1,950 per job for a trade package, whole job from $2,500, paid on delivery.
Email [email protected]Your job isn't in the library? Send us the project name or solicitation number and we'll build its checklist free.